3.2 Modelling Substation States a Using state graphs Substations are dynamic.. 1757 c Repair modelling Each sequence has a repair process in\olving seleral phases, the last of which re
Trang 1IEEE Transactions o n Power Delivery, Vol 11, No 4, October 1996 1755
EVALUATING THE AVAILABILITY OF ELECTRICAL SUBSTATIONS: A DYNAMIC METHODOLOGY
P Jourda, E B o u r g a d e ESF
Electricite, de France Clamart, France
A b s t r a c t
This paper proposes a technique for evaluating the availability of
substations and switching stations including the average cost of
repairs o f darnaged equipment (corrective maintenance), the impact
of disturbances on equipment availability, and the impact of
disturbances on the continuity of the service provided by the
substation The approach is based on the concept of disruptive
events, sequence-based processes, state graphs and Merkov
techniques The paper illustrates the technique by comparing the
availability o f two possible station layouts The results clearly
show the benefit that can be obtained using this objective method
of comparison
Keywords : Substations, availability, Markov techniques,
corrective maintenance
I INTRODUCTION
Electricity plays a fundamental role as an energy source for
both industrial and household applications It competes with other
energy sources for many of these applications, and is judged on its
price and the quality of the service it provides Many generation
and supply companies now operate in free markets, and therefore
need to maintain profitability Their ability to do so depends to a
great extent on the cost of running the facilities and on their
reliability It is therefore important to maintain or improve the
quality of service while achieving profitability levels [I] The
complete generation-transmission-supply system (HL 111) [ 2 ] must
be evaluated on several levels because of its complexity The
broadest level involves an evaluation using general data [3] and the
system is judged on its capability to deliver the energy required at
load points This model is useful for transmission system planning
but is not specific enough for evaluation of the individual
constituent facilities
O n e such facility is the substation This is multi-functional;
primary functions concern the transmission of electricity (line
connection and energy transmission), and the protection of the
generation-transmission system and constituent parts (protection
against electrical faults) In order to optimize the service and cost
provided by this and similar facilities, the analysis must go far
deeper than the previous simple global evaluation of the system
This paper suggests a methodology for evaluating the availability
of these substations on the basis of their functions in the
generation-transmission system It can, in principle, be applied to
other specific parts of the system
96 WM 007-5 PWRD A paper recommended and approved by the IEEE
Substations Committee of the IEEE Power Engineering Society for
presentation at the 1996 IEEE/PES Winter Meeting, January 21-25, 1996,
Baltimore, MD Manuscript submitted June 29, 1995; made avaiable for
printing November 13, 1995
R N Allan, Fellow IEEE
M a n c h e s t e r Centre for Electrical Energ) UMIST
M a n c h e s t e r , UK
It is vital that reliability is considered and integrated into the system at the design stage of the substation The objective is therefore to create an easy-to-use computing tool that allows substation designers to include reliability criteria in their decisions, even if they d o not have expertise in this area The tool must allow those not specialized in questions of reliability to crrate their own models from data and knowledge bases with a vien to comparing design options A topological description of the substation and a knowledge base allows the user to build an internal simulation model He can then evaluate reliability and availability and also incorporate the economic and functional data required by the designer
2 R E V I E W OF POSSIBLE METHODS 2.1 Background
Many studies of substation reliability and availability have been conducted in the past The majority fall into one of two categories The first has been concerned [4,5] with deducing
system states, their likelihood and the impact they have on connectivity including the modelling of active and passive failures The second [6,7] has been concerned with the deduction of station- orientated
outages in a composite transmission system due to active and passive failures in substations Few, if any, have dealt comprehensively with the assessment of the sequential processes that take place within the station following component failures, protection relay responses and the various reconfiguration events that can be used to recover some or all of the energy transfer processes This cannot be assessed using simple state selection approaches It is these aspects that are fundamental to the station designer so that the relationship between reliability availability and economic issues during the design stage can be understood and taken into account
