Items listed in summary form may include:• Removal techniques for the biological contaminants • Procedures and equipment required to protect workers and occupants of the regulated area f
Trang 1CHAPTER 10 Decontamination and AssessmentBrian Wight and Martha J Boss
10.7.1 Personal Protective Equipment
10.7.2 Hygiene Facilities and Practices
10.7.3 Load-Out Unit
10.7.4 Decontamination Area Entry Procedures
10.7.5 Decontamination Area Exit Procedures
10.7.6 Regulated Areas
10.7.7 Warning Signs and Tape
10.7.8 Local Exhaust Ventilation
Trang 210.7.15 Clean-Up and Disposal
10.8 Certificate of Worker’s Acknowledgment
10.9 Special Procedures for Flooding
10.9.1 Universal Precautions
10.9.2 Health Precautions
10.9.3 Washing
10.9.4 Cuts, Abrasions, Lacerations, and Puncture Wounds
10.9.5 General Biosafety Precautions
10.9.6 General Chemical Safety
10.9.7 Cleaning and Decontamination Procedures
10.9.8 Bleach
10.9.9 Personal Protective Equipment
10.9.10 Food and Drinking Water
speci-be issued, an investigation and site assessment must speci-be conducted The following text provides an assessment and decontamination hierarchy Site-specific considerations may substantially alter this hierarchy, and the scope of work should reflect the needed alterations Safety planning to provide protocols for physical safety and to ensure limited worker exposures must be developed prior to any initial entry
10.1 INITIAL ON-SITE DETERMINATION OF CURRENT CONDITIONS
(See Figure 10.1.) Note: Mediation may be by abatement of the hazard or evacuation of the
building
Figure 10.1 Decision tree based on surface type.
NO, porous materials are present. YES, only hard surfacematerials are present.
Are the materials to be decontaminated hard surfaces that will not absorb liquids during the decontamination events?
Trang 310.2 ASSESSMENT PHASE
Fill in all rows of the assessment checklist with an answer, and leave no blanks Take pictures,
if that task is in the scope of your work Do not take pictures if they are not required for your
particular task or without approval by the project manager Follow the personal protective equipment (PPE) protocols in the site planning documents (Figure 10.2) If questions arise as to safety or health, consult the project manager, who will refer any unresolved questions to safety and health personnel Do not take any chances with your health
10.3 DECONTAMINATION ASSESSMENT PHASE
For biological contamination and subsequent remediation, design documents may be required Design actions that ultimately lead to specification generation and the assemblage of bids from approved remediation contractors may be required This document presented herein is not a sub-stitute for site-specific specifications
10.3.1 Porous Materials
If possible, dispose of these as sanitary debris Check with local and state codes Federal mandates for class II biologicals are not currently codified Local and state codes may be the defining criteria for disposal of class II biologicals Most mold contamination remains a class II situation If pretreatment prior to removal of these materials is needed, the spent biocide residual
in the porous matrix may have to be considered during disposal
For instances when the porous materials must be saved, a cost–benefit analysis should be conducted Currently, guarantees of residual safety for most biocides cannot be substantiated by peer-reviewed research findings This means that while the biological risk may be ameliorated, the risk associated with the residual biocide may become preeminent Often the cost of saving these materials eliminates the ultimate benefit
Figure 10.2 Decision tree based on property use.
Is an imminent hazard suspected upon entry?
Notify the Project Manager immediately.
Back-off and await further instructions.
During the waiting period, assess your PPE needs.
Do you have adequate PPE to reenter?
Entry can be safely accomplished given initial on-site assessment.
No human beings are in danger given current conditions Any noted additional hazards to human occupancy have been mediated.
PPE is adequate and no upgrade is needed.
PPE in use
Begin assessment Begin investigation
Trang 4Mixed results have been documented for a combination of biocides and ozone treatments Often ultraviolet (UV) lighting is used as an adjunct to ozone treatments Essentially, the biocides and ozone are poisons The UV lighting is used to lyse the spore cases or encysted biologicals Repeated treatments are often required.
