Môc lôc VRAMP – CONTRACT PACKAGE RAP/CP6 7 – MAINTENANCE OF NH6 FROM KM78÷KM98 IN HOA BINH CLEARING AND GRUBBING TABLE OF CONTENTS CHAPTER I PREPRATION WORKS I PREPARATION WORKS II ARRANGEMENT OF CONS[.]
Trang 1VRAMP – CONTRACT PACKAGE:RAP/CP6-7 – MAINTENANCE OF NH6 FROM KM78÷KM98 IN HOA BINH
CLEARING AND GRUBBING
Trang 2VRAMP – CONTRACT PACKAGE:RAP/CP6-7 – MAINTENANCE OF NH6 FROM KM78÷KM98 IN HOA BINH
TABLE OF CONTENTS CHAPTER I : PREPRATION WORKS
I PREPARATION WORKS
II ARRANGEMENT OF CONSTRUCTION SITE PLAN
III MOBILIZATION OF MANPOWERS AND CONSTRUCTION
EQUIPMENT
CHAPTER II: CLEARANCE ,GRUBBING
I PRESERVATION OF PROPERTY
II CLEARING AND GRUBBING
III DISPOSAL OF CLEARED MATERIAL
IV MAIN EQUIPMENTS
Trang 3VRAMP – CONTRACT PACKAGE:RAP/CP6-7 – MAINTENANCE OF NH6 FROM KM78÷KM98 IN HOA BINH
CHAPTER I : PREPRATION WORKS
I PREPARATION WORKS
1. Construction signs
The contractor shall arrange guards 24/24 hours, with installation of the project information signs that shows information about the project, size and content of signs, which are agreed by the Engineer and the Employer
2 Electricity supply
Contractor shall contact with local electricity company to purchase electricity and install the power stations in accordance with demand In case of electric power is not available for the construction, the contractor will use generators to ensure continuous construction At the construction site, the circuit breakers with cover for protection of electrical system will be installed and electric lines will be hung
on posts to contact with construction areas, and also safety ground wires shall be installed in accordance with current safety standards of electricity
3. Water supply:
Contractor shall contact to local water suppliers to ensure enough clean and standard water for construction and living in site camping, offices It is needed to build a number of small auxiliary tanks for construction services
4. Communication and information:
The contractor will fix telephones, fax machines at the Site management Board and at the construction groups to ensure continuous communication 24/24h with all the related parties
5 Fire fighting system :
To prevent and handle fire and explosion which may occurs, some fire extinguishers at the needed points shall be equipped to dry out fires Officials inspecting the fire shall be assigned every day
6 Prepare for construction materials
The Contractor shall make the planning scheme, making purchasing orders with quarries and sources of materials such as: soil, sand, stones, steel, cement, and asphalt
The Contractor will have material samples tested for the technical specifications
in accordance with design requirements, and submit the Engineer and they can only be used for the works when having been approved by the Engineer and the Employer
Contract Package is located within the city of Can Tho, located next to the Hau River is very convenient for collecting the material The material is expected to
Trang 4VRAMP – CONTRACT PACKAGE:RAP/CP6-7 – MAINTENANCE OF NH6 FROM KM78÷KM98 IN HOA BINH
7. Selection of working groups:
By studying the topographical surveys of the site, based on work quantity, based
on the ability to mobilize equipment and manpower, to facilitate the gathering of vehicles as well as equipment and materials materials, accelerating the construction schedule so as to meet the requirements of progress and quality of the work, the Contractor shall pick up some groups for construction as specified
in the Workforce Mobilization Plan
II ARRANGEMENT OF CONSTRUCTION SITE PLAN
The contractor will to establish the Site management Board for construction nearby Km6+000
The Executive Board will be organized right next to the road for ease of movement and execution
At the Site management Board, we shall arrange housing and accommodation for executive chief, staff, health services; housing for workers, guarding house; kitchen; toilets; warehouse for gathering materials, equipment; yards for materials, machinery, yard for casting structure; electrical and water systems for construction activities, etc
III MOBILIZATION OF MANPOWERS AND CONSTRUCTION EQUIPMENT.
