An American put option to abandon the restaurant at an exercise price of $5 million.. A put option, as in b, except that the exercise price should be interpreted as $5 million in real es
Trang 1CHAPTER 22 Real Options
Answers to Practice Questions
1 a A five-year American call option on oil The initial exercise price is $32 a
barrel, but the exercise price rises by 5 percent per year
b An American put option to abandon the restaurant at an exercise price of
$5 million The restaurant’s current value is ($700,000/r) The annual standard deviation of the changes in the value of the restaurant as a going concern is 15 percent
c A put option, as in (b), except that the exercise price should be interpreted
as $5 million in real estate value plus the present value of the future fixed costs avoided by closing down the restaurant Thus, the exercise price is:
$5,000,000 + ($300,000/0.10) = $8,000,000 Note: The underlying asset
is now PV(revenue – variable cost), with annual standard deviation of 10.5 percent
d A complex option that allows the company to abandon temporarily (an
American put) and (if the put is exercised) to subsequently restart (an American call)
e An in-the-money American option to choose between two assets; that is,
the developer can defer exercise and then determine whether it is more profitable to build a hotel or an apartment building By waiting, however, the developer loses the cash flows from immediate development
f A call option that allows Air France to fix the delivery date and price
2 A commitment to invest in the Mark II would have a negative NPV The option to
invest has a positive NPV The value of the option more than offsets the negative NPV of the Mark I
.7194 )
3.0 (0.35
.1132 t
σ d d
.1132 /2
) 3.0 (0.35 )
3.0 )]/(0.35
00/1.10 log[467/(8
/2 t σ t X)]/σ log[P/PV(E
d
1 2
3 1
0 0
0
−
=
×
−
−
=
−
=
−
=
× +
×
=
+
=
N(d1) = N(-0.1132) = 0.4549
Trang 2b P = 500 EX = 900 σ = 0.35 t = 3.0 rf = 0.10
0.8010 )
3.0 (0.35 0.1948
t σ d d
0.1948 /2
) 3.0 (0.35 )
3.0 )]/(0.35
00/1.10 log[500/(9
/2 t σ t X)]/σ log[P/PV(E
d
1 2
3 1
−
=
×
−
−
=
−
=
−
=
× +
×
=
+
=
N(d1) = N(-0.1948) = 0.4228 N(d2) = N(-0.8010) = 0.2116 Call value = [N(d1) × P] – [N(d2) × PV(EX)]
= [0.4228 × 500] – [0.2116 × (900/1.103)] = $68.32
1.2417 )
3.0 (0.20 0.8953
t σ d d
0.8953 /2
) 3.0 (0.20 )
3.0 )]/(0.20
00/1.10 log[467/(9
/2 t σ t X)]/σ log[P/PV(E
d
1 2
3 1
−
=
×
−
−
=
−
=
−
=
× +
×
=
+
=
N(d1) = N(-0.8953) = 0.1853 N(d2) = N(-1.2417) = 0.1072 Call value = [N(d1) × P] – [N(d2) × PV(EX)]
= [0.1853 × 467] – [0.1072 × (900/1.103)] = $14.05
.4029 )
1.0 (0.15 0.2529
t σ d d
0.2529 /2
) 1.0 (0.15 )
1.0 )]/(0.15 /1.12
log[1.7/(2
/2 t σ t X)]/σ log[P/PV(E
d
1 2
1 1
0
−
=
×
−
−
=
−
=
−
=
× +
×
=
+
=
N(d1) = N(-0.2529) = 0.4002 N(d2) = N(-0.4029) = 0.3435 Call value = [N(d1) × P] – [N(d2) × PV(EX)]
= [0.4002 × 1.7] – [0.3435 × (2/1.121)] = $0.0669 million or $66,900
Trang 35 The asset value from Practice Question 4 is now reduced by the present value of
the rents:
PV(rents) = 0.15/1.12 = 0.134 Therefore, the asset value is now (1.7 – 0.134) = 1.566
.9503 )
1.0 (0.15 0.8003
t σ d d
0.8003 /2
) 1.0 (0.15 )
1.0 )]/(0.15 (2/1.12
log[1.566/
/2 t σ t X)]/σ log[P/PV(E
d
1 2
1 1
0
−
=
×
−
−
=
−
=
−
=
× +
×
=
+
=
N(d1) = N(-0.8003) = 0.2118 N(d2) = N(-0.9503) = 0.1710 Call value = [N(d1) × P] – [N(d2) × PV(EX)]
= [0.2118 × 1.566] – [0.1710 × (2/1.121)] = $0.0263 million or $26,300
6 a In general, an increase in variability increases the value of an option
Hence, if the prices of both oil and gas were very variable, the option to burn either oil or gas would be more valuable
b If the prices of coal and gas were highly correlated, then there would be minimal advantage to shifting from one to the other, and hence, the option would be less valuable
7 If the cash flows are delayed one year, the value of the option is:
8 For the case where the investment can be postponed for two years, the
end-of-period values and intermediate cash flows are:
million
$21.8 1.05
0) (0.657 70)
(0.343
+
×
200 16 160 16
25 250 25
