This excess material is TABLE 17.2 Phosphorus Budgets for a FWS Design Example Parameters Note: This example is based on the water budget shown in Table 17.1 ; sequential tank-to-tank ca
Trang 1A performance-based procedure is unavoidable for FWS
wet-lands because they address too many applications with
vary-ing degrees of source strength and pretreatment In general,
the targets are also variable because of the differences in
reg-ulatory requirements among countries, states, and discharge
recipients Loading specifications, whether as pollutant
kilo-grams per wetland hectare per year or as wetland hectares
per person equivalent, have not, and, in general, cannot be
developed to deal with the spectrum of situations created by
FWS diversity of applications It is not an exaggeration to say
that each FWS wetland is unique
Design of FWS wetlands may be roughly divided into
two categories: sizing calculations and physical
specifica-tions Sizing requires characterization of the incoming water
and regional meteorology as well as the goals of wetland
treatment, as discussed in Chapter 16 Here, a
comprehen-sive sizing strategy is presented, based on the information
assembled Chapter 18 will deal with physical
consider-ations, including the number of cells, layout, depth,
bathym-etry, soils and plants, structures, and lining It is recognized
that wetlands are almost never stand-alone treatment devices,
but rather form part of a treatment train Other components
may be mechanical, such as clarifiers or filters, or more
natu-ral, such as settling basins or lagoons More than one type
of wetland may be involved at the same site—FWS, VF, and
HSSF This chapter focuses on only the FWS component of
treatment systems
Based on the performance-based sizing algorithm
intro-duced in Chapter 15, the key features described in this
chap-ter are the following:
Parameter selection and calculation
6 Select rate constants and seasonality
(Select plant community type.)
7 Select DTD (hydraulic) efficiency P-value
(Select compartmentalization.)
8 Adjust area till goals are all met
Constraint checks and iteration
9 Set estimated growth cycle
10 Check biogeochemical cycles for consistency
11 Check chemical constraints
12 Check loading graph for risk assessment
13 Adjust for seasonality
Repeat this procedure as needed to meet design goals
The complexity of wetland behavior and, hence, of the
sizing calculation is such that a single equation for wetland
area cannot be written At this point in the evolution of the
treatment of wetland design, the sizing procedure must move out of the realm of the pocket calculator and into the world
of spreadsheet computations The single formula, black-box approach will not suffice
17.1 POLLUTANT REDUCTIONS AND PERFORMANCE COMPUTATIONS
The information collected is utilized as a basis to forecast the area needed to achieve the goals of the project The pro-cedure outlined here is for a steady-flow situation Different flows may need to be considered to deal with daily or sea-sonal peaking Different seasons may need to be considered,
so that the “bottleneck” period of the year is identified and analyzed
Many literature sources provide single equations into which anyone may insert numbers to compute a wetland area Although such an option would be very convenient,
it is not realistic except for a few highly specialized cases Accordingly, the procedure given here explores the effect of changing wetland area (or equivalently, detention time) on the forecasted effluent concentrations of contaminants It is presumed that the designer will conduct the design calcula-tions via a computer spreadsheet so that design changes may
be easily explored
Wetland hydrology is first determined as a necessary sor to area calculations Annualized calculations are considered first; the effects of season will be considered later in the chapter
QoQi A P( ET I) (17.1)
qoqi(P ET I) (17.2)where
wetland area, mevapotranspiratio
2
A ET
infiltration rate, m/dpreci
I P
ppitation rate, m/dhydraulic loading rate
flow rate, m /d3
Trang 2628 Treatment WetlandsThe inlet hydraulic loading will be increased by rainfall
(≈0.5–1.5 m/yr) and decreased by evapotranspiration (ET) (≈
0.5–1.5 m/yr) However, there may be seasonal imbalances
These amounts are important if the wetland is to have a very low
hydraulic loading or, correspondingly, a long detention time
The ratio a i is the atmospheric augmentation
Evapotranspiration (rain) has two effects: lengthening
(shortening) of detention time and concentration (dilution) of
dissolved constituents The use of an average flow rate
com-pensates for altered detention time but not for dilution or
concentration The fractional error in a first-order model
prediction of concentration due to flow averaging is
approxi-mately equal to a, for a −0.5 Thus, if 25% of the inflow
evaporates, use of a first-order model with average flow
pre-dicts concentrations 25% lower than required by the mass
balance If rain adds 25% to the flow, use of a first-order
model predicts concentrations 25% higher
A possibly important feature of ET is that the
transpira-tion carries water into the root zone (see Part I, Chapter 4)
Therefore, if the pollutant mass balances are done on surface
water, then the transpiration component is the same as
infil-tration: it carries materials into the soil For a fully vegetated
wetland, somewhat more than half of ET is attributable to
transpiration Transpiration is typically about one half to two
A transpiration fraction ofET, dimensionleess
The pollutant mass balances will be conducted on a
cells-in-series basis (see Figure 17.1) Results of the overall water
mass balance are apportioned to the cells according to the
chosen number of TIS For the first unit in the series:
Q1QinA P1( ET I) (17.4)where
area of tank number 1, mflow ra
1
A Q
tte out of tank 1, m /d3
Flows are thus computed sequentially, from inlet to outlet,
for the number of tanks chosen (PTIS).
