Case Study: FARB Software Development, Ltd.: Network Design and Implementation Lab exercises give you the opportunity to practice the manual skills portion of structured cabling installa

Trang 1

As-built drawings are not created until all cables are placed, all jacks are installed, and

all cables are terminated Drawing can begin while final testing is taking place, but

assurances must be made that no changes or additional work is done that is not reflected

accurately in the drawings

Floor plans, furniture plans, or T drawings usually are used as the basis for as-built

drawings The contractor is not required to redraw the building plans for the as-built

drawings The contractor draws all cable runs, terminations, and outlets, and supplies

all labeling information as it was installed

The punch list is the checklist that the customer provides the contractor with when the

contractor considers the project complete (see Figure A-53)

Figure A-53 Typical Punch List

The punch list is a list containing items that were not completed (missing outlets or

cable runs, for example), items that were completed unsatisfactorily (cables not fastened

to ladder racks or outlets that do not work, for example), or cleanup items (debris left

in corridor, for example) that the customer requires corrected before approval for final

payment The punch list can take the form of the customer’s final acceptance of the

project When the items on the punch list are completed to the customer’s satisfaction,

payment is expected

Punch List

A punch list is a record of all items within a project that the contractor must correct or complete to the satisfaction of the homeowner before the job is considered finalized.

Prior to the project closeout and final payments, homeowner and contractor or architect should jointly conduct a project walk-through to observe all items that need correcting or completing.

All parties understand that when the homeowner agrees that the punch list details itemized below have been completed to his or her satisfaction, the project

is entirely complete and all outstanding payments are due to the contractor and/or architect.

Trang 2

Case Study: FARB Software Development, Ltd.:

Network Design and Implementation

Lab exercises give you the opportunity to practice the manual skills portion of structured cabling installation The case study is designed to give you a hands-on opportunity

to participate in the design of a structured cabling system for a fictitious software-development company that is occupying a new three-story building and requires it

to be built out

Overview

To complete this case study, you should be able to

■ Gather information for the preinstallation process and lay plans for the installation process

■ Create documentation as would be required for creating a real network

■ Comply with TIA, EIA, and electrical standards Using this supplement, as well as having mastered the CCNA 3 curriculum, will prepare you to complete many tasks related to real-world network creation These objectives are spelled out within this case study in a letter from Cheryl Farb, president of FARB Software Development, Ltd., who, for this case study, is serving as the client company The following are some review items that will help you to focus on the case study

General Design Process Framework

Network design is best done by following a framework Determining where the wires

go requires knowledge of the structure of the networks You will need to know where the users are and what their applications are before you can begin to sketch out a viable network A Layer 1 LAN logical and physical topology must be developed This development includes the type of cable and the physical (wiring) topology that are selected, as well as the physical placement of infrastructure connection points on the network

A Layer 2 segmentation plan must be overlaid on the previously created Layer 1 topology This layer plan includes devices added to the topology to improve its efficiency and functionality Examples of these devices might be switches and bridges This layer also includes the use of technologies such as microsegmentation, virtual LANs (VLANs), and the Spanning Tree Protocol (STP), to add efficiency and reliability

A Layer 3 hierarchical plan then is overlaid on both of the previous two layers This plan includes adding Layer 3 devices that will provide intranetwork and internetwork functionality to the network, as well as creating a network address plan Layer 3 is

Trang 3

where routing and firewalls are implemented, imposing a logical structure on the

net-work They also can be used for segmentation of both collision and broadcast domains

An extension of the Layer 3 plan might be considered a Layer 4 plan This plan could

be laid over the first three; it moves strictly to software and controls access and

avail-ability of the network It involves access lists and firewall configuration Although a

complete network design keeps moving up the OSI model, it is beyond the focus of this

project

This design focuses on Ethernet, IP, Layer 1, Layer 2, and Layer 3, which is the focus

of this curriculum The design process logically flows up the layers of the OSI model

