5.3 University Place West Sub-basin The University Place West Sub-basin is located within the City of University Place and is bordered to the west by Puget Sound, to the north by 19th St
Trang 1Pierce County Public Works and Utilities – Sewer Utility
Unified Sewer Plan Update
Section 5
Existing Collection System
5.1 Wastewater Collection System for the Chambers Creek Basin
5.2 Conveyance System Backbone - Existing Interceptors & Force Mains
5.22 Metering Locations and Flow Monitoring
5.23 Collection System Operations & Maintenance
5.24 Infiltration and Inflow
5.27 Large On Site Sewer Systems (LOSS) Maintained By Pierce
Trang 2Section 5 – Existing Collection System
Section 5 documents the existing wastewater collection system of the Chambers Creek Regional Wastewater Treatment Plant (WWTP)
5.1 Wastewater Collection System for the Chambers Creek Basin
The Utility owns the collection facilities in Parkland, Spanaway, Frederickson, Graham, South Hill, the cities of University Place and Lakewood, and the City of DuPont The City of Tacoma and Town of Steilacoom own the collection facilities within their respective jurisdictions
5.1.1 Chambers Creek Conveyance System
The conveyance system has 58,960 (2009) connections and includes approximately 658 miles of public sewer and 172 miles of private sewer pipelines ranging in size between 8-inches (for local collection) and 84-inches in diameter (for the largest interceptor), with 15,964 manholes to access the sewer lines The system service area
is 117 square miles or 74,880 acres in total area The County’s Wastewater Utility also operates and maintains
95 pump stations with four new stations in design, and 825 residential grinder pumps in the Chambers Creek Basin (basin)
5.1.2 City of Tacoma – Western Slopes
The Western Slopes service area lies adjacent to the east shore of Tacoma Narrows and extends from North 26th Street in Tacoma to the City of University Place on the south and Pearl Street on the east The system service area is 1,804 acres in total area and drains northeasterly toward the Tacoma Narrows The area
formerly flowed to the now decommissioned Tacoma Western Slopes WWTP a primary wastewater treatment plant operated by the City of Tacoma Wastewater from this service area was transferred to the WWTP in 1990 with the construction of two pump stations and conveyance pipes The Western Slopes service area is pumped
to the Chambers Creek conveyance system by the South 27th Street and 19th and Grandview Pumping Station
5.1.3 City of University Place
The City of University Place is located east of Puget Sound, west of the City of Fircrest and 56th Street West, south of South 19th Street West and north of Chambers Creek The system service area is 5,323 acres in total area Portions of University Place were originally served by the City of Tacoma Western Slopes Treatment Plant and the Westside Sewer District In the 1970s two (2) Pierce County ULIDs, 70-1 and 76-1, incorporated much
of the remainder of University Place into the Pierce County sewer service area
In 1990 the City of Tacoma closed the Western Slopes Treatment Plant and transferred its service area flows to the WWTP for treatment In 1992, Pierce County assumed the Westside Sewer District, which served the northwestern portion of University Place
There are several pockets in University Place, approximately 980 residences, a total of 1800 developed and undeveloped properties without sanitary sewer service The largest pocket lies in the vicinity of the 67th Avenue West Interceptor south of Fircrest to Cirque Drive, between Alameda and Orchard Street The City of University Place has conducted feasibility studies to connect these remaining parcels to sanitary sewers
5.1.4 Town of Steilacoom
The Town of Steilacoom’s present wastewater service area encompasses nearly 1,850 acres, of which
approximately 1,050 acres is sewered The town entered into a 50-year sewage service and rate agreement with Pierce County in 1987 Pierce County provides treatment services; Steilacoom is responsible for collection and maintenance
Trang 3Section 5
Existing Collection System
5.1.5 City of Lakewood
The City of Lakewood, excluding the areas known as American Lake Gardens and Tillicum, is located within Utility Local Improvement District (ULID) 73-1, which is the core of the sewer service basin American Lake Gardens and Tillicum were originally intended to send flows to the Tatsolo Point WWTP on the Joint Base Lewis McChord military reserve American Lake Gardens and Tillicum, containing 968 single family and 1,124 multi-family homes will continue to be served by both individual and community on-site sewer systems until the City of Lakewood completes an extension to allow both Tillicum and American Lake Gardens to connect to the sewer system These flows are proposed to be directed to the Chambers Creek Regional Wastewater Plant in late 2011.The system service area is 11,041 acres in total area
5.1.6 DuPont - Northwest Landing
The City of DuPont is located in the southwest corner of the Basin and has contracted with Pierce County to provide sewer service to the Northwest Landing development (ULID 90-4) In October of 2000, the Northwest Landing Offsite Wastewater Facilities Project was completed and wastewater is now conveyed to the WWTP The Historic Village of DuPont was connected and flows began to be sent to the WWTP in 2008 Pierce County now provides for collection, transmission, and treatment for flows from the Northwest Landing Development (Villages I, II, III, IV, and V), Industry, Town Center, and the Historic Village of DuPont The system service area
is 3,727 acres in total area
5.1.7 Eastern Basin - Brookdale, Midland, Parkland, Spanaway, Graham, Frederickson, Cascadia,
and South Hill
The eastern portion of the Chambers Creek - Clover Creek Basin contains the largest part of the planning area The 1986 Sewerage General Plan Update defined the East Basin to include Midland, the drainage of Clover Creek from presently sewered areas of Parkland, Brookdale, and Spanaway, south to Rocky Ridge and east past Frederickson and Meridian Avenue (SR161)
In 1989, the Pierce County Council approved the inclusion of additional areas to the east of Meridian Avenue into the Chambers Creek - Clover Creek East Basin The South Hill Sewer District, in unincorporated Pierce County, was added to the Chambers Creek Regional WWTP system in 1996 The connection to the Chambers Creek Regional WWTP system is located at the end of the East Basin Interceptor The system service area is 58,965 acres in total area
Trang 45.2 Conveyance System Backbone - Existing Interceptors & Force Mains
Interceptors and force mains form the backbone of the conveyance system Pierce County typically installs interceptor lines 15” in diameter and larger and force mains 8” in diameter and larger These are the trunk and large branches of the system into which the wastewater from local collection systems flow
Existing interceptors, force mains, and pump stations for the WWTP sewer service basin are described in Tables 5.3-1 through 5.19-1 and illustrated in Figures 5.1-1 through 5.19-1
A complete inventory of the Utility’s sewer conveyance system may be found in USP Appendix K
Pipe diameter ranges signify that the size of the pipeline changes over the course of its length Each table and corresponding figure is broken down by sewer service sub-basin Figure 5.1 identifies the general location of each sub-basin
The sub basins include:
University Place West Sub-basin
University Place East Sub-basin
East Basin Sub-basin
Rainier Terrace Sub-basin
Hylebos Sub-basin
Brown’s Point Sub-basin
Trang 5!