Trang 4a At the end of the first year, the decision about whether or not to invest
should be postponed if demand at that time is low
b Because the option to delay has value, overall project Net Present Value
will be higher
c If you could undertake the project only in years 0 and 2, overall project Net
Present Value would change because choices would be constrained If, for example, demand is high at t = 1, but the project cannot be undertaken until t = 2, the intermediate cash flow of $25 will be lost
9 a The values in the binomial tree below are the ex-dividend values, with the
option values shown in parentheses
b The option values in the binomial tree above are computed using the risk
neutral method Let p equal the probability of a rise in asset value Then,
if investors are risk-neutral:
p (0.10) + (1 - p)(-0.0909) = 0.02
p = 0.581
2700 (327)
2920 (491)
3162 (712)
3428 (978)
2136 (0)
2825 (375)
2405 (115)
2605
2309 (0)
2805 (355)
2300 (0)
1892 (0)
2595 (202)
2815 (365)
Trang 5If, for example, asset value at month 6 is $3,162 (this is the value after the
$50 cash flow is paid to the current owners), then the option value will be:
[(0.419 × 375) + (0.581 × 978)]/1.02 = $711
If the option is exercised at month 6 when asset value is $3,212 then the option value is: ($3,212 - $2,500) = $712 Therefore, the option value is
$712
At each asset value in month 3 and in month 6, the option value if the option if not exercised is greater than or equal to the option value if the option is exercised (The one minor exception here is the calculation above where we show that the value is $712 if the option is exercised and
$711 if it is not exercised Due to rounding, this difference does not affect any of our results and conclusions.) Therefore, under the condition
specified in part (b), you should not exercise the option now because its value if not exercised ($327) is greater than its value if exercised ($200)
c If you exercise the option early, it is worth the with-dividend value less
$2,500 For example, if you exercise in month 3 when the with-dividend value is $2,970, the option would be worth: ($2,970 - $2,500) = $470 Since the option is worth $490 if not exercised, you are better off keeping the option open At each point before month 9, the option is worth more unexercised than exercised (As noted above in part (b) there is one minor exception to this conclusion.) Therefore, you should wait rather than exercise today The value of the option today is $327, as shown in the binomial tree above
10 a Technology B is equivalent to Technology A less a certain payment of $0.5
million Since PV(A) = $11.5 million then, ignoring abandonment value:
PV(B) = PV(A) – PV(certain $0.5 million) = $11.5 million – ($0.5 million/1.07) = $11.03 million
b Assume that, if you abandon Technology B, you receive the $10 million
salvage value but no operating cash flows Then, if demand is sluggish, you should exercise the put option and receive $10 million If demand is buoyant, you should continue with the project and receive $18 million So,
in year 1, the put would be worth: ($10 million - $8 million) = $2 million if demand is sluggish and $0 if demand is buoyant
Trang 6We can value the put using the risk-neutral method If demand is buoyant, then the gain in value is: ($18 million/$10 million) –1 = 63.2%
If demand is sluggish, the loss is: ($8 million/$11.03 million) = -27.5% Let p equal the probability of a rise in asset value Then, if investors are risk-neutral:
p (0.632) + (1 - p)(-0.275) = 0.07
p = 0.38 Therefore, the value of the option to abandon is:
[(0.62 × 0) + (0.38 × 2)]/1.07 = $0.71 million
b The only case in which one would want to abandon at the end of the year
is if project value is $5.54 (i.e., if value declines in each of the four quarters) In this case, the value of the abandonment option would be: (7 – 5.54) = 1.46
Let p equal the probability of a rise in asset value Then, using the quarterly risk-free rate, we find that, if investors are risk-neutral:
p (0.25) + (1 - p)(-0.167) = 0.017
p = 0.441
$11.50
$14.38
$17.97
$22.46
$7.98
$14.97
$9.58