The approach selected must be able to respond to a nlJmber of deterministic phenomena regulated by constant t i n e laws (protection time delays) and stochastic phenomena (electrical faults and equipment behaviour under stress) Also the method must allow precise calculation or authorize calculation to a known but greater error limit
2.2 Processing Methods
One method is random or sequential Monte-Carlo simulation, which can process both non-exponential and exponential laws and
is widely used for the generation-transmission-supply system 18.91 0885-8977/96/$05.00 0 1996 IEEE
Trang 21756
The disadvantage of this method for specific studies on substations
is that results are not consistent, and that low failure rates mean
that results can be highly imprecise or that calculation time is
extremely long
A second method is based on minimal cut sets deduced with
or without a fault tree [ I O 1 This method can be adopted if the
system's functions are defined as paths [ I l l Results are very
precise for simple models and calculation times are short [12]
However, this method is difficult to use if the system is multi-
functionai and adaptive, and can he used only for coherent systems
Moreover, to obtain results on the dynamic characteristics of fault
elimination, the approach must be followed by a study of the
sequences in the main cut sets
A third method involves systematic execution of incidznt
sequences This method is similar to simulation The objective is to
determine incident propagation sequences in a systematic manner
while applying probability limits - if necessary - to stop the search
This method is highly effective if there is little interaction among
components [13] It provides only an approximate solution if a
probability limit is applied although, in this case, the error factor
may be increased The method is less effective if the system can be
easily repaired; i.e if repair times are short in comparison with the
duration of the phenomena being studied This loss of effectiveness
is caused by loops in sequences where the same state is reached
several times in succession
A fourth option is to use Markov chains [ I O ] with
homogenous continuous time parameters to obtain an exact
mathematical solution However, despite the improvement in
resolution algorithms [14], this method is only viable on small
systems and only then with numerous modelling restrictions ; e.g
exponential distributions only
Lastly, semi-Markovian chains can be used to model systems
in which repairing a component changes its characteristics This
approach is now used widely and provides the basis for many
reliability evaluation programs [ 151 However, the problems
relating to the system size are the same as for Markovian
processes
2.3 M o d e of Representation
Initially, the mode of representation used to evaluate the
availability of a substation tends to be based on physical
components This is because the evaluation is often performed by a
designer and it is relevant for the system to be represented by the
state of its constituent parts This approach can produce extremely
large models, in which it is difficult to take account of common
m o d e s
T o simplify this type of model, states can be grouped
together by applying principles of strong and weak aggregation
[ 161 Strong aggregation offers rigorously precise calculations but
conditions of application restrict its use Weak aggregation
simplifies functional interaction between components while
neglecting certain transitions from one state to another This
technique can be useful for large systems, hut results cannot be
considered as totally precise [ 171
Another method is to divide the system into functional units
The availability o f each unit is then studied using an alternated
renewal delayed process Systems of any size can be studied, but at
present, there is no way to measure the degree of uncertainty in the
results This method is called the fictitious graph method [ 181
3.1 Features
Figure 1 is a single-line diagram of a tjpica! EdF 406 6 V
substation Like all substations, it comprises three main parts: :h- feeder bay, the busbar and the transformers The substatien's configuration is modified by circuit-breakers and disconnecturs Substation operation can be disrupted by random eiscis which are external or internal to the station and its imme2:a:: environment External events concern changes to the power s)-s:tm configuration or modifications to the generation plan These etents can be characterized by their impact on the load and inpul to substation terminals and modelled using appropriate laws Intemal events are faults within the station which it is assumed can be modelled using exponential laws Protection devices limit the impact of faults These devices receive current and voltage information when a fault is detected, and send an order that opens