Layering, such as is common in installed wall-to-wall carpeting with underlying pad and wood base, must be considered Stretched, jute-backed carpet often has a treated jute backing, and the residual stiffening agents and glue are not amenable to repeated biocide treatment The carpet manufacturer should be consulted as to the predicted outcome of biocide treatments
Treating underlying foam padding, whether in carpet or upholstered furniture, presents several problems The foam is compressible and will load with biocide liquids Transmission of the biocide throughout the layers is often not uniform, and drying is also often not uniform Drying is an important consideration both for reuse and also in terms of the added biocide effect imparted by the drying event
Hidden porous materials, such as insulation, may be present in the lining of appliances free refrigerators have a defrost cycle, and the presence of insulation that may be contaminated during the intake of air in the defrost cycle and potential leakage into refrigerator layers must be considered Refrigerators and freezers that leak a freon/mineral-oil mix from compressor and evaporative coil lines will contribute to the potential organic food base for these appliance surfaces and the surrounding areas
Frost-Dishwashers insulated to run quietly will have insulation in the dishwasher doors, and any breach of the door may have allowed this insulation to be contaminated
Items that can be washed and dried, preferably using bleach, often can be saved; however, a dryer that vents into the surrounding environs should not be used Dryers with wet basin vents should also not be used; these vents should be removed and replaced with venting to an outdoor environment Venting must not be to crawl spaces Items that can be drycleaned can sometimes be saved; however, the drycleaning establishment must be notified that a class II biological risk is present This notification should be in writing and must be secured to the items prior to delivery for cleaning Items delivered to laundry or drycleaning facilities should be bagged Alcohol bags that dissolve on contact with water are recommended for laundry, but these alcohol bags must not
be used for drycleaning!
Family heirlooms, corporate historical files, and other items of personal and professional significance to the owners can be fogged with biocide Fogging should occur in a confined, negative air pressure in a contained and filtered environment The protocols used are similar to asbestos protocols, with the added considerations for biological contaminants and biocide usage Copying and other means of reproducing paper copy should be considered, with appropriate safeguards for copy services The filtration systems in photocopier exhausts can potentially become contaminated during photocopying events
Fiberglass and foam liners, whether in ductwork or as other building components, lofts with time and is often a nest for biologicals Decontamination may involve both biocide treatment and compression of the liners Compression is accomplished mechanically either with the application
of chemical products or by relining with hard-surface, inner compression cores
Trang 5Wicking of the biocide up and through wood or other semiporous materials must also be ered Most wood finishes will not withstand the application of concentrated biocides Sequential application may be one answer to saving the wood finish The concentration of biocide used in sequential applications will be one that is not sufficient to resuspend the wood finish Repeated applications over time, however, will deposit sufficient biocide to guarantee the required residual effect.Nonliquid means of biocide application may also be used on hard surfaces Issues associated with dwell time, energy use, and repletion of treatment must all be considered No treatment, whether chemical-liquid biocides, gas-delivered biocides, biocide powders, or the application of energy sources such as UV lighting, should be considered as a guarantee The isolation of point sources of contam-ination may be easier with hard surfaces These areas can then be treated with an extra biocide or ultraviolet energy application at the outset Cabinetry and the hidden surfaces on furnishings may require additional treatment of dead air spaces associated with false bottoms The juncture points of cabinets may also contain vertical plenum spaces where biologicals can amplify.
