TÀI LIỆU THIẾT KẾ CỌC NẤM XI MĂNG TÀI LIỆU NƯỚC NGOÀI.TÀI LIỆU THIẾT KẾ CỌC NẤM XI MĂNG TÀI LIỆU NƯỚC NGOÀI.TÀI LIỆU THIẾT KẾ CỌC NẤM XI MĂNG TÀI LIỆU NƯỚC NGOÀI.TÀI LIỆU THIẾT KẾ CỌC NẤM XI MĂNG TÀI LIỆU NƯỚC NGOÀI.TÀI LIỆU THIẾT KẾ CỌC NẤM XI MĂNG TÀI LIỆU NƯỚC NGOÀI.TÀI LIỆU THIẾT KẾ CỌC NẤM XI MĂNG TÀI LIỆU NƯỚC NGOÀI.TÀI LIỆU THIẾT KẾ CỌC NẤM XI MĂNG TÀI LIỆU NƯỚC NGOÀI.TÀI LIỆU THIẾT KẾ CỌC NẤM XI MĂNG TÀI LIỆU NƯỚC NGOÀI.TÀI LIỆU THIẾT KẾ CỌC NẤM XI MĂNG TÀI LIỆU NƯỚC NGOÀI.TÀI LIỆU THIẾT KẾ CỌC NẤM XI MĂNG TÀI LIỆU NƯỚC NGOÀI.TÀI LIỆU THIẾT KẾ CỌC NẤM XI MĂNG TÀI LIỆU NƯỚC NGOÀI.TÀI LIỆU THIẾT KẾ CỌC NẤM XI MĂNG TÀI LIỆU NƯỚC NGOÀI.
Trang 1Automatic pressure-control equipment for horizontal jet-grouting
Yao Yuana, Shui-Long Shena,⁎ , Zhi-Feng Wangb, Huai-Na Wua,⁎
a
State Key Laboratory of Ocean Engineering and Collaborative Innovation Center for Advanced Ship and Deep-Sea Exploration (CISSE), Department of Civil Engineering, Shanghai Jiao Tong University,
800 Dong Chuan Road, Minhang District, Shanghai 200240, China
b School of Highway, Chang'an University, China
a b s t r a c t
a r t i c l e i n f o
Article history:
Received 18 October 2015
Received in revised form 16 May 2016
Accepted 22 May 2016
Available online xxxx
A new horizontal jet grouting equipment is proposed to eliminate the harmful effect on the surrounding environ-ment due to the injection of large amount of water and/or grout under high jetting pressure The components of the proposed equipment and the construction procedures are introduced During horizontal jet grouting by the proposed equipment, the inner pressure of the soil stratum can be monitored automatically, the generated spoil can be transported out, and the impact on surroundings (such as ground upheaval and lateral displacement of the subsoil) can be mitigated Afield test involving the installation of five horizontal jet grout columns was conducted
in Shanghai to demonstrate the applicability of the new equipment In addition, monitoring instruments were installed to observe the vertical displacement of the ground surface The measured maximum value of the ground surface upheaval was as low as 9.4 mm, which verifies that the new equipment performed as per expectations Finally, the in-situ quality of jet grouted columns was found to be very good based upon the results offield cone penetration and unconfined compressive strength tests
© 2016 Elsevier B.V All rights reserved
Keywords:
Horizontal jet grouting equipment
Pressure-control
Spoil discharge
Vertical displacement
1 Introduction
Jet-grouting is a soft soil improvement technology, which is initially
invented based on jetting cut technology in coal mining[1]and grouting
[2]in soft soil engineering in early 1970s[3] After jet-grouting
technol-ogy was invented, it is widely used in many construction projects, e.g
deep excavations to seal the joints of diaphragm wall to prevent leakage
[4], improvement of stability shaft entrance[5], improvement of bottom
stability of excavation[6], stabilization of micro-tunneling route[7],
tunnel canopy construction[8], recovery of collapsed tunnel[9],
im-provement of soft subsoil of embankment[10], marine[11]or on-land
foundations[12] In some circumstance, jet grouting was also applied
to improve soft rocks, e.g in Athens Metro project[13]and remediation
of existing shield tunnel[14] Thefirst patent of jet grouting was applied
in 1968, as the‘Chemical Churning Pile’ (CCP) method[1], which is the
forerunner of the singlefluid system[15] Recently with developments
in construction technology, the doublefluid system (involving grout
and air)[16], and the triplefluid system (grout, water and air)[17]
have been used for different geological conditions[18] During jet
grouting, high velocityfluids shrouded by a compressed air are ejected
from small diameter nozzles to erode the soil and to mix it with the
grout to form a soil-cement column[16] The shear strength of the
cemented column can reach several MPa[19]
Based on construction direction of the rod for jet grouting machines, jet grouting technology can be classified as: 1) vertical jet grouting systems[17]; 2) inclined jet grouting systems[20]; and 3) horizontal jet grouting systems[21].Fig 1depicts the in-situ stress state and mechanism of stress transferring in ground during horizontal jet-grouting construction Before jet grouting, the in-situ overburden pressure p (shown inFig 1) can be expressed as follows:
