Objectives To describe how utilities currently use combustion turbines and reciprocating engines to supportthe power delivery system; to improve industry knowledge of distributed resourc
Trang 1Combustion Turbines and Reciprocating
Engines for Grid Support
Please read the License Agreement
on the back cover before removing
the Wrapping Material.
Trang 3EPRIsolutions Project Manager
B Freeman
Combustion Turbines and
Reciprocating Engines for Grid
Support
1003962
Final Report, November 2001
Trang 4DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITIES
THIS REPORT WAS PREPARED BY THE ORGANIZATION(S) NAMED BELOW AS AN ACCOUNT
OF WORK SPONSORED OR COSPONSORED BY EPRISOLUTIONS, INC NEITHER EPRISOLUTIONS, THE ELECTRIC POWER RESEARCH INSTITUTE, INC (EPRI), ANY MEMBER
OF EPRI, ANY COSPONSOR, THE ORGANIZATION(S) NAMED BELOW, NOR ANY PERSON ACTING ON BEHALF OF ANY OF THEM:
(A) MAKES ANY WARRANTY OR REPRESENTATION WHATSOEVER, EXPRESS OR IMPLIED, (I) WITH RESPECT TO THE USE OF ANY INFORMATION, APPARATUS, METHOD, PROCESS, OR SIMILAR ITEM DISCLOSED IN THIS REPORT, INCLUDING MERCHANTABILITY AND FITNESS FOR A PARTICULAR PURPOSE, OR (II) THAT SUCH USE DOES NOT INFRINGE ON OR INTERFERE WITH PRIVATELY OWNED RIGHTS, INCLUDING ANY PARTY’S INTELLECTUAL PROPERTY, OR (III) THAT THIS REPORT IS SUITABLE TO ANY PARTICULAR USER’S CIRCUMSTANCE; OR
(B) ASSUMES RESPONSIBILITY FOR ANY DAMAGES OR OTHER LIABILITY WHATSOEVER (INCLUDING ANY CONSEQUENTIAL DAMAGES, EVEN IF EPRISOLUTIONS OR ANY EPRISOLUTIONS REPRESENTATIVE HAS BEEN ADVISED OF THE POSSIBILITY OF SUCH DAMAGES) RESULTING FROM YOUR SELECTION OR USE OF THIS REPORT OR ANY INFORMATION, APPARATUS, METHOD, PROCESS, OR SIMILAR ITEM DISCLOSED IN THIS REPORT.
ORGANIZATION(S) THAT PREPARED THIS REPORT
Power System Engineering Inc.
EPRIsolutions is a registered service mark of EPRIsolutions, Inc.
Copyright © 2001 EPRIsolutions, Inc All rights reserved.
Trang 5This report was prepared by
Power System Engineering, Inc
This report describes research sponsored by EPRIsolutions
The report is a corporate document that should be cited in the literature in the following manner:
Combustion Turbines and Reciprocating Engines for Grid Support, EPRIsolutions, Palo Alto,
CA: 2001 1003962
Trang 7REPORT SUMMARY
This report critically reviews specific examples of utilities using combustion turbines or
reciprocating engines to support the power grid The report describes common challenges inplanning, developing, installing, and operating distributed resources in grid support
Background
Distributed resources can support power delivery systems and defer significant capital
transmission and distribution (T&D) projects This potential, however, has yet to be widelyrealized due to the lack of well-documented case examples Too often, the role of distributedresources in grid support is overly simplified by both advocates and skeptics, without
consideration of actual evidence
Objectives
To describe how utilities currently use combustion turbines and reciprocating engines to supportthe power delivery system; to improve industry knowledge of distributed resources and advancethe debate from generalities to utility engineering and economic analysis that is proven by
specific case studies; to reveal the difficulties and successes of applying distributed resources tosolve T&D expansion problems; and, to provide case studies of current projects that give utilityengineers and their managers examples they need to evaluate distributed resources within thecontext of power delivery planning
Approach
The project team started by identifying utilities across the country that might be using distributedresources for grid support, then developed a survey to elicit information about these projects.Since distributed resources can provide both utility power-supply requirements and grid support,the team asked questions to help confirm that grid support was a primary objective of theseprojects They followed up by calling each utility and encouraging them to assign a specificperson to complete the survey promptly and conducted phone interviews with utilities that didnot provide a written response
The utilities’ survey responses were the primary source of information for this report The teamanalyzed responses for successes, failures, and trends that would help indicate the potential of,and challenges with, distributed resources
Trang 8completed Distributed resources can support local areas where the cost of traditional grid
capacity additions is prohibitive or where the time required to make such additions is too great.Distributed resources may be transportable, so they can be moved to new areas after the currentneed has been satisfied The case studies show that distributed resources are being used to
improve service at the regional, local, and individual customer level in a cost-effective manner.The case studies identified a few common pitfalls that can hamper project performance if notrecognized from the beginning For example, most proposed permanent installations of