The input data requirements for water mass balances are
6 Apparent number of tanks in series (P-value)
An example is detailed in Table 17.1 This hypothetical example is configured to include small rainfall, considerable
ET, and some infiltration; in other words, a leaky arid region
system The net loss of incoming water is 41%, of which 44%
is ET and 56% is infiltration.
POLLUTANT MASS BALANCES
The TIS model is then carried forward via a sequential culation of pollutant concentrations for each “tank” in the chosen hydraulic model (Figure 17.1)
cal-A first-order areal model with rate constant k is selected with necessary wetland background concentration C* A
volumetric first-order model may also be chosen for which
k EhkV The pollutant mass balance for the first of the land segments, designated by subscript “1” for steady-state,
wet-FIGURE 17.1 Conceptual TIS model for pollutant reduction.
Trang 3In this simple version, rainfall has been assumed to have zero
pollutant concentration, but it is easy to add an atmospheric
input of the pollutant if it exists Infiltration is assumed to
occur at the outlet concentration Transpiration flow of the
contaminant has been included Combining Equation 17.4
with Equation 17.5 gives the concentration exiting the
hypo-thetical segment number one:
Note that the hydraulic loading rates in Equation 17.7 are the
individual tank loading rates, not the overall system
load-ing rates This computation is then repeated sequentially
for the remaining segments, using, in each case, the outlet
concentrations and flows from the preceding unit The
wet-land outlet concentration is that exiting the final
hypotheti-cal segment
Outgoing pollutant loads are calculated as the product of
the volumetric outflow (m3/d) and the outflow concentration
is extended to illustrate these calculations, continuing the
choice of P 3 TIS Phosphorus is chosen as the pollutant of interest, entering the wetland at 2.00 mg/L The value of C*
is chosen to be low, 0.01 mg/L The rate constant is selected
to be the median shown for phosphorus in FWS systems in Table 10.11, k 10 m/yr Because the transpiration flux is
presumed to draw phosphorus into the root zone, the
frac-tion of ET, that is, transpirafrac-tion, must be selected, and in the
example it is picked as A 0.5
The computed phosphorus concentration in the surface
outflow water is Co 0.62 mg/L, or a concentration reduction
of 69% (Table 17.2) However, the existence of ET losses and
infiltration creates a different result for mass removal: 82%
of the phosphorus entering does not leave with surface water
If infiltration water departs vertically downward without ther treatment, then 15% of the phosphorus mass removal
fur-is due to infiltration Thus, it fur-is seen that load reduction and concentration reduction are two different goals, which may lead to different designs Both these types of design sizing require mass balance computations for water and rate calcu-lations for pollutants
TABLE 17.1 Water Budgets for a FWS Design Example Parameters
Note: Sequential tank-to-tank calculations are based on Equation 17.4; this example has a
com-bined detention time of 19.2 days, whereas averaging the flows leads to 17.2 days; the required input data are shown in bold.
Trang 4630 Treatment Wetlands
I NTERCONNECTED P OLLUTANTS : T HE C ASE OF N ITROGEN
Nitrogen species interconvert, thereby linking the mass
bal-ances for organic, ammonia, and oxidized nitrogen It is
some-times possible to disconnect these species, as, for instance, in
the case of wetlands that receive nitrate but little or no organic
or ammonia nitrogen However, in many cases, it is
neces-sary to account for the (internal) production of ammonia from
organic sources, i.e., from either the incoming water or the
decomposition of wetland necromass, and the internal
produc-tion of oxidized nitrogen A simple, presumed chemistry is
ORG-NlNH -N4 lNO -Nx lN2 (17.8)
In a simplified version of analysis, uptake and return from
biomass is not included The effects of the biogeochemical
cycle on nitrogen will be explored in a subsequent part of the
design process The three mass balances then become linked,
and the tank equations are:
(17.14)
Equation 17.12 is a direct analog of Equation 17.7 for an unspecified generic pollutant Equations 17.13 and 17.14 contain extra production terms from ammonification in the ammonia balance—and nitrification in the oxidized nitrogen balance The three must be solved sequentially—Equation 17.12 followed by Equations 17.13 and 17.14
D ESIGN P ARAMETERS : S OURCES OF I NFORMATION
The P-k-C* design model is the basis for this sizing analysis;
it is therefore necessary to select values of these three eters for all pollutants of concern
param-Background Concentrations
Wetland systems are dominated by plants (autotrophs), which act as primary producers of biomass However, wetlands also include communities of microbes (heterotrophs) and higher animals, which act as grazers and reduce plant biomass Most wetlands support more producers than consumers, resulting
in a net surplus of plant biomass This excess material is
TABLE 17.2 Phosphorus Budgets for a FWS Design Example Parameters
Note: This example is based on the water budget shown in Table 17.1 ; sequential tank-to-tank calculations are based
on Equation 17.6; the required input data are shown in bold; the shaded cells represent potential design targets.