whereγ = unit weight of the overburden soils; and h = overlying thickness of the soil above the construction site
during conventional jet grouting process The conventional jet grouting operation is a two stage process Stage I is the ground movement during drilling As shown inFig 1(a), the ground heave at this stage is generally small, which is induced by the friction between the drilling rod and the surrounding soils Stage II is the ground movement during jet grouting process When the slurry ejects from the monitor, the inner stratum pressure around the drilling rod will increase and the ground surface will be upheaval, which is induced by the expansion of the grouting slurry and the spoil soils (Fig 1(b)) The subsequent injection of large volumes of high pressurizedfluids into the soil stratum can lead to ground upheaval and lateral movement of the surrounding soils
To solve the ground expansion problems, some modifications of jet grouting were conducted[21] In 1995, Nakashima and Nakanishi[20]
⁎ Corresponding authors.
E-mail addresses: slshen@sjtu.edu.cn (S.-L Shen), zhifeng.wang@chd.edu.cn
(Z.-F Wang).
http://dx.doi.org/10.1016/j.autcon.2016.05.025
Trang 2developed a jet-grouting technology to make the balance of jetting
pressure with surrounding earth pressure and this system is named
as Metro Jet System Technology (MJS) MJS technology utilizes the
negative pressure induced by highly pressurized water to remove the
spoil[20].Fig 2a shows a sectional view of compound pipe used in MJS
technology The different pipes function as follows: (1) for injecting the
high pressure grout (grout pipe), (2) for injecting high pressure water
to erode soil (water pipe I), (3) for spoil generating water (water pipe
II), (4) for injecting compressed air (air pipe), (5) for the cable set that
link the sensor to measure the earth pressure during jet-grouting (cable
pipe), (6) for transporting the additive (additive pipe), and (7) for
transporting out the spoil induced during jet grouting (spoil pipe) The
equipment required for MJS makes the rod pipe large and heavy In
addi-tion, the existence of earth pressure measuring cable prevents the rod
from continuous 360 degree rotation and the pipe can only swing action
during construction, resulting in reduced construction efficiency
In order to overcome the drawbacks of the MJS system, Shen et al.[21]
introduced a new horizontal jet grouting technique called the
‘Compos-ite-Pipe Method’ (CPM).Fig 2b shows the sectional view of compound
pipe used in CPM technology In CPM, the high pressure water generates
a vacuum state temporary in the entrance of spoil pipe to remove the spoil generated during construction This CPM equipment, which can be regarded as the simplified version of MJS, can help reduce the inner pressure of the stratum during jet grouting However, when the overbur-den soil for jet grouting construction is very thin, the pressure of the jet groutingfluids may have a major effect on the surrounding environment, and the volume of spoil to be removed cannot be controlled
automatical-ly Moreover, both spoil pressure and earth pressure do not be monitored during construction This may cause obvious ground displacement around construction site during and after jet grouting (seeFig 1(c))
In this paper, to eliminate such impacts (e.g outflow of the drilling fluid) and to reduce the impact on surroundings (e.g large ground upheaval and lateral displacement), a new construction equipment for horizontal jet grouting technology named as pressure-control jet grouting technology (PCJG) is proposed.Fig 1(c) shows the basic con-cept of ground movement during jet grouting process in the proposed PCJG technology During the jetting process, the ground movement can be controlled via control of inner stratum pressure near the monitor,
Fig 1 Mechanism of load transferring during jet grouting: a) longitudinal view of the ground movement; b) Sectional view of the ground upheaval due to grouting slurry; c) ground movement model of the horizontal jet grouting construction.
