Skeletal frames constructed from reinforced concrete RC or steel columns and beams were in-filled with non-load-bearing or semi-load-bearing GFRP panels manufactured by the wet lay-up pr
Trang 1During the introduction of FRP composites into the
building and construction industry in the 1970s glass
fibres were used in a polyester matrix as a construction
material Skeletal frames constructed from reinforced
concrete (RC) or steel columns and beams were
in-filled with non-load-bearing or semi-load-bearing
GFRP panels manufactured by the wet lay-up
pro-cess or by the spray-up technique to form structural
buildings Several problems developed owing to a
lack of understanding of the FRP material, mainly
arising from insufficient knowledge of its in-service
properties relating to durability and the enthusiasm
of architects and fabricators for developing geometric
shapes and finding new outlets for their products
without undertaking a thorough analysis of them
Consequently, to improve certain physical properties
of the FRP some additives were incorporated into
the polymers by the fabricators without a full
under-standing of their effect on the durability of the FRP
material, or indeed were omitted in cases where
additives should have been added
Advanced polymer composites did not enter the
civil engineering construction industry until the middle
to late 1980s; polyester and epoxy polymers were used
initially and vinylester was introduced in the 1990s
From the 1970s, universities, research institutes and
industrial firms have been involved in researching the
in-service, mechanical properties of FRPs and in the
design and testing of structural units manufactured
from fibre/polymer composites This was followed
by the involvement of interested civil engineering
consultants undertaking industrial research and the
utilisation of the structural material in practice The
application of advanced polymer composites, over
the past 35 years for the building industry and the
past 25 years for the civil engineering industry, can
be conveniently divided into some specific areas, which
will be discussed briefly in this chapter:
• Building industry:
• infill panels and new building structures
• Civil engineering industry:
• civil engineering structures, fabricated en tirely from advanced polymer composite
ma-terial, known as all-polymer/fibre composite structures
• bridge enclosures and fairings
• bridge decks
• external reinforcement rehabilitation and retrofitting to RC structures (including FRP confining of concrete columns)
• external reinforcement rehabilitation and retrofitting to steel structures
• internal reinforcement to concrete members
• FRP/concrete duplex beam construction
• polymer bridge bearings and vibration absorbers
All these, other than the first, involve a combination
of advanced polymer composites and conventional construction materials and are therefore often termed
composite construction.
FRP composites are durable and lightweight and consequently they can fulfil many of the requirements
of structural materials for many forms of construction Ideally when new civil engineering structures are manufactured from polymer composite systems the component parts should be modular to provide rapid and simple assembly An example of the importance
of this is in the installation of highway infrastructure, where any construction or long maintenance period
of the infrastructure will cause disruption to traffic flow and will be expensive
The examples of the applications of polymer fibre composites in those areas that we will discuss in this chapter have been chosen to illustrate all the areas of use listed above
43.1 The building industry
During the 1970s two sophisticated and prestigious GFRP buildings were developed and erected in the
Applications of FRP
composites in civil
engineering
Trang 2UK, Mondial House, the GPO Headquarters in
London (Berry, 1974) and the classroom of the
primary school in Thornton Clevelys, Lancashire;
these are discussed below Other FRP buildings that
were erected during this period were Covent Garden
Flower Market (Roach, 1974; Berry, 1974), the
American Express Building in Brighton (Southam,
1978), and Morpeth School, London (Leggatt, 1974,
1978) These structures played a major role in the
development of polymer composite materials for
construction Because of the relatively low modulus
of elasticity of the material, all except one of these
buildings were designed as folded plate systems
and erected as a composite modular system, with
either steel or reinforced concrete units as the main
structural elements and the GFRP composite as the
load-bearing infill panels The exception to this is
the classroom of the primary school, Thornton