Trang 5typically buried as peat or exported from the wetland (Mitsch
and Gosselink, 1993) The net export results in an internal
release of particulate and dissolved biomass to the water
col-umn, which is measured as nonzero levels of biochemical
oxygen demand (BOD), total suspended solids (TSS), total
nitrogen (TN), and TP These wetland background
con-centrations are typically denoted by the term C* Enriched
wetland ecosystems (such as those treating wastewater) are
likely to produce higher background concentrations than
oli-gotrophic wetlands These elevated background
concentra-tions are largely due to increased biomass cycling resulting
from the higher levels of nutrients and organic carbon in the
wastewater Even land-locked wetland basins, which only
receive water inputs through precipitation, will have nonzero
background concentrations
Consequently, many pollutants are not reduced to zero
in treatment wetlands—including BOD, TSS, organic
nitro-gen, and phosphorus However, it is important to distinguish
between artifacts of data fitting and real wetland processes
Short-circuiting can lead to high values of data-fit C* for
heavily loaded systems, but these high C* can be dealt with
by improving the hydraulics Independent of hydraulics, the
wetland can manufacture water-phase organics and solids,
and cycle nutrients into and out of the water body The
chap-ters of Part I contain estimates of the C*-values for the
com-mon pollutants, and many literature sources provide ranges of
background concentrations (U.S EPA, 1999; IWA Specialist
Group on Use of Macrophytes in Water Pollution Control,
2000; U.S EPA, 2000a; Wallace and Knight, 2006; Crites
et al., 2006) A summary is given in Table 17.3.
Some individual exotic chemicals are foreign to
typi-cal wetland environments and are not expected to exhibit
background concentrations Examples include halogenated
hydrocarbons and pesticides
Number of Tanks to Be Used in the Model
The performance of the wetland depends on the number
of tanks (TIS) selected—very strongly if the design is to
approach wetland background concentrations or high degrees
of removal (see Chapter 6) If a high degree of removal is required, it will necessitate a very large wetland with poor hydraulics, or a smaller wetland with good hydraulics Figure 17.2 illustrates this high degree of sensitivity in the
region of low P for large reductions This chart quantifies the
fact that a tiny fraction of the water following a fast circuit will carry enough unreacted material to the outlet to make 99% reduction almost impossible to achieve Low
short-P numbers represent flow patterns that, by virtue of either
fast forward mixing or velocity profiles with high-speed ments, carry fractions of unreacted material directly to the outlet
ele-The P-value is somewhat at the discretion of the designer
More cells and greater length-to-width ratios can increase the
P-value As an illustration of the design decision to be made,
consider a hypothetical case relative to Figure 17.2 Suppose the wetland is to achieve a 90% reduction It is possible to
consider a one-cell wetland, with a presumptive P 3 that
needs 84 m2/(m3/d) Or, the designer can opt for two cells in a
series, each with a presumptive P 3 that needs 68 m2/(m3/d) The question might be resolved based on the economics, i.e., does the cost savings of 20% area reduction outweigh the added cost of the divider berm and structures? This illus-tration carries a zero background concentration, but the concepts are applicable to any pollutant, provided the reduc-tion fraction to background is used instead of percentage removal
It should be remembered that the designer can control
the N-value for the wetland (inert tracer tanks in series) but cannot entirely control the P-value Pollutants that are mix-
tures, which may undergo weathering in the wetland, act to
reduce the applicable P-value Table 6.3 provides some
guid-ance on the apparent P-values to be selected relative to tracer
N-values.
Rate Coefficients
In this initial, annualized analysis, the appropriate rate ficients are those (shown in the chapters of Part I) as the result of the fitting of annual data from existing wetlands Those are variable across wetlands and years, thus producing
coef-frequency distributions of the fitted k-values These are to be
found as follows:
Organic N Chapter 9, Table 9.11Ammonia N Chapter 9, Tables 9.17 and 9.20Total Kjeldahl
nitrogen (TKN) Chapter 9, Table 9.12Oxidized N Chapter 9, Table 9.23Total N Chapter 9, Table 9.14Total P Chapter 10, Table 10.11Fecal coliforms Chapter 12, Table 12.3Conspicuously absent from this list is the common constitu-ent TSS Some individual system data were presented in
Heavily Loaded
Note: In the case of fecal coliforms, lightly/heavily loaded refers
to animal use.
