The purpose of this Method Statement is to explain the procedure of the Air Preheater (APH) installation work for VINH TAN 4 unit 1, 2. With this, we can perform safely and consistently.6.2.1 Beginning mark center line of base plate at grid line Q.. 6.2.2 After marking center line the level of base plate will be checked and ensure make same level by shim plate.
Trang 1D 29.11.2016 H.J.BAE S.Y.KWAK S.J.PARK FOR APPROVAL
Owner’s Engineer
POWER ENGINEERING CONSULTING JOINT STOCK COMPANY 3
Dept MECH Dep’t
Trang 31 PURPOSE
The purpose of this Method Statement is to explain the procedure of the Air Preheater
(APH) installation work for VINH TAN 4 unit #1, #2 With this, we can perform safely andconsistently
This method statement is applied to the above mentioned works If there are any matters notmentioned in this statement then that will follow international standard such as AISC, AWSand ASTM
1) Verify the application of this procedure
2) With necessary tests and inspection
3) Verify the specification of supplied material to confirm if the delivered material is correct
4.1 Issued For Construction Drawings
4.2 Approved Contract Quality Plan
4.3 Project EHSS Management Plan
4.4 Painting Procedure (VT4-YR01-P0ZEN-070001)
4.5 American Institute of Steel Construction (AISC)
4.6 American Society for Testing and Materials (ASTM)
4.7 American Welding Society (AWS)
4.8 American National Standards Institute (ANSI)
5.1 Receiving and Storage of Material
5.1.1 Upon delivery of the material, construction engineer shall inspect if there is any discrepancy
with packing list and damage during the transportation The result shall be reported immediately to the supervisor
5.1.2 Materials should be segregated and stored at storage yard for easy handling as per erection
sequence
5.1.3 Generally, take appropriate measures such as the use of sheet covers and sleepers against
rust, strain, deformation and damage during storage of materials
5.1.4 Handling of materials and equipment shall be performed carefully so as not to damage or
loss them
5.1.5 All temporary materials, equipment, and jigs to be used for installation work shall be
carefully checked and adjusted before using them
Trang 4Sealing Frame Top Bolting
Center Support Centering & Leveling
Center Support, Thrust Bearing Installation
Rotor-Lifting Device Installation to Center Support
Hydraulic Cylinder Installation to Rotor Lifting Device
Sliding Support (Cupshaped Support) Installation
Casing Bottom Main, Side Part Installation
Sealing Frame & Shoes, Bottom Installation
Thrust Bearing Temporary Support Installation
Rotor Core Installation
Casing Support middle part Installation
Casing Top Main Part Installation
Casing Top Side Part Installation
Guide Bearing Installation
Bearing Setting Fixing
Pin-Rack Segment & Support Installation
R.D.U (Rotor Drive Unit) Setting
Cold & Hot Heating Element Installation Rotor (Closed, Open) Segment Installation
5.2.2 Prevent friction of structural elements together
5.2.3 Preserve structural elements against shocks of any kind
5.2.4 Avoid trailing structural elements
The above recommendations must permit limiting accidental damaging of the paint film
If necessary, paint touching up shall be carried out according to general specification for
Painting
5.3 Stability of very high devices and of structural elements
5.3.1 Stability of very high devices shall be ensured at all times and, in particular, out of erection
hours (night, weekends)5.3.2 The erector shall ensure the stability of the Air Preheater whenever the progress of the
erection work does not permit getting stability from the structural elements bound together
6.1 Process Flow Chart
Trang 56.2 Setting up Center Line & Level of Base Plate
6.2.1 Beginning mark center line of base plate at grid line Q
6.2.2 After marking center line the level of base plate will be checked and ensure make same
level by shim plate
6.2.3 The tolerance of level will be confirmed as ITP
6.3 Assembly of Bearing Component
6.3.1 Assembly of Thrust Bearing
The thrust bearing will be installed on shim plate which it have just been adjusted samelevel Center line of base plate will coincident with center of thrust bearing
Trang 6
6.4 Assembly of the Rotor Lifting Device
6.5 Assembly of APH-Casing at Bottom Part
6.5.1 Assembly of APH Support (sliding support)
Main & side support will lifting at level which are marked center line and it will be fixed
Trang 76.6 Lifting of Casing Bottom Main Part
Process lifting casing bottom main part after support had fixed they will fit up at position bytemporary support /or use chain block in order to tackle Ensure make level they will bechecked level and make same level by insert shim plate (Reference lifting plan)
6.7 Lifting of Casing Bottom Side Part
When casing bottom main part are fix casing bottom side part will lifting & fit up with main part, the mean while they must make same level with main part
Trang 8After finished adjustment they will process fit up stiffener pipe & angle.