distributed resources that require some type of air emissions and zoning permits Using
standardized system designs will speed procurement, reduce installation costs, and improveoperating reliability Investing extra effort during final testing and startup will improve
performance after the project is placed in service Units should be tested and checked regularly toensure their readiness for unexpected needs All readers, especially system planners, are
encouraged to fully review the survey responses in Appendix A Each response presents a uniqueexperience and provides insight into how distributed resources can be used as a power deliverytool
EPRI Perspective
The cases presented in this report and insights gained from these demonstrate that it is possible touse combustion turbines (CTs) and internal combustion engines (ICEs) for grid support Thereare still significant barriers in place that will inhibit broad proliferation, but the distributed
resource technologies are mature
Trang 9Distributed resources can support power delivery systems and defer capital transmission anddistribution (T&D) projects This potential, however, has yet to be widely understood due to thelack of well-documented examples Too often, the role of distributed resources in grid support isoverly simplified by both advocates and skeptics, without consideration of actual evidence Thisreport reviews specific examples of utilities using combustion turbines and reciprocating engines
to support the power grid The report describes common challenges in planning, developing,installing, and operating distributed resources in grid support The project team started by
identifying utilities across the country that were known to be using distributed resources for gridsupport, then developed a survey to elicit information about these projects Since distributedresources can provide both utility power-supply requirements and grid support, the survey
questions help confirm the primary objectives of these projects The cases presented in thisreport and insights gained from these demonstrate that it is possible to use combustion turbines(CTs) and internal combustion engines (ICEs) for grid support There are still significant barriers
in place that will inhibit broad proliferation, but the technologies are proven
Trang 11The authors acknowledge the contributions of the following utilities, without whom this reportwould not have been possible:
• Alliant Energy, Cedar Rapids, IA
• Central Hudson Gas & Electric, Poughkeepsie, NY
• Central Virginia Electric Cooperative, Lovingston, VA
• Dakota Electric Association, Farmington, MN
• East Mississippi Electric Power Association, Meridian, MS
• Exelon/ComEd, Chicago, IL
• Grant County Public Utility District, Ephrata, WA
• Madison Gas & Electric, Madison, WI
• Old Dominion Electric Cooperative, Glen Allen, VA
• Powder River Energy Cooperative, Sundance, WY
• Snapping Shoals Electric Membership Corporation, Covington, GA
• Wisconsin Public Service, Green Bay, WI
Trang 131 EXECUTIVE SUMMARY 1-1
2 INTRODUCTION AND SCOPE 2-1
Introduction 2-1 Report Overview 2-1
3 GRID SUPPORT WITH DISTRIBUTED RESOURCES 3-1
4 TECHNOLOGY OVERVIEW 4-1
Reciprocating Engines 4-1 Combustion Turbines 4-2 Conventional CTs 4-2 Microturbines 4-3 Generator Comparisons, Specifications, and Related Technologies 4-4
5 GENERAL ENVIRONMENTAL CONSIDERATIONS 5-1
6 CASE STUDY PROFILES 6-1
Summary of Responses 6-2 Summary Discussion by Case 6-4 Alliant Energy 6-4 Central Hudson Gas & Electric 6-5 Central Virginia Electric Cooperative 6-5 Exelon/ComEd 6-7 Dakota Electric Association 6-7 East Mississippi Electric Power Association and Tennessee Valley Authority 6-7 Grant County Public Utility District 6-10 Madison Gas & Electric 6-11 New York Power Authority 6-11
Trang 14EPRIsolutions Licensed Material
xii
Old Dominion Electric Cooperative 6-13 Powder River Energy Cooperative 6-13 Snapping Shoals Electric Membership Corporation 6-14 Wisconsin Public Service 6-14
7 LESSONS LEARNED 7-1
Lessons for Planners 7-2
A CASE SURVEY RESPONSES A-1
Trang 15LIST OF FIGURES
Figure 1-1 Distributed Resources at a Distribution Substation – East Mississippi Electric
Power Association and Tennessee Valley Authority 1-2
Trang 17LIST OF TABLES
Table 3-1 Primary Reasons for Distributed Resource Grid Support by Beneficiary 3-2 Table 3-2 Rationales for Grid Support Using Distributed Resources 3-3 Table 3-3 Distributed Resource Project Implementation, Operations, and Maintenance 3-4 Table 6-1 Study Participants, Separated by Ownership Structure 6-1 Table 6-2 Summary of Generators used by Case Participants 6-1 Table 6-3 Case Summaries and Comparisons 6-3 Table 6-4 EMEPA’s 10-Year Net Present Value Comparison of Alternatives 6-9
Trang 19customer and utility needs, a suitable site, and a willingness to examine conventional thinking to
realize grid support benefits.
