-Any project that has positive cash flows for every time period after the initial investment should beaccepted.. Câu hỏi số 3 The length of time required for an investment to generate ca
Trang 1Chapter 5
Câu hỏi số 1
The difference between the present value of an investment and its cost is the:
● A -net present value.
● B -internal rate of return.
● C -payback period.
● D -profitability index.
● E -discounted payback period
Câu hỏi số 2
Which one of the following statements concerning net present value (NPV) is correct?
● A -An investment should be accepted if, and only if, the NPV is exactly equal to zero
● B -An investment should be accepted only if the NPV is equal to the initial cash flow
● C -An investment should be accepted if the NPV is positive and rejected if it is
negative.
● D -An investment with greater cash inflows than cash outflows, regardless of when the cash flows occur, will always have a positive NPV and therefore should always be accepted
● E -Any project that has positive cash flows for every time period after the initial investment should beaccepted
Câu hỏi số 3
The length of time required for an investment to generate cash flows sufficient to recover the initial cost of the investment is called the:
● A -net present value.
● B -internal rate of return.
● C -payback period.
● D -profitability index.
Trang 2● E -discounted cash period.
Câu hỏi số 4
Which one of the following statements is correct concerning the payback period?
● A -An investment is acceptable if its calculated payback period is less than some pre-specified period of time.
● B -An investment should be accepted if the payback is positive and rejected if it is
negative
● C -An investment should be rejected if the payback is positive and accepted if it is
negative
● D -An investment is acceptable if its calculated payback period is greater than some
pre-specified period of time
● E -An investment should be accepted any time the payback period is less than the
discountedpayback period, given a positive discount rate
Câu hỏi số 5
The length of time required for a project's discounted cash flows to equal the initial cost of the project is called the:
● A -net present value.
● B -internal rate of return.
● C -payback period.
● D -discounted profitability index.
● E -discounted payback period.
Câu hỏi số 6
The discounted payback rule states that you should accept projects:
● A -which have a discounted payback period that is greater than some pre-specified
period of time
● B -if the discounted payback is positive and rejected if it is negative.
● C -only if the discounted payback period equals some pre-specified period of time.
Trang 3● D -if the discounted payback period is less than some pre-specified period of time.
● E -only if the discounted payback period is equal to zero.
Câu hỏi số 7
The discount rate that makes the net present value of an investment exactly equal to zero is called the:
● A -external rate of return
● B -internal rate of return.
● C -average accounting return
● D -profitability index
● E -equalizer
Câu hỏi số 8
An investment is acceptable if its IRR:
● A -is exactly equal to its net present value (NPV).
● B -is exactly equal to zero.
● C -is less than the required return.
● D -exceeds the required return.
● E -is exactly equal to 100%.
Câu hỏi số 9
The possibility that more than one discount rate will make the NPV of an investment equal
to zero is called the _ problem.
● A -net present value profiling
Trang 4Câu hỏi số 10
A situation in which accepting one investment prevents the acceptance of another investment is called the:
● A -net present value profile.
● B -operational ambiguity decision.
● C -mutually exclusive investment decision.
● D -issues of scale problem.
● E -multiple choices of operations decision.
Câu hỏi số 11
The present value of an investment's future cash flows divided by the initial cost of the investment is called the:
● A -net present value.
● B -internal rate of return.
● C -average accounting return.
● D -profitability index.
● E -profile period.
Câu hỏi số 12
An investment is acceptable if the profitability index (PI) of the investment is:
● A -greater than one.
● B -less than one.
● C -greater than the internal rate of return (IRR).
● D -less than the net present value (NPV).
● E -greater than a pre-specified rate of return.
Trang 5Câu hỏi số 13
All else constant, the net present value of a typical investment project increases when:
● A -the discount rate increases.
● B -each cash inflow is delayed by one year.
● C -the initial cost of a project increases.
● D -the rate of return decreases.