Clevelys, Lancashire, UK (Stephenson, 1974), which
is entirely manufactured from GFRP material
43.1.1 MondiAl House, eReCted on tHe
noRtH bAnk oF tHe tHAMes in
london 1974
This building was clad above the upper ground floor
level and the panels were manufactured from glass
fibre polyester resin The outer skin of the panel
included a gel coat that used isophthalic resin,
pig-mented white, with an ultraviolet stabiliser backed
up with a glass fibre reinforced polymer laminate; the
latter used a 3 oz per square foot chopped strand mat
and a self-extinguishing laminating resin reinforced
with 9 oz per square foot glass fibre chopped strand
mat reinforcement Some degree of rigidity was
obtained from a core material of rigid polyurethane
foam bonded to the outer skin and covered on the
back with a further glass-reinforced laminate; this
construction also provided thermal insulation Further
strength and rigidity were obtained by the use of
lightweight top-hat section beams, manufactured as
thin formers and incorporated and over-laminated
into the moulding as manufacture proceeded The
effect of the beams was transferred to the front of
the panel by means of glass-fibre reinforced ties or
bridges formed between the polyurethane foam at
the base of each beam The face of the beam was
reeded on the vertical surfaces in order to mask any
minor undulations and to provide channels off
which the water ran and thereby cleaned the surface
The reeding also gave the effect of a matt panel
without reducing the high surface white finish
The structure was visually inspected in 1994 by
Scott Bader and the University of Surrey and the
degradation was found to be minimal It was
demolished in 2007 to allow for redevelopment of that area A part of the composite material from the demolished structure was analysed at the University
of Surrey for any variations in the mechanical properties due to the degradation of the composite material during its life (Sriramula and Chryssantho-poulos, 2009)
43.1.2 An ‘All-PolyMeR CoMPosite’
ClAssRooM oF PRiMARy sCHool, tHoRnton Clevelys, lAnCAsHiRe, uk, 1974
The classroom, shown in Fig 43.1, is an ‘all-
composite’ FRP building in the form of a geometrically modified icosahedron, and is manufactured from 35 independent self-supported tetrahedral panels of chopped strand glass-fibre reinforced polyester com-posite Twenty eight panels have a solid single skin GFRP composite and in five of these panels circular apertures were constructed to contain ventilation fans
In the remaining seven panels non-opening triangular windows were inserted The wet lay-up method was utilised to manufacture the E-glass fibre/polyester composite skins The inside of the panels has a 50
mm thick integral skin phenolic foam core acting
as a non-load bearing fire protection lining to the GFRP composite skins The icosahedron structure
is separated from the concrete base by a timber hardwood ring The FRP panels were fabricated onto a mould lining of Perspex with an appropriate profile to give a fluted finish to the flat surfaces of the panels The edges of the panels were specially shaped to provide a flanged joint, which formed the connection with adjacent panels Sandwiched between two adjacent flanges is a shaped hardwood batten, which provides the correct geometric angle between
Fig 43.1 The ‘all-polymer composite’ classroom of the
primary school, Thornton Clevelys, Lancashire, UK.
Trang 3the panels; the whole is bolted together using
galvanised steel bolts placed at 450 mm intervals
The external joint surfaces between the adjacent
panels were sealed with polysulphide mastic The
glass windows were fixed in position on site by
means of neoprene gaskets The classroom was
designed by Stephenson (1974)
When the classroom structure was under
con-struction in 1974 a fire test at the BRE Fire Research
Station was undertaken on four connected GFRP
panels, with the integral skin phenolic foam in place
At the same time, tests were also undertaken on an
identical geometrically shaped school system used
at that time The results demonstrated that the GFRP
classroom had over 30 minutes fire rating whereas
the existing school system had only 20 minutes
These two descriptions of the Mondial House
and the school classroom at Thornton Clevelys have
been based on Hollaway (2009)
43.2 The civil engineering industry
The ‘all-polymer composite’ structure systems – like
those of the building industry produced to date –
have tended to be single prestigious structures,
manufactured from ‘building blocks’, Hollaway and
Head (2001) The advantages of this are:
• the controlled mechanised or manual factory
manufacture and fabrication of identical structural
units