The case studies demonstrate that the use of distributed resources for grid support is no longer alofty, unattainable concept, but is truly occurring at utilities of all sizes around the country.Providing grid support from distributed resources can be difficult, but the case studies show that
a variety of approaches can help utilities achieve their objectives
The primary drivers for utilities profiled include:
• Deferral of capacity increases in substations or transmission lines
• More reliable customer service through a redundant electric service source at the customerlocation, or at a substation that is close to the customer
• Reduction of distribution circuit overload and improvement in outage restoration time
• Relief of transmission system congestion
The examples of distributed resources for grid support encompass several generation
technologies, various placements on the power delivery system, and utility types that range frominvestor-owned to cooperatives and public power The case studies show through actual practicethat distributed resources for grid support cannot be narrowly defined; they are not a solution foronly one type of problem, nor is there any one “best” approach The range of power deliveryproblems and available creative resources are the only defining elements
Grid support is not realized in every application of distributed resources Grid benefits resultonly after careful planning and implementation focused on solving power delivery problems.Distributed resources can have unintended effects, such as burdening the grid through impropersiting or incompatible operations Distributed resources can also be of negligible support whenexisting power delivery systems already have sufficient capacity and reliability Applicationsthat do not support the grid help underscore the significance of the featured cases that do; in thepresented cases, significant grid support occurred while other objectives were met, often withdirect customer benefits
Trang 20EPRIsolutions Licensed Material
Distributed Resources at a Distribution Substation – East Mississippi Electric Power
Association and Tennessee Valley Authority
The following thirteen utilities offered case studies for this report:
• Alliant Energy
• Central Hudson Gas & Electric
• Central Virginia Electric Cooperative
• Dakota Electric Association
• East Mississippi Electric Power Association and Tennessee Valley Authority
• Grant County Public Utility District
• Madison Gas & Electric
• New York Power Authority
• Old Dominion Electric Cooperative
• Powder River Energy Cooperative
• Snapping Shoals Electric Membership Corporation
• Wisconsin Public Service
Trang 21Executive Summary
The case study examples in this report show how the potential of distributed resources to supportelectric power delivery systems can be realized Although every case had its own problems withthe technology, the local site, and public acceptance, none of these problems proved to be
overwhelming obstacles
These cases are far from the entire population (of possible cases), however their diversity
represents it well As these cases illustrate, the potential for grid support is real and the benefitsare achievable These cases should convince many in the industry that distributed resources arenow a serious alternative in terms of capacity and reliability, and are worthy of consideration inplanning electric power delivery systems
Trang 232
INTRODUCTION AND SCOPE
Introduction
Distributed resources can support power delivery systems and defer significant capital
transmission and distribution (T&D) projects However, this potential has yet to be widelyrealized due to the lack of well-documented case examples Too often, the role of distributedresources in grid support is overly simplified by both advocates and skeptics, without
consideration of actual evidence
This report critically reviews specific examples of utilities using combustion turbines or
reciprocating engines to support the power grid The report also describes common challenges inthe planning, development, installation, and operation of distributed resources in grid support
This report seeks to improve industry knowledge of distributed resources and advance the debatefrom generalities to utility engineering and economic analysis that is proven by specific casestudies
The report reveals the difficulties and successes of applying distributed resources to solve T&Dexpansion problems The case studies of current projects provide utility engineers and theirmanagers with the examples they need to evaluate distributed resources within the context ofpower delivery planning
Report Overview
The remainder of the report is divided into the following sections:
• Section 3 discusses how utilities are currently using distributed resources (DR) to providegrid support
• Section 4 discusses the background of the combustion turbines and reciprocating enginesused in the case studies
• Section 5 provides background on environmental considerations for the case studies
• Section 6 profiles utility case studies and presents tabular summaries of key data
• Section 7 provides a synopsis of tips and insights gleaned from the case studies
