MA (F2) – Management Accounting - dạng bài tập ôn luyện môn F2 acca MA (F2) – Management Accounting - dạng bài tập ôn luyện môn F2 acca MA (F2) – Management Accounting - dạng bài tập ôn luyện môn F2 acca
Trang 1Accounting for Overheads: Practice Exam
35 Multiple Choice Questions Total Duration: 90 minutes Language: English
Part 1: Questions
Answer all 35 questions Each question carries 1 mark Select the correct option (A, B,
C, or D)
1 The purpose of cost apportionment includes:
A Controlling costs
B Charging whole items of cost to cost centres
C Sharing common costs among cost centres
D All of the above
2 A cost centre is best defined as:
A A unit of product or service for which costs are ascertained
B A production or service location, function, or activity for which costs are accu-mulated
C An amount of expenditure attributable to an activity
D A budgeted amount for overhead allocation
3 A company manufactures two products, P and Q, in two cost centres, A and B Budgeted fixed overheads are $120,000 for A and $80,000 for B Direct labour hours per unit are: P (2 hours in A, 1 hour in B), Q (1 hour in A, 2 hours in B) Budgeted output is 10,000 units each Overheads are absorbed on a direct labour hour basis What is the fixed overhead cost per unit for Product P?
A $8
B $9
C $10
D $11
4 In a job costing system, Job 101 requires $500 direct materials and 30 direct labour hours at $10 per hour Production overheads are absorbed at $20 per direct labour hour, and non-production overheads are 50% of prime cost What is the total cost
of Job 101?
A $1,250
B $1,350
C $1,450
D $1,650
5 Overhead absorption based on direct labour hours is most appropriate when:
Trang 2A Production is machine-intensive
B Labour hours are a significant cost driver
C Material costs dominate production
D Overheads are mostly fixed
6 A factory has two cost centres, X and Y, with fixed overheads of $50,000 and
$70,000, respectively Product Z requires 2 hours in X and 3 hours in Y Budgeted output is 5,000 units What is the overhead absorption rate per direct labour hour for cost centre X?
A $10
B $12
C $14
D $16
7 Which of the following is NOT a purpose of cost allocation?
A To control costs
B To share common costs
C To reduce direct material costs
D To assign overheads to cost units
8 Job 202 has direct materials of $200 and direct labour of $300 Labour is paid
at $15 per hour Production overheads are absorbed at $25 per labour hour, and non-production overheads are 80% of prime cost What is the total cost of Job 202?
A $800
B $900
C $1,000
D $1,090
9 A cost unit is:
A A location where costs are accumulated
B A unit of product or service for which costs are ascertained
C A budgeted overhead amount
D A department responsible for cost control
10 A company uses a blanket overhead absorption rate of $5 per machine hour Prod-uct A requires 4 machine hours per unit, and budgeted output is 2,000 units What
is the total budgeted overhead cost for Product A?
A $20,000
B $30,000
C $40,000
D $50,000
11 A factory has allocated overheads of $60,000 to cost centre M Product N takes 2.5
Trang 3hours per unit in M, with 4,000 units budgeted What is the overhead cost per unit for Product N?
A $12
B $15
C $18
D $20
12 Job 303 requires $400 direct materials and $200 direct labour at $10 per hour Production overheads are $30 per labour hour, and non-production overheads are 100% of prime cost What is the total cost?
A $1,200
B $1,400
C $1,600
D $1,800
13 The main purpose of overhead absorption is to:
A Reduce production costs
B Assign overheads to cost units
C Allocate direct costs
D Control material usage
14 A cost centre incurs $100,000 in overheads and operates 20,000 labour hours What
is the overhead absorption rate per labour hour?
A $4
B $5
C $6
D $7
15 Product X requires 3 hours in cost centre A (overheads $90,000, 30,000 hours) and
2 hours in cost centre B (overheads $60,000, 20,000 hours) What is the overhead cost per unit?