• the transportation to site of the lightweight units,
which can be readily stacked; it is more
econom-ical to transport lightweight stacked FRP units
than the heavier steel and concrete units
McNaughton (2006) said: ‘The majority of the
Network Rail’s bridges in the UK are 100 years old
and are constructed in a variety of materials, for
example cast iron, wrought iron, steel, reinforced
concrete, brick, masonry and timber Future
con-struction is likely to use more complex forms of
composite construction, in particular fibre reinforced
polymers, which are already being used to strengthen
bridges’
Examples of some of these ‘more complex
struc-tures’ are the Aberfeldy Footbridge, Scotland (1993),
the Bonds Mill Single Bascule Lift Road Bridge,
Oxfordshire (1994) (Head, 1994), Halgavor Bridge
(2001) (Cooper, 2001), the road bridge over the
River Cole at West Mill, Oxfordshire (2002) (Canning
et al., 2004), the Willcott Bridge (2003) (Faber
Maunsell, 2003), the New Chamberlain Bridge,
Bridgetown, Barbados (2006) and the Network Rail
footbridge which crosses the Paddington–Penzance railway at St Austell, UK (2007) An innovative
£2 million Highways Agency super-strength FRP composite bridge (The Mount Pleasant Bridge) was installed in 2006 over the M6, between Junctions
32 and 33; the structure won the National Institu-tion of Highways and TransportaInstitu-tion Award for Innovation in June 2007
All these structures were of modular construction, manufactured utilising advanced composite materials; for the construction to be successful the material had to be durable, and assembly of the units had to
be rapid and simple with reliable connections As
we have already seen advanced polymer composite materials are durable and lightweight and conse-quently they fulfil these requirements, provided that the initial design of the basic building modular system is properly undertaken and the material properly installed
A number of bridges have used the concept of
the Maunsell structural plank, shown in Fig 43.2.
43.3 Bridge enclosures and
fairings
It is a requirement that all bridge structures have regular inspection and maintenance, which will often cause disruption to travellers, particularly if closure of roads and interruption to railway services are required Furthermore, increasingly stringent standards are causing the cost of closures to be high, particularly if maintenance work is over or beside busy roads and railways Most bridges that have been designed and built over the last 30 years do not have good access for inspection, and in Northern Europe and North America deterioration caused by de-icing salts is creating an increasing maintenance workload
The function of ‘bridge enclosures’ is to erect a
‘floor’ underneath the girder of a steel composite bridge to provide access for inspection and main-tenance The concept was developed jointly by the Transport Research Laboratory (TRL, formerly TRRL) and Maunsell (now AECOM) in 1982 to provide a solution to the problems Most bridge enclosures that have been erected in the UK have utilised polymer composites These materials are ideal because they add little weight to the bridge, are highly durable, and as they are positioned on the soffit of the bridge they are protected from direct sunlight
The floor is sealed on to the underside of the edge girders to enclose the steelwork and to protect it
Trang 4from further corrosion Once the enclosures have been
erected the rate of corrosion of uncoated steel in the
protected environment within the enclosure is 2–10%
of that of painted steel in the open (McKenzie, 1991;
1993) The enclosure space has a high humidity;
chloride and sulphur pollutants are excluded by
seals and when condensation does occur (as in steel
girders) the water drops onto the enclosure floor,
which is set below the level of the steel girders from
where it escapes through small drainage holes
Figure 43.3 shows an example of the enclosure
on the approach span of the Dartford River Bridge
(QE2) where it passes over the Channel Tunnel rail
link (CTRL) (before the train rails were laid)
43.4 Bridge decks
The development of FRP deck structures has been
based generally on the pultruded systems, but
occasion-ally on moulded structures Recently FRP deck
80
3
Plank cross section Connector
cross section
Box beam cross section 2310
80 × 80 voided connector
603 × 80 voided plank
Notes (i) All dimensions are in millimetres (ii) All voids are 80 × 76 mm Key
760
Fig 43.2 The Maunsell structural plank (Hollaway and Head, 2001, by permission, Elsevier).
Fig 43.3 Photograph of the enclosure on the approach
span of the Dartford River Bridge (QE2) where it passes over the CTRL (before the train rails were laid) (Courtesy of AECON).