certain circuit breakers All these features netd to be modelled at
the design stage so that the design is commensurate with :he required availability
3.2 Modelling Substation States a) Using state graphs
Substations are dynamic Some of the parameters affecting their behaviour are unpredictable and a multitude of possible changes can therefore take place To simplify the problem, system behaviour is divided into phases A phase is static, i.e it is a period
in which the parameters of observation do not change Dynamic aspects are represented by transitions between phases
The simplest method for evaluating this type of model is IO
consider each possible series of phases This is a sequence-based process This method is easy to use if sequences are simple and there is little interaction betwzen basic components The number of sequences to be analyzed can grow rapidly when complex systems are studied
Under certain conditions, all possible changes can be presented in the form of a state graph Each state corresponds to A
phase Changes in phase correspond to transitions between stares For a probabilistic evaluation, the system must obey Markovian hypotheses; the target states must depend only on the present state (i.e no memory), transition rates must be independent of time (i.e follow an exponential law) In these studies, these hypotheses have been assumed and the modelling process is based on state graphs
b) Characterizing states
In many models, states are characterized by combining component availability states This approach permits the representation of all availability states of a system and rhe incorporation of functional aspects: loss of a function is identified
by the occurrence of any of the availability states invohing components for which the function is lost The disadvantage of this representation lies in the the complexity arising from the transitions betneen states A transition from one state to anothsr can have several causes; e.g., ones causing a long or a short failure duration This means that the graph either has to be quantified in an approximate manner or some states divided so that just one transition occurs from one state to another This is also true of systems with a high degree of interaction between basic components, e.g., faults with a common cause
Trang 31757
c) Repair modelling
Each sequence has a repair process in\olving seleral phases, the last of which returns the component to its initial state Phases generally include detection, sending an operator to the site, isolating the fault and repairing it if n e c e s s q The failure-repair cqcle for a disturbance is shown in Figure 5 Certam complex systems have specific properties allowing the repair model to be simplified, e g if the transition rates of the repair processes are
independent of the size of the area affected b) the diwrbance the
size of the model can bs reduced by aggregating the states
In substations, the consequences of a short Circuit are limited
by the opening of circuit breahers and the defectike part is isolated using the disconnector In this way, the other components are again available for use The time during which components not directly affected bq the incident are unavailable IS the same in all cases and the model can be simplified by aggregating the states of the repair process (Figure 6)
Another typz of characterization for the proposed graph
model has been cnosen: event-based characterizarion The basis is
no longer the state of the system but the events occurring within
the system The method involves separating the qumtitativt
evaluation of the graph from the substation's psrfi;rmanic of iis
functions it is then possible to create smaller graphs, which are
easier to quantify
All systems are designed to perform their functions in
accordance with input parameters In the case of substations, the
input parameters are the sources at substation terminals The input
parameters are assumed to be set for each study However, no
system is perfect and other parameters will also have an influence
This second group of parameters are called disruptive events; e.g
short circuits or transformer explosions These events modify
system behaviour and can cause one or more functions to be
interrupted These are the events to be modelled
3.3 Modefling Substation Behaviour
3.4 Truncating the Graphs a) Disruptive events
Many disrupti*e events have similar characteristics because
they are caused by the same failure modes for components of the
same type A generic law of behaviour can be written that describes
the occurrence of disruptive events involving the same type of