• Section 8 highlights key points that power delivery system planners should consider whenreviewing system performance and developing plans to meet future needs
• Appendix A presents the complete survey responses submitted by the 13 utilities that
provided case-study information for this report
Trang 253
GRID SUPPORT WITH DISTRIBUTED RESOURCES
All 13 utilities that provided information for this study indicated that their distributed resourceprojects offered some form of grid support The following list illustrates which types of gridsupport were offered and which utilities offered them:
• Deferral of distribution substation capacity increases – Alliant Energy, Dakota ElectricAssociation, Exelon/ComEd
• Deferral of providing a looped transmission system – Central Hudson Gas & Electric
• Provide a redundant supply source to a distribution substation bus – Central Hudson Gas &Electric, Grant County Public Utility District
• Provide a redundant supply source to a group of customers demanding improved servicereliability – Central Hudson Gas & Electric, Dakota Electric Association, East MississippiElectric Power Association, Madison Gas & Electric, Old Dominion Electric Cooperative,Snapping Shoals EMC
• Provide transmission or distribution system voltage support – East Mississippi ElectricPower Association, Madison Gas & Electric, Powder River Energy, Wisconsin Public
Service
• Improve outage restoration time – Exelon/ComEd
• Reduce overloads on distribution circuits – Exelon/ComEd
• Relieve transmission system congestion – New York Power Authority, Old Dominion
Electric Cooperative
As can be seen, these utilities had a variety of reasons for installing distributed resources Table3-1 summarizes the primary reasons and indicates which portion of the system benefited fromthe installation Some utilities indicated more than one area of primary emphasis This explainswhy there are sum of the counts is greater than thirteen
Trang 26EPRIsolutions Licensed Material
Grid Support with Distributed Resources
3-2
Table 3-1
Primary Reasons for Distributed Resource Grid Support by Beneficiary
DR Support Type Customer Distribution Transmission
Defer System Capacity
Defer Transformer Upgrade 2
Improve Reliability 3 3 2
Improve Voltage Support 3
Provide Redundant Capacity 1 4
Customer Retention 2
Limit Outage Duration 1
The primary driver indicated by the respondents for using DR was to improve reliability Innumerous cases a load with poor reliability was served with a single distribution line Forvarious reason, it was not practical to upgrade the existing line or bring addition lines Mostlybecause of the very long time required to make the changes Faced with few other alternative,
DR emerged as the best solution to reliability problem The units were place in or very near theload in question and the generator provide options for baseload, peak-shave or emergencyoperation In some cases, a DR units was leased which provided enough time to completedistribution upgrades or new line construction
A second common scenario occurs when a significant element or group of elements in theexisting power delivery system do not have adequate capacity to supply peak load demands andthe peak load duration is only a small portion of the year (typically less than 300 hours per year).Distributed resources can offer a possible solution because the combination of their capital andoperating costs, coupled with the economic savings from avoided power supply costs, may beless than the cost of upgrading power delivery systems by alternative methods Distributedresources can be moved to another location later when the load duration increases to a point thatthe alternative upgrade becomes justified
Table 3-2 summarizes the rationales that each utility provided for using distributed resources.For more details on each utility’s circumstances and needs, see Section 6 and the case-studyinformation in Appendix A
Table 3-3 summarizes the project implementation methods, project installation costs, operatingexperience, and maintenance experience associated with development of distributed resources.Some utilities used the design-bid-build project implementation process; others used the design-build process
Trang 27Grid Support with Distributed Resources
Table 3-2
Rationales for Grid Support Using Distributed Resources 1
Survey Topic Alliant Energy
Central Hudson Gas &
Electric
Dakota Electric Association
Madison Gas &
Electric
East Mississippi
T&D System Capacity Addition Deferral Yes Yes No No Yes Yes
At what level (single customer, dist., trans.)? n/a
Provide redundant capacity for contingencies? No Yes Yes Yes Yes Yes
Survey Topic
Central Virginia Electric Cooperative
New York Power Authority
Old Dominion Electric Cooperative
Grant County Public Utility District
Powder River Energy Corp./
Basin Electric
Snapping Shoals EMC
Wisconsin Public Service
At what level (single customer, dist., trans.)? distribution
transmission &
distribution distribution all transmission single customer
transmission &
distribution
Provide redundant capacity for contingencies? No Yes Yes Yes Yes Yes No
1
For more detailed information than this table can provide, see Appendix A.