Chambers Creek Regional WWTP
Tacoma Central WWTP
Cascadia
*Note: Pierce County Lake Tapps Service Area Removed per Resolution R-2001-189 (Transfer Agreement #01-1269 Dated 03/29/02)
Fox Island
McNeil
Island
Pierce/King Coun
ty B oun dary
Roy
Pacific Ruston
9 6
10
17 3
16
The map features are approximate and are intended only to provide an indication of said feature Additional areas that have not been mapped may be present This is not
a survey Orthophotos and other data may not align The County assumes no liability for variations ascertained by actual survey
ALL DATA IS EXPRESSLY PROVIDED
‘AS IS’ AND ‘WITH ALL FAULTS’
The County makes no warranty of fitness for
a particular purpose.
Pierce County Unified Sewer Plan
PIERCE COUNTY, WASHINGTON
Pierce County Sub-Basins/Service Areas
! Wastewater Treatment Plants
Other Service Area Tributary to Chambers Creek WWTPContract Service Area
Sewerage Sub-basin Area/Service AreasSub-Basin Name
1 University Place West
2 University Place East
11 Spanaway and Roy
Pierce County Sewer Service Area Tributary
to the C/O TacomaPotential Pierce County Service Area Currently Connected to Other WWTP
Trang 65.3 University Place West Sub-basin
The University Place West Sub-basin is located within the City of University Place and is bordered to the west
by Puget Sound, to the north by 19th Street West, to the south by Chambers Creek and to the east at
approximately Bridgeport Way The sub-basin is made up of the University Place North ULID 70-1, Soundview ULID 76-1, Westside Sewer District, numerous developer extensions, and flows transferred from the City of Tacoma’s Western Slope Sub-basin
Flows received from the City of Tacoma connect to the Chambers Creek Regional WWTP collection system at approximately 19th Street West and Grandview Drive The University Place West Sub-basin consists of
approximately 3,990 acres The size and linear footage of mains in this sub-basin is identified in the table below and is graphically represented in Figure 5.3-1
Table-5.3-1 University Place West Sub-basin Existing Conveyance System 1
Interceptor Pipelines
Facility Name Size (inches) Length (feet)
Current ADWF (MGD) 4
Tributary to the City of Tacoma collection system.
Chambers Creek Tunnel
The Chambers Creek Tunnel (Tunnel) is the primary transmission facility for the entire Chambers Creek
Regional WWTP sewer service basin Within the University Place West Sub-basin the Tunnel consists of 7,433
Trang 7Section 5
Existing Collection System
lineal feet of 72-inch gravity sewer line that starts at Manhole #12367 and ends just south of Chambers Creek Road and 75th Street West The Tunnel was constructed as part of the Lakewood/Parkland ULID 73-1 under the Chambers Creek Interceptor project in 1983/1984 A phased rehabilitation of the Tunnel system, beginning with portal installation, was begun in 2000-2001 with project completion planned for 2011
Day Island Trunk
The Day Island Trunk consists of 1,691 lineal feet of 15-inch gravity sewer It conveys flows from Day Island, located in the northwest section of the University Place West Sub-basin, to the Marina Pump Station located at South 19th Street West and Day Island Way This trunk line was constructed as part of the University Place North ULID 70-1 project in 1972/1973 A study has been funded to investigate how best to repair/replace this trunk line
Grandview Drive Interceptor
The Grandview Drive Interceptor consists of 9,600 lineal feet of 30-inch gravity sewer The interceptor, running along Grandview Drive from Heitman Way west to 64th Street West, transports flows from the Tacoma Western Slope Basin as well as flows from the western portion of University Place West Sub-basin These flows
discharge into the Chambers Creek Tunnel at the Drop Structure located at 64th Street West and Chambers Creek Road West The interceptor was constructed under the University Place North/Western Slope Turnaround project in 1988/1989
Sunset Drive Trunk
The Sunset Drive Trunk consists of 2,710 lineal feet of 15-inch gravity collector sewer and serves the north central portion of the sub-basin.The line discharges to the City of Tacoma at 19th Street West and Sunset Drive These flows eventually discharge to the Tacoma Western Slope pump station and flow back through the Grandview Drive interceptor The pipeline was constructed as part of the University Place North ULID 70-1 project in 1972/1973
Tacoma Western Slope Force Main
The Tacoma Western Slope Force Main consists of 9,835 lineal feet of 20 and 24-inch force main The force main runs south from Grandview Drive near 19th Street West to Grandview Drive and Heitman Way West in the University Place West Sub-basin It transports flows from the Tacoma Western Slope Sub-basin and the
northern part of the University Place West basin before discharging to the Grandview Drive Interceptor The force main was constructed as part of the University Place North/Western Slope Turnaround project in
1988/1989
Trang 8Grandview Drive Interceptor
Chambers Creek Tunnel
PS01
PS65
PS70 PS66 PS62
a survey Orthophotos and other data may not align The County assumes no liability for variations ascertained by actual survey
ALL DATA IS EXPRESSLY PROVIDED
‘AS IS’ AND ‘WITH ALL FAULTS’
The County makes no warranty of fitness for
a particular purpose.