component In this way, the size of the process of occurrence of
disruptive events can be reduced although information on their
location is lost For example, the process of two transformer
failures shown in Figure 2 can be simplified to give Figure 3
Simplification is accurate as a result of high aggregation since the
repair processes are identical It should be noted that the greater the
number o f components of the same type, the greater the degree of
possible simplification
b) The protection system sequences
A disruptive event turns a normal state into a degraded state
Mostly, there is j u s t one degraded state for each disruptive event
However, in complex systems, the interaction between components
can give rise to several degraded states This is the case of sjstems
with components in standby redundancy The failure of one
component activates another The second component may also fail
when activated Therefore, there are two possible degraded states in
which one or both components fail
Substations contain protection systems to prevent propagation
of disruptive events caused by electrical faults However, the
system is not infallible and several degraded states can nevertheless
be caused by a single fault (Figure 4) The model must therefore
associate each disruptive event with a number of secondary events
constituted by successful or unsuccessful operation of the
protection system These operations are generally of very short
duration and involve PLCs and circuit-breakers To simplify the
modelling process, only the final states are represented, and the
time spent in intermediate states is disregarded (Figure 5 )
With this simplification, the initial state can be linked to the
resulting states by means of a transition whose rate is equal to the
rate of occurrence of the initiating event multiplied by the
probability of the path (ai) this last value being the product of the
probability of operation or failure of the various devices activated
by the protection system
Applying the three modelling steps described above gives a model of a substation that is referred to as a generic model With highly complex systems, this generic model may be too large, !n this case, the graph must be truncated by disregarding system states with a low probability of occurrence The simplest technique is to limit the number of simultaneous faults to a value k (there are always N-k elements in the normal state) This however is a deterministic rule and does not include fault probability The validity is therefore limited when the degree of probability varies
to any great extent
Instead, a truncation method is suggested which involves assessing the representativeness of the truncated graph For specific systems, when a degree of severity can be assigned to each
disturbance, truncation is performed at a criticality threshold
(probability x severity)
The method used to calculate the probability of the system being in an absorbing state was developed for sequence-based processes [ 131 An approximate value of the probabilit) of a given graph state is obtained by evaluating the probability of the sequences leading dirzctly to the state [13] The method is valid as long as the state involves no more than a small number of disturbances, but loses its validity when the number of fault combinations increases
3.5 Processing the Model
The proposed model using the previous reduction techniques
is of an acceptable size for studying an electrical substation The final probability, average duration and average number of entries to and departures from each state are determined using conventional Markov soiution techniques [IO] The information is generic To make it specific, the graph must be broken dobrn and instantiated
a) Breaking down the graph
Consider the test substation shown in Figure 7 and the
disruptions, B : short circuit on a busbar, L : short circuit on a line
To simplify the graph assume first order events and the combination "loss of a line - loss of a busbar" Also assume that the short-circuit protection system for busbars is perfect, i.e there are
no intermediate states Finally, assume that in the case of a line, there is an intermediate state, L', before the line fault is isolated
Trang 41758
The generic graph associated with this substation and assumptions
is shown in Figure 8 where N represents the norma! state
The graph is now instantiated (high level of breakdown), to
give the specific graph of the test substation Figure 9 shows part of
the graph obtained by replacing B and L u i t h their inslantiated
values The probability, average duration and average number of
entries and departures from each state are obtained from the
corresponding values in the generic graph
b) Availability of t h e substation
The previous information is not sufficient to evaluate the
behaviour of the substation in terms of its connection and energy