Trang 28EPRIsolutions Licensed Material
Grid Support with Distributed Resources
3-4
Table 3-3
Distributed Resource Project Implementation, Operations, and Maintenance
Survey Topic Alliant Energy
Central Huds on Gas & Electric
Dak ota Electric
As s ociation
Madis on Gas &
Electric
Eas t Mis s is s ippi
nothing anticipated
Future air quality
Base could close, Rate may end, T line could be built
Poor perf ormance, lack of application, excessive O&M costs
turnkey to
Emissions-6-12 months
Emissions & oil retainage - 4
not enough experience
Survey Topic
Central Virginia Electric Cooperative
New York Power Authority
Old Dominion Electric Cooperative
Grant County Public Utility Dis trict
Powder River Energy Corp./
Bas in Electric
S napping
S hoals EMC
Wis cons in Public S ervice
W hat might b ring the project to an end?
Premature customer contract termination, sale to third party
Ongoing litigation
to limit operation
to 3 years
Transmission improvements to relieve congestion
w ould permit units
to be relocated to improve reliability
1 year emergency license provision Pursuing permanent license
Changes in EPA pollution requirements
The addition of a large base load
or large peaking generator peaking unit
How was project implem ented?
Turnkey to customer
design build by
W hat permits were required/how long to get?
emissions - 3 months
emissions - 3-4
Emissions & zoning
8 w eeks, acoustical 4
w eeks
A ir quality 4 months
A ir quality, f uel storage
Emissions 2 months, interconnection 3 months
$216 +f ound &
Maintenance costs?
$71,233/yr total
f or 13 units
Still in dow n mode See
A pprox $10/kW/yr
Failures? (after com missioning)
SCA DA & onsite
Trang 29Grid Support with Distributed Resources
In most cases, some permits or licenses were required; these applications need to be made at thevery beginning of project design so that authorization can be obtained in time for project
construction Air emissions and zoning/land use permits were the most common requirements.Temporary installations with less than a one-year lifetime require fewer permits than permanent
or long-term installations
Several utilities split the project implementation into two parts They hired a turnkey vendor to
do the complete generator design, procurement, and installation, then used their own personnel tocomplete the electrical connections to the utility grid, complete the control system connections,and perform the final check-out and startup
Diesel generators typically cost $300 to $400 per kW for permanent installations, or they areleased for short-term projects Operating costs are ten cents per kilowatt-hour or less, depending
on fuel prices Combustion turbines tend to cost more to install, but are less expensive to
operate Combustion turbine projects should be evaluated individually to account for specificdesign and construction variations Most utilities use their system control and data acquisitionsystem or dial-up methods to monitor the project equipment
Trang 314
TECHNOLOGY OVERVIEW
While a number of technologies may be suitable for grid support, the scope of this report wascombustion turbines and reciprocating engines The discussion in this section provides a generaloverview of the distributed resource technologies used in the cases
Reciprocating Engines
Nine of the thriteen case studies were projects using reciprocating engines Although these ninereciprocating engine projects were unique, each used diesel engines These engines typicallyoffer the following advantages:
• Low cost
• Utilities have used them previously with favorable results
• The economic benefits from wholesale rate incentives for peak shaving adequately cover thecost of using diesel generators, if they are operated less than 300 hours per year
• Diesel projects can be implemented within a relatively short time (2 to 6 months)
• Rental equipment is readily available
• Generators can be easily moved from one location to another
• Diesel engines have quick start capability
Most study participants agreed on the above advantages and often used these points as a rationalefor their projects Some of their comments include:
• “The generators provide savings to the cooperative.” – Central Virginia Electric Cooperative
• “Sixty to 70% of the units are customer leased, based on favorable economics.” – Dakota
Electric Association
• “Reciprocating engines are the best choice for back-up generators.” – Madison Gas &
Electric
• “The project was completed in six months.” – East Mississippi Electric Power Association
• “Mobile generators were identified as the best solution to improve customer satisfaction.” –
Exelon/ComEd
• “Fast track distributed generation…may be dispatched to relieve congestion.” – Old
Dominion Electric Cooperative
Trang 32EPRIsolutions Licensed Material
Technology Overview
4-2
• “These generators were available to us at the time the project was approved.” – Grant
County Public Utility District
• “Diesel engines provide quick-start capabilities.” – Snapping Shoals EMC
• “Leasing portable units was the quickest and most economical solution to the problem.” –
Wisconsin Public Service