Trang 5replacements in conjunction with FRP superstructure
replacement for road bridges have been carried out
This type of construction is becoming popular for
replacement decks of bridges up to 20 m span
Figure 43.4 illustrates a typical cross-section of a
bridge deck The reasons for FRP material being
used in particular circumstances are:
• the bridge deck is the most vulnerable element
in the bridge system because it is exposed to the
direct actions of wheel loads, chemical attack,
and temperature/moisture effects including freeze–
thaw shrinkage and humidity; FRP material
characteristics satisfy these requirements
• reduced future maintenance (FRP composites are
durable materials)
• quick installation owing to prefabrication and
easy handling
In the USA over 100 concrete bridge decks have
been replaced by FRP deck installations, most of
which have been built using proprietary experimental
systems and details The lack of standardisation is
a challenge to bridge engineers, who traditionally
have been accustomed to standard shapes, sizes and
material properties The first FRP European bridge
deck and superstructure replacement was conceived
and developed under the innovative European ASSET
Project led by Mouchel Consulting It culminated
in 2002 in the construction of the West Mill Bridge
over the River Cole in Oxfordshire; the beam and
deck structures were manufactured by the pultrusion
technique
The first vehicle-carrying FRP bridge deck in the
UK to span over a railway replaced the existing
over-line bridge at Standen Hey, near Clitheroe,
Lancashire; it has a span of 10 metres, weighs
20 tonnes and was completed in March 2008 This
is the first of Network Rail’s six trial sites in the country The consultants Tony Gee and Partners were respon sible for the design of the deck, which comprises three layers of ASSET panel deck units made from E-glass fibres in the form of biaxial mats within a UV-resistant resin matrix
Composite Advantage (CA) has recently built (April 2008) a new ‘drop-in-place’ GFRP composite prefabricated integral beams and deck bridge super-structure, 6.77 m long by 19.0 m wide (22 feet by
62 feet) in Hamilton County, Ohio, USA No heavy lifting equipment was required and it took one day
to install (Composite Advantage, 2008)
A new single carriageway road bridge over the M6 motorway (UK) has recently been completed
by the UK Highways Agency The superstructure comprises a novel pre-fabricated FRP deck spanning transversely over, and adhesively bonded to, two longitudinal steel plate girders The Mouchel Group designed the FRP bridge deck, which provides general vehicular access to an equestrian centre
(Fig 43.5); this was designed for unrestricted traffic
loading (Canning, 2008)
43.5 External reinforcement to
reinforced concrete (RC) structural members
The repair, upgrading and strengthening/stiffening
of deteriorated, damaged and substandard infra-structure has become one of the fastest growing and
There are three types of FRP deck:
1 Honeycomb: core construction provides considerable flexibility in tailored depth,
however the wet lay-up method now employed requires painstaking attention to quality control in the bonding of the top and bottom face material to the core.
2 Solid core sandwich: solid core decks have foam or other fillers in the core.
3 Hollow core sandwich: consists of pultruded shapes fabricated together to form
deck sections FRP decks typically have continuous hollow core patterns, as shown above.
Wearing surface
Hollow core
Sandwich beam
Fig 43.4 A typical cross-section of an FRP bridge deck.
