1. Trang chủ
  2. » Kỹ Thuật - Công Nghệ

Handbook of Reliability, Availability, Maintainability and Safety in Engineering Design - Part 30 ppsx

10 267 0
Tài liệu đã được kiểm tra trùng lặp

Đang tải... (xem toàn văn)

THÔNG TIN TÀI LIỆU

Thông tin cơ bản

Định dạng
Số trang 10
Dung lượng 502,15 KB

Các công cụ chuyển đổi và chỉnh sửa cho tài liệu này

Nội dung

Using the SCADA data, a criticality ranking of the systems and their related as-semblies was determined, which revealed that the highest ranking systems were the drying tower, hot gas fe

Trang 1

3.4 Application Modelling of Reliability and Performance in Engineering Design 273

Fig 3.77 Hazards criticality analysis logistics worksheet

Distributed control systems are dedicated systems used to control processes that are continuous or batch-oriented A DCS is normally connected to sensors and

ac-tuators, and uses set-point control to control the flow of material through the plant.

The most common example is a set-point control loop consisting of a pressure sen-sor, controller, and control valve Pressure or flow measurements are transmitted to the controller, usually through the aid of a signal conditioning input/output (I/O) device When the measured variable reaches a certain point, the controller instructs

a valve or actuation device to open or close until the flow process reaches the desired set point Programmable logic controllers (PLCs) have recently replaced DCSs, es-pecially with SCADA systems

A programmable logic controller (PLC), or programmable controller, is a digital computer used for automation of industrial processes Unlike general-purpose con-trollers, the PLC is designed for multiple inputs and output arrangements, extended temperature ranges, immunity to electrical noise, and resistance to vibration and im-pact PLC applications are typically highly customised systems, compared to spe-cific custom-built controller design such as with DCSs However, PLCs are usually configured with only a few analogue control loops; where processes require hun-dreds or thousands of loops, a DCS would rather be used Data are obtained through

a connected supervisory control and data acquisition (SCADA) system connected

Trang 2

274 3 Reliability and Performance in Engineering Design

Fig 3.78 Hazards criticality analysis logistics spreadsheet

to the DCS or PLC The term SCADA usually refers to centralised systems that monitor and control entire plant, or integrated complexes of systems spread over large areas Most site control is performed automatically by remote terminal units (RTUs) or by programmable logic controllers (PLCs) Host control functions are usually restricted to basic site overriding or supervisory level intervention For ex-ample, a PLC may control the flow of cooling water through part of a process, such

as the reverse jet scrubber, but the SCADA system allows operators to change the set points for the flow, and enables alarm conditions, such as loss of flow and high tem-perature, to be displayed and recorded The feedback control loop passes through the RTU or PLC, while the SCADA system monitors the overall performance Using the SCADA data, a criticality ranking of the systems and their related as-semblies was determined, which revealed that the highest ranking systems were the drying tower, hot gas feed, reverse jet scrubber, final absorption tower, and IPAT SO3 cooler More specifically, the highest ranking critical assemblies and their re-lated components of these systems were identified as the drying tower blowers’ shafts, bearings (PLF) and scroll housings (TLF), the hot gas feed induced draft fan (PFC), the reverse jet scrubber’s acid spray nozzles (TLF), the final absorption tower vessel and cooling fan guide vanes (TLF), and the IPAT SO3 cooler’s cool-ing fan control vanes (TLF) These results were surpriscool-ing, and further analysis was

Trang 3

3.4 Application Modelling of Reliability and Performance in Engineering Design 275

Fig 3.79 Typical data accumulated by the installation’s DCS

required to compare the results with the RAMS analysis design specifications De-spite an initial anticipation of non-correlation of the FMECA results with the design specifications, due to some modifications during construction, the RAM analysis appeared to be relatively accurate However, further comparative analysis needed

to be considered with each specific system hierarchy relating to the highest ranked systems, namely the drying tower, hot gas feed, reverse jet scrubber, final absorption tower, and IPAT SO3 cooler