transmission functions States are characterized by the occurrence
of disturbances, i.e intrinsic unavailability of substation
components If the protection system works correctly, these states
correspond to the substation’s real availability states, since
disturbances are closely isolated This is not the case in reality as
the protection system is also subject to failure (Figures 4 5)
Therefore when the system fails, the area isolated may be greater
than the component affected by the disruption
Consider the test substation in Figure 7 If a fault occurs on
line L1, there are three possibilities:
the first b e l of the protection system functions correctly
and circuit breaker CB 1 opens,
the first level of the prokction system fails, but the second
level works: CBI does not opep, but CB3 CB1 and CB5 do,
the second level of the protection system fails CBI, CB3
C B I and CB5 do not open, CB2 and the circuit-breaker at
the other end of LI open
These three cases correspond to the minimum, intermediate
and maximum losses in Figure 4 In all three cases, the intrinsic
availability state o f the substation’s HV components is the same (all
available except for line L I ) However, this is not the case for the
substation‘s connectivity behaviour For example, the connection
between L3 and L2 is maintained in the first case, but not in the
other two cases Therefore, the graph must be broken down once
more This is done in two steps : identify the paths leading to each
state, take into account the protection system for each path
Step 1 - Identifying t h e paths
Consider the combination of two disturbances on the test
substation in Figure 7 : a short circuit on B1 and a short circuit on
LI The paths leading from the normal state (N) to state B l L l in
the graph shown in Figure 9 are (shown in bold)
Path 1 : N -+ L‘1 + LI + B l L l
P a t h 2 : N -+ BI -+ BIL’I -+ B l L l
P a t h 3 : N + L‘I -+ BIL’I -+ B l L l
The search for sequences leading to a specific state is
performed by a process of back chaining All sequences start from
the state under consideration and return to the normal state The
conditional probability Pi of each path i can be calculated knowing
that in the final state:
Where S(P) ordered states of the path I
P,
j(L)
probability of being in state X of the specific graph
set of states uhere one failure leads to state li
For example, using the following values:
A., = 2 x 1 O-6;h, A.B = 7 x 1 O-’ih, @IL = 5 x 1 O-lih,
p, = 8 x 10”ih pB = 3 s 10-’/h gives for state B I L I :
prob (path I ) =
= 0.28
prob (path 2) = 0.71 prob (path 3) = 5 IO-’
Therefore, if the substation is in the state “short circuit on L l and B l ” , in 71% of cases, the short circuit will have occurred on busbar BI first and then on line L I
Step 2 - Incorporation of t h e protection system
The operation of the protection system for each path is now incorporated To d o this, the real state of the substation for each state in the path is evaluated taking into account the operation of protection devices
In the above example, the substation’s real state is the same
as the states in each of the paths, except when a short circuit occurs
on the line prior to isolation In this last case, one of the three possibilities applicable to short circuits on LI will occur, depending on the probability of a malfunction at each level of the protection system, (assumed to be IE-2 in the present example) Therefore taking path 1 (short circuit on L1, isolation, then short circuit on busbar BI), the first state of the path, (L’I) is:
P(LI isolated) = P(L‘1) x 0.99 : - CBI opens P(B1 isolated) = P ( L ’ l ) x IO-’ x 0.99 :
- CB3, C B I and CB5 open P(B1 and B2 isolated) = P(L’I) x IO-’ x IO-’ :
- CB2 opens
If the graph is broken down by applying the three previous steps, (high aggregation, path identification, incorporation of the protection system), it is possible to create all the availability states for the connection functions This is achieved by assigning an isolated substation area to each availability state
Define:
Ai : graph generic state i
Aij : specific state j of generic state i
Aijk path k leading to specific state j of generic state i
Aijk, : real availability state of the substation following
activation of the protection system for state Aij
and path Aijk
:
Trang 51759 Each disturbance triggers a response from the system In the event of a simple failure (s), the component is isolated and replaced If the disturbance causes a short circuit (sc), the protection system intervenes and opens the breakers The component is then isolated manually by opening the disconnecters The protection system modelled in the example isolates the component as closely as possible If one of the breakers does not open the protection system opens the next closest set of circuit breakers
The average duration of the repair process phases are also shown in Table I