As demonstrated in the above comments, mobility and quick installation were recurring themesthat made diesel generation more attractive than other alternatives However, diesel reciprocatingengines have their limitations of their own:
• Diesel reciprocating engines require regular test starts to confirm that the units are ready forfast start-up
• Reliability issues such as overheating problems, lubrication problems, and air intake
problems can cause unplanned shutdowns For more details, see Appendix A (questions 4.3and 5.6 in the survey responses)
• The possibility exists for diesel engines to run out of fuel if not routinely monitored andregularly supplied
• The potential exists for fuel leaks and spills
• Diesel engines create high noise and emissions levels
These issues are important and can be addressed in a variety of ways Under the case
circumstances, however, these limitations were either outweighed by other factors, temporarilydeferred, or of little concern, depending on the case For more discussion of these issues and thetechnologies to address them, see Section 6
Combustion Turbines
Four of the thirteen case studies were projects that used combustion turbines Some slightvariations were found in turbine and fuel type Three of the four cases employed traditional CTtechnology, using natural gas or coal bed methane as fuel, and another used microturbine
technology running propane fuel Differences between CTs and diesel reciprocating engines areevident
The CT market was almost exclusively made up of Conventional CTs (those generally sized onthe order of megawatts) until recently Microturbines in the kW range are a relatively recentdevelopment
Conventional CTs
Given the longer history and predominance of conventional CTs, it was no surprise to find thatthree of four CT projects were using them As representative of the market in general, theydiffered in size and fuel type (Specific details are provided in Section 6.) Using conventional
CT technologies for grid support has several advantages:
• Conventional CT units are manufactured in sizes large enough to meet project requirements
Trang 33Technology Overview
• They operate well using natural gas fuel
• CT units can be installed quickly to meet project requirements
Again, our study showed a high degree of overlap between the characteristics of the technologyand the reasons cited for its selection Specific examples include:
• “No alternative other than this was available to meet [grid] capacity needs [for 2001].” –
New York Power Authority
• “This DG option is simply the most practical and expedient.” – Powder River Energy
Corporation
However, utilities that consider using conventional CTs must also consider the following
limitations of the technology:
• They are much less mobile than small diesel units
• They require more planning and more site work for a typical installation
• They are not commonly available on a rental basis
• Renewal of emissions permits may become more difficult in future years
In fact, changing emissions requirements may limit the total number of years certain large scale
DG installations can operate before they must be shut down or modified to meet stricter limits
For more discussion of these issues and the technologies to address them, see Section 6 andAppendices B and C
Microturbines
Microturbines typically range from 30 to 75 kW, and are seen by some as offering great potentialfor grid support Beyond the benefits of conventional CTs, microturbines promise:
• Similarly cost-effective to CTs when deployed in multi-unit packs
• Low emissions without supplementary equipment
• Small, compact installation suitable for individual customer environments
As with any developing technology, however, price alone may be a prohibitive factor untileconomies of scale are reached Other challenges faced by microturbines include:
• Optimizing the technology to obtain many hours of trouble-free operation
• Developing cost-effective inverter systems that can easily handle both interconnected andstand-alone operation
This balancing of opposing forces is demonstrated in the following response from Alliant:
Trang 34EPRIsolutions Licensed Material
Technology Overview
4-4
“This project will enable Alliant Energy to better understand the operation of Capstone
Microturbines…We are particularly interested in how the units will respond through numerous start-stop sequences.”
Generator Comparisons, Specifications, and Related Technologies
A wide breadth of technologies can be used effectively for grid support, including reciprocatingengines and CTs, among others Additionally, many meaningful differences exist within aparticular technology, such as the availability of “intercooled recuperated cycle” combustionturbines and “high-pressure gas-injected dual-fuel” engines Incorporating DR into a system isnot a simple process of selecting “reciprocating engine” or “CT” and then moving forward withthe permits Narrowing the possibilities to the most appropriate technologies requires answers tothe following questions:
• What unit sizes are desired?
• What are the anticipated hours of operation per year?
• What fuel options are available?
• What installation timeframe is required?