Trang 6most important challenges confronting the bridge
engineer worldwide It is generally much less
expensive and less time consuming to repair a bridge
or building structure than to replace it
Civil infrastructure routinely has a serviceable life
in excess of 100 years It is inevitable that some
structures will eventually be required to fulfil a role
not envisaged in the original specification It is often
unable to meet these new requirements, and
con-sequently needs strengthening Changes in use of a
structure include:
• Increased live load For example, increased traffic
load on a bridge; change in use of a building
resulting in greater imposed loads
• Increased dead load For example, additional
load on underground structures owing to new
construction above ground
• Increased dead and live load For example,
widening a bridge to add an extra lane of traffic
• Change in load path For example, by making
an opening in a floor slab to accept a lift shaft,
staircase or service duct
• Modern design practice An existing structure
may not satisfy modern design requirements; for
example, owing to the development of modern
design methods or to changes in design codes
• Design or construction errors Poor construction
workmanship and management, the use of inferior
materials, or inadequate design, can result in
deficient structures that are unable to carry the
intended loads
• New loading requirements For example, a
struc-ture may not have originally been designed to carry blast or seismic loads
• Material deterioration For example, concrete
degradation by the alkali–silica reaction or corrosion of steel reinforcement in marine or industrial environments or from the de-icing salts used on highways, all of which were discussed
in Chapter 24
• Structural deterioration The condition of a
structure will deteriorate with time owing to the service conditions to which it is subjected In some cases this deterioration might be slowed or rectified by maintenance, but if unchecked the structure will become unable to perform the purpose for which it was originally designed
• Fatigue This is a secondary cause of structural
degradation, and it can govern the remaining life
of a structure, as discussed in Chapter 2
Structural degradation can also result from hazard events, such as impact (for example, ‘bridge bashing’
by over-height vehicles), vandalism, fire, blast load-ing or inappropriate structural alterations durload-ing maintenance A single event may not be structurally significant, but multiple events could cause significant cumulative degradation to a structure
The following discussions and examples illustrate the strengthening of members by external bonding
of FRP plates or members These will be considered
as un-stressed at the time of bonding onto the structural beam It is however possible to pre-stress the plate before bonding it onto the beam; this is known as active flexural strengthening This topic will not be discussed here but further reading on it may be
found in Teng et al (2002) and De Lorenzis et al
(2008), and a practical example is cited in Hollaway (2008)
Many experimental and analytical research inves-tigations have been undertaken on reinforced con-crete beams strengthened by FRP composites; some
of these are discussed in Triantafillou and Plevris
(1991), Hollaway and Leeming (1999), Teng et al
(2002), Concrete Society Technical Reports (2000, 2003), Oehlers and Seracino (2004) and Hollaway
and Teng (2008) Both flexural and shear upgrading
can be undertaken using FRP composites
43.5.1 ReHAbilitAtion oF degRAded FlexuRAl RC stRuCtuRAl beAMs using FRP PlAtes
Within the scope of ‘strengthening’ concrete, it is essential to differentiate between the terms repair, rehabilitation, strengthening and retrofitting; these
Fig 43.5 Craning in the 100-tonne FRP deck onto
the supports of the bridge over the M6 (Courtesy of
Mouchel).
Trang 7terms are often erroneously interchanged but they
do refer to four different structural upgrading
procedures
• Repair to an RC structural member implies the
filling of cracks by the injection of a polymer
into the crack
• Rehabilitation of a structural member (of any
type) refers to the improvement of a functional
deficiency of that member, such as caused by severe
degradation, by providing it with additional
strength and stiffness to return it to its original
structural form
• Strengthening of a structural member is specific
to the enhancement of the existing designed
performance level
• Retrofit is used to relate to the upgrading of
a structural member damaged during a seismic
event
Bonding of FRP plates to the adherend
As with all bonding operations the adherends must
be free of all dust, dirt and surface grease
Conse-quently, the concrete or steel surface onto which
the composite is to be bonded must be grit blasted
to roughen and clean the surface It will then be air
blasted to remove any loose particles and wiped with
acetone or equivalent to remove any grease before
the bonding operation The surface preparation of
component materials of FRP composite plate
bond-ing to concrete surfaces is described in Hutchinson
(2008)
The thickness of the adhesive and FRP composite
plate would generally be about 1.0–1.5 mm and
about 1.2 mm, respectively; the total length of the
FRP plate as delivered to site would be of the order
of 18 metres It is possible to roll the material into
a cylinder of about 1.5 metre diameter for