6.9 Installation Seal Frame
Seal frame will be erected at top face of casing bottom part they are connected to together see fig blow
Trang 96.10 Assembly and Mounting of APH Rotor.
6.10.1 Arrangement of the thrust bearing pivot: if case they are loose part, they will be
assembly at a ground with temporary support see blow Fig
6.10.2 Arrangement of the rotor core and pivots
Rotor core will put frame after thrust bearing will lifting assembly with it after they are fixed, the guide bearing will be erected
Trang 106.10.3 Assembly of the hydraulic cylinder for rotor lifting device.
6.10.4 Arrangement of the rotor core
The thrust bearing, rotor core, guide bearing pivot which assembly become 1 unit approximate 20ton they will make lifting plug in order to lifting up to casing bottom disc center fit up by temporary support.(Reference lifting plan )
Trang 116.11 Assembly of APH Casing Middle-part
6.11.1 Erection of APH casing support segment
Casing middle main & side part will fit first at position
6.11.2 Mounting of APH casing middle-part
The rest of segment will be erected fill space after main & part have already fixed
6.12 Assembly of Sealing Frame
Seal frame will be erected at top face of casing top part they are connected to together by bolt see fig blow
Trang 126.13 Assembly of Sealing Frame
6.13.1 Lifting of casing top main part (Reference lifting plan)
6.14 Adjustment of support bearing and guide bearing
6.14.1 Installation of guide bearing
Trang 136.14.2 Installation of shaft seal top
6.14.3 Adjustment of support bearing and guide bearing
Trang 146.15 Arrangement of the Rotor Segment.
6.15.1 Alignment of rotor closed segment
After the rotor had fixed, the rotor closed segment will be assembly with rotor core by bolt, Pin, screw, tack weld Total closed segment have 6pcs with weigh each of piece is 8.23ton They will be installed as per step (reference lifting plan)
6.15.2 Arrangement of the opened segment
The opened segment will be assembly after closed segment temporary fit up
Trang 156.15.3 Arrangement of the rotor completed
See fig after they had finished assembly
6.16 Lifting of casing top
6.16.1 Lifting of casing top side part( reference lifting plan)
6.16.2 Installation of casing top completed
Trang 166.17 Installation of the pin rack
6.18 Installation of the drive-unit
6.19 Installation of the seal gap adjusting devices, top and bottom
Trang 176.20 Installation of heating elements
Trang 186.22 Installation of water washing device
6.23 Installation of the fire extinguishing device
Trang 196.25 Installation of the expansion sleeve
6.26 Installation Lube oil Circulation, Lube oil Pipe & Oil Flushing
6.26.1 Lube Oil Circulation Installation
Install the Lube Oil Circulation System Horizontally, giving carefully consideration to proper installation position and the method of keeping the connection duct warm
Thoroughly clean the piping before installing it in the field
Apply Oil Flushing prior to trial run
Trang 206.26.2 Oil Pipe Assembly for Guide Bearing Circulation System
Assembly Oil Pipe follows Drawing of Guide Bearing Circulation After Welding done Cleaning inside pipe by Air cleaning
6.26.3 Oil Flushing for Guide Bearing Circulation System
Oil Flushing Procedure refer VT4-DD09-P0ZEN-040364 MS for U1 & U2 Air Preheater Oil
Trang 217 JSA (Job Safety Analysis)
List of All Job
A Workers A.1 Not properly equipped with A.1 Instructing to wear proper PPE
Trang 22B Crash/ traffic accident
C Crushing accident during assembly work
D Crushing may cause fatal injury
or permanent disability
E.1 Falling accident
E.2 Falling accident of material