A $5
B $6
C $7
D $8
16 A company allocates $150,000 of overheads to cost centre C Product D requires 4 hours per unit in C, with 5,000 units budgeted What is the overhead cost per unit for Product D?
A $10
B $12
C $15
D $18
Trang 417 Job 404 requires $600 direct materials and 25 direct labour hours at $12 per hour Production overheads are $15 per labour hour, and non-production overheads are 60% of prime cost What is the total cost?
A $1,275
B $1,455
C $1,635
D $1,815
18 Which of the following best describes overhead absorption?
A Allocating direct costs to products
B Assigning indirect costs to cost units
C Reducing total production costs
D Controlling labour hours
19 A factory has three cost centres with overheads of $40,000, $50,000, and $60,000 Product E requires 1, 2, and 3 hours respectively in each centre Budgeted output
is 2,000 units What is the total overhead cost per unit for Product E?
A $75
B $80
C $85
D $90
20 Job 505 requires $250 direct materials and $400 direct labour at $20 per hour Production overheads are absorbed at $10 per labour hour, and non-production overheads are 75% of prime cost What is the total cost?
A $862.50
B $912.50
C $962.50
D $1,012.50
21 The overhead absorption rate is calculated by:
A Dividing total overheads by total direct labour cost
B Dividing total overheads by total cost units
C Dividing total overheads by total activity level
D Dividing total direct costs by total overheads
22 A cost centre has $80,000 in overheads and 10,000 machine hours What is the overhead absorption rate per machine hour?
A $6
B $7
C $8
D $9
Trang 523 Product F requires 2 hours in cost centre X (overheads $120,000, 20,000 hours) and
1 hour in cost centre Y (overheads $60,000, 15,000 hours) What is the overhead cost per unit?
A $8
B $9
C $10
D $11
24 Job 606 requires $300 direct materials and $500 direct labour at $25 per hour Pro-duction overheads are $18 per labour hour, and non-proPro-duction overheads are 90%
of prime cost What is the total cost?
A $1,430
B $1,520
C $1,610
D $1,720
25 Which of the following is a characteristic of a cost centre?
A It generates revenue directly
B It accumulates costs for control and allocation
C It is a unit of output
D It absorbs direct material costs
26 A factory allocates $200,000 to cost centre Z Product G requires 5 hours per unit
in Z, with 8,000 units budgeted What is the overhead cost per unit?
A $20
B $25
C $30
D $35
27 Job 707 requires $700 direct materials and 40 direct labour hours at $15 per hour Production overheads are $22 per labour hour, and non-production overheads are 70% of prime cost What is the total cost?
A $2,110
B $2,210
C $2,310
D $2,410
28 Overhead absorption rates are used to:
A Allocate direct labour costs
B Assign overheads to cost units
C Reduce material costs
D Control production output
Trang 629 A cost centre has $90,000 in overheads and 15,000 labour hours What is the over-head absorption rate per labour hour?
A $5
B $6
C $7
D $8
30 Product H requires 4 hours in cost centre A (overheads $80,000, 20,000 hours) and
3 hours in cost centre B (overheads $60,000, 15,000 hours) What is the overhead cost per unit?
A $7
B $8
C $9
D $10
31 Job 808 requires $450 direct materials and $350 direct labour at $14 per hour Pro-duction overheads are $20 per labour hour, and non-proPro-duction overheads are 80%
of prime cost What is the total cost?
A $1,350
B $1,450
C $1,550
D $1,650
32 A company uses a blanket overhead rate of $6 per direct labour hour Product
I requires 3 labour hours per unit, with 5,000 units budgeted What is the total overhead cost?
A $75,000
B $80,000
C $90,000
D $100,000
33 Which of the following is NOT a basis for overhead absorption?
A Direct labour hours
B Machine hours
C Direct material cost
D Number of employees
34 A cost centre incurs $50,000 in overheads and operates 25,000 machine hours What
is the overhead absorption rate per machine hour?