Pierce County Unified Sewer Plan
PIERCE COUNTY, WASHINGTON University Place West Sub-Basin
DISCLAIMER
University Place West Sewerage Sub-basin Conveyance System
Date: December 2010
Figure 5.3-1
NNTS°
Municipal BoundaryState, Federal or County RouteWater Features
Sewerage Sub-basin Area
Gravity Collectors14" and smaller gravity sewersGravity Transmission Pipelines15" and greater gravity sewersTransmission Force Mains7" and smaller force mainsTransmission Force Mains8" and greater force mains
Private Sewer LinesTransmission Siphon Mains
Trang 9Section 5
Existing Collection System
5.4 University Place East Sub-basin
The University Place East Sub-basin consists of approximately 1,700 acres and is located within the City of University Place and is bordered to the west by Bridgeport Way, to the north by 27th Street West, to the south by Chambers Creek and to the east by Lakewood Drive and Orchard Streets The size and linear footage of mains
in this sub-basin are identified in the table below and is graphically represented in Figure 5.4-1
Table 5.4-1 University Place East Sub-basin Existing Conveyance System 1
Interceptor Pipelines
Facility Name Size (inches) Length (feet)
The 67th Avenue Interceptor consists of 7,608 lineal feet of 15 to 18-inch gravity sewer The interceptor begins
at the intersection of 65th Avenue West and Cirque Drive, travels north and west through residential streets and easements to 47th Street West and 67th Avenue West, and then parallels 67th Avenue West where it terminates
to the west of 38th Street West and 67th Avenue West The pipeline was constructed under the Stonewood developer extension in 1977/1978, the Roman Ridge developer extension in 1978, the Cirque Drive ULID 78-1 project in 1980/1981, and the 67th Avenue West Interceptor developer extension SWLE #151887
A portion of the interceptor was replaced in 1995 under the Cirque Drive ULID Line 6 Replacement project It serves the northern portion of the sub-basin The flows from this interceptor discharge to the Cirque Drive Interceptor
Cirque Drive Interceptor
The Cirque Drive Interceptor consists of 2,910 lineal feet of 15 to 18-inch gravity sewer The interceptor begins
at the intersection of Alameda Avenue West and Cirque Drive, travels west along 56th Street West and
terminates at 54th Street Court West and 67th Avenue West The interceptor collects flows from the central portion of the University Place West sub-basin The pipeline was constructed as part of the Stonewood
developer extension in 1977/1978 and flows from the interceptor discharge to the Leach Creek Interceptor
Trang 10Leach Creek Interceptor
The Leach Creek Interceptor consists of 3,404 lineal feet of 30-inch pipeline It begins in an easement located east of Bridgeport Way and south of Alameda Avenue, then travels to the north and east where it terminates at
56th Street West and Alameda Avenue This interceptor is the primary transmission line for the entire sub-basin The pipeline was constructed as part of the Leach Creek Interceptor project in 1987 The flows from the
interceptor discharge to the Chambers Creek Tunnel
Chambers Creek Tunnel
The Chambers Creek Tunnel is the primary transmission facility for the entire Chambers Creek Regional WWTP sewer service basin Within the University Place East Sub-basin the Tunnel consists of 4,526 lineal feet of 72-inch gravity sewer that starts just east of Bridgeport Way near 67th Avenue West, through an easement
paralleling Bridgeport Way to the east and terminates at the city limits of the City of University Place and City of Lakewood The Tunnel was constructed as part of the Lakewood/Parkland ULID 73-1 under the Chambers Creek Interceptor project in 1983/1984 In this sub-basin the Tunnel receives flows from the Leach Creek
Interceptor A phased rehabilitation for relining the interior surface of the Tunnel began in 2000-2001 with project completion planned for 2011
Trang 1131ST ST W
64TH ST W
REGENTS BL VD
ELECTRON WY
37TH ST W
ONYX DR S W
PS64 PS74
PS76
PS16
PS31
PS89 PS14
PS12
PS13 PS02
PS65
PS70
The map features are approximate and are intended only to provide an indication of said feature Additional areas that have not been mapped may be present This is not
a survey Orthophotos and other data may not align The County assumes no liability for variations ascertained by actual survey
ALL DATA IS EXPRESSLY PROVIDED
‘AS IS’ AND ‘WITH ALL FAULTS’
The County makes no warranty of fitness for
a particular purpose.
Pierce County Unified Sewer Plan
PIERCE COUNTY, WASHINGTON University Place East Sub-Basin
DISCLAIMER
University Place East Sewerage Sub-basin Conveyance System
Date: December 2010
Figure 5.4-1
°NNTS
Municipal BoundaryState, Federal or County RouteWater Features
Sewerage Sub-basin Area
Gravity Collectors14" and smaller gravity sewersGravity Transmission Pipelines15" and greater gravity sewersTransmission Force Mains7" and smaller force mainsTransmission Force Mains8" and greater force mains
Pump Stations
!
Private Sewer Lines
Pierce County Sewer Service Area Tributary
to the C/O Tacoma, Pierce County, OTHER WWTPOther Service Area Tributary to Chambers Creek WWTPPotential Pierce County Service Area Currently
Connected to Other WWTP
Trang 125.5 Oakbrook Sub-basin
The Oakbrook Sub-basin is located in the City of Lakewood It is bordered to the west by Puget Sound, to the north by Chambers Creek, to the south by the Fort Steilacoom Golf Course and to the east by 93rd Avenue Court West and consists of approximately 134 acres The size and linear footage of mains in this sub-basin are identified in the table below and is graphically represented in Figure 5.5-1
The conveyance system within the Oakbrook Sub-basin consists of small diameter gravity and force mains that primarily serve residential development, the Oakbrook Sub-basin discharges downstream of the energy
dissipater at the Chambers Creek Regional WWTP via a 4-inch and 6-inch siphon main
The sanitary sewer pipelines serving the Oakbrook Sub-basin were constructed as a developer extension in two phases The first phase was originally connected to a community on-site sewer system and were transferred the sewer system once the Lakewood/Parkland ULID 73-1 sewer lines were installed The remaining lines that serve the sub-basin were installed in 1985
Table 5.5-1 Oakbrook Sub-basin Existing Conveyance System
Interceptor Lines
No Interceptor lines within this Sub-basin
Small Collectors Size (inches) Length (feet)
1 Wastewater Collections Maintenance Pierce County, for pump station data
Trang 13a survey Orthophotos and other data may not align The County assumes no liability for variations ascertained by actual survey
ALL DATA IS EXPRESSLY PROVIDED
‘AS IS’ AND ‘WITH ALL FAULTS’
The County makes no warranty of fitness for
a particular purpose.
