Trang 2TABLE OF CONTENT
1 INTRODUCTION 4
1.1 Purpose of Project 4
1.2 Project Description 4
2 PROJECT MANAGEMENT 4
2.1 Project Management Plan(PMP) 4
2.2 Project Management Objectives/Targets 5
3 PROJECT CONSTRUCTION SCHEDULE 5
3.1 Project Construction Schedule 5
4 PROJECT ORGANISATION AND RESPONSIBILITIES/AUTHORITIES 5
4.1 Project Organization / Quality Control Organization. 5
4.2 Responsibility and Authority 5
4.2.1 Project Manager 5
4.2.2 Deputy Project Manager No1: 6
4.2.3 Deputy Project Manager No2: 6
4.2.4 Deputy Project Manager No3: 7
4.2.5 Construction Manager 7
4.2.6 Project Quality Assurance Engineers 7
4.2.7 Environmental Officers 8
4.2.8 Safety Officer 8
4.2.9 Site Engineers 9
4.2.10 Mechanical/Electrical Engineer 9
4.2.11 Design Engineers (CAD Operators) 9
4.2.12 Quantity Surveyors 9
4.2.13 Material Engineers 10
4.2.14 Office Managers 10
4.2.15 Procurement Assistant 10
4.2.16 Accountants 10
4.2.17 General Affairs 10
4.2.18 Others Position 11
APPENDIX 4.1 12
Trang 3PROJECT MANAGEMENT TARGET
V I N A W A C O A N D P H U O N G T H A N H T R A N C O N S I N s h a l l c a r r y o u t t h e
required work in full compliance with the requirements stated in the Contract
o n q u a l i t y , e n v i r o n m e n t , h e a l t h & s a f e t y w i t h t h e f o l l o w i n g P r o j e c t Management Policies at all levels within Project site:
Quality Target:
“To produce high quality construction products consistent with the
requirements of the Employer as specified in the Contract”
Environmental Target:
“ T o i m p l e m e n t t h e w o r k i n f u l l c o m p l i a n c e w i t h V i e t n a m e s e
Standards, law, ordinance and other regulations on environment to
f u l f i l l t h e r e q u i r e m e n t s w i t h c o n t i n u o u s l y i m p r o v e t h e m i t i g a t i o n
method for any environmental impacts during construction period”
Health and Safety Target:
“ To promote safety culture and healthy environment on Project site
full compliance with Legal requirements”
JOIN OPERATION VINAWACO AND PHUONG THANH TRANCONSIN
shall ensure continuous improvement of the Project Management system.
Hanoi, May 2012
Trang 4
REPRESENTATIVE OF JOIN OPERATION
1 INTRODUCTION
1.1 Purpose of Project
The Project, North – South Expressway (HCMC– Dau Giay Section), was originally
configured as a section from the starting point of RR2 HCMC (KM4+000, that is the starting
point of viaduct) to the ending point of Dau Giay (KM54+982) with a total length of about
51km expressway
Due to demarcation of the component between East-West Highway project and the
Project, the section between KM0+000 and KM4+000 plus the Ring Road 2 interchage were
decided to be included into the Project
1.2 Project Description
1) Project Name: Package 7: Km 0+000 to Km 2+000
North South Expressway Construction Project ( Ho Chi Minh City-Dau Day Section) Loan No: VN10-P7
2) Employer: Vietnam Expressway Corporation
3) Location: Dong Nai province in Socialist Republic of Vietnam
4) Contract Period: 24 months
5) Scope of Work: Km0+000 to Km2+000
Bridge Work: Contruct ion of 2 bridge s: Muong Kenh bri dge, Ba Dai bri dge
with length total 616,2m
Road Work: C o n t r u c t i o n f r o m K m 0 + 0 0 0 t o K m 2 + 0 0 0 w i t h l e n g t h t o t a l :
1383,8m (included An Phu intersection)
2.1 Project Management Plan(PMP)
The Project shall follow the Corporate’s Integrated Management System(IMS-will be
submited w P henc rojecti l w t arry-out)r o I n9 ine Iith he equirements f SO 001:2000, SO 14001:1996 a O 1nd HSAST P a8001:1999.s e t P hef t roject lso hall stablish he MP or he
Trang 5additional i tems/areasf s a c or o tupervisionP w s t nds ontrol f his roject hich et he pecific
o p e r a t i o n a l p r o c e d u r e s , r e s o u r c e s , a c t i v i t i e s a n d r e s p o n s i b i l i t i e s r e l e v a n t t o t h i s
Project
P M P s h a l l b e r e v i e w e d w h e n e v e r n e c e s s a r y , t o e n s u r e e f f e c t i v e n e s s , c o n t i n u i n g
suitability and improvement
2.2 Project Management Objectives/Targets
J O I N O P E R A T I O N V I N A W A C O A N D P H U O N G T H A N H T R A N C O N S I N w i l l
e s t a b l i s h o b j e c t i v e s f o r t h i s P r o j e c t o n q u a l i t y , e n v i r o n m e n t , h e a l t h a n d s a f e t y i n
a c c o r d a n c e w i t h t h e P r o j e c t ’ s t a r g e t (w i l l b e s u b m i t e d a f t e r c a r r y - o u t P r o j e c t )
S i g n i f i c a n t e n v i r o n m e n t a l a s p e c t s / h e a l t h a n d s a f e t y h a z a r d s a r e c o n s i d e r e d i n t h e
setting of these objectives / targets Review of objectives by the Project Management,
if necessary shall be carried out but not less than the limitations stipulated in the local
Authorities requirements for this Project
3.1 Project Construction Schedule
The construction period for this Project shall be 24 months with the detailed schedule