consid-The interior of toilet bowls and the make-up water tank must also be decontaminated Any failure of the toilet seal should also be considered as problematic, as leaking sewage and waters will contribute to the potential biological amplification under toilets Hard-surface structures with numerous crevices or folds will present additional problems An example is flexible ductwork; each
of the folds in the ductwork can become a biological amplification site
10.4 PROJECT MANUAL
A project manual is necessary to accurately define the work and to establish the contract terms and conditions The project manual consists of bidding requirements, contract forms, conditions of the contract, and technical specifications The bidding requirements, contract forms, and conditions
of the contract are typically called the upfront specifications A technical specification is the part of
the contract documents or project manual that describes the technical work requirements necessary
to complete the decontamination Specifications are intended to complement the drawings and present the specific materials, equipment, biocides, and procedures required to complete the decontamination Drawings are the part of the contract documents that describes the geometry of the work This chapter describes the information required in a decontamination technical specification
A technical specification is typically separated into three parts: Part 1, General; Part 2, Products; and Part 3, Execution Each part generally contains several main items, or subparts
• Part 1 (General) defines the summary, related work, references, definitions, submittals, quality assurance/quality control, project conditions, and certificates
• Part 2 (Products) describes the technical requirements for the products and materials used in the execution of the work
• Part 3 (Execution) defines the specific work practices and procedures to complete the work
These parts and sample subparts are discussed here, with sample sections following the sion Keep in mind that the specifications are site specific, and the sample sections presented here may or may not be applicable to your project needs
discus-10.5 PART 1: GENERAL 10.5.1 Summary
This subpart describes the work covered by the technical specifications In many cases, several decontamination technical specifications are needed to define the work accurately For example, if
Trang 6a project has mold contamination on the drywall and in the air-handling unit (AHU), the project manual would likely have a drywall decontamination specification and an AHU decontamination specification Summary statements usually include statements of work and/or scope of work items Items listed in summary form may include:
• Removal techniques for the biological contaminants
• Procedures and equipment required to protect workers and occupants of the regulated area from contact with airborne biocides, biological contaminants, dust, and debris
• Containment, storage, transportation, and disposal of the generated biological contaminants/wastes
10.5.2 Related Work
This subpart references other specifications that may be related to the work covered by the technical specifications Referencing is done to reduce duplication of methods that can be used by more than one technical specification Text duplication from one specification sector to another is avoided to eliminate the potential for describing work methods differently from one specification sector to another For example, if a large decontamination project has a site-specific health and safety specification, that specification is listed as related work instead of repeating the health and safety requirements throughout the separate specification text elements
10.5.3 References
This subpart presents references that will be used in the execution of the work and in obtaining products and materials These references typically include federal, state, and local regulations and codes A project may include several technical specifications that reference the same federal, state, and local regulations In these cases, the project manual may include a reference specification section in each technical specification, or a separate composite section may be developed either as
a stand-alone document or in parallel to separate listings in each technical specification
10.5.4 Definitions
This subpart defines the terms in the technical specification that will be used in the execution
of the work and in obtaining products and materials Defining the terms reduces the potential for conflict when two entities define the terms differently For example, the contractor may define a
disposable bag as a trashcan liner bought at the local grocery store, when the actual definition may
be a 6-mil-thick, leaktight, plastic bag that is prelabeled and used for transporting waste to the
disposal site Another example is the term contractor, which, as used in this chapter, means the
abatement contractor Other contractors may also be present on-site and a clear definition of who, what, and where is consistently required in all project documents In order to determine that everyone starts out with the same definitions for certain terms, some definitions are listed within the body of specifications When regulatory definitions are used, the standards or regulations may also be listed
Sample Definitions
• Adequately wet: To sufficiently mix or penetrate with liquid to prevent the release of particulate
(defined in 40 CFR 61, Subpart M, and EPA 340/1-90-019)
• Aggressive method: Removal or disturbance of building material by sanding, abrading, grinding,
or other method that breaks, crumbles, or disintegrates material
• Amended water: Water containing a wetting agent or surfactant with a surface tension of at least
29 dynes per square centimeter when tested in accordance with ASTM D 1331
Trang 7• Authorized person: Any person authorized by the contractor and required by work duties to be
present in the regulated areas
• Building inspector: Individual who inspects buildings for biological decontamination adequacy.