From there, case specifics will likely determine the next considerations or series of questions
Trang 355
GENERAL ENVIRONMENTAL CONSIDERATIONS
Although distributed resource technologies offer significant potential for grid support, theirbenefits, costs, and viability as a whole must be viewed within the context of their environmentalimpacts Permitting and siting requirements will differ from project to project, but typicallyinclude the following factors:
• Air emissions
• Land use
• Noise (acoustical)
• Oil spill containment
Factors that influence permitting and siting requirements, along with the time and effort to obtainsuch permits, are:
• Location relative to adjacent land uses
• How long the project will operate
• The size and number of units at one location
In our study, each utility faced particular environmental considerations We asked in Question
5.1 of the survey, “What permits were needed and how long did it take to get each of them
approved (emissions, water, waste water, interconnection, acoustical, zoning, other)?”
Generally speaking, air emissions represented the most common permit requirement; such
permits took two to four months to obtain Air emissions concerns mainly focused on NOx, but
in some cases addressed greenhouse emissions and other air quality issues The permits that wererequired, and the time needed to obtain them in each case, are presented in Table 3-3 of
Section 3 Additional discussion of the environmental considerations in each case is reported inSection 6, and the direct survey responses are available as Appendix A
Trang 376
CASE STUDY PROFILES
Twenty-three utilities thought to be using DG for grid support were contacted Thirteen utilitiesresponded with information about their programs and projects Four utilities did not respond toour inquiries; the rest were either unable to respond fully because they had no qualifying
projects, were prohibited from responding due to management direction, or did not have thetime This section presents a general summary of the 13 utility responses that became casestudies for this project
The participating utilities represented three separate types of corporate governance and
ownership, as shown in Table 6-1
Table 6-1
Study Participants, Separated by Ownership Structure
Investor Owned Utilities Public Power Authorities Electric Cooperatives
Alliant Energy New York Power Authority Dakota Electric Association
Central Hudson Gas &
Electric Snapping Shoals EMC
The respondants indicated that the following types of DR units were used by the participatingutilities:
Table 6-2
Summary of Generators used by Case Participants
Generator Types
Total Units
Total Net Capacity Fuel Type
3 utilities used combustion
Trang 38EPRIsolutions Licensed Material
Case Study Profiles
6-2
The majority of these projects were installed between 1998 and 2001; the earliest project wasinstalled in the 1970s, and one project is currently being completed All thirteen projects providegeneration capacity to the grid, although three do so indirectly by providing standby power toindividual customers who voluntarily interrupt their load at times of system peak All 13
projects in some form, improve service reliability at the customer, distribution system, or
transmission system level
Summary of Responses
Table 6-3 summarizes the cases, listing the utilities in alphabetical order The table has beensplit into two sections to improve readability The table portrays the key characteristics of the
DR projects and the primary justification for installing them
The 13 responses broadly illustrate the types of distributed resources used across the UnitedStates Other DR projects are in operation and could be surveyed in the future to build a strongerdatabase For example, Wisconsin alone has approximately 10 investor-owned utilities, 70municipal utilities, and 25 cooperative electric utilities Various contacts and reports suggestthat at least half these utilities have some type of distributed resource installations, or haveutility-sponsored customer ownership programs This indicates that DR technologies have broadrecognition and acceptance as a way of meeting the electric energy needs of individual
customers These examples show that distributed resources can be used effectively to supportvarious transmission and distribution system deficiencies, in addition to meeting electric systemgeneration requirements
Table 6-3 shows that diesel-fueled combustion turbines and reciprocating engines are commonlyused in a variety of applications In every case, the installations provided better service
reliability to customers, along with various levels of support for transmission and/or distributionsystem voltage and other forms of capacity relief
Trang 39Case Study Profiles
Table 6-3
Case Summaries and Comparisons
S urvey Topic Alliant Energ y
Central Huds on Gas & Electric
Dak ota Electric
Combus tion Turbines
Rec iproc ating Engines
Rec iproc ating Engines
Rec iproc ating Engines
Rec iproc ating Engines
S ize k W & Install Date