as that refer to Technical Schedule 6
RESPONSIBILITIES/AUTHORITIES
4.1 Project Organization / Quality Control Organization.
Appendix 4 s t.1P howsS o hezation crojectfhartt k itepor herganiw wey ersonnel ho ill
l e a d t h e P r o j e c t M a n a g e m e n t i n t h e i n t e g r a t e d m a n a g e m e n t s y s t e m o f q u a l i t y ,
environmental, health and safety for this Project
4.2 Responsibility and Authority
4.2.1 Project Manager
The Project Manager shall be responsible for the management of this Project
He has the authority and responsibility for the engineering, scheduling, cost, industrial r celations,a ontracto e dministrationh a s n nvironmental, ealth nd afety matters of the Project He appoints qualified and suitable personnel together
w i t h e s s e n t i a l r e s o u r c e s t o e n s u r e t h e i m p l e m e n t a t i o n a n d c o n t r o l o f t h e Integrated Management System including the followings:
Trang 6 E n s u r e t h e a d m i n i s t r a t i o n a n d i m p l e m e n t a t i o n o f t h e I n t e g r a t e d
M a n a g e m e n t S y s t e m ( I M S ) i n c o m p l i a n c e t o t h e r e q u i r e m e n t s o f specifications, s and ltandards,egalr equirementsw f p o t hich orm art f he Contract
To develop and authorize the PMP in consultation with Project QEHS Manager
T o a p p r o v e s u b - c o n t r a c t o r s / s u p p l i e r s b a s e d o n e v a l u a t i o n o f t h e i r abilities to meet the specified requirements
To liaise with the Employer on matters concerning the management of the Contract and IMS
Approve promotion activities/ training programs for all staff including sub-contractors on Employer’s requirements
The Project Manager shall liaise with the QEHS Manager from Hanoi Head office on any deviation required
4.2.2 Deputy Project Manager No1:
The Deputy Project Manager shall assist/support the Project Manager’s duties
d e s c r i b e d a b o v e a n d m a i n l y a r e o n f i e l d s : B r i d g e a n d R o a d Construction/Traffic A M TssurenceP M w anager.a he roject anager ill ppointed
the Deputy Project Manager No1 to act on his behalf during his absence
4.2.3 Deputy Project Manager No2:
The Deputy Project Manager shall assist/support the Project Manager’s duties
d e s c r i b e d a b o v e a n d m a i n l y a r e o n f i e l d s : T e c h n i c a l / E c o n o m i c &
Planing/Quality Assurance/Environmental/Health & Safety Manager
- Special with his duty of Health & Safety Manager, he will be in-charge of the I MSi mplementedi t P H r n thisf roject.d e eviews he ollowing ocuments, prepares and controls the IMS for compliance with:
Contract Document
Authorities’ requirements & Standards
Relevant legislations His duties include:
I m i t a t e t h e P r o j e c t ’ s A s p e c t s a n d H a z a r d s A n a l y s i s f o r s e t t i n g t h e Project’s objectives and targets
C o m m u n i c a t e a n d o b t a i n i n f o r m a t i o n a f t e r d i s c u s s i o n w i t h P r o j e c t
Q u a l i t y A s s u r a n c e E n g i n e e r s , E n v i r o n m e n t a l O f f i c e r a n d S a f e t y Officer to establish the PMP
P r o p o s e / O b t a i n a p p r o v a l t o t h e T r a i n i n g P r o g r a m f r o m t h e Project Manager
Trang 7 Monitor and update IMS training program
Select, evaluate and control the Subcontractors/Suppliers 4.2.4 Deputy Project Manager No3:
The Deputy Project Manager shall assist/support the Project Manager’s duties
d e s c r i b e d a b o v e a n d m a i n l y a r e o n f i e l d s : A c c o u n t i n g a n d F i n a n c i a l Manager/Administration
4.2.5 Construction Manager
The C onstructionM o e s anagerh t r f acha a ection as he esponsibility nd uthority to:
Plan on the process including special construction method
Establish, prepare and implement the Project Quality Assurance Plan (PQAP)
Initiate a t ctionp t oo revento a n he ccurrencer f ny onconformities elating
to the product, process and the IMS
Receive report/feedback of problems from Project site