According to the design integrity methodology in the RAMS analysis, the design specification FMECA for the drying tower indicates an estimated criticality value

of 32 for the no.1 SO2 blower scroll housing (TLF), which is the highest estimated value resulting in the topmost criticality ranking The no.1 SO2 blower shaft seal (PLF) has a criticality value of 24, the shaft and bearings (PLF) a criticality value of

10, and the impeller (PLF) a criticality value of 7.5 From the FMECA case study extract given in Table 3.25, the topmost criticality ranking was determined as the drying tower blowers’ shafts and bearings (PLF), and scroll housings (TLF) as 5th and 6th The drying tower blowers’ shaft seals (TLF) featured 9th and 10th, and the impellers did not feature at all

Although the correlation between the RAMS analysis design specifications illus-trated in Fig 3.80 and the results of the case study is not quantified, a qualitative

Trang 4

Table 3.24 Acid plant failure modes and effects analysis (ranking on criticality)

System Assembly Component Failure

description

Failure mode

consequences

Failure causes

Hot gas

feed

Hot gas

(ID) fan

Excessive vibration

PFC Hot gas ID fan would trip on high vibration, as detected by any of four fitted vibration switches Results in all gas directed to main stack

Production Dirt accumulation on impeller due to

excessive dust from ESPs

Reverse

jet

scrubber

Reverse jet

scrubber

W/acid spray nozzles

Fails to deliver spray

TLF Prevents the distribution of acid uniformly in order to provide protection

to the RJS and cool the gases Hot gas temp exiting in RJS will be detected and shut down plant

Production Nozzle blocks due to foreign materials

in the weak acid supply or falls off due

to incorrect installation

Drying

tower

No.2 SO2

blower

Shaft &

bearings

Fails to contain

PLF No immediate effect but can result in equipment damage

Production Leakage through seals due to breather

blockage or seal joint deterioration Drying

tower

No.1 SO2

blower

Shaft &

bearings

Excessive vibration

PFC Can result in equipment damage and loss

of acid production

Production Loss of balance due to impellor

deposits or permanent loss of blade material by corrosion/erosion Drying

tower

Drying

tower

Restricted gas flow

PLF Increased loading on SO2 blower Production Mist pad blockage due to ESP

dust/chemical accumulation Drying

tower

No.1 SO2

blower

Scroll housing

Fails to contain

TLF No effect immediate effect other than safety problem due to gas emission

Health hazard Cracked housing due to operation

above design temperature limits or restricted expansion

Drying

tower

No.1 SO2

blower

Shaft seal Fails to

contain

TLF No effect immediate effect other than safety problem due to gas emission

Health hazard Carbon ring wear-out due to rubbing

friction between shaft sleeve and carbon surface

Trang 5

Table 3.24 (continued)

System Assembly Component Failure

description

Failure mode

consequences

Failure causes

Final

absorb.

tower

Final

absorb.

tower

Fails to absorb SO3 from the gas stream

TLF Will result in poor stack appearance, loss

in acid production and plant shutdown due to environmental reasons

Environment Loss of absorbing acid flow or non

uniform distribution of flow due to absorbing acid trough or header collapsing

Final

absorb.

tower

FAT cool.

fan piping

Inlet guide vanes

Vanes fail to rotate

TLF Loss of flow control leading to loss of efficiency of the FAT leading to possible SO2 emissions This will lead to plant shutdown if the emissions are excessive

or if temp is>220 ◦C

Environment Seized adjustment ring due to roller

guides worn or damaged due to lack of lubrication

Final

absorb.

tower

FAT cool.

fan piping

Inlet guide vanes

Vanes fail to rotate

TLF Loss of flow control leading to loss of efficiency of the FAT leading to possible SO2 emissions This will lead to plant shutdown if the emissions are excessive

or if temp is>220 ◦C

Environment Seized vane stem sleeve due to

deteriorated shaft stem sealing ring and ingress of chemical deposits

Final

absorb.

tower

FAT cool.

fan piping

Inlet guide vanes

Operation outside limits of control

TLF Loss of flow control leading to loss of efficiency of the FAT leading to possible SO2 emissions This will lead to plant shutdown if the emissions are excessive

or if temp is>220 ◦C

Environment Loose or incorrectly adjusted vane link

pin due to incorrect installation process

or over-stroke condition

I/P

absorb.

