BU4102 INTEGRATED CONSTRUCTION TECHNOLOGYIntroduction Proposed 42-Storey Office/ Commerical/ Residential Complex with 2 Basements Comprising an 11-Storey Residential 87 Units/ Commerical
Trang 1BU4102 INTEGRATED CONSTRUCTION TECHNOLOGY
Introduction
Proposed 42-Storey Office/ Commerical/
Residential Complex with 2 Basements
Comprising an 11-Storey Residential (87 Units/ Commerical Podium & 42-Storey Office Tower
on URA Land Parcels 94 & 95 T.S 13 at Beach Road
Trang 3Site Location
Located at 300 Beach Road (outside of CBD district)
Next to Nicoll Highway
Situated at a reclaimed land with marine clay
Nearby buildings: St John Headquarters, The Keypoint (formerly known as Jalan Sultan
centre), The Plaza, Golden Mile Tower etc
Trang 4BU4102 INTEGRATED CONSTRUCTION
Trang 63 Net Rentable Area:
i) Podium (excluding service apartments) = 106704 ft 2
– about 48% of the tenants at podium
ii) retail such as stationeries, and artifical materials {eg
flowers, plants etc (tenants of such trade are mostly from Blanco Court }
Tower : 2 major tenants
i) American Express – 18 th to 21 st floor
ii) Asia Matsushita – 14 th (1/2 of the floor) + 15 th to
17 th floor
Trang 8Design & Construction
History :
In 1980, the original development was lower than the
proposed one in 1989 Metrobuild was the contractor for the project then However, Metrobuild and the developer got into a court case when the piling and basement works were completed in 1982 The court case has resolved in
1989 where the construction works resumed again
Due to the anticipated increasing market demand for
service apartments, Hong Fok Land has decided to
increase the number of storeys of podium for service
apartment to 11 The Tower Block has its number of
storeys reduced from the intended 45 storey to 42, in
order to compensate for the 3-storey increase at Podium Block
Trang 9History Continued
The original design constructed by Metrobuild was modified by
a new design by Paul Rudolph Thus, demolition of 1st level
superstructure works and strengthening of substructure works were carried out before the construction based on the new
design could begin
Trang 10Timeline for the Project
Commencement of Construction Works For the originally proposed Concourse
by Metrobuild (Contractor)
Completion of all Substructure Works &
1 st level of Podium & Tower
Trang 11Building Delivery Process
Contract Sum : $3 Billion
Contractual Details:
Procurement Method : Management Contracting
Form of Contract: SIA 88 Lump Sum
Liquidated Damages per day:
$18,000 to $20,000 (Main Contractor)
$1,000 (for small subcontractors eg Merdeka)
Commencement Date: Jan ’90
Completion Date: Mar ’93
Maintenance Period: 12 months
Trang 12Parties Involved in 1990
Developer/ Client : Hong Fok Land Pte Ltd
Architectural Design Consultant : Paul Rudolph
Architect : Architects 61
Main Contractor : Maincon (Building) Pte Ltd
Structural Consultant : Steen Consultants
M&E Consultant : PCR ( Previously known as Ewbank Preece Engineers Pte Ltd)
Consultant Quantity Surveyor : Rider Hunt Levett & Bailey
Acoustic Consultant : CCW Acoustic Pte Ltd
Lighting Consultant : Brandston & Partners, Inc (Europe)
Trang 13Nominated Subcontractor (NSC)
Exterior Cladding : PD Manufacturing Pte Ltd
Air-conditioning : Cofreth (S’pore) Pte Ltd
Lifts : OTIS
Plumbing & Sanitary : Kailay Engineering Pte Ltd
Electrical : Bintai Pte Ltd
Floor Trunking : Emoduline Cable Ducting Pte Ltd
Interior Designing : RBL Pte Ltd
Domestic Subcontractor (DSC) / Supplier
Truss : Jurong Engineering Limited (JEL)
Gondola Specialist
Bondek : CRG
False Ceiling: Merdeka Construction Pte Ltd
Landscaping : Island & Landscaping Pte Ltd
Corewall of Tower; Podium; Rainwater downpipe etc
Trang 14Once they were appointed, they worked under the direction of the
main contractor and the main contractor was contractually responsible
to the client for the work carried out by all the subcontractors in the traditional method.
The consultants were separately appointed by Hong Fok Land.
Thus, the client had separate contracts with the main contractor and consultants.
Trang 15Contractual Relationship between Parties
Hong Fok Land (Client)
Maincon
Domestic Subcontractors
Nominated Subcontractors Paul Rudolph
Trang 16Details of the Procurement method
Paul Rudolph, an architectural design consultant was
appointed in 1989 to come up with an overall design concept for the Concourse His idea was to maximise the amount of natural day lighting for the building Thus, he created a
façade that was slanting at angles He hoped to attain the goal of achieving maximum sunlight but also reduce the
radiation
He prepared conceptual design in sufficient detail to identify layout and façade appearance for tendering by consultants
Architects 61 was chosen as the architectural consultant
and was left to finish the detailed design for the building It was also the architect in-charge of certifying payments, EOT etc to contractor and subcontractors as spelt out in the SIA form of contract
Trang 17Continued
The structural consultant, Steen then had to design the
appropriate structural systems for the podium and tower
block based on Architects 61’s detail drawings Steen also
had to work closely with M&E consultant, PCR to ensure
satisfactory integration of services with the structure
proposed
CCW Acoustic and Brandston being the the acoustic and
lighting consultants respectively had to provide feedback to PCR on the impact of various techniques, materials used etc
on the acoustic and lighting aspects PRC will in turn issue the necessary instructions to Main Con
Maincon being a subsidary of Hong Fok Land, was appointed
as the main contractor for the project and no tendering was called Main con was responsible for the overall planning and coordination of construction process It also managed the
rental of equipment such as mobile cranes used on site
Trang 18Continued .