Trang 6632 Treatment Wetlands
Chapter 7 and analyzed for rate coefficients However,
incom-ing TSS is often reduced rather quickly, and wetland-effluent
TSS results from a balance of generation and resuspension in
the FWS wetland The removal rate coefficients that pertain
to the inlet region of the wetland are often quite high, ≈10 m/d
(3,650 m/yr), as shown in Figure 7.8 Colloidal materials are
an exception to this generality The design recommendation
suggested here is the use of a high-rate coefficient for TSS
(perhaps 200 m/yr), unless the design-limiting bottleneck
happens to be TSS In that event, it is strongly suggested that
settling tests be conducted on the candidate wetland influent
waters
The frequency distributions of the reference tables are
generally quite broad It is up to the designer to narrow the
selection for a given application, either by choosing the
pre-ferred degree of risk (blind to modifying factors), or by
delv-ing further into the details of existdelv-ing wetland data sets, and
to narrow the selection to wetlands closest to the intended
application in terms of operating conditions Regrettably,
there is no modern, published, all-inclusive database to which
to turn The reader is cautioned that older databases such as
the NADB (Knight et al., 1993) and the 1994 Danish
data-base (in Kadlec and Knight, 1996) have been superseded
Also, old databases are uneven in the quality and quantity of
the data presented There are numerous examples of
misin-terpretation in such databases, and it is concluded that their
use as a sole source of narrowing the information field is
dan-gerous Because there are now so many treatment wetlands, it
is not feasible to provide detailed data In this book, the
com-promise is to provide analysis, references, and the generic list
of sources used herein (see Appendix A)
D ESIGN S IZING G OALS : L OAD R EDUCTION
VERSUS C ONCENTRATION R EDUCTION
A key feature of treatment wetlands is the ability to design
or manage the system for either concentration reduction or
for mass removal, but only one at the expense of the other (Trepel and Palmeri, 2002) Wetland performance, as mod-eled previously, follows the rule of mass action: the removal rate of a pollutant is greater at higher pollutant concentra-tions in the water The first-order model assumes a (nearly) direct proportionality: doubling the concentration doubles the removal rate As a result of this observed behavior, removal rates decrease as water passes through the treatment wet-land, and pollutant concentrations are reduced (Figure 17.3) However, the actual mass of the pollutant that is removed increases with increasing hydraulic loading Thus, increas-ing hydraulic loads result in more kilograms removed, but at the expense of higher effluent concentrations This trade-off between removal efficiency and load reduction is a key feature
of wetland design for nutrient control These may be
quanti-fied via the first-order model A simple version for C* 0 and no water loss is
¦¥
³µ´
condi-If the output load of a pollutant is to be held below some regulatory limit, then that has the same general effect as specifying an outlet concentration However, because the load of a pollutant in the wetland outflow is usually taken to
FIGURE 17.2 The effect of the number of tanks on the area required for different degrees of removal The calculations are for k 15 m/yr
and C* 0.
10 100 1,000 10,000 100,000
Trang 7be that in the surface water discharge, any reduction in flow
through the wetland assists in providing lower output loads
as well as higher load reductions
All three of the potential design goals (concentration out,
load out, load reduction) may be sensible, depending on the
pollutant in question These are marked as shaded cells in
the example in Table 17.2 For instance, a low required outlet
concentration can be of use in preventing ammonia toxicity
in receiving waters But if there is a load allocation, as might
be the case for a discharge contributing to the total
maxi-mum daily load (TMDL) for an impaired water body, then
the mass of the contaminant is of more direct interest Lastly,
if there is a desire to maximize the benefits of a given
wet-land footprint, then the goal should be to dissipate or retain
the maximum amount of pollutant in the wetland
Because it is easy to confuse these potentially conflicting
goals, it is recommended that the designer clearly identify
and state the purpose of the design
17.2 AREA COMPUTATIONS
At this point in the development of constructed wetland
tech-nology, it would be disingenuous to provide overly simplistic
design-calculation procedures But it is also a mistake to think
that adding more factors that may play a significant role in
perfor-mance lends more accuracy or precision to design predictions
GOAL SEEKING: DETERMINATION
OF THE REQUIRED WETLAND AREA
The fundamental and straightforward technique for
deter-mining the area is to adjust that area until the specified
crite-rion is met That is easy if the calculations have been set up
on a spreadsheet; the area can then be sequentially and
man-ually changed by the user until the criterion is met, or
auto-matic searches may be invoked, such as the Solver™ routine
in Microsoft Excel™ The hypothetical phosphorus example
is continued to illustrate this process
Concentration Criterion
A common criterion for phosphorus in the United States is for monthly means to be less than 1.0 mg/L Realistically, the project owner would not want to encounter exceed-ances very often For the example, choose the compliance frequency to be 90% From Table 10.13, the multiplier to contain exceedance at that frequency is 1.94 Therefore, the design target is adjusted downward to 1.00/1.94 0.52 mg/L, which becomes the value to be achieved as the wetland area
is varied
In just three manual iterations, the starting guess of 24
ha (Co 0.62 mg/L, Table 17.2) is changed to 27.6 ha (Co0.52 mg/L) The same result may be obtained using Solver™,which provides the answer in an essentially instantaneous search from any plausible starting condition
The exceedance containment multipliers for common constituents may be found as follows:
Organic N Chapter 9, Table 9.11Ammonia N Chapter 9, Table 9.21Oxidized N Chapter 9, Table 9.25Total N Chapter 9, Table 9.16Total P Chapter 10, Table 10.13Fecal coliforms Chapter 12, Table 12.4(TKN is not in this list because it is not normally regulated.)
Maximum Load Criterion
The same philosophy of regulation might lead to an annual load limitation on the effluent from the system An outlet con-centration of 1.0 mg/L at a flow rate of 5,000 m3/d (inflow rate) implies a maximum annual load of 1,825 kgP/yr leaving the wetland (50% load reduction) A search for the wetland area leads to a value of 10.1 ha This is very much lower than that for the concentration goal for two reasons First, the exceed-ance factor is not in play because of the annual character
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95
Hydraulic Loading, HLR (m/yr)
0 50 100 150 200 250 300
2 · yr)
Concentration Reduction Load Removal
FIGURE 17.3 Concentration reduction and load reduction as a function of hydraulic load for a hypothetical nitrate treatment wetland
Parameters: Ci 10 mg/L, k 35 m/yr, C* 0, P 4.
