Confirmation testing is testing fixes to a set of defects and Regression testing is testing to establish whether any defects have been introduced as a result of changes.. Confirmation te
Trang 121/9/2018 Test (Before class)
Question 1
Correct
Mark 1.00 out of
1.00
Question 2
Correct
Mark 1.00 out of
1.00
Started on Friday, 21 September 2018, 7:26 AM
State Finished Completed on Friday, 21 September 2018, 7:38 AM
Time taken 11 mins 39 secs
Marks 39.00/40.00 Grade 9.75 out of 10.00 (98%)
Match every stage of the software development life cycle with the testing life cycle:
Business requirements Acceptance Test
Your answer is correct
The inputs for developing a test plan are taken from
Select one:
a Support plan
b None of the above
c Project plan
d Business plan
Your answer is correct
Kiem thu phan mem_
2018_2019_HKI_Sang_Thu6
Trang 221/9/2018 Test (Before class)
Question 3
Correct
Mark 1.00 out of
1.00
Question 4
Correct
Mark 1.00 out of
1.00
Which of the following is TRUE?
Select one:
a Confirmation testing is testing fixes to a set of defects and Regression testing
is testing to establish whether any defects have been introduced as a result of changes
b Confirmation testing and Regression testing are both testing to establish whether any defects have been introduced as a result of changes.
c Confirmation testing and Regression testing are both testing fixes to a set of defects.
d Confirmation testing is testing to establish whether any defects have been introduced as a result of changes and Regression testing is testing fixes to a set
of defects.
Your answer is correct
Which of the following are characteristic of regression testing?
i) Regression testing is run ONLY once ii) Regression testing is used after fixes have been made iii) Regression testing is often automated
iv) Regression tests need not be maintained
Select one:
a ii, iii.
b ii, iv.
c i, iii, iv
d iii.
Your answer is correct
Trang 321/9/2018 Test (Before class)
Question 5
Correct
Mark 1.00 out of
1.00
Question 6
Correct
Mark 1.00 out of
1.00
Question 7
Correct
Mark 1.00 out of
1.00
What principle is BEST described when test designs are written by a third party?
Select one:
a Interoperability testing
b Independent testing
c Integration testing
d Exploratory testing
Your answer is correct
Which of the following combinations correctly describes a valid approach to component testing:
i) Functional testing of the component in isolation
ii) Structure-based testing of the code without recording incidents
iii) Automated tests that are run until the component passes
iv) Functional testing of the interfaces between modules
Select one:
a iii
b i and ii.
c I ii and iii
d ii and iv
Your answer is correct
What is the name of a skeletal implementation of a software component that is used for testing?
Select one:
a Driver
b Stub
c Domain
d Use case
Your answer is correct
,
Trang 421/9/2018 Test (Before class)
Question 8
Correct
Mark 1.00 out of
1.00
Question 9
Correct
Mark 1.00 out of
1.00
Question 10
Correct
Mark 1.00 out of
1.00
Testing where in we subject the target of the test, to varying workloads to measure and evaluate the performance behaviors and ability of the target and of the test to continue to function properly under these different workloads
Select one:
a Load Testing
b System Testing
c Usability Testing
d Integration Testing
Your answer is correct
Performs sufficient testing to evaluate every possible path and condition in the application system The only test method that guarantees the proper functioning of the application system is called as _
Select one:
a Exhaustive Testing
b Branch Testing
c Regression Testing
d Basic Path Testing
Your answer is correct
During this event the entire system is tested to verify that all functional information structural and quality requirements have been met A predetermined combination of tests is designed that when executed successfully satisfy management that the system meets specifications
Select one:
a Validation Testing
b System Testing
c Integration Testing
d User Acceptance Testing
Your answer is correct
Trang 521/9/2018 Test (Before class)
Question 11
Correct
Mark 1.00 out of
1.00
Question 12
Correct
Mark 1.00 out of
1.00
Question 13
Correct
Mark 1.00 out of
1.00
During testing, a defect was found in which the system crashed when the network got disconnected while receiving data from the server The defect was fixed by correcting functionality which checks the network availability during data transfer Existing test cases did cover 100% of the module statements To verify the fix and ensure more extensive coverage, some tests were designed and added to the test suite What types of testing are mentioned above?
