Scheduling, a crucial aspect of project planning, is then described in Chapter 8, along with the most common scheduling models such as the Program Evaluation and Review Technique (PERT), the Critical Path Method (CPM), and precedence diagramming.
Trang 1Scheduling
Trang 7Network Scheduling Techniques: PERT (ADM) and CPM (PDM)
– PERT used probabilistic time estimates
Microsoft Project (and others) have blended
CPM and PERT into one approach
Trang 11Sequential Activities
Trang 12AON and AOA Format
Trang 14814
Trang 15Sample of Network Construction
Trang 18Microsoft Project Gantt Chart
Trang 19Microsoft Project AON Network
Trang 21Solving the Network
Trang 22The AON Network from the previous table
Trang 232
2 2
6
6
4
a b
b m
a TE
Trang 24The Results
Trang 25Parkinson’s Law
Trang 26Critical Path and Time
Trang 27Critical Path and Time Continued
Trang 28Slack
Trang 29Slack Values
Trang 31Precedence Diagramming Conventions
Trang 32Microsoft Project
Trang 33Gantt Chart
Trang 34AON Network
Trang 35Microsoft Project Calendar
Trang 3745
52 645
1 745
5 43
22
1 745
5
7 33
43 50
)
(
2
Z D
D Z
Trang 38 When using 5%, the divisor changes to 3.29
When using 10%, the divisor changes to 2.56
Trang 39Risk Analysis Using Simulation with Crystal Ball
Trang 40Risk Analysis Using Simulation with Crystal Ball
840
Trang 41Risk Analysis Using Simulation with Crystal Ball
Trang 42Risk Analysis Using Simulation with Crystal Ball
842
Trang 43Risk Analysis Using Simulation with Crystal Ball
Trang 44Simulation Analysis
844
Trang 45Simulation Analysis
Trang 46Simulation Analysis
846
Trang 47after the analyst has a good
understanding of the traditional statistical approach.
all paths and activities that may
potentially impact the project’s ability to
be completed on time