The state graph showing the combinations of events in the system is built using the proposed modelling methodology described previously It is based on the model representing the occurrence of disrupting events, the model incorporating the protection system and the model of the repair processes The practical limits applied to this study were; states whose average estimated probability is less than IE-9 are not represented, and two levels of emergency back-up are planned for the protection system The resulting generic graph for substation F3 comprises about 1,900 states (1,000 for F2) The graphs are evaluated using Markov techniques (Mcinq software developed by EDF) It should be noted that, without aggregation, the instantiated graph for F3 would comprise 40,000 states (20,000 for F2) and evaluation would be difficult if not impossible
This gives
P(Aijkl) = P(Ai) x P(AdAi) x P(Aij,/A,j) x P(Aijkl/Aijk)
An isolated area of the substation corresponds to each of the
AIJkl states and It is easy to check if substation connection functions
are performed or not in each such state If the loads and sources at
the substation terminals are known, the transmission functions can
be evaluated
4 APPLICATION 4.1 Description of the Application
Transmission systems are not designed in one phase They
are deve!oped through successive additions of complementary
facilities One of the problems encountered by designers is how to
evaluate the impact of a new facility in an existing system One
specific problem that has been examined is the impact of tapping
into a transmission system by extracting part of the energy
transmitted through a double line to supply a lower voltage
secondary system Several alternatives have been proposed; two are
studied in this paper Both cases have the same base structure
However, one uses two parallel transformers to supply the
secondary systen and the other uses three The diagram showing
the installation with three transformers (F3) is shonn in Figure 1
The installation with two transformers (F2) is similar but without
the centre transformer The high-voltage side of the substation
comprises two line pairs: L1 and L3, and L2 and L4 LI and L2 are
connected to electrical sources The low-voltage system is supplied
via line L5
The comparison criteria selected for the study are the outage
duration on the low-voltage system, the outage duration on the
high-voltage side and corrective maintenance (repair) costs The
first two criteria are derived directly from failure and restoration
statistics The third requires additional cost information
4.2 Modelling
In order to evaluate the comparison criteria, a mathematical
model of the substation behaviour must be constructed The
previous method was used to study, first the incidental and then the
functional aspects
a) Modelling events
An event is the cause of a change in the system's state The
change can affect the entire system (e.g., flooding from a nearby
river), or just basic components due to individual faults In the
first case, the disturbances are associated with a common cause
linked to the geographical location They are not modelled in this
study since this seeks to compare intemal substation structures
Moreover, they do not involve any particular modelling problems
Therefore, only initiating events linked to the failure of basic
components are modelled
To identify initiating events, a list of all the basic
components is compiled, followed by detailing the failure modes of
each component and their impact on the system Lastly, the
disrupting events corresponding to the same component failure
mode are grouped together This list of generic disrupting events is
given in Table I
b) Functional study
The substation was designed to supply energy to customers
on the low-voltage power system However, it is also necessary to minimize disturbances on the link (double circuit line) between external HV substations These two aspects can be modelled on the basis of the path between the two lines Components in the same link can be grouped into a single object This object is in the up- state if all its components are in an up-state Its maximum capacity
is the smallest capacity of its components Using the diagram of substation F3 in Figure 1, all the paths between the two lines can be
constructed
4.3 Evaluating the Availability of the Tapped Substation
To obtain definitive results, the state graph must be divided showing the events taking place in the substation and the functional analysis of each real state performance In this example, this process allows some 40,000 combinations of specific initiating events to be taken into account Dividing the protection system operation gives a breakdown of the substation's real states The study of substation F3 involves approximately one million sequences corresponding to the dynamic changes in the substation This list of sequences can be used directly for sensitivity studies The results can be obtained without a functional re-evaluation of each physical state, so calculation is fast
