1. Trang chủ
  2. » Tài Chính - Ngân Hàng

Project management a managerial approach chapter 08

26 155 0

Đang tải... (xem toàn văn)

Tài liệu hạn chế xem trước, để xem đầy đủ mời bạn chọn Tải xuống

THÔNG TIN TÀI LIỆU

Thông tin cơ bản

Định dạng
Số trang 26
Dung lượng 1,49 MB

Các công cụ chuyển đổi và chỉnh sửa cho tài liệu này

Nội dung

Network Techniques: PERT and CPM• With the exception of Gantt charts, the most common approach to scheduling is the use of network techniques such as PERT and CPM • The Program Evaluatio

Trang 1

Project Management: A Managerial Approach

Chapter 8 – Scheduling

Trang 3

• Taken together with the plan and budget,

it is probably the major tool for the

management of projects

Trang 4

Simple Schedule – Gantt Chart

Trang 5

Network Techniques: PERT and CPM

• With the exception of Gantt charts, the most

common approach to scheduling is the use of

network techniques such as PERT and CPM

• The Program Evaluation and Review Technique (PERT) was developed by the U.S Navy in 1958

• The Critical Path Method (CPM) was developed

by DuPont, Inc during the same time period

Trang 6

Scheduling Terminology

• Activity - A specific task or set of tasks that are

required by the project, use up resources, and take time to complete

• Event - The result of completing one or more

activities An identifiable end state occurring at a particular time Events use no resources

• Network - The combination of all activities and

events define the project and the activity

precedence relationships

Trang 7

Scheduling Terminology

• Path - The series of connected activities (or

intermediate events) between any two events

in a network

• Critical - Activities, events, or paths which, if

delayed, will delay the completion of the

project A project’s critical path is understood

to mean that sequence of critical activities that connect the project’s start event to its finish

event

Trang 8

Scheduling Terminology

• An activity can be in any of these conditions:

– It may have a successor(s) but no predecessor(s) -

Trang 9

6 20

13 30

TE=64

Calculate t(e) and Z for this network……

Trang 10

Activity and Project Frequency Distributions

Trang 11

PERT Activity Calculation

b = Most Pessimistic (MP)t(e) = Activity Duration

When a single estimate for activity time is not sufficient!

Trang 12

PERT Schedule Probability

Z is derived from a table of predetermined probabilities

T(S) = Scheduled DurationT(E) = Critical Path Duration

Trang 13

PERT Activity Times & Variances

Trang 14

Variance of Activity Estimates

Trang 15

Possible Project Durations

TE=64

TS=67

Trang 17

Gantt Charts

• The Gantt chart shows planned and actual progress for a number of tasks displayed against a horizontal time scale

• It is an effective and easy-to-read method of

indicating the actual current status for each set of

tasks compared to the planned progress for each item

of the set

• It can be helpful in expediting, sequencing, and

reallocating resources among tasks

• Gantt charts usually do not show technical

dependencies

Trang 18

• The choice between AOA and AON

representation is largely a matter of personal

preference

Trang 19

Hypothetical Network

1

4 3

Trang 20

AOA Network Building Blocks

80

79 Install software

Event Activity

Trang 21

Partial Koll Business Center - AOA

4

5

Application approval

D Service availability check

C Traffic study

B Construction plans

Trang 22

Partial AOA Network

Trang 23

Partial AOA Network

F

?

Trang 24

Full AOA Network

KOLL BUSINESS CENTER County Engineers Design Department

G 170

H 35

E 15

D 5

Activity

Duration

Legend

Trang 25

Activity-on-Node Network Fundamentals

X

Y

Z

Y and Z are preceded by X

Y and Z can begin at the same time, if you wish

M

J, K, & L can all begin at the same time, if you wish (they need not occur

simultaneously)

All (J, K, L) must be completed before M can begin

Trang 26

Copyright 2006 John Wiley & Sons, Inc.

All rights reserved Reproduction or translation of this work beyond that permitted in section 117

of the 1976 United States Copyright Act without express permission of the copyright owner is unlawful Request for further information should be addressed to the Permissions Department, John Wiley & Sons, Inc The Publisher assumes no responsibility for errors, omissions, or

damages caused by the use of these programs or from the use of the information herein.

Ngày đăng: 10/01/2018, 15:33

TỪ KHÓA LIÊN QUAN

TÀI LIỆU CÙNG NGƯỜI DÙNG

  • Đang cập nhật ...

TÀI LIỆU LIÊN QUAN