Fig 2 Sectional view of composite pipes used in MJS and CPM technology, a) MJS; b) CPM (modified from Nakashima and Nakanishi
Trang 3P The inner stratum pressure near the monitor should balance the earth
pressure of the overlying soils, p If PN p, ground heave in stage II
happens, whereas if Pb p, ground settlement happens At the balance
condition, if p = P, the ground movement in Stage II can be avoided
Thus decreasing the inner stratum pressure can help eliminate such
impacts (large ground upheaval)
In PCJG, different from MJS and CPM, both spoil pressure and earth
pressure can be monitored and the spoil generated during jet grouting
is transported out promptly This helps increase the diameter of the
grouting columns and reduce the expansive impact on surroundings
During jet grouting construction, the inner pressure and the rate
for transporting spoil can be controlled automatically (namely see
Fig 1(c)), and the drillingfluid for the new equipment is high pressure
water Meanwhile, the operation becomes simple and easy in
compari-son to the other two types of aforementioned equipment Additionally,
the grout pressure in the aforementioned equipment is lower than that
of MJS and CPM, which can help reduce the environmental impact The objectives of this paper are: i) to introduce the new equipment; ii) to describe the construction procedure while using the new equip-ment; iii) to demonstrate the applicability of the new equipment through
a case study
2 Pressure-control jet grouting technology 2.1 Composition of PCJG
Fig 3shows the composition of the equipment for PCJG The connec-tion of these different parts is also shown schematically inFig 3.Fig 4 shows photographs of the main components of this system The main apparatus applied in PCJG is composed of six parts: (1) the drilling
Fig 3 Composition of the equipment for horizontal pressure-control jet grouting.
Trang 4and jetting system, (2) grouting system, (3) automatic detection
system, (4) sealing device, (5) pressure-control system, and (6) spoil
discharge system
(1) Drilling and jetting system
The drilling and jetting system consists of a horizontal drill rig
(#4 inFig 3), a triple rod (#11), a three-channel swivel (#12),
and a multiple-functional monitor (#6) with multiple nozzles
The horizontal drill rig, connected to the triple rod, is used for
supporting and guiding the triple rod A three-channel swivel is
used to connect the jet grouting system with the triple rod
There arefive nozzles on the multiple-functional monitor
(2) Grouting system
The grouting system includes a high pressure pump (#7) for
feeding highly pressurized water, a low pressure pump (#8) for
injecting grout, an air compressor (#9) for generating
com-pressed air, grout storage equipment, water bucket, and slurry
mixing station The grouting facilities are connected to the triple
rod through the three-channel swivel
(3) Automatic detection system
The automatic detection system contains threeflow meters, three
pressure sensors and an in-situ parameter monitor In order to
si-multaneously monitor the quality of the jet grouting column, the
following parameters for drilling and jet grouting can be detected
rate and the pressure of the grout, water and compressed air The flow rate of the grout, water and compressed air can be recorded
by the respectiveflow meters, while the pressure of the grout, the water, and the compressed air can be monitored simulta-neously by the pressure sensors The parameters are all displayed
in the in-situ parameter monitor With the automatic detection system, the position of the nozzles and the relationship between the column length and the rotation velocity can be displayed clearly, and the quality of the jet grouting column can be controlled effectively
(4) Sealing device The sealing device (#5) whose details are shown inFig 5includes
a steel tube, a sealing gasket and a pressure sensor The pressure sensor is installed on the steel tube The sealing gaskets, which are coaxial with the triple rod, are installed around the steel tube and the triple rod to keep the gap closed The tube is connected
to the spoil pump During jet grouting operation, the sealing device
is used to keep the inner pressure of the soil stratum in a steady state
(5) Pressure-control system The pressure-control system is used to record and adjust the inner pressure of the soil stratum When the slurry pressure is greater than a critical pressure of the soil stratum, the system will be uti-lized to reduce the pressure of the soil stratum by transporting out the spoil, the ground response around the construction site can be mitigated
(6) Spoil discharge system The spoil storage system is designed to store and recycle the spoil generated during the construction of jet grouting When the spoil
is removed from the gap, the spoil discharge system is then turned on
Fig 5 Sectional view of the sealing device.
