1. Trang chủ
  2. » Kinh Doanh - Tiếp Thị

Introduction to operations and supply chain management 3e bozarth chapter 12

57 258 0

Đang tải... (xem toàn văn)

Tài liệu hạn chế xem trước, để xem đầy đủ mời bạn chọn Tải xuống

THÔNG TIN TÀI LIỆU

Thông tin cơ bản

Định dạng
Số trang 57
Dung lượng 2,94 MB

Các công cụ chuyển đổi và chỉnh sửa cho tài liệu này

Nội dung

 Discuss the role of production activity control and vendor order management and how these functions differ from higher-level planning activities.. Planning and Control Planning and co

Trang 1

Managing Production across the

Supply Chain

Chapter 12

Trang 2

Complete the calculations for the MRP record and interpret the results

Discuss the role of production activity control and vendor order management and how these functions differ from higher-level planning activities

Explain how distribution requirements planning (DRP) helps synchronize the supply chain and complete the calculations for a simple example

Trang 3

Planning and Control

Planning and control – A set of tactical and execution-level business activities that

includes master scheduling, material

requirements planning, and some form of

production activity control and vendor order management.

Trang 4

Top-Down Model of Manufacturing

Planning and Control Systems

Trang 5

Master Scheduling

Master Scheduling – A detailed planning process that tracks production output and matches this output to actual customer orders.

 Controls the timing and quantity of production for products or product families.

 Serves as the primary interface point for actual customer

Trang 6

Link between S&OP

Trang 7

Master Schedule Record

Trang 8

Forecasted Demand

vs Booked Orders

Forecasted demand – A company’s best

estimate of the demand in any period.

Booked orders – Confirmed demand for

products

Projected Requirements =

Maximum (Forecasted demand, Booked orders)

Trang 9

Master Production Schedule (MPS)

Master Production Schedule (MPS) – The

amount of product that will be finished and available for sale at the beginning of each

week.

 The MPS quantities drive more detailed planning activities, such as material requirements planning.

Trang 11

Available to Promise (ATP)

Available to Promise – A field in the master

schedule record that indicates the number of units that are available for sale each week, given those that have already been promised to customers.

Trang 12

Available to Promise (ATP)

Calculating ATP for the first week of the master schedule record:

Trang 13

Available to Promise (ATP)

Calculating ATP for any subsequent week in which MPS > 0:

Trang 14

Partial Master Schedule Record

(Snowblowers)

Figure 12.4

Trang 15

Calculating ATP

Figure 12.5

Trang 16

Calculating ATP

Figure 12.6

Trang 17

Complete Master Schedule Record

(Snowblowers)

Figure 12.7

Trang 18

MPS Example (Backpacks)

Now Calculate Projected Ending Inventory and

Figure 12.8

Trang 19

Calculations (Backpacks)

Calculating Ending Inventory:

Calculating ATP:

Trang 20

MPS Example (Backpacks)

with ATP

What are the implications of the Master Production Schedule?

Figure 12.9

Trang 21

Planning Horizon

Planning Horizon – The amount of time the master schedule record or MRP record

extends into the future.

 The longer the production and supplier lead times, the longer the planning horizon must be.

Trang 22

Material Requirements Planning

Material Requirements Planning (MRP) – A planning process that translates the master production schedule into planned orders for the actual parts and components needed to produce the master schedule items.

 Manages dependent demand inventory

Trang 23

Material Requirements Planning

Trang 24

Bill of Material for Chair

Bill of material (BOM) – A listing of all the

subassemblies, intermediates, parts, and raw

materials that go into a parent assembly showing the quantity of each required to make an assembly.

© 2010 APICS Dictionary

Trang 25

Product Structure Tree

Figure 12.13

Trang 26

Lead Time

Chair Assembly (1 week)

Week 5

Week 4

If final assembly takes

one week, then we

must start

the assembly at the

beginning

of Week 4

Trang 27

Lead Time

Chair Assembly

Back Assembly

Leg Assembly

(1 week)

(1 week) Seats (2 weeks)

Week 5 Week 4

Trang 28

Lead Time

Chair Assembly

Back Assembly

Leg Assembly

(1 week) (1 week)

Week 3 Week 2

Week 1

Trang 29

Lead-Time Key Points

To have finished chairs at the beginning of Week 5 with no work in progress or

finished inventory, we must begin

production and order materials in Week 1.