I Functional testing
II Structural testing III Confirmation testing
IV Performance testing
Select one:
a II and IV
b I and III
c I, III and IV
d I, II and III
Your answer is correct
Which test investigates both functional and non-functional system requirements?
Select one:
a Alpha testing
b Acceptance testing
c Confirmation testing
d System testing
Your answer is correct
Which test may not mimic real world situations
Select one:
a Structural Testing
b All of the above
c None of the above
d Functional testing
Your answer is correct
Trang 621/9/2018 Test (Before class)
Question 14
Correct
Mark 1.00 out of
1.00
Question 15
Correct
Mark 1.00 out of
1.00
Question 16
Correct
Mark 1.00 out of
1.00
The process starting with the terminal modules is called:
Select one:
a Bottom-up integration
b Top-down integration
c None of the above
d Module integration
Your answer is correct
Which testing is used to verify that the system can perform properly when internal program or system limitations have been exceeded
Select one:
a Load Testing
b Stress Testing
c Performance Testing
d Volume testing
Your answer is correct
Which of the following is true of the V - model?
Select one:
a It states that modules are tested against user requirements.
b It only models the testing phase.
c It includes the verification of designs.
d It specifies the test techniques to be used.
Your answer is correct
Trang 721/9/2018 Test (Before class)
Question 17
Correct
Mark 1.00 out of
1.00
Question 18
Correct
Mark 1.00 out of
1.00
Question 19
Correct
Mark 1.00 out of
1.00
During which fundamental test process activity do we determine if MORE tests are needed?
Select one:
a Evaluating test exit criteria.
b Test implementation and execution.
c Test analysis and design.
d Test planning and control.
Your answer is correct
Which of the following is a major task of test planning?
Select one:
a Evaluating exit criteria and reporting.
b Measuring and analyzing results.
c Determining the test approach.
d Preparing test specifications.
Your answer is correct
Which test levels are USUALLY included in the common type of V - model?
Select one:
a Alpha testing, beta testing, black-box testing, and white-box testing
b Component testing, integration testing, system testing, and acceptance testing
c Incremental testing, exhaustive testing, exploratory testing, and data driven testing
d Integration testing, system testing, acceptance testing, and regression testing
Your answer is correct
Trang 821/9/2018 Test (Before class)
Question 20
Correct
Mark 1.00 out of
1.00
Question 21
Correct
Mark 1.00 out of
1.00
Question 22
Correct
Mark 1.00 out of
1.00
Place the stages of the Fundamental Test Process in the usual order (by time)
a Test closure activities
b Analysis and design
c Planning and control
d Implementation and execution
e Evaluating exit criteria and reporting
Select one:
a c, b, d, a, e
b c, b, d, e, a
c b, c, d, e, a
d c, b, e, d, a
Your answer is correct
During which activity of the Fundamental Test Process do you compare actual with expected results?
Select one:
a Test implementation and execution
b Test analysis and design
c Evaluating exit criteria and reporting
d Test closure activities
Your answer is correct
Which activity in the Fundamental Test Process creates test suites for efficient test execution?
Select one:
a Planning and control
b Implementation and execution
c Analysis and design
d Test closure
Your answer is correct
Trang 921/9/2018 Test (Before class)
Question 23
Correct
Mark 1.00 out of
1.00
Question 24
Correct
Mark 1.00 out of
1.00
Question 25
Incorrect
Mark 0.00 out of
1.00
Which of the following is a MAJOR activity of test planning?
Select one:
a Measuring and analysing results
b Initiation of corrective actions
c Monitoring and documenting progress
d Determining the exit criteria
Your answer is correct
As part of which test process do you determine the exit criteria?
Select one:
a Evaluating exit criteria and reporting
b Test planning.
c Test closure.
d Test control.
Your answer is correct
Which of the following is a MAJOR task of test implementation and execution?
Select one:
a Reporting discrepancies as incidents.
b Assessing if more tests are needed.
c Identifying test conditions or test requirements.
d Measuring and analyzing results.
Your answer is incorrect
Trang 1021/9/2018 Test (Before class)
Question 26
Correct
Mark 1.00 out of
1.00
Question 27
Correct
Mark 1.00 out of
1.00
Question 28
Correct
Mark 1.00 out of
1.00
What is beta testing?