Trang 8634 Treatment Wetlands
of the load limit Secondly, credit is built into the calculation
for the loss of water to ET and for wetland infiltration.
M INIMUM L OAD R EDUCTION C RITERION
A slightly different regulatory philosophy requires a minimum
load reduction For instance, some wetland systems in South
Florida require a minimum of 75% phosphorus load reduction
A search for the wetland area leads to a value of 19.8 ha
M ULTIPLE C OMPOUNDS OF C ONCERN
The projected outlet concentrations of all constituents of
interest are calculated via the preceding Equation 17.7 (or
Equations 17.12–17.14 in the case of nitrogen) All computed
outgoing concentrations and loads vary with the selected
wetland area Area is adjusted until the most stringent
cri-terion is met Criteria often include outlet concentration
specifications, each with an associated allowable frequency
of exceedance But in other cases, outlet pollutant loads may
be specified (or load reduction) Loads are easily calculated
using the outlet concentrations and flows from the last unit
If the contaminants are considered singly, then a last step
remains: all performances are calculated on the controlling
(maximum required) wetland area
As an example of multiple contaminants, the previous
phosphorus illustration, along with the additional
require-ments to also reduce BOD and total nitrogen, is continued
BOD enters the wetland at 30 mg/L, and total nitrogen, at 30
mg/L The value of C* is chosen to be 2 mg/L for BOD, and
shown for BOD and TN in FWS systems in Tables 8.2 and
9.14, i.e., kBOD 33 m/yr and kTN 13 m/yr It is assumed
that exceedances must be contained at the 90th percentile
The multipliers are 1.56 for BOD5 (Table 8.6) and 1.55 for
TN (Table 9.16)
The calculations of the required areas for each of the
three contaminants are shown in Table 17.4 The largest area
is needed for the reduction of total nitrogen—40 ha for the
5,000-m3/d flow When that area is applied to the calculation
of performance for BOD5 and TP, those pollutants are reduced more than necessary (Table 17.5)
This concludes the preliminary calculation of the required wetland area It may seem that there are no further steps needed, but in fact there is no guarantee that these pre-liminary calculations fit into reasonable, known patterns of wetland behavior It is critical that the bounds of plausible biogeochemical cycles are not exceeded, that the required ancillary chemicals (oxygen, carbon) are present in ample supply, and that the forecasted results are reasonable com-pared to known performance data Further, the seasonality of the system has yet to be investigated via forecasting
17.3 CHECKING THE BIOGEOCHEMICAL CYCLES
In this phase of design, vegetation in the prospective land and its role in nutrient processing is brought into the picture The rate coefficient-based analysis has provided first estimates of the quantities of materials entering and leaving the system, but there has been no allocation of the removals
wet-to the various processes that comprise the entire ecosystem function It is not feasible to go too far in breaking down processes because the knowledge base does not support great detail Here, the processing of carbon, nitrogen, and phos-phorus are examined via the mass balances used in ecosys-tem analysis in Part I (see Chapter 9, Figure 9.14)
In the analysis that follows, two points are important First, the analysis is based on estimates of what the eco-system will be like Such estimates cannot be precise, and, consequently, the analysis is “order-of-magnitude” only The intent is to gain some insight into the relative importance of wetland processes that will likely be operating if the proj-ect is built Second, the analysis is for an annual period, and hence there remains the issue of seasonality Seasonal analy-sis proceeds more readily if we can first establish whether the wetland should be viewed as an agronomic system or a microbial system
Trang 9C, N, AND P CYCLES
The pollutant removals simplistically described in the
pre-ceding section take no account of wetland functions; they are
based on purely empirical k-values and outlet concentration
data It is therefore prudent to examine the empirical
fore-casts and to ascertain whether they comply with an estimated
set of wetland processes Of particular interest are the
car-bon, nitrogen, and phosphorus cycles
The carbon cycle involves the growth, death, and
decom-position of biological materials, including animals, plants,
algae, and microbes For many wetlands, the standing crop
of these organic materials is relatively constant throughout
the year, but the proportions of living and dead may vary
considerably, as may the physical location (i.e., standing dead
or litter) Further, the speed of cycling varies with the nature
of the material and the time of the year (see Chapter 3) Fine
detritus from microbes cycles rapidly, whereas the
decompo-sition of some woody plant parts may take years However,
the important feature of the carbon cycle is the amount of
material that does not decompose, for it is this residual that
accretes in the ecosystem and forms storage for many
pollut-ants, including phosphorus This storage is relatively
perma-nent under appropriate hydroperiod conditions
An approximate assessment of the implied impacts of
the carbon cycle can be made on the basis of two
numeri-cal characteristics: the speed of the cycle in grams of dry
material per square meter per year, and the fraction of the
cycled material that does not decompose The speed of the
cycle may also be characterized by the standing crop, in
g/m2, plus a turnover rate, in number of times per year The
recycled organic fraction contains carbon that is a source of
support for denitrification and other heterotrophic processes
The burial fraction leads to sediment buildup and storage of
nitrogen, phosphorus, and other trace contaminants that
par-tition to organics Typical values for the vegetative standing
crop, turnover time, speed, and burial fraction are given in
Table 17.6
In general, the algal and microbial standing phytomass
is small compared to the vegetative phytomass However,
turnover times are also small, so the annualized rate of
uptake and burial for this component of the phytomass may
be estimated to be 50–100% of the vegetative annual rates
Simply stated, the amounts of N and P processed by the big
green biomass are not very much larger than those processed
by the nearly invisible microbes and algae This nondisparity
has been characterized as the “buckets and teacups” analogy
set forth by Richardson et al (1986).