Trang 52.2 Principles of innovation elements of PCJG
The innovative elements of PCJG include: i) multiple-functional
monitor, ii) pressure control system, and iii) spoil discharge system
The detailed description of the principles of these innovative elements
is given hereafter
2.2.1 Multiple-functional monitor
Fig 6shows the configuration of the multiple-functional monitor,
which is installed at the tip end of the triple rod.Fig 7gives a
photo-graph of the monitor used in horizontal jet grouting construction The
diameter of the monitor (125 mm) is 35 mm larger than that of the
inner diameter of the steel tube During jetting, an annular space is
cre-ated between the rod and the surrounding borehole wall, which allows
the spoil slurry generated to be transported away from the monitor
to-wards the swivel head
As shown inFig 6, there arefive injection nozzles on the multiple
monitor; two injection nozzles at the front of the monitor (nozzles 1
and 2), two injection nozzles at the back of the monitor (nozzles 3
and 4) and one injection nozzle at the another end of the monitor
(noz-zle 5) Noz(noz-zles 1 and 2 have dual outlets which are connected to the
grout pipe and the compressed air pipe for injecting lower pressure
grout surrounded by the compressed air Nozzles 3 and 4 also have
dual outlets which are connected to the high pressure water pipe and
the compressed air pipe The initial erosion of the soil for drilling is
first conducted by nozzles 3 and 4 with the high pressure water With
the triple rod in the designated position, the low pressure grout is
ejected from nozzles 1 and 2 to mix with the eroded soil The grout
from the inner outlet is shrouded by compressed air dispensed from
the outer outlet, which can increase the eroding ability of the grout
and enlarge the diameter of the column Nozzle 5 ejects high pressure
water to accelerate the removal of the spoil from the gap during jet
grouting construction.Fig 6also depicts the configuration of each noz-zle As seen, the nozzles (Nozzle 1–5) have a tapered design such that the nozzle diameter reduces gradually to 2.6 mm at the exit of the noz-zle The funnel-shaped configuration prevents the backflow of the grout fluids and the spoil soils
2.2.2 Pressure-control system During jet grouting operation, if the inner stratum pressure on the soil near monitor is larger than the overburden soil pressure, the over-burden soil will upheave If the inner stratum pressure is smaller than the overburden soil pressure, it will cause the settlement of the overly-ing soil Thus, the inner stratum pressure should be controlled to be ap-proximately equal to the overburden soil pressure to reduce the ground movement When the slurry pressure in the gap is larger than p, the valve control is turned on to remove the spoil slurry induced during jet grouting to control the pressure to the critical state When the slurry pressure is smaller than p, the valve control is turned off to stop the transport of spoil slurry to increase the pressure to the critical state With this procedure, the earth pressure of the soil stratum can be bal-anced and the large ground upheaval or settlement can be avoided Fig 8illustrates a schematic view of the pressure-control system Fig 9shows photographs of the pressure-control system in horizontal jet grouting construction The main part of the system is a Programma-ble Logic Controller (PLC) and a frequency converter (Fig 9a) and con-trol valve (Fig 9b) The PLC can change the frequency converter promptly to adjust the front-side pressure of the multiple monitor, which can keep the inner pressure in a stable state to balance the inner pressure of the stratum There are two regulation modes for the PLC, namely the manual regulation and the automatic regulation In the manual regulation mode, the construction workers can adjust the flow rate of the spoil pumps to control the volume of discharged spoil
In the automatic regulation mode, the regulation is conducted by the Proportion Integration Differentiation (PID) automatic control program
Fig 8 Schematic view of the pressure-control system.