● E -all cash inflows occur during the last year of a project's life instead of periodically
throughout thelife of the project
Câu hỏi số 14
The primary reason that company projects with positive net present values are considered acceptable is that:
● A -they create value for the owners of the firm.
● B -the project's rate of return exceeds the rate of inflation.
● C -they return the initial cash outlay within three years or less.
● D -the required cash inflows exceed the actual cash inflows.
● E -the investment's cost exceeds the present value of the cash inflows.
Câu hỏi số 15
If a project has a net present value equal to zero, then:
I the present value of the cash inflows exceeds the initial cost of the project.
II the project produces a rate of return that just equals the rate required to accept the project.
III the project is expected to produce only the minimally required cash inflows.
IV any delay in receiving the projected cash inflows will cause the project to have a
negative net present value.
● A -II and III only
● B -II and IV only
● C -I, II, and IV only
● D -II, III, and IV only
● E -I, II, and III only
Trang 6Câu hỏi số 16
Net present value:
● A -cannot be used when deciding between two mutually exclusive projects.
● B -is more useful to decision makers than the internal rate of return when comparing different sized projects.
● C -is easy to explain to non-financial managers and thus is the primary method of
analysis used by the lowest levels of management
● D -is not an as widely used tool as payback and discounted payback.
● E -is very similar in its methodology to the average accounting return.
Câu hỏi số 17
Payback is frequently used to analyze independent projects because:
● A -it considers the time value of money.
● B -all relevant cash flows are included in the analysis.
● C -it is easy and quick to calculate.
● D -it is the most desirable of all the available analytical methods from a financial
perspective
● E -it produces better decisions than those made using either NPV or IRR.
Câu hỏi số 18
The advantages of the payback method of project analysis include the:
I application of a discount rate to each separate cash flow.
II bias towards liquidity.
III ease of use.
IV arbitrary cutoff point.
● A -I and II only
● B -I and III only
● C -II and III only
● D -II and IV only
● E -II, III, and IV only
Trang 7Câu hỏi số 19
All else equal, the payback period for a project will decrease whenever the:
● A -initial cost increases.
● B -required return for a project increases.
● C -assigned discount rate decreases.
● D -cash inflows are moved earlier in time.
● E -duration of a project is lengthened.
Câu hỏi số 20
The discounted payback period of a project will decrease whenever the:
● A -discount rate applied to the project is increased.
● B -initial cash outlay of the project is increased.
● C -time period of the project is increased.
● D -amount of each project cash inflow is increased.
● E -costs of the fixed assets utilized in the project increase.
Câu hỏi số 21
The discounted payback rule may cause:
● A -some positive net present value projects to be rejected.
● B -the most liquid projects to be rejected in favor of less liquid projects.
● C -projects to be incorrectly accepted due to ignoring the time value of money.
● D -some projects with negative net present values to be accepted.
● E -Both some positive net present value projects to be rejected; and some projects with negative net present values to be accepted.
Trang 8Câu hỏi số 22
The internal rate of return (IRR):
I rule states that a typical investment project with an IRR that is less than the required rate should be accepted.
II is the rate generated solely by the cash flows of an investment.
III is the rate that causes the net present value of a project to exactly equal zero.
IV can effectively be used to analyze all investment scenarios.
● A -I and IV only
● B -II and III only
● C -I, II, and III only
● D -II, III, and IV only
● E -I, II, III, and IV
Câu hỏi số 22*
The internal rate of return (IRR):
I rule states that a project is acceptable when the IRR exceeds the required rate of return.
II ignores the initial investment in a project.
III is the rate that causes the net present value of a project to equal zero.
IV can effectively be used to analyze all investment scenarios.
A.I and III only
B.II and IV only
C.I and II only
D.II, III, and IV only
E.I, II, III, and IV
Câu hỏi số 23
The internal rate of return for a project will increase if:
● A -the initial cost of the project can be reduced.
Trang 9● B -the total amount of the cash inflows is reduced.
● C -each cash inflow is moved such that it occurs one year later than originally projected.
● D -the required rate of return is reduced.