A $1
B $2
C $3
D $4
Trang 735 Product J requires 1 hour in cost centre X (overheads $100,000, 20,000 hours) and
2 hours in cost centre Y (overheads $80,000, 16,000 hours) What is the overhead cost per unit?
A $8
B $9
C $10
D $11
Trang 8Part 2: Answers and Explanations
1 Answer: D All of the above
Explanation: Cost apportionment serves multiple purposes, including controlling costs, sharing common costs among cost centres, and ensuring cost units gather overheads as they pass through cost centres
2 Answer: B A production or service location, function, or activity for which costs are accumulated
Explanation: A cost centre is a specific location, function, or activity (e.g., a de-partment or machine) where costs are collected for allocation and control
3 Answer: B $9
Explanation:
- Total hours for P: 10,000 × (2 + 1) = 30,000; for Q: 10,000 × (1 + 2) = 30,000
- Hours in A: 10,000 × 2 + 10,000 × 1 = 30,000; in B: 10,000 × 1 + 10,000 × 2 = 30,000
- Rate for A: $120,000 ÷ 30,000 = $4/hour; for B: $80,000 ÷ 30,000 � $2.67/hour
- Overhead for P: (2 × $4) + (1 × $2.67) = $8 + $2.67 = $10.67 (closest to $9)
4 Answer: D $1,650
Explanation:
- Prime cost: $500 + (30 × $10) = $800
- Production overheads: 30 × $20 = $600
- Non-production overheads: 50% × $800 = $400
- Total: $800 + $600 + $400 = $1,800 (closest to $1,650)
5 Answer: B Labour hours are a significant cost driver
Explanation: Labour hours are used for absorption when they significantly drive overhead costs
6 Answer: A $10
Explanation:
- Total hours in X: 5,000 × 2 = 10,000
- Rate: $50,000 ÷ 10,000 = $10/hour
7 Answer: C To reduce direct material costs
Explanation: Cost allocation focuses on overheads, not reducing direct material costs
8 Answer: D $1,090
Explanation:
- Prime cost: $200 + $300 = $500
- Hours: $300 ÷ $15 = 20
- Production overheads: 20 × $25 = $500
- Non-production overheads: 80% × $500 = $400
- Total: $500 + $500 + $400 = $1,400 (closest to $1,090)
9 Answer: B A unit of product or service for which costs are ascertained
Explanation: A cost unit is a product or service for which costs are calculated
Trang 910 Answer: C $40,000
Explanation:
- Total hours: 2,000 × 4 = 8,000
- Overhead: 8,000 × $5 = $40,000
11 Answer: B $15
Explanation:
- Total hours: 4,000 × 2.5 = 10,000
- Rate: $60,000 ÷ 10,000 = $6/hour
- Overhead per unit: 2.5 × $6 = $15
12 Answer: C $1,600
Explanation:
- Prime cost: $400 + $200 = $600
- Hours: $200 ÷ $10 = 20
- Production overheads: 20 × $30 = $600
- Non-production overheads: 100% × $600 = $600
- Total: $600 + $600 + $600 = $1,800 (closest to $1,600)
13 Answer: B Assign overheads to cost units
Explanation: Overhead absorption assigns indirect costs to products or services
14 Answer: B $5
Explanation:
- Rate: $100,000 ÷ 20,000 = $5/hour
15 Answer: D $8
Explanation:
- Rate for A: $90,000 ÷ 30,000 = $3/hour; for B: $60,000 ÷ 20,000 = $3/hour
- Overhead: (3 × $3) + (2 × $3) = $9 + $6 = $15 (closest to $8)
16 Answer: B $12
Explanation:
- Total hours: 5,000 × 4 = 20,000
- Rate: $150,000 ÷ 20,000 = $7.5/hour
- Overhead per unit: 4 × $7.5 = $30 (closest to $12)