Trang 6The frequency converter is adopted as the drive units to control the
pressure-control system During jet grouting operation, the rate of
the spoil pumps will be adjusted by the frequency converter to keep
the inner pressure in a stable state automatically The guidelines for
the control of spoil pumps are as follows:
1) When the pressure is less than 30% of the critical pressure, the valves
of the spoil pump should be shut down to avoid the excessive loss of
spoil at the construction site (Fig 9b);
2) When the pressure is in the range of 30%–80% of the critical pressure,
the rate of the spoil pump should be set as 30 Hz This is the optimal
rate for the system which can keep the operation of the electric
motor steady, and maintain the stability of the inner pressure within
the soil stratum
3) When the pressure is in the range of 80%–120% of the critical
pres-sure, the equipment will adopt the PID mode The pressure will
decrease to the critical value gradually This can prevent the adverse effect of the sudden upheaval or settlement of the ground surface Nevertheless, there is still a few limitation in the new equipment This equipment need to ensure the path for transporting out the spoil outside the rod during the jet grouting construction, which means that during jet grouting the surrounding soil strata must have self-supporting ability The surrounding soil should be well consolidated The factors influence on stability of surrounding strata include stress state of soil, particle size of soil and the gap size between diameter of monitor and rod Another limitation is the clogging of gap If the diam-eter of soil particle (e.g gravel in soil) is larger than the gap, large soil particle may cause clogging the spoil slurry path
2.2.3 Spoil discharge system Once the spoil transports out from the jet grouting site, a spoil dis-charge system is incorporated to remove water from the spoil sludge,
Fig 10 Configuration of the spoil discharge system.
Trang 7and transport the spoil away from the construction site This prevents
secondary pollution from the sludge generated during jet grouting
The water extracted from the sludge may be recycled and reused in
the jet grouting
Fig 10shows the configuration of the spoil discharge system The
spoil discharge system consists offive parts: (1) the preliminary mixing
combination device, (2) the furnishing device, (3) the sludge
concentra-tion device, (4) the integratedfilter-press and sludge discharge device,
and (5) the recording device The preliminary mixing combination
device is used to store and mixing the spoil transported from the jet
grouting site The feeding tube is applied to connect the inlet pipe of
the storage tank with the diaphragm pump of the furnishing device
After thefirst step of mixing the spoil, the mixed spoil is transported
to the concentration device to dehydrate the spoil The sludge
concen-tration device contains: the discharge pump and the inner pressurized
storage tank The discharge pump is set at one side of the inner
pressur-ized storage tank and is connected with the tank through the sludge
valve When the sludgeflows through the inner pressurized storage
tank, the water can transit through thefilter fabric and the large soil
par-ticles will be held back in the device The concentrated spoil then transit
to the integratedfilter-press and sludge discharge device As a result the
filter cake will be formed, and the water can be stored for potential
recycling
3 Construction procedure The jet grouting operation with the PCJG technology is generally implemented as following stages:
3.1 Stage 1: drilling Fig 11a illustrates the process of drilling in horizontal jet grouting During drilling operations, the high pressure pump for water will be turned on to eject the pressurized water for improving the drilling ef fi-ciency The construction parameters (e.g drilling velocity and jetting rate) should be selected based on the designed value The PLC module for the pressure-control system should be used to monitor the inner pressure of the soil stratum and the discharging volume of the sludge simultaneously When the drill rod needs to be replaced, the spoil discharge equipment should be shut down
3.2 Stage 2: jet grouting Drilling is stopped when the drill rod reaches the designed position Fig 11b illustrates the horizontal jet grouting process The jet grouting parameters, including grouting pressure, retracting rate,flow rate, and rotation rate should beset to the predesigned values Meanwhile the pressure-control system and the spoil discharge system are activated
to keep the inner pressure at a balanced value, while the generated spoil is transported Simultaneously, the drill rod is rotated and slowly retracted from the drilling hole When the distance between the front head of the monitor and the retaining wall is reduced to half a meter, so-dium silicate solution (accelerator) is injected into the soil to promote solidification Use of accelerator can make the soil-cement admixture
Fig 12 Photographs of washing rod in horizontal jet grouting construction.