● E -the salvage value of the project is omitted from the analysis.
Câu hỏi số 24
The internal rate of return is:
● A -more reliable as a decision making tool than net present value whenever you are
considering mutually exclusive projects
● B -equivalent to the discount rate that makes the net present value equal to one.
● C -difficult to compute without the use of either a financial calculator or a
computer.
● D -dependent upon the interest rates offered in the marketplace.
● E -a better methodology than net present value when dealing with unconventional cash
flows
Câu hỏi số 25
The internal rate of return tends to be:
● A -easier for managers to comprehend than the net present value.
● B -extremely accurate even when cash flow estimates are faulty.
● C -ignored by most financial analysts.
● D -used primarily to differentiate between mutually exclusive projects.
● E -utilized in project analysis only when multiple net present values apply.
Câu hỏi số 26
You are trying to determine whether to accept project A or project B These projects are mutually exclusive As a part of your analysis, you should compute the incremental IRR by determining.
● A -the internal rate of return for the cash flows of each project.
● B -the net present value of each project using the internal rate of return as the discount
rate
Trang 10● C -the discount rate that equates the discounted payback periods for each project.
● D -the discount rate that makes the net present value of each project equal to 1.
● E -the internal rate of return for the differences in the cash flows of the two
projects.
Câu hỏi số 27
Graphing the NPVs of mutually exclusive projects over different discount rates helps demonstrate:
● A -how the incremental IRR varies with changes in the discount rate
● B -how decisions concerning mutually exclusive projects are derived.
● C -how the duration of a project affects the decision as to which project to accept
● D -how the payback period and the initial cash outflow of a project are related
● E -how the profitability index and the net present value are related
Câu hỏi số 28
The profitability index is closely related to:
● A -payback.
● B -discounted payback.
● C -average accounting return.
● D -net present value.
● E -internal rate of return.
Câu hỏi số 29
Analysis using the profitability index:
● A -frequently conflicts with the accept and reject decisions generated by the application
of the net present value rule
● B -is useful as a decision tool when investment funds are limited.
● C -cannot be used to aid capital rationing.
● D -utilizes the same basic variables as those used in the average accounting return.
Trang 11● E -produces results which typically are difficult to comprehend or apply.
Câu hỏi số 30
When the present value of the cash inflows exceeds the initial cost of a project, then the project should be:
● A -accepted because the internal rate of return is positive.
● B -accepted because the profitability index is greater than 1.
● C -accepted because the profitability index is negative.
● D -rejected because the internal rate of return is negative.
● E -rejected because the net present value is negative.
Câu hỏi số 31
Which one of the following is the best example of two mutually exclusive projects?
● A -Planning to build a warehouse and a retail outlet side by side.
● B -Buying sufficient equipment to manufacture both desks and chairs simultaneously.
● C -Using an empty warehouse for storage or renting it entirely out to another firm.
● D -Using the company sales force to promote sales of both shoes and socks.
● E -Buying both inventory and fixed assets using funds from the same bond issue.
Câu hỏi số 32
The Liberty Co is considering two projects Project A consists of building a wholesale book outlet on lot #169 of the Englewood Retail Center Project B consists of building a sit-down restaurant on lot #169 of the Englewood Retail Center When trying to decide whether to build the book outlet or the restaurant, management should rely most heavily on the
analysis results from the _ method of analysis.
● A -profitability index
● B -internal rate of return
● C -payback
● D -net present value
● E -accounting rate of return
Trang 12recommendation given this information His recommendation should be to accept:
● A -project B because it has the shortest payback period.
● B -both projects as they both have positive net present values.
● C -project A and reject project B based on their net present values.
● D -project B and reject project A based on other criteria not mentioned in the problem.