• Certified Industrial Hygienist (CIH): Industrial hygienist certified in the practice of industrial
hygiene by the American Board of Industrial Hygiene (ABIH)
• Clean room: Uncontaminated room having facilities for the storage of employees’ street clothing
and uncontaminated materials and equipment
• Competent person: In addition to the definition in 29 CFR 1926, Section.32(f), a person who is
capable of identifying existing hazards and selecting the appropriate control strategy and has the authority to take prompt corrective measures to eliminate these hazards
• Contractor/supervisor: Individual who supervises decontamination work and has the necessary
training to be deemed competent
• Critical barrier: One or more layers of plastic sealed over all openings into a regulated area or
any other similarly placed physical barrier, sufficient to prevent airborne transmittal of biological contaminants and/or migration of biocide fogs in a regulated area to an adjacent area
• Decontamination area: Enclosed area adjacent and connected to the regulated area and consisting
of an equipment room, shower area, and clean room, which are used for the decontamination of workers, materials, and equipment contaminated with biological contamination or biocides
• Demolition: The wrecking or taking out of any load-supporting structural member and any related
razing, removing, or stripping of building materials
• Disposal bag: A 6-mil-thick, leaktight, plastic bag that is prelabeled and used for transporting
waste from containment to disposal site
• Disturbance: Activities that disrupt the matrix of biological contaminants, crumble or pulverize
biological contaminants, or generate visible debris from biological contaminants Disturbance includes the cutting away of small amounts of materials containing biological contaminants, no greater than the amount that can be contained in one standard-sized glovebag or wastebag, not larger than 60 inches in length and width, in order to access a building component
• Equipment room or area: An area adjacent to the regulated area used for the decontamination of
employees and their equipment
• Employee exposure: That exposure to airborne biological contamination and/or biocides that would
occur if the employee were not using respiratory protective equipment
• High-efficiency particulate air (HEPA) filter: Filter capable of trapping and retaining at least
99.97% of all monodispersed particles 0.3 µm in diameter
• Industrial hygienist: Professional qualified by education, training, and experience to anticipate,
recognize, evaluate, and develop controls for occupational health hazards
• Intact: Biological contaminated material that has not crumbled, been pulverized, or otherwise
deteriorated
• Modification: A changed or altered procedure, material, or component of a control system that
replaces a procedure, material, or component of a required system
• Negative exposure assessment: A demonstration by the contractor to show that biological
contam-ination is not in evidence, given sampling results
• Permissible exposure limits (PELs): Concentration of chemicals not in excess of the Occupational
Safety and Health Administration (OSHA)-established limits for an 8-hour time-weighted average (TWA)
• Regulated area: Area established by the contractor to demarcate areas where biological
decontam-ination work is conducted, debris and waste from such biological contamdecontam-ination work accumulate, and airborne concentrations of biocides or biological contaminants exceed (or there is a reasonable possibility they may exceed) the permissible exposure limit (defined in 29 CFR 1926, Sec-tion.1101)
• Removal: All operations where biological contaminants are taken out or stripped from structures
or substrates, including demolition operations
• Repair: Overhauling, rebuilding, reconstructing, or reconditioning of structures or substrates,
including encapsulation or other repair of biological contaminants attached to structures or substrates
Trang 8• Spills/emergency clean-ups: Clean-up of sizable amounts of waste and debris which has occurred, for
example, when water damage occurs in a building and sizable amounts of biological contaminants are dislodged A competent person evaluates the site and biological contaminants to be handled and, based
on the type, condition, and extent of the dislodged material, decides on clean-up methods to be used
• Worker: Individual (not designated as the competent person or a supervisor) who performs
bio-logical decontamination work and has been trained to perform said work safely
10.5.5 Submittals
This subpart is used to specify the information required in each submittal Submittal items include, but are not limited to, manufacturers’ data sheets, Material Safety Data Sheets, health and safety plans, training certificates, and physician’s statements Various submittals may be required before work begins Because the generation of these documents can involve time and effort, these costs must be included in all project estimates Examples of submittal items are provided below
Materials and equipment lists include manufacturers’ data for all materials and equipment to
be used, including brand name, model, capacity, performance characteristics, and any other pertinent information Following are examples of such materials and equipment:
• Vacuum cleaning equipment (must have manufacturer’s certifications showing compliance with ANSI Z9.2)
• Water filtration equipment
• HEPA local exhaust equipment, other ventilation equipment, or pressure differential monitor for HEPA local exhaust equipment
• Air monitoring equipment
• Respirators and PPE