B.1 Check the access road before passing the area
B.2 Designate a signalman who wear the red suit and safety helmet and control the work
C.1 Clearance of safety access roadC.2 Communication with the Signal manD.1 Preparation of a rigging lift list and plans for lifts of ten (10) tons or greater
D.2 Only a qualified and Certified operators Signalman should be in-place
D.3 Do not stand beneath the lifting areasD.4 Ensure loads are fixed with sling belt correctly
D.5 All lifting equipments must be in good conditions
D.6 Experienced lifting supervisor at all timesD.7 Only monthly checking color attached lifting tools allowed to use
D.8 All lifting tools must have identification tag (including serial number, certification number, SWL inspection date and due date)D.9 Provide safe entrance and exit access road for the labors passing
E.1 Proper equipping of PPEE.1 Proper uses the harness (2 lanyards) and life line over 2 meters
E.1 Checking the signal of signal man and checking the direction of the material lifting direction
E.1 All worker who work over 2 meters must
be trained the working at height training.E.2 Checking the joint status of lifting gearsE.2 Prohibiting man access under the lifting area
device to suit the crane capacity
F Equipment
and material
preparation
for Temp
F.1 Collision between machines
Overturning may cause death or permanent disability
F.1 Always keeps the site clear of any obstructions
F.1 Tool-box talks on a daily basisF.1 Adequate warning signboards
Trang 23and damage to materials
F.3 Equipment oil leakage during operation
G.1 Working operation of the equipments may cause injury to personnel due to poor visibility of the area
H.1 Electric shock, fire, burn to body and injury to eye may cause death or permanent disability
F.2 Designate a signalman who wear the red suit and safety helmet and control the workF.2 Heavy machinery should have backward movement warning light and beacon
F.2 Equipment used to clear the site should be controlled and sorted by a banksman
F.2 Provide safe entrance and exit for the workers going to the area
F.2 All vehicles entering on the site must
turn-on their headlights day and night timeF.3 Daily check of the equipments prior to work
G.1 Must provide sufficient lightings on the entire working area
G.1 All equipments must ensure all lights are operational and not obscured by dirt or mudG.1 Supervisor must always be present for the entire working operation
G.1 All workers must be wearing proper PPEG.1 Ambulance and nurse must be available
in first aid station G.1 Must use industrial socket and plugG.1 Electric cabinet should not affect any water
H.1 Proper earthing and connection of weldingmachines and generators
H.1 Flashback arrestor and gauge should be installed prior to use cutting cylindersH.1 Proper PPE to be worn at all timesH.1 Must use and connect 3 core codes electricwire and separate distribution panel (must pass arrangement of ELCB) and avoid any water affect
H.1 Must use industrial socket and plugH.1 Electric cabinet should not affect any water
List of All Job
H Welding and
cutting works
H.2 Generator(diesel) equipment oil leakage during operation
H.2 Daily check of the equipments prior to start of work
H.2 Regular monitoring of the equipment in order to control and prevent oil leakage and other engine trouble
H.2 Provide secondary containment protection under the equipment to prevent contamination of the soil by oil spillageH.2 If oil leakage, must remove the oil and
Trang 24H.3 Oil/chemical storage H.3 Diesel/chemical shall be stored in