tower

I/PASS

absorb.

tower

Fails to absorb SO3 from the gas stream

TLF Will result in additional loading of converter 4th pass and final absorbing tower with possible stack emissions

Environment Loss of absorbing acid flow due to

absorbing acid trough or header collapsing

Trang 6

Table 3.24 (continued)

System Assembly Component Failure

description

Failure mode

consequences

Failure causes

Drying

tower

Drying

tower

Fails to remove moisture from the gas stream

TLF Will result in blower vibration problems, deterioration of catalyst and loss of acid production

Quality Damage, blockage or dislodged mist

pad due to high temp./excessive inlet gas flow, or gas quality

Drying

tower

Drying

tower

Fails to remove moisture from the gas stream

TLF Will result in blower vibration problems, deterioration of catalyst and loss of acid production

Quality Damage, blockage or dislodged mist

pad due to improper installation of filter pad retention ring

IPAT

SO3

cooler

SO3 cool.

fan piping

Inlet guide vanes

Vanes fail to rotate

TLF Loss of IPAT efficiency due to poor temperature control of the gas stream.

Temperature control loop would cut gas supply if gas discharge temperature at IPAT cooler too high

Quality Seized adjustment ring due to roller

guides worn or damaged due to lack of lubrication

IPAT

SO3

cooler

SO3 cool.

fan piping

Inlet guide vanes

Vanes fail to rotate

TLF Loss of IPAT efficiency due to poor temperature control of the gas stream.

Temperature control loop would cut gas supply if gas discharge temperature at IPAT cooler too high

Quality Seized vane stem sleeve due to worn

shaft stem sealing ring and ingress of chemical deposits

IPAT

SO3

cooler

SO3 cool.

fan piping

Inlet control vanes

Operation outside limits of control

TLF Loss of IPAT efficiency due to poor temperature control of the gas stream.

Temperature control loop would cut gas supply if gas discharge temperature at IPAT cooler too high

Quality Loose or incorrectly adjusted vane link

pin due to incorrect installation process

or over-stroke condition

Trang 7

Table 3.25 Acid plant failure modes and effects criticality analysis

consequences

Probability Failures/

year

Severity Risk Crit.

value

Failure cost/year

Crit rate Fail cost

Drying tower No.1 SO2 blower Shaft & bearings Production 100% 12 5 5.0 60.0 $287,400 High crit High cost Drying tower No.2 SO2 blower Shaft & bearings Production 100% 12 5 5.0 60.0 $287,400 High crit High cost Hot gas feed Hot gas (ID) fan Production 100% 12 4 4.0 48.0 $746,400 High crit High cost Reverse jet

scrubber

Reverse jet

scrubber

W/acid spray nozzles

Production 100% 6 6 6.0 36.0 $465,000 High crit High cost Drying tower No.1 SO2 blower Scroll housing Health hazard 80% 4 10 8.0 32.0 $1,235,600 High crit High cost Drying tower No.2 SO2 blower Scroll housing Health hazard 80% 4 10 8.0 32.0 $1,235,600 High crit High cost Drying tower No.1 SO2 blower Shaft & bearings Production 100% 7 4 4.0 28.0 $449,400 High crit High cost Drying tower No.2 SO2 blower Shaft & bearings Production 100% 7 4 4.0 28.0 $449,400 High crit High cost Drying tower No.1 SO2 blower Shaft seal Health hazard 80% 3 10 8.0 24.0 $366,300 High crit High cost Drying tower No.2 SO2 blower Shaft seal Health hazard 80% 3 10 8.0 24.0 $366,300 High crit High cost

IPAT SO3

cooler

SO3 cool fan

piping

Inlet guide vanes Quality 100% 3 7 7.0 21.0 $219,600 High crit High cost IPAT SO3

cooler

SO3 cool fan

piping

Inlet control vanes

Quality 100% 3 7 7.0 21.0 $215,100 High crit High cost I/P absorb.

tower

I/PASS absorb.

tower

Environment 60% 4 8 4.8 19.2 $915,600 High crit High cost Final absorb.

tower

FAT cool fan

piping

Environment 80% 3 8 6.4 19.2 $216,600 High crit High cost

Trang 8

280 3 Reliability and Performance in Engineering Design

Fig 3.80 Design specification FMECA—drying tower

assessment of the design integrity methodology of the RAMS analysis can be

de-scribed as accurate.