Four 30 kW - 6/29/01
Tw o 25 MW - late 70's
Sev enty - 50 kW
to 14 MW 2000-01
Forty - 550 to
2250 kW - 01
2000-Fiv e - 1825 kW 1/1/98
Three - 2000 kW Spring, 2001
all Diesel, nat'l gas
Top 2-3 Reasons For Project
1 Def er Sub trans f ormer upgrade
1 Trans miss ion
c ustomers , buildings , neighborhoods
2 Unders tand Caps tone Mic roturbines
2 Bac kup f or dis t transf ormer
f ailure
2 Cus tomer reliability
2 Generators
av ailable f or grid
s upport
2 Improv e s y s tem reliability
2 Prevent dis tribution s ub and c irc uit
ov erloads
not prov ided
3 Sy s tem generation
3 Improv e v oltage regulation
3 Provide
s tandby capacity
to reduc e outage duration
Tim e from projec t authorization
S urvey Topic
Central Virg inia Electric Cooperative
New York Power Authority
Old Dominion Electric Cooperative
Grant County Public Utility Dis trict
Powder River Energ y Corp./
B as in Electric
S napping
S hoals EMC
W is cons in Public S ervice
Generator Type
Rec iproc ating Engines
Combus tion Turbines
Rec iproc ating Engines
Rec iproc ating Engines
Combus tion Turbines
Rec iproc ating Engines
Rec iproc ating Engines
S iz e k W & Ins tall Date
One of Tw elv e -
2000 kW 11/1999
Elev en - 44 MW 6/1/2001
Ten - 2000 kW
In progres s
Tw enty - 1600 kW 7/2001
Three - 5 MW 1s t Qtr, 2002
Fiv e - 1.85 MW 3/1999 Three - 1.85 MW In- progres s
Sev enty - 68 to
1500 kW Total
102 MW 6/1/2001
24.9, 69, 115, &
138 kV
Top 2-3 Reas ons For P rojec t
1 Competitiv e reas on to improv e reliability
1 NY PA obligation to
s upply 80% of
NY C peak demand In City
1 Reliability improv ement @ deliv ery points
w ith c ritic al loads
or undes irable reliability
1 Capac ity to
c ov er low w ater
y ear f or hy dro units
1 V oltage s upport
f or radial 69 kV trans mis s ion
1 Prov ides low er
c os t peaking pow er during Summer
1 Meet res erv e
c apac ity requirement of
to s y s tem
2 Prov ide v oltage
& s y s tem s upport
to trans mis s ion
3 Prov ide low er pric ed energy during high c os t periods
3 Blac k s tart
c apability if grid
3 Prov ides bac kup f or HQ
w hen Subs tation
is outaged
3 Reduc e ris k to market pric ing
Continuing bas ed
on generation needs
Tim e from projec t authoriz ation
to c om m erc ial s ervic e?
$216 +f oundation
Trang 40EPRIsolutions Licensed Material
Case Study Profiles
6-4
Summary Discussion by Case
A condensed profile of each case study is provided in the following summaries The surveyresponses were the primary source of information for most of the report Confidentiality
concerns limited the information that some utilities were willing to provide Utility web sitesand presentations provided additional information for the Alliant Energy, East Mississippi, andNew York Power Authority case studies
Alliant Energy
Alliant Energy (Cedar Rapids, IA) presented its Capstone Microturbine project to defer a
distribution substation capacity upgrade in a straightforward application of distributed resourcesnear Racine, Minnesota Alliant reports that the project construction and startup was completedwith relative ease The project started operating on June 29, 2001, and the longest-running unithas logged 66 hours to date with no problems
Alliant Energy’s utility operations serve more than 1.2 million customers in mid-sized cities andrural areas within Iowa, Illinois, Minnesota, and Wisconsin Alliant’s service territory covers54,000 square miles, with more than 9,700 miles of transmission lines and 8,000 miles of naturalgas mains Alliant was formed by the merger of IES Utilities, Interstate Power Company, andWisconsin Power and Light Company
Alliant’s rural Racine Junction Substation is a 24.9-12.47 kV, 750-kVA substation The peakload on the substation was 842 kW (112% of capacity) in 1999 Alliant examined three
alternatives to resolve the substation transformer overload:
• Alternative #1 involved upgrading the substation and replacing the substation transformerswith three new 500-kVA units at an expected cost of $111,000
• Alternative #2 involved converting the circuit to 24.9 kV from 12.47 kV
• Alternative #3 was to install four 30-kW Capstone Microturbines to alleviate substationtransformer overloading during peak load periods
Alliant opted to use the Capstone Microturbines to gain firsthand, working knowledge of the use
of distributed resources on the utility system The Capstone Microturbines were placed in
service on June 29, 2001 and are fueled with propane The generators are to be used during thesubstation peak load period to defer a capacity upgrade and permit Alliant to better understandthe load growth in the area before committing to a final, long-term solution Alliant also hopes
to gain operating experience to better understand the performance of the Capstone
Microturbines
This project was developed in a design-build fashion using Alliant engineers Planning anddesign began in November 2000 Air quality permits were not required, but the County Planningand Zoning Committee required a Conditional Land Use Permit for the site, which took fourweeks to obtain