$11.97
$9.97
$28.08
$18.71
$18.71
$12.47
$12.47 7
$8.31
$5.54
Trang 7The risk-neutral probability of a fall in value in each of the four quarters is:
(1 – 0.441)4 = 0.0976 The expected risk-neutral value of the abandonment option is:
0.0976 × 1.06 = 0.1035 The present value of the abandonment option is:
(0.0976 × 1.06)/1.07 = 0.0967 or $96,700
12.Decision trees are potentially more complex that the simple binomial trees For
example, decision trees might recognize three or more outcomes at each stage Furthermore, decision trees are used to help decision-makers to understand the alternative courses of action available, while the binomial trees in Chapter 22 are used for valuation purposes
13 The valuation approach proposed by Josh Kidding will not give the right answer
because it ignores the fact that the discount rate within the tree changes as time passes and the value of the project changes
14.We can no longer rely on arbitrage arguments for assets that are not traded in
financial markets, but we can use the risk-neutral method, which is an application
of the certainty-equivalent concept (See the end of Section 22.6.)
Trang 8Challenge Questions
1 a You don’t take delivery of the new plant until month 36 Think of the
situation one month before completion You have a call option to get the plant by paying the final month’s construction costs to the contractors One month before that, you have an option on the option to buy the plant The exercise price of this second call option is the construction cost in the next to last month And so on
b Alternatively, you can think of the firm as agreeing to construction and
putting the present value of the construction cost in an escrow account Each month, the firm has the option to abandon the project and receive the unspent balance in the escrow account Thus, in month 1, you have a put option on the project with an exercise price equal to the amount in the escrow account If you do not exercise the put in month 1, you get
another option to abandon it in month 2 The exercise price of this option
is the amount in the escrow account in month 2 And so on
2 The present value of the investment is:
PV = 250/0.15 = $1,667 The net present value is:
NPV = -1,000 + 1,667 = $667 Considered by itself, the project has a positive Net Present Value
Now consider the option to wait one year This is a call option with an exercise price of $1,000 The possible cash flows and end-of-period values for the first year are:
1,667
Cash flow = 50
Cash flow = 450
Trang 9If fuel savings are $450 per year, then the project has a cash flow of $450 the first year and an end-of-year value equal to: ($450/0.15) = $3,000 The total return is: [(450 + 3,000)/1,667] – 1.0 = 1.07 = 107% On the other hand, if fuel savings are $50 per year, then the project has a cash flow of $50 the first year and an end-of-year value equal to: ($50/0.15) = $333 The total return is:
[(50 + 333)/1,677] – 1.0 = -0.77 = -77% In a risk-neutral world, the expected return would be equal to the risk-free interest rate Let p be the probability that fuel prices are high, under the assumption of risk-neutrality:
(p × 1.07) + [(1 - p) × (-0.77)] = 0.10
p = 0.473 = 47.3%
To value the call option, consider its possible values If fuel prices rise to $450, the option will be worth: ($3,000 - $1,000) = $2,000 If fuel prices fall to $50, the option is worthless Thus, today the option to invest in energy-saving equipment
is worth:
$860 1.10
0]
.473) 0 [(1 2,000) (0.473
=
×
− +
×
If the energy-efficient investment is undertaken today, its value is $667
However, the value of the option to wait is $860 Hence, it makes sense for consumers to wait
portfolio of expansion options, it has higher risk than the risk of the assets currently in place
b The cost of capital derived from the CAPM is not the correct hurdle rate for
investments to expand the firm’s plant and equipment, or to introduce new products The expected return will reflect the expected return on the real options as well as the assets in place Consequently, the rate will be too high