That said, it is important to remind ourselves of one of the purposes of structured

cabling The cabling system must be able to withstand change and growth over its life

of service Odds are good that most companies will be in different quarters by the time

their structured cabling system is worn out This means that care must be taken to not

follow the current network layout so closely that the cables are not good for any other

organization that may follow An appropriate structured cabling system may be said to

fit the network today, but accommodate easily the network of tomorrow

The most important—and, many times, the most neglected—part of network design

and operation is the documentation The main focus of this project is the documentation

of the network design Documentation for this project should include wiring maps,

addressing schemes, any brainstormed ideas, problem-solving matrices, and any other

notes made while making these determinations

Predesign Process

Before a network can be designed, the data needed to design the network must be

gathered For a network to be effective and serve the needs of its users, this data

should be gathered according to a systematic series of preplanned steps These steps

provide a guide to completely discover the data needed to create the network

The first step in the process is to gather information about the organization This

information should include the following:

■ Organization history and current status

■ Projected growth

■ Operating policies and management procedures

■ Building diagrams (blueprints)

■ Existing network diagrams and documentation

■ Office systems and procedures

■ Viewpoints of the people who will be using the LAN

Trang 4

In the information packet that follows this section, you will find communications from the president outlining FARB Software Development, Ltd This document exists at FARB Software Development LTD.doc

In this letter, Farb indicates her specific requirements for this project

The second step is to make a detailed analysis and assessment of the current and pro-jected requirements gathered in the first step This step identifies and defines issues or problems that need to be addressed (for example, a remote room in the building might not have network access) It also provides information about future network expansion needs, access, and security

The third step is to identify the resources and constraints of the organization Organi-zation resources that can affect the implementation of a new LAN system fall into the categories of hardware, software, and human resources If this were a network expansion

or upgrade, existing computer hardware and software would have to be documented Identification and definition of those projected needs also must be done The answers

to some of these questions also will help determine how much training will be required and how many people will be needed to support the LAN The questions asked should include the following:

■ What are the financial resources of the organization?

■ How are these resources currently linked and shared?

■ How many people will be using the network?

■ What are the computer skill levels of the network users?

■ What are the attitudes toward computers and computer applications?

Following these steps, documenting the information in the framework of a formal report will help estimate costs and develop a budget for the implementation of a LAN

Design Methodology and Deliverables

With the material that has been presented to this point, a strong foundation and understanding should have been developed for the concepts of a layered communica-tions model Using the OSI model as the framework, an understanding of the funccommunica-tions and devices that support operations at those layers also should have been gained

To perform this case study, material related to the physical design and installation of a network must be learned As was presented in previous material, rules and standards govern how a network is designed and built These rules and standards must be learned before the actual case study can be performed

Trang 5

Students completing this lesson should be able to

■ Develop a Layer 1 and 2 topology

■ Gather information for both the preprocess and the process

■ Create documentation during the course of the process

■ Comply with TIA, EIA, and electrical standards

Note that this aligns with Farb’s requests for her company’s project

Standards Organizations

When designing and building networks, it is necessary to ensure compliance with all

applicable fire codes, building codes, and safety standards Perhaps the most important

part of the network-design process is designing according to the EIA/TIA and ISO/IEC

industry standards The focus in this curriculum is on the standards for networking

media that have been developed and issued by the following groups:

ISO—International Organization for Standardization (not an acronym—see

glossary)

IEEE—Institute of Electrical and Electronics Engineers

UL—Underwriters Laboratories

EIA—Electronic Industries Alliance

TIA—Telecommunications Industry Association

The latter two organizations jointly issue a list of standards called the TIA/EIA standards

In addition to these organizations, local, state, county, and national government agencies

issue specifications and requirements that can impact the type of cabling that can be

used in a local-area network

It is also important to understand that these standards are being reviewed constantly

and are updated periodically to reflect new technologies and the ever-increasing

requirements of voice and data networks Just as new technologies are added to the

standards, others are dropped or phased out In many cases, a network might include

technologies that are no longer a part of the current standard or that are being

elimi-nated Typically, this does not require an immediate changeover, but these older, slower

technologies eventually are replaced in favor of faster ones

Standards Definitions

The primary standards that will affect layer design have been created by the TIA/EIA

The Telecommunications Industry Association (TIA) and the Electronic Industries

Alli-ance (EIA) are trade associations that jointly develop and publish a series of standards

Trang 6

covering structured voice and data wiring for LANs These industry standards evolved after the U.S telephone industry deregulation in 1984, which transferred responsibility for on-premises cabling to the building owner Before that, AT&T used proprietary cables and systems