• Duct tape, disposal containers, disposal bags, sheet plastic, polyethylene sheeting
• Wetting agents, biocides, and coating materials (must have certificates from the manufacturers stating that materials meet the applicable specified performance requirements)
• Prefabricated or constructed decontamination units
• Material Safety Data Sheets (for all chemicals proposed)
• Encapsulants (must have test results and certificates from the manufacturers substantiating pliance with performance requirements of this specification)
com-• Miscellaneous necessary items, such as scrapers; brushes; brooms; staple guns; tarpaulins; shovels; rubber squeegees; dust pans; other tools; scaffolding; staging; enclosed chutes; wooden ladders; lumber necessary for the construction of containments; Underwriters Laboratories (UL)-approved temporary electrical equipment, material, and cords; groundfault circuit interrupters; water hoses
of sufficient length; fire extinguishers; first aid kits, portable toilets; logbooks; log forms; markers with indelible ink; spray paint in bright colors to mark areas; project boundary fencing; etc
Descriptions, detailed project drawings, and site layouts may be required and should include worksite containment area techniques, local exhaust ventilation system locations, decontamination and load-out units, other temporary waste storage facilities, access tunnels, location of temporary utilities (electrical, water, sewer), and boundaries of each regulated area
The Qualifications and Organization Report is a written report providing evidence of cations for personnel assigned to the work may be required This report should include copies of
Trang 9qualifi-all required certifications and training documentation The contractor should furnish a written Qualifications and Organization Report providing evidence of:
• Qualifications of the contractor, the contractor’s project supervisor, designated competent person, supervisors, and workers
• Designated independent Certified Industrial Hygienist (CIH)
• Independent testing laboratory (including name of firm, principal, and analysts who will perform analyses)
• All subcontractors to be used, including disposal transportation and disposal facility firms, contractor supervisors, subcontractor workers, and any others assigned to perform biological decontamination or abatement and support activities
sub-The report should include an organization chart showing the contractor’s staff organization for this project by name and title, chain of command, and reporting relationship with all subcontractors The report should be signed by the contractor, the contractor’s on-site project manager, designated competent person, independent CIH, designated testing laboratory, and the principals of all sub-contractors to be used
The contractor should provide in writing:
• The name, address, telephone number, and résumé of the contractor’s designated competent person/site supervisor
• Evidence that the full-time designated competent person is qualified and experienced in the administration and supervision of biological decontamination or abatement projects, including:
• Exposure assessment and monitoring
• Work practices and abatement methods
• Protective measures for personnel
• Setting up and inspecting abatement work areas
• Evaluating the integrity of containment barriers
• Placement and operation of local exhaust systems
• Biological-contaminant-generated waste containment and disposal procedures
• Decontamination unit installation and maintenance requirements
• Site safety and health requirements
• Notification of other employees on-site
The duties of the competent person should include the following:
• Control entry to and exit from the regulated area
• Supervise employee exposure monitoring
• Ensure that all employees working within a regulated area wear the appropriate PPE, are trained
in the use of appropriate methods of exposure control, and use the hygiene facilities and tamination procedures specified
decon-• Ensure that engineering controls in use are in proper operating condition and are functioning properly
The designated competent person should be responsible for compliance with applicable federal, state, and local requirements and the contractor’s Site-Specific Safety and Health Plan (SSHP) The designated competent person should be on-site at all times this project is conducted
The owner should provide the name, address, telephone number, résumé, and other information specified below for the designated CIH who has been selected to:
• Review the contractor’s Biological Decontamination Plan
• Review the contractor’s Training Program
• Direct air monitoring
Trang 10The designated CIH should be a person who is board certified in the practice of industrial hygiene as determined and documented by the American Board of Industrial Hygiene and has a minimum of 2 years of comprehensive experience in planning and overseeing biological decon-tamination or abatement activities A copy of the designated CIH’s current, valid ABIH certification should be included The designated CIH should be on-site at all times during the initial first week
of biological decontamination/abatement and visit the site at least once per week for the duration
of biological decontamination or abatement activities and should be available for emergencies In addition, the designated CIH should submit the names, addresses, telephone numbers, and résumés
of additional industrial hygienists (IHs) and industrial hygiene technicians (IHTs) who will be assisting the designated CIH in performing on-site tasks