Initiate, recommend or advise solutions through designated channels
Verify the implementation of solutions
Control non-conforming issues until corrected
4.2.6 Project Quality Assurance Engineers
T h e P r o j e c t Q u a l i t y A s s u r a n c e E n g i n e e r i s a p p o i n t e d b y t h e P r o j e c t Manager/Project QEHS Manager, who has the responsibility and authority on
all aspects relating to the quality and quality control of the works including stoppage of the work which is not in compliance with the Contract He can instruct any removal of any or all non-conforming work placed/installed
His duties include:
Ensure quality non-conformance found on site corrected with records
Review for preventive measure from re-occurrence
Provide training if required
Verify purchased products and materials with records
A s s i s t i n t h e p r e p a r a t i o n o f P M P w i t h i d e n t i f i c a t i o n o f s p e c i a l construction process, if any
D e v e l o p a n d r e v i e w t h e s y s t e m f o r i d e n t i f i c a t i o n a n d t r a c e a b i l i t y o f materials or section of work and inspection and tests status
Provide the standard procedure for calibration of equipment and check
on the calibration test result
Assist in the preparation of PQAP with checks on the implementation
of PQAP
Trang 84.2.7 Environmental Officers
Environmental Officer shall be appointed to be in-charge of issues relating to environment w o i ithin b t Pr nfluencedH s p a y hist roject e hall rovide ssistance o the Deputy Project Manager No2 for the preparation and implementation of
IMS His duties shall include the followings:
I d e n t i f y e n v i r o n m e n t a l p a r a m e t e r m o n i t o r i n g r e q u i r e m e n t s w i t h methods
To establish emergency response plans
T o p ro mo t e a wa re ne ss o f th e r eq ui r em e n ts r el a t i ng t o e nv ir on m e nt a l issues/matters for this Project with training, briefings, meetings, etc
T o e s t a b l i s h a n d m a i n t a i n w i t h r e g u l a r r e v i e w t o g e t h e r w i t h P r o j e c t
Q E H S M a n a g e r o n t h e o b j e c t i v e s / t a r g e t s f o r r e p o r t t o t h e P r o j e c t Manager
T o c o n t r o l t h e r e q u i r e d m o n i t o r i n g w o r k s o f t h e n o m i n a t e d Subcontractor
To maintain and update list of applicable legal and other requirements
on environment
T o t a k e n e c e s s a r y a c t i o n f o r c o r r e c t i v e a n d p r e v e n t i v e a c t i o n s f o r environmental non-conformance whenever necessary
4.2.8 Safety Officer
S a f e t y O f f i c e r w i l l b e i n - c h a r g e o f a l l m a t t e r s c o n c e r n i n g h e a l t h a n d s a f e t y within this Project He shall provide assistance to the Deputy Project Manager
No2 for the preparation of the IMS His duties shall include the followings:
I d e n t i f y p a r a m e t e r m o n i t o r i n g r e q u i r e m e n t s c o n c e r n i n g h e a l t h a n d safety hazards with methods
Analyze c auseo a f f ccidentn a ort b t ecessarya c ction o e aken s orrective
a n d p r e v e n t i v e m e a s u r e s w i t h r e p o r t t o b e s u b m i t t e d t o t h e P r o j e c t Manager
To establish emergency response plans
T o p r o m o t e a w a r e n e s s o f t h e r e q u i r e m e n t s r e l a t i n g t o s a f e t y issues/matters for this Project with training, briefings, meetings, etc
T o e s t a b l i s h a n d m a i n t a i n w i t h r e g u l a r r e v i e w t o g e t h e r w i t h P r o j e c t
Q E H S M a n a g e r o n t h e o b j e c t i v e s / t a r g e t s f o r r e p o r t t o t h e P r o j e c t Manager
To ensure site activities conform to IMS
To r ecorda t n nd aake f aecessaryn ctionf o or ny on-conformance ound n site
Trang 9 To maintain and update list of applicable legal and other requirements
on safety
4.2.9 Site Engineers
The S Eite ngineersw r t t C ill eportM iot her onstruction anagers n heir espective section of work Each Site Engineer has the responsibility and authority:
T o e x e c u t e r e s p e c t i v e e n g i n e e r i n g w o r k o n s i t e i n a c c o r d a n c e t o relevant plans
T o t a k e t h e n e c e s s a r y a c t i o n t o p r e v e n t a n y o c c u r r e n c e o f non-conformances relating to the process or procedures in the IMS on
the Project site
To i dentifya r andp ecord r ny t troblems/issuesw o a elating o he orks r ny influence to others due to the works carried out on the Project site
T o d i s c u s s / r e c o m m e n d s o l u t i o n s t o C o n s t r u c t i o n M a n a g e r / P r o j e c t QEHS Manager
T o m on i t or /c o nt r ol / st op a ny w or ks of n on -c o nf or mi n g i ssue s/ m a t te r s until deficiency or unsatisfactory condition has been corrected
4.2.10 Mechanical/Electrical Engineer
T h e M e c h a n i c a l / E l e c t r i c a l E n g i n e e r ( M & E E n g i n e e r ) w i l l r e p o r t t o t h e
r e s p e c t i v e C o n s t r u c t i o n M a n a g e r f o r t h e m e c h a n i c a l / e l e c t r i c a l w o r k s H e i s responsible for maintenance and arrangement of machineries used for the site
works e verydayi o t c on t rderw e o arrya a ut hea orks fficiently nd ppropriately s directed by the Construction Manager
4.2.11 Design Engineers (CAD Operators)
The D esignE w ngineerr t t Q illA eport of dhe uality ssuranceManager or rafting works i t Pn hisT p roject w dhe s a reprovided bermanent E york mployer/esign
T h e E n g i n e e r w i t h s o m e d e t a i l i n g w o r k s r e q u i r e d f o r e x e c u t i o n o f t h e works
4.2.12 Quantity Surveyors
The Quantity Surveyor will report to the Quality Assurance Manager for the
w o r k s r e l a t i n g t o q u a n t i t i e s o f c o n s t r u c t i o n w o r k s T h e y w i l l p r e p a r e / c h e c k the quantities of construction work done necessary for
Monthly certificate by Employer/The Engineer for progress payment
Payment to subcontractors/suppliers 4.2.13 Material Engineers
Trang 10The Material E w illangineer tssistC he M onstructioni t w T anager n he ork heir duties involve the followings:
To check the materials to be used comply to the requirements in the Contract document or submission for the required work either by
a) tests carried out in laboratory b) check and confirm materials at the time of receiving
To prevent any occurrence of non-conformances of materials/works
T o i d e n t i f y , r e p o r t a n d r e c o r d a n y p r o b l e m s / i s s u e s r e l a t i n g t o t h e materials
C h e c k a n d u p d a t e s t a t u s o f m a t e r i a l c o n s u m p t i o n a n d q u a n t i t y i n storage on regular basis
4.2.14 Office Managers
Office Managers will report to the Project Manager/Deputy Project Managers
f o r t h e w o r k s r e l a t i n g t o a d m i n i s t r a t i o n , f i n a n c e a n d p r o c u r e m e n t m a t t e r s
Assistants/Accountants in this section of work
4.2.15 Procurement Assistant
T h i s P r o c u r e m e n t A s s i s t a n t i s r e s p o n s i b l e f o r t h e c o n t r o l o f p u r c h a s i n g materials for this Project with maintenance of the records to its latest status
The Procurement Assistant (or called Purchaser) shall provide the followings under the supervision of the Office Manager:
M a t e r i a l O r d e r S h e e t b a s e d o n t h e P u r c h a s e R e q u e s t w h i c h w a s approved by the Project Manager and records of these Order Sheets to
be kept by him/her
received d ocumentf a m or t nyw r aterialb P hats as eceived y roject’s taff
to be kept with the material certificate under his/her care
4.2.16 Accountants
T h e a c c o u n t a n t s w i l l a s s i s t t h e O f f i c e M a n a g e r f o r t h e w o r k s r e l a t i n g t o administration, finance Their duties include:
To check/prepare records/bills and arrange for payment to suppliers / subcontractors
To prepare/maintain records regarding the personnel management 4.2.17 General Affairs