Both the TIA and the EIA are accredited by the American National Standards Institute (ANSI, section 6.2.7) to develop voluntary industry standards for a wide variety of telecommunications products This means that many standards often are labeled ANSI/ TIA/EIA The various committees and subcommittees of TIA/EIA develop standards for fiber optics, user premises equipment, network equipment, wireless communications, and satellite communications

TIA/EIA 568-A is the Commercial Building Standard for Telecommunications Wiring The standard specifies minimum requirements for telecommunications cabling, recom-mended topology and distance limits, media and connecting hardware performance specifications, and connector and pin assignments Several supplements cover some of the newer, faster copper media This standard has been replaced by TIA/EIA-568-B TIA/EIA-568-B is the Cabling Standard This standard specifies the component and transmission requirements for media TIA/EIA-568-B.1 specifies a generic telecommu-nications cabling system for commercial buildings that will support a multiproduct, multivendor environment TIA/EIA-568-B.1.1 is an addendum that applies to four-pair unshielded twisted-pair (UTP) and four-pair screened twisted-pair (ScTP) patch cables’ bend radius TIA/EIA-568-B.2 specifies cabling components, transmission, system mod-els, and the measurement procedures needed for verification of twisted-pair cabling TIA/EIA-568-B.3 specifies the component and transmission requirements for an optical-fiber cabling system

TIA/EIA 569-A is the Commercial Building Standard for Telecommunications Pathways and Spaces The standard specifies design and construction practices within and between buildings that are in support of telecommunications media and equipment Specific standards are given for rooms or areas and pathways into and through which telecom-munications equipment and media are installed

TIA/EIA-606 is the Administration Standard for the Telecommunications Infrastructure

of Commercial Buildings, including cable-labeling standards The standard specifies that each hardware-termination unit must have some kind of unique identifier This identifier must be marked on each termination hardware unit or on its label When identifiers are used at the work area, station terminations must have a label on the faceplate, the housing, or the connector itself All labels must meet legibility, deface-ment, and adhesion requirements as specified in UL969

Trang 7

TIA/EIA-607 is the standard for Commercial Building Grounding and Bonding

Require-ments for Telecommunications It supports a multivendor, multiproduct environment,

as well as the grounding practices for various systems that might be installed on

cus-tomer premises The standard specifies the exact interface points between the building

grounding systems and the telecommunications equipment grounding configuration,

and specifies building grounding configurations needed to support this equipment

Electrical Safety

Generally, electrical current follows the path of least resistance Because metals such as

copper provide little resistance, they frequently are used as conductors for electrical

current Materials such as glass, rubber, and plastic provide more resistance and do not

make good electrical conductors Instead, these materials frequently are used as

insula-tors They are used to insulate conductors to prevent shock, fires, and short circuits

Many different shapes of electrical outlets exist throughout the world Two of the three

connection points provide the power circuit The third connector protects people and

equipment from shocks and short circuits This connector is called the safety ground

connection In electrical equipment where this is used, the safety ground wire is connected

to any exposed metal part of the equipment If there is a wiring fault inside of the device,

the ground connection protects people from exposure to hazardous voltages

An accidental connection between the hot wire and the chassis is an example of a wiring

fault that could occur in a network device If such a fault were to occur, the safety ground

wire connected to the device would serve as a low-resistance path to the earth ground

The safety ground connection provides a lower resistance path than the human body,

thus reducing the risk of shock or electrocution

When properly installed, the low-resistance path, provided by the safety ground wire,

offers sufficiently low resistance and current carrying capacity to prevent the buildup of

hazardously high voltages The circuit links directly to the hot connection to the earth

Telecommunications Room Requirements

Layer 1 design is the largest component of the total network design It involves the

implementation of the preliminary designs gathered in the preprocess phase of the

net-work design to create the structured cabling system This includes, but is not limited

to, creating the logical topology, creating the wiring map, selecting wiring closets, and

More Information

For more information on the various TIA/EIA standards codes, visit

www.rvcomp.com/wiring/EIA/organizations_codes.htm.