Pierce County Unified Sewer Plan
PIERCE COUNTY, WASHINGTON
Oakbrook Sub-Basin
DISCLAIMER
Oakbrook Sewerage Sub-basin Conveyance System
Date:December 2010
Figure 5.5-1
NNTS
°
Municipal BoundaryState, Federal or County RouteWater Features
Other Service Area Tributary to Chambers Creek WWTP
Sewerage Sub-basin Area
Gravity Collectors14" and smaller gravity sewersGravity Transmission Pipelines15" and greater gravity sewersTransmission Force Mains7" and smaller force mainsTransmission Force Mains8" and greater force mains
Private Sewer LinesTransmission Siphon Mains
Pump Stations
!
Waste Water Treatment Plants
!
Trang 145.6 Lakewood West Sub-basin
The Lakewood West Sub-basin is located in the City of Lakewood It is bordered to the west by Puget Sound, to the north by Chambers Creek, to the south by Lake Steilacoom and the Town of Steilacoom and to the east by Gravelly Lake and American Lake and consists of approximately 4,277 acres The Town of Steilacoom connects
to the Chambers Creek Regional WWTP collection system at the treatment plant’s energy dissipator The size and linear footage of mains in this sub-basin are identified in the table below and is graphically represented in Figure 5.6-1
Table 5.6-1 Lakewood West Sub-basin Existing Conveyance System 1
Interceptor Lines
Facility Name Size (inches) Length (feet)
ULID 90-4 Interceptor
5
0.605
Trang 15Section 5
Existing Collection System
Pump Stations 1
No Name Type Location in (gpm) Capacity 2 AWWF
(MGD) 3 ADWF
(MGD) 4
Wastewater Collections Maintenance Pierce County, for pump station data
2 All pump stations are duplex pump systems except PS53 – Lake City which is a triplex pump system
3 Average Wet Weather Flows are the average flows taken from station data Except where noted, pump station data is based on pump run time
4
Average Dry Weather Flows are the average flows taken from station data Except where noted, pump station data is based on pump run time
5 Pump station data based on flow meters.
Lake City Pump Station – Force Main
The Lake City Pump Station Force Main consists of 2,933 lineal feet of 14-inch pressure sewer The Lake City Pump Station is a wet well/dry well pump station with odor control The pump station has a capacity of 1,250 gallons per minute The pump station pumps wastewater from the Lake City Interceptor in the southwest portion
of the sub-basin to the Phillips-Hipkins Interceptor The pump station was constructed as part of the
Lakewood/Parkland ULID 73-1 under the Lakewood Pump Stations Phase I project 1984/1985
Lake City Interceptor
The Lake City Interceptor consists of 7,336 lineal feet of 10 to 24-inch gravity sewer It begins just east of the intersection of 88th AVCT SW and 116th Street SW, travels west to the intersection of Holden Road and 116thStreet SW It collects flows to the Lake City Pump Station, where the interceptor heads to the west along Forest Avenue, then at 93rd Avenue SW it turns south to Washington Boulevard, then from there it goes west and north until it terminates at Holden Road and 116th Street SW The Lake City interceptor was constructed as part of the Lakewood/Parkland ULID 73-1, Lake City Area Schedule B project in 1984 The interceptor collects flows from the southwestern portion of the Lakewood West Sub-basin These flows discharge into the Phillips-Hipkins Interceptor
Phillips-Hipkins Interceptor
The Phillips-Hipkins Interceptor consists of 18,802 lineal feet of 18 to 36-inch gravity sewer The interceptor begins just west of the intersection of Onyx Drive SW and Phillips Road SW, and then continues south along Phillips Road to Steilacoom Boulevard, then west along Steilacoom Boulevard to 83rd Avenue SW where it goes south along 83rd Avenue and terminates just west of the intersection of Idlewood Road SW and 112th Street SW The interceptor was constructed as part of the Lakewood/Parkland ULID 73-1 under the Phillips-Hipkins
Interceptor project (1983/1984) and the Lake City Area Schedule A project (1984) The interceptor is the primary transmission main for the sub-basin These flows continue through the Phillips-Hipkins in the Lakewood East Sub-basin
Trang 16ULID 90-4 DuPont Interceptor
The ULID 90-4 Interceptor begins with 8,644 lineal feet of 18 to 36-inch gravity main at 83rd
Avenue and Steilacoom Boulevard in the City of Lakewood and travels west to Farwest Drive From the intersection of Farwest Drive and Steilacoom Boulevard the pipeline continues south along Farwest Drive as a single 3,770 lineal foot 26-inch low pressure main In front of Lakes High School the pipeline connects to twin 22-inch
pressure mains 4,197 lineal feet in length where they eventually leave the sub-basin just west of 106th Avenue Court SW and 112th Street This pipeline was constructed as part of the Northwest Landing ULID 90-4 project in 1999-2000 and transfers flows from the ULID 90-4 Interceptor from the DuPont sub-basin to the Phillips-Hipkins Interceptor
Trang 17PS18 PS89
PS60 PS68
PS63
PS58 PS52
PS53
PS73
PS51
PS71 PS72
R SW
ZIR CO
a survey Orthophotos and other data may not align The County assumes no liability for variations ascertained by actual survey
ALL DATA IS EXPRESSLY PROVIDED
‘AS IS’ AND ‘WITH ALL FAULTS’
The County makes no warranty of fitness for
a particular purpose.