● E -project B and reject project A based on both the payback period and the average
● B -You need to use the other methods since conventional practice dictates that you only
accept projects after you have generated three accept indicators
Trang 13● C -You need to use other methods because the net present value method is unreliable
when a project has unconventional cash flows
● D -The internal rate of return must always indicate acceptance since this is the best
method from a financial perspective
● E -The discounted payback method must always be computed to determine if a project
returns apositive cash flow since NPV does not measure this aspect of a project
Câu hỏi số 36
In actual practice, managers may use the:
I IRR because the results are easy to communicate and understand.
II payback because of its simplicity.
III net present value because it is considered by many to be the best method of analysis.
● A -I and II only
● B -II and III only
● C -I and III only
● D -I, II, and III
● E -None of these
Câu hỏi số 37
No matter how many forms of investment analysis you do:
● A -the actual results from a project may vary significantly from the expected results.
● B -the internal rate of return will always produce the most reliable results.
● C -a project will never be accepted unless the payback period is met.
● D -the initial costs will generally vary considerably from the estimated costs.
● E -only the first three years of a project ever affect its final outcome.
Câu hỏi số 38
Which of the following methods of project analysis are biased towards short-term projects?
I Internal rate of return
II Net present value
Trang 14III Payback
IV Discounted payback
● A -I and II only
● B -III and IV only
● C -II and III only
● D -I and IV only
● E -II and IV only
Câu hỏi số 39
If a project is assigned a required rate of return equal to zero, then:
● A -the timing of the project's cash flows has no bearing on the value of the project.
● B -the project will always be accepted.
● C -the project will always be rejected.
● D -whether the project is accepted or rejected will depend on the timing of the cash
flows
● E -the project can never add value for the shareholders.
Câu hỏi số 40
You are considering a project with the following data:
Internal rate of return 8.7%
Profitability ratio 98
Net present value -$393
Payback period 2.44 years
Required return 9.5%
Which one of the following is correct given this information?
● A -The discount rate used in computing the net present value must have been less than
8.7%
● B -The discounted payback period will have to be less than 2.44 years.
● C -The discount rate used to compute the profitability ratio was equal to the internal rate
of return
Trang 15● D -This project should be accepted based on the profitability ratio.
● E -This project should be rejected based on the internal rate of return.
Câu hỏi số 41
Accepting positive NPV projects benefits the stockholders because:
● A -it is the most easily understood valuation process.
● B -the present value of the expected cash flows are equal to the cost.
● C -the present value of the expected cash flows are greater than the cost.
● D -it is the most easily calculated.
● E -None of these.
Câu hỏi số 42
Which of the following does not characterize NPV?
● A -NPV does not explicitly incorporate risk into the analysis.
● B -NPV incorporates all relevant cash flow information.
● C -NPV uses all of the project's cash flows.
● D -NPV discounts all future cash flows.
● E -Using NPV will lead to decisions that maximize shareholder wealth.
Câu hỏi số 43
The payback period rule:
● A -discounts cash flows.
● B -ignores initial cost.
● C -always uses all possible cash flows in its calculation.
● D -Both discounts cash flows; and always uses all possible cash flows in its calculation.
● E -None of these.
Câu hỏi số 44
Trang 16The payback period rule accepts all investment projects in which the payback period for the cash flows is:
● A -greater than one.
● B -greater than the cutoff point.
● C -less than the cutoff point.
● D -positive.
● E -None of these.
Câu hỏi số 45
The payback period rule is a convenient and useful tool because:
● A -it provides a quick estimate of how rapidly the initial investment will be recouped.
● B -results of a short payback rule decision will be quickly seen.
● C -it does not have to take into account time value of money.
● D -All of these.
● E -None of these.
Câu hỏi số 46
The discounted payback period rule:
● A -considers the time value of money.
● B -discounts the cutoff point.
● C -ignores uncertain cash flows.
● D -is preferred to the NPV rule.
● E -None of these.
Câu hỏi số 47
The payback period rule:
● A -determines a cutoff point so that all projects accepted by the NPV rule will be
accepted by the payback period rule
Trang 17● B -determines a cutoff point so that depreciation is just equal to positive cash flows in
the payback year
● C -requires an arbitrary choice of a cutoff point.