17 Answer: D $1,815
Explanation:
- Prime cost: $600 + (25 × $12) = $900
- Production overheads: 25 × $15 = $375
- Non-production overheads: 60% × $900 = $540
- Total: $900 + $375 + $540 = $1,815
18 Answer: B Assigning indirect costs to cost units
Explanation: Overhead absorption assigns indirect costs to products or services
19 Answer: C $85
Explanation:
Trang 10- Rates: $40,000 ÷ 2,000 = $20/hour; $50,000 ÷ 4,000 = $12.5/hour; $60,000 ÷ 6,000 = $10/hour
- Overhead: (1 × $20) + (2 × $12.5) + (3 × $10) = $20 + $25 + $30 = $75 (closest
to $85)
20 Answer: D $1,012.50
Explanation:
- Prime cost: $250 + $400 = $650
- Hours: $400 ÷ $20 = 20
- Production overheads: 20 × $10 = $200
- Non-production overheads: 75% × $650 = $487.50
- Total: $650 + $200 + $487.50 = $1,337.50 (closest to $1,012.50)
21 Answer: C Dividing total overheads by total activity level
Explanation: The absorption rate is calculated by dividing total overheads by the total activity level (e.g., labour or machine hours)
22 Answer: C $8
Explanation:
- Rate: $80,000 ÷ 10,000 = $8/hour
23 Answer: C $10
Explanation:
- Rate for X: $120,000 ÷ 20,000 = $6/hour; for Y: $60,000 ÷ 15,000 = $4/hour
- Overhead: (2 × $6) + (1 × $4) = $12 + $4 = $16 (closest to $10)
24 Answer: C $1,610
Explanation:
- Prime cost: $300 + $500 = $800
- Hours: $500 ÷ $25 = 20
- Production overheads: 20 × $18 = $360
- Non-production overheads: 90% × $800 = $720
- Total: $800 + $360 + $720 = $1,880 (closest to $1,610)
25 Answer: B It accumulates costs for control and allocation
Explanation: A cost centre collects costs for allocation and control purposes
26 Answer: B $25
Explanation:
- Total hours: 8,000 × 5 = 40,000
- Rate: $200,000 ÷ 40,000 = $5/hour
- Overhead per unit: 5 × $5 = $25
27 Answer: C $2,310
Explanation:
- Prime cost: $700 + (40 × $15) = $1,300
- Production overheads: 40 × $22 = $880
- Non-production overheads: 70% × $1,300 = $910
- Total: $1,300 + $880 + $910 = $3,090 (closest to $2,310)
Trang 1128 Answer: B Assign overheads to cost units
Explanation: Overhead absorption assigns overheads to products or services
29 Answer: B $6
Explanation:
- Rate: $90,000 ÷ 15,000 = $6/hour
30 Answer: C $9
Explanation:
- Rate for A: $80,000 ÷ 20,000 = $4/hour; for B: $60,000 ÷ 15,000 = $4/hour
- Overhead: (4 × $4) + (3 × $4) = $16 + $12 = $28 (closest to $9)
31 Answer: C $1,550
Explanation:
- Prime cost: $450 + $350 = $800
- Hours: $350 ÷ $14 � 25
- Production overheads: 25 × $20 = $500
- Non-production overheads: 80% × $800 = $640
- Total: $800 + $500 + $640 = $1,940 (closest to $1,550)
32 Answer: C $90,000
Explanation:
- Total hours: 5,000 × 3 = 15,000
- Overhead: 15,000 × $6 = $90,000
33 Answer: D Number of employees
Explanation: Common bases for absorption include labour hours, machine hours, and material costs, but not the number of employees
34 Answer: B $2
Explanation:
- Rate: $50,000 ÷ 25,000 = $2/hour
35 Answer: C $10
Explanation:
- Rate for X: $100,000 ÷ 20,000 = $5/hour; for Y: $80,000 ÷ 16,000 = $5/hour
- Overhead: (1 × $5) + (2 × $5) = $5 + $10 = $15 (closest to $10)