Pierce County Unified Sewer Plan
PIERCE COUNTY, WASHINGTON
Lakewood West Sub-Basin
DISCLAIMER
Lakewood West Sewerage Sub-basin Conveyance System
Date: December 2010
Figure 5.6-1
NNTS°
Municipal BoundaryState, Federal or County RouteWater Features
Sewerage Sub-basin Area
Gravity Collectors14" and smaller gravity sewersGravity Transmission Pipelines15" and greater gravity sewersTransmission Force Mains7" and smaller force mainsTransmission Force Mains8" and greater force mains
Private Sewer LinesTransmission Siphon Mains
Trang 185.7 Lakewood East Sub-basin
The Lakewood East Sub-basin consists of approximately 5,584 acres and is located primarily in the City of Lakewood It is bordered to the west by Lake Steilacoom and Gravelly Lake, to the north by 64th Street West, to the south by Pacific Highway South and Joint Base Lewis McChord and to the east by I-5 and South Tacoma Way The size and linear footage of mains in this sub-basin is identified in the table below and are graphically represented in Figure 5.7-1
Table 5.7-1 Lakewood East Sub-basin Existing Conveyance System 1
Facility Name Size (inches) Length (feet) Interceptor Lines
Trang 19Section 5
Existing Collection System
Table 5.7-1 Lakewood East Sub-basin Existing Conveyance System 1
Avondale Pump Station
The Avondale Pump Station is a wet well/dry well station with odor control The pump station has a design capacity of 1,200 gallons per minute It pumps flows from the Clover Creek Interceptor in the south central portion of the sub-basin to the Custer Interceptor The pump station was constructed as part of
Lakewood/Parkland ULID 73-1 under the Lakewood Pump Stations Phase I project in 1984/1985
Bridgeport Interceptor
The Bridgeport Interceptor consists of 23,235 lineal feet of 15 to 54-inch gravity sewer The interceptor begins at Bridgeport Way and Meadow Park Road and continues south through the City of Lakewood, along Bridgeport Way where it terminates to the southwest of the intersection of Bridgeport Way and Pacific Highway SW The
interceptor was constructed as part of the Lakewood/Parkland ULID 73-1 under the Bridgeport Interceptor project (1981/1982) and the Bridgeport Area Schedule C (1984) It is the primary transmission interceptor for the entire sub-basin The flows from the interceptor discharge to the Chambers Creek Tunnel
Spanaway Loop PS Bypass Interceptor Phase III
The Spanaway Loop Pump Station Bypass Interceptor Phase III (IS99-03) will be an extension of the existing 72-inch Spanaway Loop Bypass Interceptor The bypass of the Spanaway Loop Pump Station will allow it to be removed from service The 72-inch, 6,367-foot (1.2 miles) long gravity pipeline will expand transmission capacity across Interstate-5 to handle future flows from the sub-basins to the east The interceptor extension will continue east on 112th Street SW, then south on Steele Street and Spanaway Loop Road to 116th Street South It is then continued in the Bypass Interceptor Project on the west side of Interstate 5
Chambers Creek Tunnel
The Chambers Creek Tunnel is the primary transmission facility for the entire Chambers Creek Regional WWTP sewer service basin Within the Lakewood East Sub-basin the Tunnel consists of 2,900 lineal feet of 54 and 72-inch gravity sewer that starts at the city limits of the City of University Place and City of Lakewood and continues south where it terminates at Bridgeport Way and Meadow Park Road The Tunnel was constructed as part of
Trang 20the Lakewood/Parkland ULID 73-1 under the Chambers Creek Interceptor project in 1983/1984 It receives flows from the Bridgeport Interceptor and the Phillips-Hipkins Interceptor and eventually discharges to the Chambers Creek Regional WWTP
Custer Interceptor
The Custer Interceptor consists of 11,409 lineal feet of 21 to 24-inch gravity sewer, the Avondale Pump Station, and 470 feet of 14-inch pressure sewer The interceptor begins at the intersection of Custer Road and
Bridgeport Way, then continues to the south and terminates at the Avondale Pump Station located at the
intersection of Meadow Road SW and Avondale Road SW The pipeline was constructed as part of the
Lakewood/Parkland ULID 73-1 under the Custer Area project in 1979/1980 The interceptor collects flows from the south central portion of the Lakewood East sub-basin These flows discharge into the Bridgeport Interceptor
Clover Creek Interceptor
The Clover Creek Interceptor consists of 10,588 lineal feet of 15 to 24-inch gravity sewer The interceptor begins
at the intersection of Meadow Road SW and Avondale Road SW at the Avondale Pump Station, and then continues to the south and east where it terminates at 120th Street SW and Woodbine Lane SW The pipeline was constructed as part of the Lakewood/Parkland ULID 73-1 under the Clover Creek Area project in
1984/1985 The interceptor collects flows from the south central portion of the Lakewood East sub-basin These flows discharge into the Custer Interceptor
Flett Creek Trunk
The Flett Creek Trunk consists of 1,655 lineal feet of 15-inch gravity sewer The trunk begins at the intersection
of Custer Road and Bridgeport Way, and then continues east to 60th Avenue W, turns south down 60th Avenue, then at 78th Street W turns east and terminates at the intersection of 78th Street W and Burgess Street West The pipeline was constructed as part of the Lakewood/Parkland ULID 73-1 under the Bridgeport Schedule A project in 1983/1984 The trunk collects flows from a small area of the northeast portion of the sub-basin These flows discharge into the Bridgeport Interceptor
Lakeview I Interceptor
The Lakeview I Interceptor consists of 3,634 lineal feet of 15 to 18-inch gravity sewer The interceptor begins at the intersection of Bridgeport Way and Filbert Lane SW, continues to the east and terminates just north of the intersection of Lakeview Avenue SW and Pacific Street SW The pipeline was constructed as part of the
Lakewood/Parkland ULID 73-1 under the Bridgeport Area Schedule B project in 1983/1984 The interceptor collects flows from the eastern portion of the Lakewood East sub-basin These flows discharge into the
Bridgeport Interceptor
Lakeview II Interceptor
The Lakeview II Interceptor consists of 4,082 lineal feet of 15 to 18-inch gravity sewer The interceptor begins at the intersection of Bridgeport Way and 108th Street W, continues to the south and east, terminating at the intersection of 111th Street West and Halcyon Road SW The pipeline was constructed as part of the