● D -varies the cutoff point with the interest rate.
● E -Both determines a cutoff point so that all projects accepted by the NPV rule will be
accepted by the payback period rule; and varies the cutoff point with the interest rate
Câu hỏi số 48
Modified internal rate of return:
● A -handles the multiple IRR problem by combining cash flows until only one change in
sign change remains
● B -requires the use of a discount rate.
● C -does not require the use of a discount rate.
● D -Both handles the multiple IRR problem by combining cash flows until only one change in sign change remains; and requires the use of a discount rate.
● E -Both handles the multiple IRR problem by combining cash flows until only one
change in signchange remains; and does not require the use of a discount rate
Câu hỏi số 49
A mutually exclusive project is a project whose:
● A -acceptance or rejection has no effect on other projects.
● B -NPV is always negative.
● C -IRR is always negative.
● D -acceptance or rejection affects other projects.
● E -cash flow pattern exhibits more than one sign change.
Câu hỏi số 50
The two fatal flaws of the internal rate of return rule are:
● A -arbitrary determination of a discount rate and failure to consider initial expenditures.
Trang 18● B -arbitrary determination of a discount rate and failure to correctly analyze mutually
exclusive investment projects
● C -arbitrary determination of a discount rate and the multiple rate of return problem.
● D -failure to consider initial expenditures and failure to correctly analyze mutually
exclusive investment projects
● E -failure to correctly analyze mutually exclusive investment projects and the multiple rate of returnproblem.
Câu hỏi số 51
A project will have more than one IRR if:
● A -the IRR is positive.
● B -the IRR is negative.
● C -the NPV is zero.
● D -the cash flow pattern exhibits more than one sign change.
● E -the cash flow pattern exhibits exactly one sign change.
Câu hỏi số 52
Using internal rate of return, a conventional project should be accepted if the internal rate
of return is:
● A -equal to the discount rate.
● B -greater than the discount rate.
● C -less than the discount rate.
Trang 19● A -the discount rate that makes the NPV equal to zero.
● B -the difference between the market rate of interest and the NPV.
● C -the market rate of interest less the risk-free rate.
● D -the project acceptance rate set by management.
● E -None of these.
Câu hỏi số 54
The problem of multiple IRRs can occur when:
● A -there is only one sign change in the cash flows.
● B -the first cash flow is always positive.
● C -the cash flows decline over the life of the project.
● D -there is more than one sign change in the cash flows.
● E -None of these.
Câu hỏi số 55
The elements that cause problems with the use of the IRR in projects that are mutually exclusive are:
● A -the discount rate and scale problems.
● B -timing and scale problems.
● C -the discount rate and timing problems.
● D -scale and reversing flow problems.
● E -timing and reversing flow problems.
Câu hỏi số 56
If there is a conflict between mutually exclusive projects due to the IRR, one should:
● A -drop the two projects immediately.
● B -spend more money on gathering information.
Trang 20● C -depend on the NPV as it will always provide the most value.
● D -depend on the payback because it does not suffer from these same problems.
● E -None of these.
Câu hỏi số 57
The profitability index is the ratio of:
● A -average net income to average investment.
● B -internal rate of return to current market interest rate.
● C -net present value of cash flows to internal rate of return.
● D -net present value of cash flows to return on equity.
● E -present value of cash flows to initial investment cost.
Câu hỏi số 58
Which of the following statement is true?
● A -One must know the discount rate to compute the NPV of a project but one can compute the IRR without referring to the discount rate.
● B -One must know the discount rate to compute the IRR of a project but one can
compute the NPV without referring to the discount rate
● C -Payback accounts for time value of money.
● D -There will always be one IRR regardless of cash flows.
● E -Return on equity is the ratio of total assets to total net income.
Trang 21● B -Internal Rate of Return; Net Present Value
● C -Net Present Value; Payback Period
● D -Modified Internal Rate of Return; Internal Rate of Return
● E -Modified Internal Rate of Return; Net Present Value