Select one:
a Testing performed by product developers at the customer's location.
b Testing performed by potential customers at their own locations.
c Testing performed by product developers at their own locations.
d Testing performed by potential customers at the developers location.
Your answer is correct
System testing should investigate
Select one:
a Non-functional requirements and Functional requirements
b Functional requirements only not non-functional requirements
c Non-functional requirements only not Functional requirements
d Non-functional requirements or Functional requirements
Your answer is correct
Contract and regulation testing is a part of
Select one:
a Smoke testing
b Integration testing
c Acceptance testing
d System testing
Your answer is correct
Trang 1121/9/2018 Test (Before class)
Question 29
Correct
Mark 1.00 out of
1.00
Question 30
Correct
Mark 1.00 out of
1.00
Question 31
Correct
Mark 1.00 out of
1.00
The _ testing will be performed by the people at client own locations
Select one:
a Alpha testing
b Field testing
c Performance testing
d System testing
Your answer is correct
Arc testing is known as
Select one:
a Agile testing
b Beta testing
c Branch testing
d Ad-hoc testing
Your answer is correct
Which test can be performed at all test levels?
Select one:
a Operational testing
b Structural testing
c Integration testing
d System testing
Your answer is correct
Trang 1221/9/2018 Test (Before class)
Question 32
Correct
Mark 1.00 out of
1.00
Question 33
Correct
Mark 1.00 out of
1.00
Question 34
Correct
Mark 1.00 out of
1.00
Which is the non - functional testing?
Select one:
a Unit testing
b Regression testing
c Performance testing
d Sanity testing
Your answer is correct
Link Testing is also called as:
Select one:
a Component Sub System Testing
b Maintenance testing
c Component System Testing
d Component Integration testing
Your answer is correct
When a defect is detected and fixed then the software should be retested to confirm that the original defect has been successfully removed This is called:
Select one:
a Regression testing
b Confirmation testing
c None of the above
d Maintenance testing
Your answer is correct
Trang 1321/9/2018 Test (Before class)
Question 35
Correct
Mark 1.00 out of
1.00
Question 36
Correct
Mark 1.00 out of
1.00
Question 37
Correct
Mark 1.00 out of
1.00
What is the Software Testing Life Cycle?
Select one:
a It is a life cycle about the software development process.
b It is a set of steps that can be performed in any order to test the quality of software.
c It is a set of specifications the programmers write to decide the functions of the software.
d It is a set of steps that needs to be performed in sequence to test the quality
of software.
Your answer is correct
How are the SDLC and STLC models related?
Select one:
a A software testing life cycle (STLC) test is needed only after all software development life cycle (SDLC) steps are complete.
b A software testing life cycle (STLC) test is needed at each stage of the software development life cycle (SDLC).
c The software testing life cycle (STLC) test is done by the development team.
d The software testing life cycle (STLC) test is done by a separate test team.
Your answer is correct
What are the benefits of integrating the development and testing in the software development life cycle?
Select one:
a Management philosophy mandates testing after development
b It improves mentorship and empowerment in software development
c It simplifies identifying and fixing errors before they make it into the final product
d It makes sure that errors and oversights are caught after the system goes into production
Your answer is correct
Trang 1421/9/2018 Test (Before class)
Question 38
Correct
Mark 1.00 out of
1.00
Question 39
Correct
Mark 1.00 out of
1.00
Question 40
Correct
Mark 1.00 out of
1.00
What is the phase where a determination is made about what version of the software will be tested?
Select one:
a Test environment phase
b Development phase
c Planning phase
d Requirements phase
Your answer is correct
Why is developing the test case important?
Select one:
a The planning phase follows the plan as outlined in the test case.
b The execution of the test follows the plan as outlined in the test case.
c The requirement analysis follows the plan as outlined in the test case.
d Closing the test cycle follows the plan as outlined in the test case.
Your answer is correct
To check whether we are developing the right product according to the customer requirements are not It is a static process
Select one:
a Validation
b Quality Control
c Verification
d Quality Assurance
Your answer is correct
Return to: Week 3 (21/09)