Lakewood/Parkland ULID 73-1 under the Bridgeport Area Schedule C project in 1984 The interceptor collects flows from the eastern portion of the Lakewood East sub-basin These flows discharge into the Bridgeport Interceptor
McChord Gate Interceptor
The McChord Gate Interceptor consists of 2,356 lineal feet of 15 to 18-inch gravity sewer The interceptor begins at the intersection of Bridgeport Way and Pacific Highway SW, continues to the southwest, and
terminates at Pacific Highway SW and New York Avenue SW The pipeline was constructed as part of
Lakewood/Parkland ULID 73-1 under the Bridgeport Area Schedule D project in 1984 The interceptor collects flows from the southeastern portion of the Lakewood East Sub-basin south of I-5 These flows discharge into the Bridgeport Interceptor
Phillips-Hipkins Interceptor
The Phillips-Hipkins Interceptor consists of 2,915 lineal feet of 36-inch gravity sewer and 3,558 feet of 14 to inch triple barrel siphon main The interceptor was constructed as part of the Lakewood/Parkland ULID 73-1
Trang 2118-Section 5
Existing Collection System
under the Phillips-Hipkins Interceptor project in 1983/1984 The interceptor collects flows from the western portion of the Lakewood East sub-basin These flows discharge into the Bridgeport Interceptor and the
Lakewood West Sub-basin
Seeley Lake Interceptor
The Seeley Lake Interceptor consists of 2,202 lineal feet of 15-inch gravity sewer The interceptor begins at the intersection of Steilacoom Boulevard and Lakewood Drive SW, and then continues south along Lakewood Drive terminating at 98th Street SW The pipeline was constructed as part of the Lakewood/Parkland ULID 73-1 under the Bridgeport Schedule A project in 1984 The interceptor collects flows from the eastern portion of the
Lakewood East sub-basin These flows discharge into the Steilacoom Boulevard Interceptor
Steilacoom Boulevard Interceptor
The Steilacoom Boulevard Interceptor consists of 7,138 lineal feet of 36-inch gravity sewer The interceptor begins at the intersection of Bridgeport Way and Steilacoom Boulevard, continues to the east along Steilacoom Boulevard, and continues through the South Tacoma Sub-basin to where the Burlington Northern Railroad intersects Steilacoom Boulevard The interceptor was constructed as part of the Lakewood/Parkland ULID 73-1 under the Bridgeport Interceptor project in 1981/1982 The interceptor collects flows from the eastern portion of the Lakewood East sub-basin and also transfers flows from the South Tacoma Sub-basin These flows
discharge into the Bridgeport Interceptor
Spanaway Loop By-Pass Interceptor
The Spanaway Loop By-Pass Interceptor consists of 12,405 lineal feet of 42 to 84-inch gravity sewer The interceptor begins at the intersection of 111th Street SW and Bridgeport Way, then moves east along 111thStreet, crosses under I-5 at 112th Street South and terminates in 112th Street just east of 34th Avenue South This pipeline was constructed as part of the Spanaway Loop Bypass, Schedule A project in 1994 and the under the Lakewood/Parkland ULID 73-1, Bridgeport Area Schedule C project in 1984 It includes a 54” crossing under I-5 The interceptor transfers flows from the eastern portions of the Chambers Creek Regional WWTP sewer service basin These flows discharge into the Bridgeport Interceptor
Trang 22McChord Gate Interceptor
Spanaway Loop Bypass Interceptor
Lakeview II InterceptorLakeview I Interceptor
Steilacoom Boulevard Interceptor
Seeley Lake Interceptor
Flett Creek Trunk
PS59
PS48
PS46 PS55
PS50
PS43
PS47
PS41 PS40
PS42
PS65 PS70 PS66 PS62
PS67 PS69
PS61 PS60
PS68 PS63
PS58 PS52
CUST
ER RSW
S STEEL
AV SW
a survey Orthophotos and other data may not align The County assumes no liability for variations ascertained by actual survey
ALL DATA IS EXPRESSLY PROVIDED
‘AS IS’ AND ‘WITH ALL FAULTS’
The County makes no warranty of fitness for
a particular purpose.
Pierce County Unified Sewer Plan
PIERCE COUNTY, WASHINGTON
Lakewood East Sub-Basin
DISCLAIMER
Lakewood East Sewerage Sub-basin Conveyance System
Figure 5.7-1
NNTS
°
Municipal BoundaryState, Federal or County RouteWater Features
Sewerage Sub-basin Area
Gravity Collectors14" and smaller gravity sewersGravity Transmission Pipelines15" and greater gravity sewersTransmission Force Mains7" and smaller force mainsTransmission Force Mains8" and greater force mains
Private Sewer LinesTransmission Siphon Mains
Trang 23Section 5
Existing Collection System
5.8 DuPont Sub-basin
The DuPont Sub-basin consists of approximately 3,727 acres and is located to the west and north of the Historic Village of DuPont It is bordered to the west by Puget Sound, to the north and south by the Joint Base Fort Lewis McChord Air Field and to the east by Steilacoom Road The Historic Village of DuPont is included in the sub-basin and is under an existing contract for sewer services The size and linear footage of mains in this sub-basin is identified in the table below and are graphically represented in Figure 5.8-1
Table 5.8-1 DuPont Sub-basin Existing Conveyance System 1
- 5
Northwest Landing Pump Station
The Northwest Landing Pump Station is a wet well/dry well pump station with odor control The pump station consists of four pumps, 3 centrifuge pumps and 1 submersible pump, with a capacity of 1950/2400 gallons per minute respectively The station pumps flows through the ULID 90-4 Interceptor from the DuPont Sub-basin to the Lakewood West Sub-basin where it connects with the Phillips-Hipkins Interceptor The Northwest Landing pump station was constructed under the Northwest Landing ULID 90-4 in 1999/2000
Trang 24DuPont Interceptor
The DuPont Interceptor consists of 14,324 lineal feet of 15 to 36-inch gravity sewer It is a compilation of all the interceptor pipelines that serve the DuPont area The flows discharge into the DuPont Pump Station The interceptor pipeline has been constructed under various developer extension projects
ULID 90-4 Interceptor
The ULID 90-4 Interceptor consists of 25,687 lineal feet of twin 22-inch pressure sewer pipelines This pipeline was constructed as part of the Northwest Landing ULID 90-4 project in 1998-2000 It transfers flows from the DuPont Pump Station to the Lakewood West Sub-basin
Trang 25NT RD SW
SOUTH DR
CEN
TER DR
CENTER DR
PS06
HASKE
LL STBAR KS DAL
E AV
ULID 90-4 InterceptorDuPont Interceptor
a survey Orthophotos and other data may not align The County assumes no liability for variations ascertained by actual survey
ALL DATA IS EXPRESSLY PROVIDED
‘AS IS’ AND ‘WITH ALL FAULTS’
The County makes no warranty of fitness for
a particular purpose.