The RAMS analysis design specification FMECA for the hot gas feed indicates

an estimated criticality value of 6 for both the SO2 gas duct pressure transmitter and temperature transmitter From the FMECA case study extract given in Table 3.25, the criticality for the hot gas feed’s induced draft fan (PFC) ranked 3rd out of the topmost 15 critical items of equipment, whereas the design specification FMECA ranked the induced draft fan (PFC) as a mere 3, which is not illustrated in Fig 3.81 The hot gas feed’s SO2 gas duct pressure and temperature transmitters, illustrated

in Fig 3.81, had a criticality rank of 6, whereas they do not feature in the FMECA case study extract given in Table 3.25

Although this does indicate some vulnerability of accuracy in the assessment and evaluation of design integrity at the lower levels of the systems breakdown structure (SBS), especially with respect to an assessment of the critical failure mode, the identification of the hot gas feed induced draft fan as a high failure critical and high cost critical item of equipment is valid

The RAMS analysis design specification FMECA for the reverse jet scrubber

indicates an estimated criticality value of 6 for both the RJS pumps’ pressure indi-cators From the FMECA case study extract given in Table 3.25, the criticality for

Trang 9

3.4 Application Modelling of Reliability and Performance in Engineering Design 281

Fig 3.81 Design specification FMECA—hot gas feed

the reverse jet scrubber’s acid spray nozzles (TLF) ranked 4th out of the topmost

15 critical items of equipment, whereas the design specification FMECA ranked the acid spray nozzles (TLF) as 4.5, which is not illustrated in Fig 3.82 Similar

to the hot gas feed system, this again indicates some vulnerability of accuracy in the assessment and evaluation of design integrity at the lower levels of the systems breakdown structure (SBS), especially with respect to an assessment of the critical failure mode

The identification of the reverse jet scrubber’s pumps as a high failure critical item of equipment (with respect to pressure instrumentation), illustrated in Fig 3.82,

is valid, as the RJS pumps have a reliable design configuration of 3-up with two operational and one standby

The RAMS analysis design specification FMECA for the final absorption tower

indicates an estimated criticality value of 2.475, as illustrated in Fig 3.83, which gives a criticality rating of medium criticality The highest criticality for components

of the final absorption tower system is 4.8, which is for the final absorption tower temperature instrument loop From the FMECA case study criticality ranking given

in Table 3.25, the final absorption tower ranked 15th out of the topmost 15 critical items of equipment, whereas the design specification FMECA does not list the final absorption tower as having a high criticality

Trang 10

282 3 Reliability and Performance in Engineering Design

Fig 3.82 Design specification FMECA—reverse jet scrubber

Similar to the hot gas feed system and the reverse jet scrubber system, this once more indicates some vulnerability of accuracy in the assessment and evaluation of design integrity at the lower levels of the systems breakdown structure (SBS) How-ever, the identification of the final absorption tower as a critical system in the RAMS design specification was verified by an evaluation of the plant’s failure data

b) Failure Data Analysis

Failure data in the form of time (in days) before failure of the critical systems (dry-ing tower, hot gas feed, reverse jet scrubber, final absorption tower, and IPAT SO3 cooler) were accumulated over a period of 2 months These data are given in Ta-ble 3.26, which shows acid plant failure data (repair time RT and time before failure TBF) obtained from the plant’s distributed control system

A Weibull distribution fit to the data produces the following results:

Acid plant failure data statistical analysis

Ngày đăng: 02/07/2014, 10:20

TỪ KHÓA LIÊN QUAN

TÀI LIỆU CÙNG NGƯỜI DÙNG

TÀI LIỆU LIÊN QUAN