“Exploding” the bill of materials tells us

when to order things and how many to

order.

Trang 30

Material Requirements Planning

to determine what should be ordered when,

and how much to order.

Trang 31

Material Requirements Planning

Trang 32

Calculating the MRP Record

for Seats

Trang 33

Calculating the MRP Record

for Seats (Key)

A: Mgmt needs 500 chairs at the beginning of week 5.

B: Because the planning lead time is 1 week, the workers need to start assembling the chairs in week 4.

C: The Gross Requirement for weeks 1-3 is zero because no chairs need to be assembled in those weeks.

D: The Gross Requirement for week 4 is 500 from the MPS Start quantity in week 4.

E: The Net Requirements for week 4 =

Trang 34

Calculating the MRP Record

for Seats (Key)

F: Managers should plan on ordering enough to meet the net requirement in week 4.

G: There is a two-week planning lead time, so they must release the order for seats in week 2.

H: Ending Inventory for week 4 =

Trang 35

MRP Records for Level 1 Components

Trang 36

Calculating the MRP Record Quantities (Key)

I: There are 25 leg assemblies in inventory beginning in

week 1.

J: An order for 1000 is placed even though the net

requirements are 475 units because 1000 is the minimum order quantity.

K: No order is placed because there is more inventory (525) than the gross requirements (400) in week 5.

L: There is a scheduled receipt for 250 units in week 1.

Trang 37

Partial MRP Records

Trang 38

Calculating the MRP Record Quantities (Key)

M: Because each leg assembly requires two legs, the gross requirements for legs in week 3 is 2,000 legs.

N: Each back assembly requires two side rails Therefore, there is a planned order for 300 back assemblies in week 5 that results in a gross requirement of 600 side rails in the same week.

Crossbar Gross Requirements:

Trang 39

Advantages of MRP

MRP is directly tied to the master production

schedule and indicates the exact timing and

quantity of orders for all components.

MRP allows managers to trace every order for

lower-level items through all the levels of the BOM,

up to the Master Production schedule.

MRP tells a firm and its suppliers precisely what

needs to be made when.

Trang 40

Special Considerations

Organizational discipline

Accurate information

Uncertainty

MRP nervousness – A term used to refer to the

observation that any change, even a small one, in the requirements for items at the top of the bill of material can have drastic effects on items further down the bill of material.

Trang 41

Production Activity Control and Vendor Order Management

Emphasis shifts from planning to execution with capabilities to:

 Route and prioritize jobs going through the supply chain.

 Coordinate the flow of goods and materials

between a facility and other supply chain

partners.

 Provide supply chain partners with performance data on operations and supply chain activities.

Trang 42

Job Sequencing

Job sequencing rules – Rules used to

determine the order in which jobs should be processed when resources are limited and multiple jobs are waiting to be done.

 First come, first served

 Earliest due date

 Critical ratio

• Calculated as:

Trang 43

• The job is going to be late unless something changes.

 Jobs with the lowest Critical Ratio are scheduled

to go first.

Trang 44

Job Sequencing – Example 12.7

Table 12.1

Trang 45

Job Sequencing – Example 12.7

First come, first served

From Table 12.2

Trang 46

Job Sequencing – Example 12.7

Earliest Due Date

From Table 12.2

Trang 47

Job Sequencing – Example 12.7

Critical Ratio

From Table 12.2

Trang 49

Synchronized Planning and Control

Figure 12.22

Trang 50

DRP Example

(Snowblowers)

Trang 51

Downstream Supply Chain

Figure 12.23

Trang 53

Impact of Forecast Changes

Trang 54

Impact of Forecast Changes

When forecasted demand changes, managers will need to increase the master production schedules accordingly.

DRP quickly translates downstream demand

into upstream production decisions.

Trang 55

Synchronizing Plans

in the Supply Chain

Trang 56

Managing Production

Case Study

The Realco Breadmaster

Trang 57

All rights reserved No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or by any means, electronic, mechanical, photocopying, recording, or

otherwise, without the prior written permission of the publisher

Printed in the United States of America.

Ngày đăng: 08/01/2018, 16:37

TỪ KHÓA LIÊN QUAN