trans-portation and for bonding the plate onto the beam
in one operation
Power actuated (PA) fastening ‘pins’ for
fastening FRP composites
This method, which has been recently developed, is
known as the Mechanically-fastened unbonded FRP
(MF-UFRP) method and is a viable alternative to
the adhesive bonding of a preformed pultruded or
a prepreg rigid plate It mechanically fastens the
FRP plate to the RC beam by using many closely
spaced steel power-actuated (PA) fastening ‘pins’
and a limited number of steel expansion anchors
The process is rapid and uses conventional hand
tools, lightweight materials and unskilled labour In
addition, the MF-UFRP method requires minimal
surface preparation of the concrete and permits immediate use of the strengthened structure The advantage of using multiple small fasteners as opposed
to large diameter bolts, which are generally used for anchorages, is that the load is distributed uniformly over the FRP strip and this reduces the stress con-centrations that can lead to premature failure The method was developed by researchers at the University
of Wisconsin, Madison, USA (Bank, 2004) Bank
et al (2003a, 2003b) have discussed the
streng-thening of a 1930 RC flat-slab bridge of span 7.3 m
by mechanically fastening the rigid FRP plates using the MF-UFRP method
Unstressed FRP plates
Figure 43.6 shows an FRP composite flexural plate
bonded in position The plate material used for the bonding or the MF-UFRP operations is generally the high-modulus (European Definition) CFRP, AFRP (Kevlar 49) or GFRP composite These will be fabricated by one of three methods:
• the pultrusion technique, in which the factory made rigid pre-cast FRP plate is bonded onto the degraded member with cold-cure adhesive polymer
• the factory made rigid fully cured FRP prepreg plate, which is bonded to the degraded member with cold-cure adhesive polymer
• the lowtemperature mould prepreg FRP prepreg/ adhesive film placed onto the structural member and both components are cured simultaneously
on site under pressure and elevated temperature (see Chapter 41, section 41.1.2)
The third method for the bonding operation is superior to the precast plate and cold-cure adhesive systems (first and second methods) as the site com-paction and cure procedure of the prepreg and film adhesive ensure a low void ratio in the composite and an excellent join to the concrete The current drawback to this method is the cost; it is about twice
as expensive as the other two, and the currently preferred manufacturing system for upgrading is either the first or the second method With these systems the plate material cannot be reformed to cope with any irregular geometry of the structural member In addition, a two-part cold-cure epoxy adhesive is used to bond the plate onto the substrate This is the Achilles’ heel of the system, particularly
if it is cured at a low ambient temperature since without post cure the polymerisation of the polymer will continue over a long period of time; this incom-plete polymerisation might affect the durability of the material
Trang 8Near-surface mounted (NSM) FRP composite
reinforcement technique
This is another method for the rehabilitation of RC
structural members CFRP, AFRP and GFRP
com-posites can be utilised and generally the cross-section
of the member is either circular or rectangular Grooves
are cut into the surface of the member, generally
into the soffit of the concrete beam, but if the cover
to the steel rebars is insufficient for this the grooves
may be cut into the vertical side of the beam as
near to the bottom of the section as is practical The
NSM FRP reinforcement is embedded and bonded
into this groove with an appropriate binder (usually
high-viscosity epoxy or cement paste) Figure 43.7
shows the position of NSM bars in an RC structural
member
The NSM reinforcement can significantly increase
the flexural capacity of RC elements Bond may be
the limiting factor to the efficiency of this technique
as it is with externally bonded laminates A review
of the technique has been given by De Lorenzis and
Teng (2007)
NSM FRP reinforcement has also been used to
enhance the shear capacity of RC beams In this
case, the bars are embedded in grooves cut into the
sides of the member at the desired angle to the axis
Utilising NSM round bars, De Lorenzis and Nanni
(2001) have shown experimentally that an increase
in capacity as high as 106% can be achieved, thus
when stirrups are used a significant increase can be
obtained
Flexural strengthening of pre-stressed
concrete members
Limited research has been undertaken on
strength-ening pre-stressed concrete (PC) members; the fib
have reported that less than 10% of FRP-strengthened bridges as of 2001 are pre-stressed (fib Task Group 9.3, 2001) Strengthening usually takes place when all long-term phenomena (creep, shrinkage, relaxation) have fully developed, which may com-plicate the preliminary assessment of the existing condition As in RC strengthening, the required amount of FRP will generally be governed by the ultimate limit state design in PC members Addi-tional failure modes controlled by rupture of the pre-stressing tendons must also be considered, and consideration should be given to limitations on cracking
Soffit Plate Adhesive layer U-strip composite anchor
Uniformly distributed load
Plated RC beam with FRP U-strip end anchorage
Section of beam
Fig 43.6 An FRP flexural plate bonded in position with cold-cure adhesive.