The results depend on the numerical data in Table 1 These
data are obtained from estimates, which have not been specifically validated Therefore they are included only to illustrate the methodology employed and have no intrinsic value The evaluation produces three types of information : average cost of
of disturbances on equipment availability, the impact of disturbances on the continuity of the service provided by the substation
Trang 61760
Table 2 shows the main results for the equipment (frequency
a i d aberage duration of disturbances average replacement cost)
The corrective maintenance costs for substations F2 and F3 can be
compared The difference between the two alternatives is
significant at FFr 310,000 or 2.5 'YO of substation F3 costs The
existence of a third transformer is therefore seen to have an impact
on operating costs, assuming preventive maintenance costs to be
comparable These results are explained by the fact that the second
cause of corrective niaintenance costs are the failures of
transformers and are therefore dependent of substation layout
Two types of indicators can be calculated for service
continuity: average frequency of link losses between lines, average
link outage time during the year
Table 3 shows that the average annual outage time of the link
between the high-voltage and low-voltage systems (connections
between lines 1 or 2 and line 5 ) is 40% less for substation F3 than
for F2 However, the average annual outage time of the HV
interconnection increases by 15% (connection of lines 1 and 3 and
connection of lines 2 and 4) This shows, as expected, that there
will be a detrimental effect of tapping a new substation into an
existing network using a greater number of components
The impact of disturbances on equipment availability is
measured by the average annual outage time for any given piece of
equipment The study showed that the substation layout makes
little difference
S CONCLUSIOSS
The methodology described in this paper relies on event-
b a e d modelling and state graphs It has been successfully applied
to the evaluation o f the availability of a substation tapped into an
esisting circuit Results indicate that the probability of substation
connection f u x t i o n s being unavailable are the main affected
factors as well as the costs incurred as a result of this
unavailability The methods developed have been used to study
large substations within reasonable calculation times (between a
few minutes and twenty minutes on a workstation) with a
simplified representation of protection system operation It is
therefore intended to focus the further development of this
methodology with a link-up with Topase 1 [I91 to adopt a more
realistic representation and to supplement the reliability results that
can be supplied by Topase I Finally, the computing facilities are
being tested on a representative sample of substations in order to
serve as a starting point for the Topase tool, this being aimed at
designers of electrical substations as routine applications
6 REFERENCES
R.N Allan, R Billinton, "Probabilistic methods applied to
electrical power systems: is it worth it?" IEE Power
Engineering Journal, pp 121-129, May 1992
R Billinton, R.N Allan, "Power system reliability in
perspective" IEE Journal on Electronics and Power, March
M.P Bhavaraju, "Composite system reliability evaluation"
Electric Power and Energy Systems, Vol IO, No 3, pp 174-
179, July 1988
M.S Grover, R Billinton, "A computerized approach to
substation and switching station reliability evaluation," IEEE
Trans Power Apparatus Syst., vol PAS-93, no 5 , pp 1488-
1497, Sept./Oct 1974
1984, 30, pp 231-236
[ 5 ]
[6]
R Billinton R.N Allan, "Reliability Evaluation of power systems" Plenum Publishing, New York USA, 1984
R Billinton, T.K.P Medicheria, "Station originated multiple outages in the reliability analysis of a composite generation and transmission system," IEEE Trans Power Apparatus Syst., vol PAS-100 no 8, pp 3870-3878, Aug 1981 R.N Allan, J.R Ochoa "Modelling and assessment of station originated outages for composite systems reliability evaluation" IEEE Trans on Power Systems, 1988, PWRS-3,
pp 158-165
J Roman Ubeda R.N Allan "Reliability assessment of composite hydrothermal generation and transmission systems using sequential simulation" Proc IEE, 141 Part C.1994, pp
J.C Dodu, L Dubost, A Merlin, "Recentes ameliorations apportees au modele #estimation de la dCfaillance dans les Ctudes de planification de transmission (modkle Mesico)", EDF Bulletin du DER Serie C, No 2, 1978
[IO] R Billinton, R.N Allan, "Reliability evaluation of engineering systems: Concepts and techniques" Second edition, Plenum Publishing, New York, USA, 1992