Trang 8

selecting cable This design must conform to the appropriate standards organization’s rules for design

Students completing this lesson should be able to:

■ List location and design requirements for telecommunications rooms

■ Explain cable-management design and specification

■ List considerations for selecting and installing equipment racks

■ Explain key environmental, safety, and power considerations in telecommunica-tions room location, design, and installation

Work-Area Cabling

Work-area cabling extends from the telecommunications outlet in a room to the user workstation Work-area cabling is designed to be relatively simple to interconnect so that it can be moved or changed relatively easily Each work area serves a maximum of 10m2 of usable floor space

Work-area equipment includes the following components:

■ Workstation equipment, such as computers, data terminals, telephones, fax machines, and printers

■ Cables, such as patch cables, modular cords, PC adapter cables, and fiber jumpers

■ Adapters external to the telecommunications outlet The TIA/EIA-568-B standard requires a minimum of two telecommunication outlets for each individual work area The first outlet must be a four-pair, 100 Ω unshielded twisted pair (UTP) or screened twisted pair (ScTP) cable and connector Category 5e is recommended for this outlet The standard allows three choices for the second outlet:

■ Four-pair, 100 Ω UTP or ScTP cable and connector (Category 5e recommended)

■ Two-fiber 62.5/125 µm or 50/125 µm optical fiber and connector

■ 150Ω shielded twisted-pair (STP) cable and connector (not recommended for new installations)

Network Applications at FARB

Estimating the amount of traffic that the network will carry requires you to understand the nature of the traffic Database transfers seem to take a lot of bandwidth, as does videoconferencing Web applications are often gentle on bandwidth, with the excep-tion of streaming audio and video applicaexcep-tions

The IT staff at FARB has an accumulated a list of software applications frequently used

by the staff This is broken out by which group of users uses which application

Trang 9

You can find the information about FARB and software requirement list in the Case

Study Materials section on the CD-ROM that accompanies this book

Where Does It All Go?

FARB has not progressed in its planning to the point that you have been told which

users get what seats, nor even which department gets which area of the building You

have been handed some fairly developed blueprints from which to begin your efforts

They are entirely adequate for locating the telecommunications rooms in the project

You can find these drawings for desk assignments, plumbing and HVAC, rooms, and

electric telephone and lighting, along with the building plan legend, roof cross-section

end view and side view, in the Case Study Materials section on the CD-ROM that

accompanies this book

As is often the case, not all the information that you need is on any one drawing

Fur-thermore, some of the drawings seem to be not useful to your requirements

Neverthe-less, they are a good start toward designing a network to meet FARB’s requirements

Note that there is no indication of where the TRs should go, with the exception of the

entrance facility, marked Point of Presence, on the ground floor There is no indication

of which areas of the building are to be occupied by which department Consult the

teacher or lab instructor of for this information

The following section contains hints that should help students work out some of these

issues

Structured Cabling Case Study Hints

This case study will give you experience in practicing your networking and cabling

skills As you work through the study, you goal is to design the network layout for

FARB Software Development, Ltd You will reach this goal by performing several

tasks involved in understanding the request for information and in deriving that

infor-mation from the drawings

Four layers of documentation are involved:

1. A file that specifies President Cheryl Farb’s idea for the network facility in the

proposed new FARB building

2. A requirements document that has been worked up by the internal IP staff, of

which you are a part This lists what must be connected where

3. Several sets of drawings of each of the four floors of the building

Trang 10

4. Some detail drawings to give you some idea of the methods of construction to

be used This will help you make decisions about cable routing

Take your time as you work through this case study You will find that much of the value will come from trying several different approaches Discussion with class mem-bers and teammates might help solidify your understanding of the important topics that this case study brings forward

Instructions:

Locate the letter to the internal support team from President Cheryl Farb This docu-ment shows ten items on which your ideas and input are requested The last part of the letter includes a forecast of the company growth

Here are the ten items (some of them have several steps):

3. Any construction requirements

4. Network equipment locations

5. A wiring plan that includes the following:

— A horizontal and vertical logical layout

— A horizontal and vertical physical cabling layout

— A cabling plan for the server room

— Layouts of all MDFs and IDFs

— Work-area cable outlet identification plan

6. Security and fire prevention recommendations for server room, MDF, and IDFs

7. Electrical protection for equipment

8. An IP addressing scheme for all devices on the network

9. A cost projection for the implementation of the network, including the following:

— Equipment purchase costs

— Cabling and testing costs

— Equipment installation costs

— Training and support costs

10. A timeline for the implementation of the network Following is a study guide that contains hints to help you complete these tasks