secondary containment and MSDS requirements shall be communicated with all concerned
8 RISK ASSESSMENT
8.1 Layout Configuration
Trang 258.2 Crane Radius
Trang 268.3 Casing Bottom Installation
Trang 278.4 Rotor and Shaft Installation
Trang 288.5 Top Casing Installation
Trang 29DOC.NO.VT4- DD09-P0ZEN-040332 Rev D 28 of 41
Trang 308.6 Heavy Equipment Load Test for Safety
All of the heavy equipments should be inspection and load test by Doosan EHS department according to the current regulation of Viet Nam (TCVN 4244; 2005)
9.1 Arrangement Drawing
Trang 319.4 Organization Chart
9.5 Manpower Mobilization Plan
9.6 Erection Schedule for Air Preheater
9.7 WPS for Air Preheater (WPS No WT – G1Y – 1010 – 015)
9.8 Certificate of Lifting Equipments using for APH erection
9.1 Arrangement Drawing
Trang 33No Description Specification Unit Quantity Remark
Trang 349.3 Scaffolding work plan
Trang 35Mr Pham Van ChienTel: 0916.709.786
Lilama Construction Manager
Mr Hoang Van HuynhTel: 0968618218
Lilama QA/QC Manager
Mr Nguyen Tri ThucTel: 0939398217
QC StaffMr: La Manh TuanTel: 01666839879
Doosan MechanicalGeneral Manager
Mr S.W Lee Tel: 094.343.3871
Doosan MechanicalManager
Mr J H Bae Tel: 0949.763.154
Doosan QA/QC Manager
Mr J.C LeeTel: 0943.220.475
DS Non-press Part Engineer
Mr Nguyen Van NinhTel: 0120 572 6581
Doosan Site Director
Mr G B GwakTel: 0943.174 649
Supervisor Mr.: Nguyen Dang LocTel: 0963 167 012
Trang 369.5 Manpower Mobilization Plan
Trang 37DOC.NO.VT4- DD09-P0ZEN-040332 Rev D 36 of 41
Trang 38Actual 2016-01-04 -42372 - Current 2016-01-18 2016-03-01 44 29.2 14.6 50.0% 15 15 Actual 1 29.2 - 0.0%
-Current 2016-01-21 2016-03-11 51 29.8 14.9 50.0% 15 15 Actual 1 29.8 - 0.0%
Current 2016-01-16 2016-03-15 60 22.0 11.0 50.0% 11 11 Actual 1 22.0 - 0.0%
Current 2016-02-06 2016-02-13 8 - Actual 1 - - Current 2016-02-15 2016-03-17 32 24.2 - 0.0% 12 12 Actual 1 24.2 - 0.0%
-Current 2016-02-18 2016-03-23 35 8.1 - 0.0% 4 4 Actual 1 8.1 - 0.0%
Top sleeve angle install
Machining of the rotor
Booster pump & chemical injection system install
Radial seal plate welding
Fire extinguishing device install
Sensor & panel install
Radial seal plate install & welding
Grating & platform install
Assembly of retrectable sootblower
Water washing devices install
TET HOLIDAY
Top casing main erection on the structure
Bottom & middle casing welding
Seal gap adjusting devices,top and bottom
Roller conveyer install
Installation of heating elements
Support & Guied bearing final aligment
Machining devices install
Pinrack install & tack weld
Pinrack adjusting & welding
Driver units install
Rotor casing middle part install & welding ( remain open)
Crane hoist setting
Guied bearing install & centering disc removal
Support & Guied bearing adjusting work
Shaft sealing to install
Rotor segment lifting & setting
1CF1515W42A05A
% Dur.
Finish Weight(ton)
INSTALLATION AIR-PRE HEATER A&B
Activity ID Activity Name '16.01.29 Start
1CF1515W42A04
Aligment of rotor core/rotor parts
Welding (regarding the sequence) of rotor
Rotor core install
Casing middle install
Lifting & bolting top seal frame on the rotor
Marking of position of the supports
Leveling steel struture (Grinding)
Thrust bearing into the steel structure
Top main and middle casing welding (incl guide BRG platform)
Top casing erection on structure steel
Top & middle casing welding
1CF1515W42A04A.01
1CF1515W42A04A.02
Work scaffold installation
Dismantling STR'L & handrail interference
1CF1515W42A04B.01
1CF1515W42A04B.02
1CF1515W42A04B.03
Bottom casing erection on steel structure (incl stiff Pipe)
Sleeve angle install
Seal frame on bottom casing install
Rotor core pre-assembly