The term nutrient poor would reflect very low nutrient
status, with TP < 20 µg/L and NH4-N 0.2 mg/L
Nutrient-moderate wetlands would have TP < 200 µg/L, with NH4
-N < 1.0 mg/L -Nutrient-rich wetlands would have TP ≈ 1.0
mg/L, with NH4-N ≈ 5.0 mg/L Very-nutrient-rich systems
would have TP 5.0 mg/L, with NH4-N 10.0 mg/L These
definitions do not correspond to the equivalents for aquatic
water bodies, where the dominant vegetation is plankton In
the treatment wetland context, bacterial and algal materials
are of comparable importance with above- and belowground macrophytic vegetation
The magnitude of the biogeochemical cycle increases with increasing nutrient availability—up to some presumptive limit enforced by availability of space and sunlight This fer-tilizer response is not well-quantified for treatment wetlands and, therefore, cannot be used directly in design However, rough estimates are of value in assessing the potential impor-tance of the biogeochemical cycle—particularly to check that the empirical design calculations do not imply unreasonable ecosystem functions
One technique for making such checks is to graphically link a presumed cycle to the mass balance calculations avail-able from the preliminary sizing step The biogeochemistry
check, thus, is implemented via linked ecosystem mass
bal-ances, one each for C, N, and P These do not replace, nor
can they substitute, the water column mass balances used in
k-rate removal calculations In an annualized mass balance
storage calculation, the following equations may be used:
wherebiomass burial, g/m dbiomass deco
2
B D
biomass growth, g/m d
2 2
The Carbon Cycle
The nomenclature for biomass processes in treatment lands is a bit confusing The growth, death, and decomposi-tion processes are referred to as part of the wetland carbon cycle, but more than carbon is involved However, most veg-etation and other wetland organisms are about 40% carbon;
wet-so, either dry biomass or carbon serves to track the amount
of the material involved Carbon itself is withdrawn from atmospheric sources as carbon dioxide for photosynthesis Likewise, it is returned to the atmosphere as methane from anaerobic mechanisms, or carbon dioxide from oxidative processes (respiration included)
The ability to estimate nutrient cycling rests upon our knowledge of the biomass pools in the wetlands and their changes Guidelines are shown in Table 17.6 According to Equations 17.17–17.19, on an annual basis, the important esti-mation quantities are
necromass biomass times turnover per year)
Annual burial fraction (undecomposable residual
fraction)
Trang 10636 Treatment Wetlands
An assumption is made that the nutrients taken up, but not
buried as accretion, are returned to the water column of the
FWS wetland For nitrogen, this is the maximum estimate, as
microbial processes in abovewater tissues can transfer
nitro-gen to the atmosphere without entering the water These
phy-tomass quantities, together with phyphy-tomass nutrient content
(percentage or mg/kg), allow checks on the empirical removal
calculations
For purposes of design, for order-of-magnitude checks
on the calculated nutrient removals, the total growth rate and
burial fraction are assumed based on the strength of the water
to be treated This provides a rough annual estimate of the
biomass cycle (Figure 17.4) Note that the magnitude of this
cycle and the nutrient contents are a function of the degree of fertilization of the wetland (see Chapter 3)
The wetland carbon cycle is also critical to observe formance as it relates to sediment oxygen demand and to the carbon supply for denitrification The implied supply con-straints of this carbon cycle are examined in the constraint check section of this chapter
per-The Phosphorus Cycle
For phosphorus, the calculated removal is represented as a
large uptake (GX G)—in major part balanced by the return
of soluble phosphorus from tissue decomposition (DX D) For
TABLE 17.6
Estimates of Wetland Nutrient Cycling in Biomass
Nutrient Poor Nutrient Moderate Nutrient Rich Very Nutrient Rich Organic matter
Note: Bacterial and algal cycling are included in these values.
Source: For first two categories, data from Davis (1994) In Everglades: The Ecosystem and Its Restoration Davis
and Ogden (Eds.), St Lucie Press, Delray Beach, Florida, pp 357–378 For the second two, data from Kadlec (1997a)
Ecological Engineering 8(2): 145–172.
FIGURE 17.4 Estimated annual biomass cycle in a FWS treatment wetland for a rich nutrient condition Note that the standing stock and
turnover refers to above- and belowground material, and to macrophytes, algae, invertebrates, and microbes.