Training documentation will be required for all employees performing biological nation or abatement operations Such documentation should be submitted on a contractor-generated form titled Certificate of Worker’s Acknowledgment, to be completed for each employee in the same format and containing the same information as the example certificate at the end of this section Training course completion certificates (initial and most recent update refresher) required
decontami-by the information checked on the form should be attached
The contractor should provide the name, medical qualifications, address, telephone number and résumé of the physician who will or has performed the medical examinations and evaluations of the persons who will conduct the biological decontamination or abatement work tasks The phy-sician should be currently licensed by the state where the workers will be or have been examined, have expertise in pneumoconiosis, and should be responsible for the determination of medical surveillance protocols and review of examination and test results performed in compliance with 29 CFR 1926, Section 1101, paragraph Medical Requirements The physician should be familiar with the hazards of the site and the scope of the project
The names of at least two persons who are currently trained in first aid and cardiopulmonary resuscitation (CPR) by the American Red Cross or other approved agency should be designated and should be on-site at all times during site operations They should be trained in Universal Precautions and the use of PPE as described in the Bloodborne Pathogens Standard of 29 CFR
1910, Section.1030, and should be included in the contractor’s Bloodborne Pathogen Program These persons may perform other duties but should be immediately available to render first aid when needed A copy of each designated person’s current, valid First Aid and CPR certificate should be provided
The CIH should provide the name, address, and telephone number of the independent testing laboratory selected to perform the sample analyses and report the results
The contractor should provide written evidence that the landfill to be used is approved for biological decontamination/abatement disposal by the U.S Environmental Protection Agency (EPA) and state and local regulatory agencies Copies of signed agreements between the contractor (including subcontractors and transporters) and the biological waste disposal facility to accept and dispose of all sanitary and construction waste generated during the performance of this contract should be provided Qualifications should be provided for each subcontractor or transporter to be used, indicating previous experience in transport and disposal of biological waste to include all required state and local waste hauler requirements for sanitary waste The contractor and transporters should meet the Department of Transportation (DOT) requirements of 49 CFR 171, 49 CFR 172, and 49 CFR 173, as well as the registration requirements of 49 CFR 107 and other applicable state
or local requirements The disposal facility should also meet applicable state or local requirements
The training program is a copy of the written project site-specific training material that will be used to train on-site employees The training document should be signed by the contractor’s designated CIH and competent person Prior to commencement of work, each
Trang 11worker should be instructed by the independent CIH and competent person in the following project-specific safety training:
• The hazards and health effects of the specific types of biological contaminants to be abated
• The content and requirements of the SSHP
• Hazard Communication Program
• Heat and/or cold stress monitoring specific to this project
• Air monitoring program and procedures
• Medical surveillance (including medical and exposure recordkeeping procedures)
The Respiratory Protection Program includes records of the respirator program and a copy of the contractor’s own Respiratory Protection Program The independent CIH should establish min-imum respiratory protection requirements based on measured or anticipated levels of mold and fungi and treatment biocides The contractor’s Respiratory Protection Program should include at least the following elements:
• Company policy, used for the assignment of individual responsibility, accountability, and mentation of the Respiratory Protection Program
imple-• Standard operating procedures covering the selection and use of respirators (respirator selection should be determined by the hazard to which the worker is exposed)
• Medical evaluation of each user to verify that the worker may be assigned to an activity where respiratory protection is required
• Training in the proper use and limitations of respirators
Note that filters and cartridges used in biological decontamination cannot be reused after workers
go through the decontamination sequence The potential for growth of microorganisms on wetted filter material must always be considered when filters and cartridges have been used in biocontam-inated areas
• Respirator fit-testing (i.e., quantitative, qualitative, and individual functional fit checks)
• Regular cleaning and disinfection of respirators
• Routine inspection of respirators during cleaning and after each use when designated for emergency use
• Storage of respirators in convenient, clean, and sanitary locations
• Surveillance of regulated area conditions and degree of employee exposure (e.g., through air monitoring)
• Regular evaluation of the continued effectiveness of the respiratory protection program