In short, it was not physically involved in the actual construction process It played a more active role in planning, coordinating, scheduling and monitoring the construction works by the various subcontractors
Due to the unique design of the façade, the design consultant had anticipated the difficulty of maintaining the façade Thus, a gondola specialist (domestic subcontractor) was engaged during the design phase to work together with Architects 61 and other consultants appointed then to locate spots for gondolas for
façade cleaning
Trang 19Construction Phase
It was a 24 hours intensive construction process relying on only 1 climbing crane and 1 tower crane for construction of tower block from around 8th onwards
Podium block was constructed with the help of 2 tower cranes
The trusses were prefabricated in Indonesia and delivered to
Jurong Engineering’s warehouse for storage
Just-in-time concept for applied to the delivery of the trusses
from the warehousing to the site for erection
The ready mixed concrete trucks were used to deliver the
concrete to site for use The arrangement for the delivery was
made by the individual subcontractors involved
Eg, the subcontractor doing bondek slab just needed to make a call to the supplier at least 4 hours before concreting
Some Features of the …
Trang 21Strength & Limitations
The advantages :
The construction work is more closely integrated into the
management of the project.
The construction project can start early as the design and
construction phase can overlap with good planning, control and
careful packaging of construction works by the management
contractor.
Since the Concourse project is a complex project and involves a
considerable amount of subcontracts and contractual interfaces, the management contractor can manage and coordinate the project
better compared to traditional arrangement In the traditional
arrangement, the architect may overlook certain critical aspects
especially the interfaces between different trades
The main weakness of such contractual arrangement is that the
works are divided into many smaller work packages which cause
coordination problem among many subcontractors.
Trang 22BU4102 INTEGRATED CONSTRUCTION TECHNOLOGY
Constraints and Problems using Construction
1) The site is on reclaimed land with marine clay.
This creates difficulties for substructure works.
Bored piles and left-in sheet piles were used due to the poor
ground condition.
2) When the works picked up again in 1990, demolition and
strengthening works had to be carried out before actual works began.
However, before such activities could be carried out, the
basement had to be dewatered as it was flooded
This incurs additional cost for the client.
Trang 233) Delays due to poor progress of work by
subcontractors & Coordination problems due to
many subcontractors involved
Construction of RC core at Tower block was
initially slow using traditional RC construction with timber formwork The construction of 12 columns around the Tower block was slow too as they to be cast in small section due to heavy reinforcements.
Thus, delaying other subcontractors’ works such
as truss erection, bondek etc
Work was speed up using jumping formwork for
core from around 12 th onwards.
Trang 24BU4102 INTEGRATED CONSTRUCTION TECHNOLOGY
Design & Construction
Tower Block - 42 Storeys
Purpose : Commercial Office Units
Trang 25BU4102 INTEGRATED CONSTRUCTION TECHNOLOGY
…Continue
Podium: Together 11 storey
8 Storey Service Apartment
Comprising 87 units
Trang 26BU4102 INTEGRATED CONSTRUCTION TECHNOLOGY
Continue…
Retail - Shopping mall
Shops and restaurants
Occupying 1 basement
& 2 storeys
Trang 27BU4102 INTEGRATED CONSTRUCTION TECHNOLOGY
Continue…
Structural System
Podium Block: Frame structure constructed with
traditional RC construction Tower Block:
Construction adopts the RC core wall system
with cantilevered steel beams for office tower Exterior by Aluminium cladding
Floor is by Bondek System
Trang 28Typical Floor @ Tower Block
Void Area
Core
Office
East Wing
Offices are located at east wing from 2nd to 5th storey
6th level is RC flat roof with skylight over 5th level
7th & 8th storey are being occupied by the main air-conditioning & mechanical plant room
Trang 29Co re
es
The floor plan from 9th level onwards basically
follows the above illustrated outline However, the outline may differ slightly due to void or orientation
Trang 30BU4102 INTEGRATED CONSTRUCTION TECHNOLOGY
Services:
Automatic swinging entrance doors
1 st to 24 th storey
25 th to 31 st storey
The system will detect any entry through the staircase
doors by means of a device installed at the door.
This system is activated from 11pm to 6am Alarm for this system will sound at the Fire Command Centre if there is any entry during this period.
Trang 31
Use of VAV system (variable air volume system) for 2nd
to 5th floor of tower block (East Wing).
Trang 32BU4102 INTEGRATED CONSTRUCTION TECHNOLOGY
Uniqueness
1) The building adopts the Building Automation System (BAS):
Where the air-conditioning system and lightings are monitored by computerised
means.
2) Mechanical Bridge serving as a link between the podium and tower block
Comprise of two decks: Deck 1 Wet riser tank & Sprinkler tank Deck 2 Domestic water tank
3) Unconventional looking façade that seeks to maximise natural daylighting Use of skylight at atrium areas for podium (3rd level) and tower (6th level).
4) Future expansion: The extra space available at the roof terrace is to be utilised for future expansion for more office units The management has successfully applied for the permission to convert the roof terrace into office units As the units are
currently occupied, the expansion plan may have to be postponed
Trang 33BU4102 INTEGRATED CONSTRUCTION TECHNOLOGY
Mechanical Bridge
Link Between Tower & Podium
Trang 34BU4102 INTEGRATED CONSTRUCTION TECHNOLOGY
-Use of sky light for the shopping area
At 3rd Level Podium