Pierce County Unified Sewer Plan
PIERCE COUNTY, WASHINGTON
DuPont Sub-Basin
DISCLAIMER
DuPont Sewerage Sub-basin Conveyance System
Date: December 2010
Figure 5.8-1
NNTS
°
Municipal BoundaryState, Federal or County RouteWater Features
Sewerage Sub-basin Area
Gravity Collectors14" and smaller gravity sewersGravity Transmission Pipelines15" and greater gravity sewersTransmission Force Mains7" and smaller force mainsTransmission Force Mains8" and greater force mainsPrivate Sewer LinesPump Stations
!
Trang 265.9 South Tacoma Sub-basin
The South Tacoma Sub-basin consisting of approximately 4,733 acres of which 211 acres is designated Rural Service Area and is located in the South Tacoma and Midland area It is bordered to the west by approximately South Tacoma Way and to the east by 22nd Avenue East The northern and southern boundaries vary as
represented in Figure 5.2-1 with the extreme northern boundary at 72nd Street East and the extreme southern boundary located at 121st Street East The size and linear footage of mains in this sub-basin are identified in the table below and are graphically represented in Figure 5.9.1
Table 5.9-1 South Tacoma Sub-basin Existing Conveyance System 1
Interceptor Lines
Facility Name Size (inches) Length (feet)
nd Street
th Avenue
Midland Pump Station
The Midland Pump Station is a submersible pump station with a capacity of 800 gallons per minute per pump The pump station transfers wastewater from the Midland ULID trunk into the South Tacoma Sub-basin through the Midland Interceptor The pump station was constructed under the Midland Interceptor project in 1996/1997
Trang 27Section 5
Existing Collection System
South Tacoma Interceptor
The South Tacoma Interceptor consists of 15,775 lineal feet of 36-inch gravity sewer The interceptor begins at South Tacoma Way and 96th Street SW, then proceeds to the east where it reaches Ainsworth Street South, continues south to 104th Street South, turns east to South Sheridan Avenue, then heads south along South Sheridan to 108th Street South and then follows 108th Street South where it terminates at 8th Avenue This pipeline was constructed as part of the Lakewood/Parkland ULID 73-1 under the South Tacoma Way Area Sewer project (1979/1980) and the Parkland No 1 project (1979/1980) The interceptor collects flows from the western portion of the sub-basin These flows discharge into the Steilacoom Boulevard Interceptor
Midland Trunk
The Midland Trunk consists of 10,848 lineal feet of 15 to18-inch gravity sewer and 5,680 lineal feet of 10-inch pressure sewer The interceptor begins at McKinley Avenue East and 107th Street East, then proceeds to the north where it reaches 96th Street East, continues east to Amhurst East, turns north to 91st Street East, and then heads north along Golden Given Road where it terminates at to 80th Street The pipeline was constructed under the Midland Trunk Phase I project (1996) and the Midland Trunk Phase II project (1997) (Pump Station and Force main) The interceptor collects flows from the eastern portion of the sub-basin (Midland ULID Trunk) The flows from the interceptor discharge to the Parkland II Interceptor
Midland ULID Trunk
The Midland ULID Trunk consists of 3,272 lineal feet of 15-inch gravity The pipeline begins at Midland Pump Station located at 72nd Street East and 21st Avenue East, and then proceeds to the south where it terminates at
80th Street East and 22nd Avenue East The pipeline was constructed as part of the Midland Sanitary Sewer System ULID 80-2 project in 1982/1983 The pipeline collects flows from the northeastern portion of the sub-basin The flows from the trunk sewer discharge to the Midland Interceptor.
Parkland II Interceptor
The Parkland II Interceptor consists of 13,216 lineal feet of 15 to 30-inch gravity sewer The interceptor begins
at 108th Street South and 10th Avenue South, then proceeds easterly along 108th Street to Golden Given Road, then proceeds north where it reaches 103rd Street East, continues to the north where it terminates at 14th
Avenue East and 97th Street East The pipeline was constructed as part of the Lakewood/Parkland ULID 73-1 under the Parkland No 1 Sewer project (1979/1980) and the Parkland No 2 Sewer project (1982/1983) It is a primary transmission main that collects flows from the central area of the basin and also transfers flow from the Midland Interceptor and Golden Given force main The flows from the interceptor discharge to the South
Tacoma Interceptor
Parkland III Interceptor
The Parkland III Interceptor consists of 3,530 lineal feet of 18 to 30-inch gravity sewer The interceptor begins
116th Street East and 8th Avenue South, and then flows north along 10th Avenue South where it discharges to the South Tacoma Interceptor located at 108th Street South This interceptor was constructed as part of the Lakewood/Parkland ULID 73-1, under the Parkland No 3 project in 1983/1984 The interceptor collects flow from the south-central portion of the sub-basin
Steilacoom Boulevard Interceptor
The Steilacoom Boulevard Interceptor consists of 1,784 lineal feet of 36-inch gravity sewer The interceptor begins at Burlington Northern Railroad on Steilacoom Boulevard, and then proceeds to the east where it
reaches South Tacoma Way, continues south to Sales Road, and terminates at Sales Road and 108th Street South This pipeline was constructed as part of the Lakewood/Parkland ULID 73-1 under the Steilacoom
Boulevard Division 2 Sewer project (1981/1982) and the South Tacoma Way Area Sewer projects (1979/1980) The interceptor collects flows from the western portion of the sub-basin and transfers flow from the South
Tacoma Interceptor These flows eventually discharge into the Bridgeport Interceptor (Lakewood East basin)
Trang 28Steilacoom Boulevard Interceptor
South Tacoma Interceptor
PS77 PS44
PS43
PS47
PS41 PS40
a survey Orthophotos and other data may not align The County assumes no liability for variations ascertained by actual survey
ALL DATA IS EXPRESSLY PROVIDED
‘AS IS’ AND ‘WITH ALL FAULTS’
The County makes no warranty of fitness for
a particular purpose.