NSM FRP composite rod [either GFRP
or CFRP]
Steel rebar Steel stirrups
High viscosity epoxy or cenemt paste adhesive surrounding the NSM bar Main tensile steel rebars
Fig 43.7 Near-surface mounted (NSM) FRP composite
reinforcement technique.
Trang 9Seismic retrofit of RC columns
The properties of FRP composites (their light weight
and tailorability characteristics) provide immense
advantages for the development of structural
com-ponents for bridges and buildings in seismic regions
The retrofit of RC structures improves the strength
of those members that are vulnerable to seismic
attack
The seismic retrofit of RC columns tends to change
the column failure mode from shear to flexural
failure, or to transfer the failure criteria from column
to joint and/or from joint to beam failure, depending
upon the strengthening parameters This technique
is used in existing reinforced concrete columns
where insufficient transverse reinforcement and/or
seismic detailing are provided; three different types
of failure mode can be observed under seismic input
These are:
• Column shear failure mode: This mode of failure
is the most critical one The modern seismic
co-lumn designs contain detailed transverse or shear
reinforcement, but the shear strength of existing
substandard columns can be enhanced by providing
external shear reinforcement or by strengthening
the column through composite fibres in the hoop
direction
• Confinement failure at the flexural plastic hinge:
Subsequent to flexural cracking, the cover-concrete
will crush and spall; this is followed by buckling
of the longitudinal steel reinforcement, or a
com-pression failure of the concrete, which in turn
initiates plastic hinge deterioration
• Confinement of lower ends of columns: Some
bridge columns have lap splices in the column
reinforcement; these are starter bars used for
ease of construction and are located at the lower
column end to form the connection between the
footings and the columns This is a potential
plastic hinge region and it is advantageous to
provide confinement by external jacketing or
continuous fibre winding in this area
None of these failure modes and associated column
retrofits can be viewed separately since retrofitting
for one deficiency may shift the seismic problem
to another location and a different failure mode
without necessarily improving the overall deformation
capacity
The confinement of RC columns can be undertaken
by fabricating FRP composites using techniques such
as the wet lay-up, the semi-automated cold-melt
factory-made pre-impregnated fibre or the automated
filament-winding processes The fib have discussed
the use of prefabricated (pre-cured) elements in the
form of shells or jackets that are bonded to the concrete and to each other to provide confinement (fib Task Group 9.3, 2001) The wet lay-up and the prefabricated systems are generally placed with the principal fibre direction perpendicular to the axis of the member The concrete column takes essentially axial load therefore the ratio of the areas
of the circumferential to axial fibres of the composite
is large thus providing confinement to the concrete This allows the tensile strength in the circumferen-tial direction to be virtually independent of the axial stress value A review of the effectiveness of FRP composites for confining RC columns has been given
in De Lorenzis and Tepfers (2003)
43.5.2 sHeAR stRengtHening oF degRAded RC beAMs
Shear strengthening of RC beams and columns may
be undertaken by bonding FRP laminates to the sides
of the member The principal fibre direction is parallel
to that of the maximum principal tensile stresses, which in most cases is at approximately 45° to the member axis However, for practical reasons it
is usually preferable to attach the external FRP reinforcement with the principal fibre direction per-pendicular to the member axis Various researchers – ElHacha and Rizkalla (2004), Triantafillou (1998) – and current design recommendations – El-Refaie
et al (2003) and Ibell and Silva (2004) – have shown
that an FRP-shear-strengthened member can be modelled in accordance with Mörsch’s truss analogy Further information on this topic can be found in
Lu et al (2009).