Standing stock: 3,000 g/m2 · yr
Turnovers per year: 3.0 Turnover rate: 9,000 g/m2 · yr
Burial fraction: 0.250 Bulk density: 0.100 g/cm3
Accretion: 2.25 cm/yr
Necromass
Soil Air
Trang 11a stable ecosystem past startup, the net phosphorus removal
associated with the k-rate calculation is assigned to accretion
Sorption and the building of additional biomass are no
lon-ger sinks for phosphorus (Kadlec, 1997a) Because the k-rate
calculation is independent of the biomass cycle calculation,
there is one degree of freedom, which is taken to be the
com-puted accretion fraction It is known through extensive data
from treatment wetlands that this percentage ranges from
≈500 to 5,000 mgP/dry kg, or from 0.05–0.5% dry weight
A somewhat narrower range is shown in Table 17.6 because
extremely nutrient-poor wetlands are uncommon in
treat-ment applications It is unlikely that higher removals can be
sustained via accretion The corresponding accretion rates
are 0.01–20 gP/m2·yr The values in Table 17.6 are provided
as an order-of-magnitude check point If a design is forecast
to exceed these approximate cycling, removal, and storage
values, then more detailed mass balances should be invoked
If it appears that the phosphorus removal calculated by a
k-rate exceeds the ecosystem capacity to store, then the k-value
should be adjusted downward
As a graphic illustration, the design example is
car-ried forward (Figure 17.5) Because the nutrient
concentra-tions are high (2 mg/L P and 20 mg/L TN), it is anticipated
that the nutrient-rich condition will prevail, as illustrated in
Figure 17.4 The biogeochemical cycle removes 27 gP/m2·yr
from the water column (9,000 gdw/m2·yr × 0.3% P), far more
than the loading to the wetland of 9.1 gP/m2·yr The k-rate
cal-culations indicate that 7.4 gP/m2·yr are removed, and, hence,
it is deduced that (27 − 7.4) 19.6 gP/m2·yr are returned to
the water from decomposition and leaching of the biomass
The removal to accretion is thus 7.4/27 28% of the biomass
uptake These uptakes and returns involve aboveground plant
parts (≈50%), belowground plant parts (≈15%), and microbes
and algae (≈35%) The 28% burial rate for phosphorus is
somewhat higher than the comparison value in Table 17.6 of 20% If phosphorus were the controlling substance for siz-ing, it would be advisable to adjust the rate coefficient down-ward from the value of 10 m/yr used in the design forecast But, the wetland is overdesigned for phosphorus reduction,
and, hence, it is probably not necessary to revise the k-rate
calculation
The Nitrogen Cycle
For nitrogen, a more complex situation occurs as a result of the multiple speciation of water column nitrogen The details of nitrogen mass balancing have been presented in Part I, Chap-ter 9 The water column contains organic, ammonium, and nitrate nitrogen Their interconversions are computed from
the empirical k-rates The biogeochemical cycle is linked in
a manner analogous to phosphorus, but with abstraction from both the ammonium and nitrate pools in the water, and return from both the ammonium and organic pools in the water This allocation recognizes a split of plant uptake between ammo-nium and nitrate (Martin and Reddy, 1997) and the fact that decomposition processes produce organic nitrogen The nitro-gen content in accreting sediments is known from extensive
data from treatment wetlands to range from ≈1.0–2.5% dry
weight (Table 17.6) A lower value would be associated with nutrient-poor wetlands, a higher with nutrient-rich systems
Again, because the k-rate calculations are independent of the
cycle calculation, there is one degree of freedom, which for nitrogen is taken to be an assumed percentage of the cycled nitrogen that is buried in accreting sediments A nitrogen deficit may be assumed to be supplied by fixation, a process known to occur in nitrogen-deficient wetland environments
FIGURE 17.5 Estimated annual phosphorus cycle in a FWS treatment wetland for a nutrient-rich condition Flows, concentrations, and
loadings leaving the wetland are from k-rate forecasts The cycle turnover and tissue-phosphorus concentrations are presumptive The
frac-tion of phosphorus buried as accrefrac-tion is calculated by mass balance.