Pierce County Unified Sewer Plan
PIERCE COUNTY, WASHINGTON
South Tacoma Sub-Basin
DISCLAIMER
South Tacoma Sewerage Sub-basin Conveyance System
Figure 5.9-1
NNTS
°
Municipal BoundaryState, Federal or County RouteWater Features
Sewerage Sub-basin Area
Gravity Collectors14" and smaller gravity sewersGravity Transmission Pipelines15" and greater gravity sewersTransmission Force Mains7" and smaller force mainsTransmission Force Mains8" and greater force mains
Pump Stations
!
Private Sewer Lines
Other Service Area Tributary to Chambers Creek WWTPPierce County Sewer Service Area Tributary
to the C/O Tacoma, Pierce County, OTHER WWTPPierce County Rural Sewer Service Area
Trang 29Section 5
Existing Collection System
5.10 Summit-Waller Sub-basin
The Summit-Waller Sub-basin consists of approximately 195 acres and is located in unincorporated Pierce County The majority of the service area is located in the Lexington Hills development where gravity collector mains and low pressure force mains discharge to Pump Station #22 which transfers the flows via an 8-inch force main to the gravity system located in the South Tacoma Sub-basin A small portion of this area is zoned as Rural Service Area The size and linear footage of mains in this sub-basin are identified in the table below and are graphically represented in Figure 5.10-1
Table 5.10-1 Summit-Waller Sub-basin Existing Conveyance System 1
Interceptor Lines
Facility Name Size (inches) Length (feet)
There are no Interceptor lines within this sub-basin
1
Wastewater Collections Maintenance, Pierce County, for pump station data
2
This pump station is a duplex pump system
3 Average Wet Weather Flows are the average flows taken from station data Except where noted, pump station data is based on pump run time
Trang 308"
PS32 PS22
PS26 PS27
a survey Orthophotos and other data may not align The County assumes no liability for variations ascertained by actual survey
ALL DATA IS EXPRESSLY PROVIDED
‘AS IS’ AND ‘WITH ALL FAULTS’
The County makes no warranty of fitness for
a particular purpose.
Pierce County Unified Sewer Plan
PIERCE COUNTY, WASHINGTON
Summit-Waller Sub-Basin
DISCLAIMER
Summit-Waller Sewerage Sub-basin Conveyance System
Date:December 2010
Figure 5.10-1
NNTS
°
Municipal BoundaryState, Federal or County RouteWater Features
Sewerage Sub-basin Area
Gravity Collectors14" and smaller gravity sewersGravity Transmission Pipelines15" and greater gravity sewersTransmission Force Mains7" and smaller force mainsTransmission Force Mains8" and greater force mains
Pump Stations
!
Waste Water Treatment Plants
!
Private Sewer Lines
Contract Service AreaOther Service Area Tributary to Chambers Creek WWTPPierce County Sewer Service Area Tributary
to the C/O Tacoma, Pierce County, OTHER WWTPPierce County Rural Sewer Service Area
Trang 31Section 5
Existing Collection System
5.11 Parkland Sub-basin
The Parkland Sub-basin consists of approximately 4,197 acres of which 67 acres is designated Rural Service Area and is located in unincorporated Pierce County It is bordered to the west by Joint Base Fort Lewis and McChord Air Field and Spanaway Loop Road, to the north generally by 121st Street East (with the northwest portion of the boundary extending all the way to SR 512), to the south by Spanaway Lake and 152nd Street East and to the east by 13th Avenue East The size and linear footage of mains in this sub-basin are identified in the table below and are graphically represented in Figure 5.11-1
Table 5.11-1 Parkland Sub-basin Existing Conveyance System 1
Brookdale Interceptor
The Brookdale Interceptor (also referred to the Parkland-Brookdale Interceptor) consists of 15,911 lineal feet
of 21 to 72-inch gravity sewer It is a continuation of the Brookdale Interceptor that flows through the
Brookdale Sub-basin In the Parkland Sub-basin it begins at the intersection of Garfield Street South and
Spanaway Loop Road and continues to the south and east where it ends just west of the Brookdale Golf
Course located on Brookdale Road The Brookdale Interceptor was constructed as part of the
Lakewood/Parkland ULID 73-1 under the Brookdale No.1 Schedule 2 Sewer project (1983/1984) and the
East 131st Street and Brookdale Road East Sanitary Sewer project (1981)
Brookdale II Interceptor
The Brookdale II Interceptor consists of 7,234 feet of 36-inch gravity sewer It begins at 133rd Street East and
“A” Street, moves south along “A” Street to 138th
Street East, then east along 138th Street to 6th Avenue East, then south along 6th Avenue East to where it intersects with Johns Road East, then south easterly along
Johns Road where it ends at Johns Road East and Golden Given Road East It serves the southeastern
portion of the Parkland sub-basin The pipeline was constructed as part of the Lakewood/Parkland ULID 73-1 under the Brookdale No 2 Schedule 2 Sewer project in 1983/1984
Parkland III Force Main
The Parkland III Force Main consists of 3,188 feet of 16-inch pressure sewer It begins at 116th Street South and Spanaway Loop Road, then to 116th Street East where it discharged to the Parkland III Interceptor
located at 116th Street South and 10th Avenue South The force main was installed as part of the
Lakewood/Parkland ULID 73-1 under the Brookdale Number 1 Sewer project in 1983/1984 and has since been abandoned in place for possible future use should demand increase