• Recognition and procedures for the resolution of special problems as they affect respirator use (e.g., facial hair coming between the respirator facepiece and face or interfering with valve function, prescription eye wear or contact lens usage)
• Proper training in putting on and removing respirators
Trang 1210.5.5.7 Hazard Communication Program
A Hazard Communication Program should be established and implemented in accordance with
29 CFR 1910.1200 Material Safety Data Sheets (MSDSs) should be provided for all hazardous materials brought onto the worksite
The contractor should develop and submit a written comprehensive Site-Specific Safety and Health Plan (SSHP) at least 10 days prior to the preremediation conference The Safety and Health Plan should address on-site work to be performed by the contractor and subcontractors The plan should be prepared, signed, and dated by the contractor’s competent person and the project super-visor The SSHP should include a discussion of:
• PPE to be used
• Location and description of regulated areas, including clean and dirty areas, access tunnels, and decontamination units (clean room, shower room, equipment room, storage areas such as a load-out unit)
• Initial exposure assessment
• Level of supervision
• Method of notification of other employers at the worksite
• Abatement method to include containment and control procedures
• Interface of trades involved in the construction
• Sequencing of work
• Storage and disposal procedures and plan
• Type of biocide and coating agents to be used
• Location of local exhaust equipment
• Air monitoring methods (personal, environmental and clearance)
• Bulk sampling and analytical methods (if required)
• Detailed description of the method to be employed in order to control the spread of biological contaminants wastes and airborne concentrations
• Fire and medical emergency response procedures
• The security procedures to be used for all regulated areas
Reports include the results of exposure assessment and air monitoring, local exhaust ventilation records, and pressure differential recordings
10.5.5.10 Licenses, Permits, and Notifications
Necessary licenses, permits, and notifications should be obtained in conjunction with the project’s biological decontamination or abatement, transportation, and disposal actions and timely notification furnished of such actions as required by federal, state, regional, and local authorities
10.5.5.11 Clean-Up and Disposal
The clean-up and disposal waste section includes the shipment record forms to be used
10.5.6 Quality Assurance/Quality Control
This subpart is used to specify the quality assurance/quality control requirements In general,
a system of checks and balances is defined and established, including specific details of any testing programs (e.g., air monitoring or clearance sampling) and who is completing (e.g., a third party, owner, or engineer) and paying (e.g., owner and contractor) for the testing programs Typically,
Trang 13the contractor and competent person are required to have a minimum number of years of experience
in work similar to the work being completed
Testing program elements are usually determined by a CIH, and the contractor maintains responsibility for the work force Thus, decisions as to exposure monitoring for personnel will be made by the contractor’s CIH Quality assurance monitoring that duplicates the contractor’s per-sonnel monitoring, area monitoring, and final clearance monitoring is usually conducted by a third party in an oversight role for the project owner The third party team includes CIHs and industrial hygiene technical staff
The daily air-monitoring log should contain the following information for each sample:
• Sampling and analytical method used
• Date sample collected
• Sample number
• Sample type (P, preabatement; E, environmental; C, abatement clearance)
• Location, activity, facility namewhere sample collected
• Sampling pump manufacturer and model and serial numbers, beginning flow rate, end flow rate, average flow rate (liters/minute)
• Calibration date, time, method, location, name of calibrator, signature
• Sample period (start time, stop time, elapsed time [minutes])
• Total air volume sampled (liters)
• Sample results
• Laboratory name, location, analytical method, analyst, and confidence level
Also included should be the printed name and a signature and date block for the industrial hygienist who conducted the sampling and for the industrial hygienist who reviewed the daily air monitoring log to verify the accuracy of the information
10.5.7 Project Conditions
This subpart is used to describe the existing site conditions and conditions related to the work These conditions affect the work practices of the abatement contractor Existing site considerations may include:
• Determining the cause of the mold growth and whether or not the problem area has been repaired
• Describing the work environment
Note that descriptions of the work environment should specify whether the contaminated area
is occupied, unoccupied, or partially occupied Information related to location in a building should
be provided (e.g., on a fourth floor with limited access for hauling material and waste out of the building; back area of an open office space; near children, a school, or a daycare center or in a retirement village or nursing home) The extent of the area should be estimated (e.g., contamination
is limited to the drywall)
• Limiting the work to certain hours
• Specifying if utilities (e.g., sanitary, telephone, water, and electricity) are available
• Presenting analytical sample results
• Specifying that all, part, or none of the ventilation and electrical systems can be locked out/tagged out
• Describing the area of contamination