Total Phosphorus
in Water
Litter Live
Trang 12638 Treatment Wetlands
An illustration of the use of the nitrogen cycle and
inter-conversions to confirm the design k-rate calculations is shown
in Figure 17.6 The previous illustrative example is continued,
but for simplicity, the details of the k-rate calculations for the
various nitrogen species are not shown here As indicated in
Figure 17.6, the incoming nitrogen is presumed to be mostly
organic (9 mg/L) and ammonia (10 mg/L), comprising nearly
all of the 20 mg/L of TN The nitrogen loading to the wetland
is 91 gN/m2·yr, which is a low loading that places the system
in the category of an agronomic system (see Chapter 9) It is
therefore expected that the biogeochemical cycling of
nitro-gen will play an important role in the overall reduction, but
not to the exclusion of microbial processes
Once the size of the biomass cycle has been selected,
together with the phytomass nutrient content, mass balances
fix all the nitrogen fluxes for the specified inflows and
out-flows For this proposed design example, the cycling of
bio-mass nitrogen is very important The required nitrogen to
build the annually cycled biomass is 180 gN/m2·yr, which
is just about double the amount of nitrogen supplied in the
wastewater (Figure 17.6) However, there is no concern that
the plants will starve, because there is a correspondingly
large return flux of nitrogen from leaching and
decomposi-tion of necromass It is again necessary to keep in mind that
these uptakes and returns involve aboveground and
below-ground plant parts as well as microbes and algae
The ultimate fate of removed nitrogen in the example
is apportioned to accretion (56%), denitrification (21%), and
seepage (23%) Interestingly, this does not mean that there are
only small amounts of nitrification occurring, because about two thirds of the incoming nitrogen load winds up being nitrified (61.7 out of 91.3 gN/m2 yr, Figure 17.6) because of leakage and a small amount of biomass uptake The question then arises as to whether there is sufficient oxygen supply to support the nitrification implied by this mass balance This implied supply is evaluated in the next section
17.4 CHEMICAL SUPPLY CONSTRAINTS
Traditional chemistry assumptions indicate a requirement for carbon to support heterotrophic denitrification and oxygen to support nitrification
Table 17.7 lists some of the more important chemical and biological constraints on wetland processes The top block
of information shows that the carbon balance, and, hence, the implied biochemical oxygen demand (BOD), is due to removal of incoming BOD and to the carbon formed by the biogeochemical cycle Denitrification requires 4.0 g of chem-ical oxygen demand (COD) to reduce 1 g of nitrate nitrogen (U.S EPA, 1993b; Crites and Tchobanoglous, 1998) Decom-posing biomass is far more important than added BOD in the water in many instances However, some moderate fraction
of the biomass decomposition takes place in air, thus ing the available carbon for denitrification
reduc-The second block concerns nitrification, for which there are associated oxygen and alkalinity requirements An oxy-gen equivalent is retrieved as the result of denitrification (third block, Table 17.7), as well as some of the required
FIGURE 17.6 Estimated annual nitrogen cycle in a FWS treatment wetland for a nutrient-rich condition Flows, concentrations, and
load-ings leaving the wetland are from k-rate forecasts The cycle turnover and tissue–N concentrations are presumptive The fraction of biomass
nitrogen buried as accretion is assumed to be 25%.
Denitrification
Uptake Uptake
Trang 13alkalinity for nitrification The carbon produced in the
wet-land supplies some or all that is necessary for denitrification
(fourth block, Table 17.7) The accretion process implies a
rate of sediment buildup determined from the sediment bulk
density Finally, the possibility of sulfur-driven
denitrifica-tion carries a demand for sulfide-sulfur
These constraints are critical to design because wetland
chemical processes cannot proceed without the necessary
ancillary compounds Nowhere is this more apparent than in
the need for oxygen to drive ammonia removal routes
There-fore, if inadequate supplies of ancillary chemicals are
fore-cast, rate constants and loadings must be reduced until the
constraints are met Alternatively, additional supplies may be
introduced into the wetland This may require costly
supple-ments, such as the addition of methanol to fuel denitrification
(Gersberg et al., 1984) However, sometimes rearrangements
of flows can resolve the supply problem, such as the feed-
forward of high BOD unpretreated influent for a carbon
sup-plement for denitrification (Burgoon, 2001)
OXYGEN SUPPLY
The various oxygen requirements for the example design are
calculated (estimated) in Table 17.8 Removal of BOD (0.35
gO/m2·d) and nitrification (0.73 gO/m2·d) appears to exert
only a small demand, which should easily be supplied by
atmospheric reaeration The decomposition of the generated
necromass would consume something like 10 gO/m2·d, but
that decomposition is in part due to anaerobic processes and,
in part, occurs above the water as standing dead materials
oxidize Another part of oxidation may involve root tion, which comprises plant oxygen transfer Therefore, it is difficult to attach great significance to the apparent need for large amounts of oxygen for necromass oxidation
of solid residuals is an important factor The implied rate of sediment buildup is 2.3 cm/yr, which is comparable to the rates observed in operating wetlands (Kadlec, 1997a)
I NTERSYSTEM P ERFORMANCE C HECKS
The question addressed next is, how does the proposed design compare with results from existing wetlands for which there
is operating data? The annual performance period is retained for this phase of investigation
The intersystem loading chart for phosphorus (ure 17.7) shows that the overall scatter follows an increasing trend of outlet concentrations with increasing loading How-ever, in design, the loading variable is usually restricted to
Fig-a fixed inlet concentrFig-ation, whereFig-as the hydrFig-aulic loFig-ading is variable in response to different choices of the wetland area Therefore, in any particular design, only a subset of the larger loading group is relevant For phosphorus and most common pollutants, a particular inlet concentration subset shows a more modest increasing trend than that of the whole set
A generic loading chart looks similar to the tual “cloud” indicated in Figure 17.8 The larger data group encompasses all systems for all inlet concentrations, whereas each subgroup at a specific range of inlet concentrations occupies a smaller group The left side of either data cloud represents less efficient systems, and hence these are proto-types of low risk for the design The right side represents more efficient systems, a riskier assumption Any perfor-mance calculation is represented by a single point on this plot and, therefore, may be compared to the intersystem data scatter on this chart
concep-The loading graphs that allow intersystem comparisons for common constituents may be found as follows:
Organic N Chapter 9, Figure 9.17Ammonia N Chapter 9, Figure 9.37
Oxidized N Chapter 9, Figure 9.51
Fecal coliforms Chapter 12, Figure 12.11
Supply and Demand Constraints
Nitrate-N equivalent of BOD
removed
COD (BOD) SOD equivalent of decomposing
biomass
Max oxygen required for BOD
Alkalinity produced by
denitrification