1 Manpower:
The contractor will assign the key staff with corresponding professional qualifications, experience and good health to undertake the work
For technical workers, drivers, machine operators: the skilled, experienced construction labor with high productivity, consistent with work requirements to achieve effective highest quality as well as work progress will be assigned
For the unskilled workers: Take advantage of the existing force of the Contractor,
if in shortage, the Contractor will hire additional employees of the locality to ensure and create jobs for local workforce seasonally
2 Construction equipment and machineries
The contractor shall arrange the construction equipment and machinery with good quality for project implementation
All kinds of construction equipment have been tested and registered for licensing activities by relevant agency When mobilized for the project must be approved
by the Engineer
Use of construction equipment with the best performance, ensure high productivity, good quality, low cost, and mitigate the hard work for the employees
Trang 5VRAMP – CONTRACT PACKAGE:RAP/CP6-7 – MAINTENANCE OF NH6 FROM KM78÷KM98 IN HOA BINH
Chain method for construction will be applied based on characteristics of the construction, construction technology, construction schedule, volume and other conditions
Regular and timely adjust the workforce of equipments and labor in order to ensure consistency, balance and facilitate the application of advanced construction technology
Constantly improve the management level, technical level and repair and well periodic maintenance of construction equipment and implement
Construction equipment and materials for construction are organized by centralized management and stability in the construction teams, as well as highly specialized
When management and use of materials, construction equipment (including: using, engineering maintenance, maintenance, transportation) must comply with the technical documentation of manufacturers
Assignment of drivers and construction machine operators must match with trained professions and worker levels as in accordance with the regulations for type of vehicles, construction machine specifically
The vehicles, construction machines put into operation must ensure the technical reliability and labor safety For these vehicles, construction machines must be registered for safety, before being put into execution, must fulfill the registration inspection under the provisions of the competent authorities of
The technical maintenance will be responsible by specialized team
Trang 6VRAMP – CONTRACT PACKAGE:RAP/CP6-7 – MAINTENANCE OF NH6 FROM KM78÷KM98 IN HOA BINH
CHAPTER II: CLEARANCE, GRUBBING
I Preservation of Property
Existing highways, improvements, facilities, adjacent property, utilities, services, and trees and plants designated for preservation shall be protected from injury or damage
In order to reduce the risk of erosion no topsoil shall be removed from the areas outside the limits of earthworks Any topsoil outside these limits, which is inadvertently removed during clearing and grubbing operations or otherwise, shall immediately be replaced by the Contractor at its own expense
Trees outside the construction width but within the proposed right-of-way having
a trunk girth of more than 450 mm at a point 600 mm above the ground shall not
be cut down without the prior approval of the Project Manager Those trees that are not to be removed shall be protected from injury or damage resulting from Contractor's operations
II. Clearing and Grubbing
Setting out and staking of each cross section as the approved construction method statement, mark the locations, limiting the areas to clear trees, cut grasses, excavate roots of trees, remove away debris and then submit the Engineer for approval before conducting the next work
The clearing and grubbing shall consist of clearing the designated areas of all trees, down timber, snags, vegetation, rubbish and objectionable material and shall include grubbing stumps and roots and disposing of all material resulting from the clearing or grubbing It shall also include the demolition removal and disposal of structures that obtrude into or encroach upon or obstruct the work, except where provided for otherwise
Also included in this work shall be the removal of loose pavement material, road signs, right-of-way markers, kilometre stones, guide posts and all other incidentals within the limits of construction
Using the measures to ensure effective safety and warnings for the areas of construction and arrange lights at night if necessary
Any debris shall be removed or buried in the right places accepted by the Engineer and the Employer within the range of the project and filled up at least 30cm above to create the shape and visible slope
The lower architecture of the old works (if no other requirements), which needs to
be destroyed up to the natural stream bottom, the other structures outside the range of natural water flow will be excavated to at least 50cm below the natural soil surface
Outside the limits of the earthworks, and under embankments trees and stumps
Trang 7VRAMP – CONTRACT PACKAGE:RAP/CP6-7 – MAINTENANCE OF NH6 FROM KM78÷KM98 IN HOA BINH
above ground level and not less than 450 mm below the embankment slopes and everything else to ground level
In cut areas clearing shall include the removal of stumps and roots exceeding 80
mm in diameter, to a depth of 450 mm below the finished surface except that in rounding areas at the tops of cut slopes they may be cut flush
Grubbing shall be carried out on the area of embankment foundations where the embankment height is less than 1.5 metres Grubbing shall consist of the removal and disposal of topsoil, stumps, roots, etc., to a depth of at 150 mm below ground
Where existing embankment is to be raised or widened, all vegetation and topsoil
shall similarly be completely removed from shoulders, slopes and ground under the widening before the operations of actual widening can be commenced
Where roadway excavations are to be made, and where ditches, streams and rivers, are to be diverted, all vegetation, roots stumps and the like shall be completely removed and placed outside the excavation area concerned before the excavation works can be commenced
The construction ensure that cleaning and grubbing will be carried out within the construction area, does not affect outside area
Besides the "excavation and relocation of works and obstacles" will comply with all the provisions of the technical instructions
III Disposal of Cleared Material
All other timber except timber to be used and all brush, stumps, roots, logs, and other refuse from the clearing and from the grubbing operations shall be burned, provided that, when permitted in writing by the authority having jurisdiction over the area through which the highway is being constructed, large stumps may be disposed of without burning at locations out of sight of the roadway
Piles of material for burning shall be placed either at or near the centre of the cleared area, or in adjacent open spaces where no damage to trees or other vegetation shall occur
Should the burning precede the construction operations, the material piles may
be placed in the centre of the right of way; otherwise the material piles shall be placed in the most convenient location at the side of the right of way and beyond slope line where they may be burned without damage to the surrounding trees or adjacent property All burning shall be done in conformance with regulations and
at such times and in such manner as to prevent the fire from spreading to areas adjoining the right of way
All fences, buildings, structures, and encumbrances of any character, except those to be removed by others, upon or within the limits of the right of way, shall
Trang 8VRAMP – CONTRACT PACKAGE:RAP/CP6-7 – MAINTENANCE OF NH6 FROM KM78÷KM98 IN HOA BINH
otherwise disposed of as indicated on the drawings or as directed by the Project Manager
IV Main Equipments:
Main equipments include:
Survey Equipments:
- And full sets of test devices