43.6 Upgrading of metallic
structural members
Advanced polymer composite materials have not been utilised to upgrade metallic structures to the same extent as they have been for reinforced con-crete structures However, as a result of research into this subject, which commenced at the latter part of the 20th century (Mertz and Gillespie, 1996; Mosallam and Chakrabarti, 1997; Luke, 2001; Moy, 2001; Tavakkolizadeh and Saadatmanesh,
2003; Cadei et al., 2004; Moy, 2004; Luke and Canning, 2004, 2005; Photiou et al., 2006; Holla-way et al., 2006; Zhang et al., 2006), there have
been a number of applications of CFRP to metallic structures that have shown that the technique can have significant benefits over alternative methods
of strengthening
Trang 10The number of applications to date in the UK
has led to the publication of two comprehensive
guidance documents:
1 ICE Design & Practice Guide FRP Composites
– Life Extension and Strengthening of Metallic
Structures (Moy, 2001).
2 CIRIA Report C595 Strengthening Metallic
Structures using Externally-Bonded FRP (Cadei
et al., 2004).
Design guidance has also been published recently
by the Italian National Research Council (CNR,
2006), Schnerch et al (2006) and ISIS (Canada),
2007
FRP strengthening can be used to address any of
the structural deficiencies described in the concrete
section The reasons for using FRP to rehabilitate
a metallic or concrete structure may be similar;
however, the way in which the FRP works with an
existing metallic structure can often be very different
to that in a concrete structure
The FRP composite plate material used for the
bonding operation is either the ultra-high-modulus
(European definition) or the high-modulus (European
definition) CFRP, AFRP (Kevlar 49) or possibly
GFRP composites and these will be fabricated by
one of four methods:
1 The pultrusion technique, in which the factory
made rigid pre-cast FRP plate is bonded onto
the degraded member with cold-cure adhesive
2 The factory made rigid fully cured FRP prepreg
plate bonded to the degraded member with
cold-cure adhesive
3 The low-temperature mould prepreg FRP prepreg/
adhesive film placed onto the structural member
and both components compacted and cured under
vacuum at an elevated temperature
4 Vacuum infusion (The Resin Infusion under Flexible
Tooling (RIFT) process)
Figure 43.8 shows the upgrading of a curved steel
structural beam by a carbon fibre/epoxy composite
prepreg
It should be mentioned that the ultra high-modulus
carbon fibre composite has a low strain to failure,
of the order of 0.4% strain, and a modulus of
elasticity of the composite of about 40 GPa, so the
system will fail with a small inelastic characteristic
The high-modulus CFRP composites have a value
of ultimate strain of the order of 1.6% strain for
modulus of elasticity of 28 GPa This implies that
the material is ductile and is unlikely to fail in a
rehabilitation situation by ultimate strain but by
some other method (Photiou, 2006)
43.7 Internal reinforcement to
concrete members
FRP rebars for reinforcing concrete members are generally fabricated by the pultrusion method (Nanni, 1993; ACI, 1996; Pilakoutas, 2000; Bank, 2006) The rebars can be manufactured from carbon, aramid and glass fibres using epoxy or vinylester polymers The surfaces of pultruded composites are smooth and therefore it is necessary to post-treat them to develop a satisfactory bond characteristic between the concrete and the rebar Several techniques are used for this, including:
• applying a peelply to the surface of the pultruded bar during the manufacturing process; the peel ply is removed before encasing the bar with concrete, thus leaving a rough surface on the pultruded rebar
• overwinding the pultruded rebar with additional fibres
• bonding a layer of sand with epoxy adhesive to the surface of the pultruded rod; this is a secondary operation at the end of the pultrusion line The features and benefits of using FRP rebars are:
• they are noncorrosive – they will not corrode when exposed to a wide variety of corrosive elements, including chloride ions, and are not susceptible to carbonation-initiated corrosion in
a concrete environment
Fig 43.8 The upgrading of a curved steel structural
beam by the carbon fibre/epoxy composite low-temperature mould prepreg (Courtesy of Taylor Woodrow, UK, and ACG Derbyshire, UK).