Discuss the role of production activity control and vendor order management and how these functions differ from higher-level planning activities.. Planning and Control Planning and co
Trang 1Managing Production across the
Supply Chain
Chapter 12
Trang 2 Complete the calculations for the MRP record and interpret the results
Discuss the role of production activity control and vendor order management and how these functions differ from higher-level planning activities
Explain how distribution requirements planning (DRP) helps synchronize the supply chain and complete the calculations for a simple example
Trang 3Planning and Control
Planning and control – A set of tactical and execution-level business activities that
includes master scheduling, material
requirements planning, and some form of
production activity control and vendor order management.
Trang 4Top-Down Model of Manufacturing
Planning and Control Systems
Trang 5Master Scheduling
Master Scheduling – A detailed planning process that tracks production output and matches this output to actual customer orders.
Controls the timing and quantity of production for products or product families.
Serves as the primary interface point for actual customer
Trang 6Link between S&OP
Trang 7Master Schedule Record
Trang 8Forecasted Demand
vs Booked Orders
Forecasted demand – A company’s best
estimate of the demand in any period.
Booked orders – Confirmed demand for
products
Projected Requirements =
Maximum (Forecasted demand, Booked orders)
Trang 9Master Production Schedule (MPS)
Master Production Schedule (MPS) – The
amount of product that will be finished and available for sale at the beginning of each
week.
The MPS quantities drive more detailed planning activities, such as material requirements planning.
Trang 11Available to Promise (ATP)
Available to Promise – A field in the master
schedule record that indicates the number of units that are available for sale each week, given those that have already been promised to customers.
Trang 12Available to Promise (ATP)
Calculating ATP for the first week of the master schedule record:
Trang 13Available to Promise (ATP)
Calculating ATP for any subsequent week in which MPS > 0:
Trang 14Partial Master Schedule Record
(Snowblowers)
Figure 12.4
Trang 15Calculating ATP
Figure 12.5
Trang 16Calculating ATP
Figure 12.6
Trang 17Complete Master Schedule Record
(Snowblowers)
Figure 12.7
Trang 18MPS Example (Backpacks)
Now Calculate Projected Ending Inventory and
Figure 12.8
Trang 19Calculations (Backpacks)
Calculating Ending Inventory:
Calculating ATP:
Trang 20MPS Example (Backpacks)
with ATP
What are the implications of the Master Production Schedule?
Figure 12.9
Trang 21Planning Horizon
Planning Horizon – The amount of time the master schedule record or MRP record
extends into the future.
The longer the production and supplier lead times, the longer the planning horizon must be.
Trang 22Material Requirements Planning
Material Requirements Planning (MRP) – A planning process that translates the master production schedule into planned orders for the actual parts and components needed to produce the master schedule items.
Manages dependent demand inventory
Trang 23Material Requirements Planning
Trang 24Bill of Material for Chair
Bill of material (BOM) – A listing of all the
subassemblies, intermediates, parts, and raw
materials that go into a parent assembly showing the quantity of each required to make an assembly.
© 2010 APICS Dictionary
Trang 25Product Structure Tree
Figure 12.13
Trang 26Lead Time
Chair Assembly (1 week)
Week 5
Week 4
If final assembly takes
one week, then we
must start
the assembly at the
beginning
of Week 4
Trang 27Lead Time
Chair Assembly
Back Assembly
Leg Assembly
(1 week)
(1 week) Seats (2 weeks)
Week 5 Week 4
Trang 28Lead Time
Chair Assembly
Back Assembly
Leg Assembly
(1 week) (1 week)
Week 3 Week 2
Week 1
Trang 29Lead-Time Key Points
To have finished chairs at the beginning of Week 5 with no work in progress or
finished inventory, we must begin
production and order materials in Week 1.
“Exploding” the bill of materials tells us
when to order things and how many to
order.
Trang 30Material Requirements Planning
to determine what should be ordered when,
and how much to order.
Trang 31Material Requirements Planning
Trang 32Calculating the MRP Record
for Seats
Trang 33Calculating the MRP Record
for Seats (Key)
A: Mgmt needs 500 chairs at the beginning of week 5.
B: Because the planning lead time is 1 week, the workers need to start assembling the chairs in week 4.
C: The Gross Requirement for weeks 1-3 is zero because no chairs need to be assembled in those weeks.
D: The Gross Requirement for week 4 is 500 from the MPS Start quantity in week 4.
E: The Net Requirements for week 4 =
Trang 34Calculating the MRP Record
for Seats (Key)
F: Managers should plan on ordering enough to meet the net requirement in week 4.
G: There is a two-week planning lead time, so they must release the order for seats in week 2.
H: Ending Inventory for week 4 =
Trang 35MRP Records for Level 1 Components
Trang 36Calculating the MRP Record Quantities (Key)
I: There are 25 leg assemblies in inventory beginning in
week 1.
J: An order for 1000 is placed even though the net
requirements are 475 units because 1000 is the minimum order quantity.
K: No order is placed because there is more inventory (525) than the gross requirements (400) in week 5.
L: There is a scheduled receipt for 250 units in week 1.
Trang 37Partial MRP Records
Trang 38Calculating the MRP Record Quantities (Key)
M: Because each leg assembly requires two legs, the gross requirements for legs in week 3 is 2,000 legs.
N: Each back assembly requires two side rails Therefore, there is a planned order for 300 back assemblies in week 5 that results in a gross requirement of 600 side rails in the same week.
Crossbar Gross Requirements:
Trang 39Advantages of MRP
MRP is directly tied to the master production
schedule and indicates the exact timing and
quantity of orders for all components.
MRP allows managers to trace every order for
lower-level items through all the levels of the BOM,
up to the Master Production schedule.
MRP tells a firm and its suppliers precisely what
needs to be made when.
Trang 40Special Considerations
Organizational discipline
Accurate information
Uncertainty
MRP nervousness – A term used to refer to the
observation that any change, even a small one, in the requirements for items at the top of the bill of material can have drastic effects on items further down the bill of material.
Trang 41Production Activity Control and Vendor Order Management
Emphasis shifts from planning to execution with capabilities to:
Route and prioritize jobs going through the supply chain.
Coordinate the flow of goods and materials
between a facility and other supply chain
partners.
Provide supply chain partners with performance data on operations and supply chain activities.
Trang 42Job Sequencing
Job sequencing rules – Rules used to
determine the order in which jobs should be processed when resources are limited and multiple jobs are waiting to be done.
First come, first served
Earliest due date
Critical ratio
• Calculated as:
Trang 43• The job is going to be late unless something changes.
Jobs with the lowest Critical Ratio are scheduled
to go first.
Trang 44Job Sequencing – Example 12.7
Table 12.1
Trang 45Job Sequencing – Example 12.7
First come, first served
From Table 12.2
Trang 46Job Sequencing – Example 12.7
Earliest Due Date
From Table 12.2
Trang 47Job Sequencing – Example 12.7
Critical Ratio
From Table 12.2
Trang 49Synchronized Planning and Control
Figure 12.22
Trang 50DRP Example
(Snowblowers)
Trang 51Downstream Supply Chain
Figure 12.23
Trang 53Impact of Forecast Changes
Trang 54Impact of Forecast Changes
When forecasted demand changes, managers will need to increase the master production schedules accordingly.
DRP quickly translates downstream demand
into upstream production decisions.
Trang 55Synchronizing Plans
in the Supply Chain
Trang 56Managing Production
Case Study
The Realco Breadmaster
Trang 57All rights reserved No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or by any means, electronic, mechanical, photocopying, recording, or
otherwise, without the prior written permission of the publisher
Printed in the United States of America.