[ I I] J Endrenyi, "Reliability modeling in electric power systems",
J Wiley and Sons, New York, 1978 [ 121 E.N Dialynas, "Evaluating the approximate probability distributions of load point reliability indices in power distribution networks", IEE Proc, Vol 135, No 5 , pp 450-
460, September 1988 [I31 J.L Bon, J Collet, "An algorithm in order to implement reliability esponential approximations", Reliability Engineering and System Safety, Vo1.43, N o 3, pp 263-268
1994 [I41 H .4bdallah, R Marie, "Efficacite de la methode des puissances uniformisies pour les chaines de Markov raides", IRISA (Institut de Recherche en Informatique et Systkmes AlCatoires), October 1989
[ 151 R Geist K Trivedi, "Reliability evaluation of fault-tolerant systems: tools and techniques", Computer, pp 52-61 July
1990 [ 161 F Kervegant, "Contribution aux simplifications quantitatives des modelisations d e s0rete"Doctoral thesis at Universite de Technologie d e Compitgne, October 1991
[I71 J Devooght, B Tombuyses, C Smidts, "The use of the components influence graph to reduce the size o f the markovian reliability problems", Proceedings of the European Safety and Reliability Conference, pp 661-670, May 1993 [ 181 C Cocozza-Thivent, L Quagliaro, "Une nouvelle methode pour I'etude quantitative de la SDrete de Fonctionnement des systtmes de grande taille", 256 journees de statistiques , Vannes, France, 1993
P Jourda, "Probabilistic assessment of risk and quality in high voltage systems", UMIST, Ph.D Thesis, 1993
[7]
[8]
257-262
[9]
[I91
Trang 71761 Biographies
P JOLRDA : Electrical Engineer He has completed a PhD at
UXlIST in 1993 in Electrical Engineering He has contributed to
this work while working at Research and Development Division of
Electricit6 de France
R N ALLAN : Professor of Electrical Energy Systems in the Manchester Centre for Electrical Energy, UMIST He is a Fellou
of the IEEE and a Chartered Engineer in the UK
E BOURGADE : Reliability Engineer He is currently working at
Electricitt de France, Research ans Development Division, on
dependability of electrical systems, control systems and nuclear
plants
c
CB
c
Bb : busbar, CB : circuit breaker, D : disconnector, L : line, Lk : link, T : transformer
Figure 1 - 400 kV substation, F3
Figure 2 - State graph for two transformers
Figure 3 - Reduced graph for two transformers
Protection not hctioning system I > - Protection not hctioning system 2 -
> -
Trang 81762
Figure 4 - Possible protection sequences
CB2
Figure 7 - Test substation
Propagation Detection ; operator
sent to site Fault
of consequences
isolation
r
Repairs
Figure 5 - Failure/repair cycle
h, :
p L :
pL :
hB :
pB :
rate of occurrence of a short circuit on a line rate of occurrence of short circuit isolation on a line repair rate of a line following a short circuit rate of occurrence of a short circuit on a busbar repair rate of a busbar following a short circuit
Propagation of Detection : operator Isolation
consequences sent to site of the fault
Repair
Figure 6 - Reduced failure/repair cycle
B2
Figure 8 - Generic graph
Figure 9 - Specific graph and paths to B l L l
C B 1, CB2, CB3, CB4, CBS :
circuit breakers
Trang 91763
Table 1-Disruption events and lnput Data
Basic c o m p o n e n t
phase 2 (thousands ( h r s ) of Francs)
265
100
Cost i Duration
165
250
215
165
sc:
U:
m:
corresponds to earthing and mode 2 to untimely opening Length of lines : 50, 50, 100 100 kilometers
simple component failure causing a short circuit
assume that j u s t one event of this type occurs in the substation at a given time (single occurrence)
the above restriction (U) no longer applies (multiple occurrence)
To simplify the example, failure modes are designated simply by a number; e.g in the case of the HV circuit-breaker, mode I
Trang 10Disturbance = component
and number of failure
mode
HV line
Voltage transformer 1
HV earth disconnector
Information collector 1
Information collector 2
Junction
HV disconnector
Cable
HV circuit-breaker 1
HV circuit-breaker 2
Current transformer
Busbar
Po\+er transformer 1
Power transformer, 2
Voltage transformer 2
Phase lightning arrester 1
Phase lightning arrester: 2
Phase lightning arrester 3
Tertiary lightning arrester 1
Tertiary lightning arrester 3
Bushing
Auxiliary transformer
Combined transformer
LV circuit-breaker I
LV circuit-breaker: 2
LV disconnector
Total
Difference F3 - F2
Tertiary lightning arrester 2
The failure mode number is given only when there are several failure modes for one b p e of component
Annual Duration of Average annual Annual Duration of AFerage annual probability non-repaired cost of repairs probability non-repaired cost of repairs 1
i
of state (hours) (in thousands of of state (hours) (in thousands j
, ,
~~~
I
I
i
1
i
1
f
i
I
1
I
Table 3: Average annual outage times of connections