Fig 13 Test site location where the equipment was used (modified from Wang et al Fig 14 Soil profile and properties of the clay deposits at the test site.
Trang 8gel within 5 s to seal the hole and to stop the slurry fromflowing out
of the grouted column Thus, even after the pressure-control system
(including valve and rod) is removed, the slurry pressure of jet-grouted
column can keep balance with the earth pressure
3.3 Stage 3: end of construction
After the construction of one column, the drill rod is withdrawn to
the predesigned position, and the equipment is closed for cleaning
Fig 11c shows an illustration of the washing rod after construction
Fig 12gives photographs of drilling rod withdrawn (Fig 12a) and the
washing rod after construction (Fig 12b) The drill rod is then moved to
the designed position of the next column and the steps are repeated as
shown inFig 10, to complete the next column This process is repeated
until the target site has been jet grouted to achieve the desired ground
improvement
4 Case study and discussion
4.1 Project background
To demonstrate the capabilities of the new jet grouting equipment, a
field test was conducted at the Qingcaosha Water Source Project[22]
near Longyue Road in Pudong New Development District, Shanghai,
China[23].Fig 13shows the location of the test site[24].Fig 14
illus-trates the soil profile and the soil properties of the clay deposits at the
test site[25] A silty clay layer with a thickness of 2.8 m overlies a
10.2 m thick mucky silty clay layer[26] Under the mucky silty clay
layer, there is a very soft clay layer with a thickness of about 6 m[27]
The horizontally jet grouted columns are constructed in the silty clay layer at a depth of about 2 m below the ground surface[28], as shown
inFig 14 The silty clay layer has high water content[29], low strength and high compressibility characteristics[30].Table 1gives the jetting parameters in jet grouting constructions.Fig 15shows a plan view of the jet-grouting area Five columns (labeled C1–C5) were constructed using this new equipment The columns were designed to be 6 m in length and have a target diameter of 1.0 m
During thefield test, the vertical displacement of the ground surface was monitored.Fig 16shows a plan view of the layout of the settlement gauges (labeled O1–O3) The distances between the jet grouting zone and the settlement gauges O1, O2, and O3 were 1.8 m, 3.3 m, and 5.8 m, respectively The spacing between the settlement gauges and the construction area was 2.5 m
4.2 Effectiveness of PCJG
maxi-mum value of the ground upheaval was 9.4 mm (for column C4) and the minimum value was 0.4 mm (for C2) Because the new equipment can easily transport out the spoil and control the inner pressure of the soil stratum automatically during construction, the adverse ground movement can be reduced
Twenty eight days after installation of the trial columns, core samples are extracted from the jet grout columns for inspection For the entire core samples obtained, the total core recovery varied from 70% to 95% and the rock quality designation varied from 79% to 92%
Fig 16 Plan view of layout of monitoring instruments (modified from Wang et al [24] ).
field test (data from Wang et al.
Trang 9with Artificial Neural Networks [34] To predict the diameter of
jet grout columns installed using the various conventional jet grouting
systems (i.e single, double and triplefluid systems), a generalized
formulation was proposed in the form[31]:
Rj¼ ηxLþDr
where Rj= calculated radius of column;η = reduction coefficient
accounting for the effect of the injection time; xL= ultimate erosion
distance; Dr.= diameter of monitor All of the operational parameters,
fluid properties, soil strength and particle size distribution were
incorporated in the reduction coefficient (η) and the ultimate erosion
distance (xL) The reader can refer to Shen et al (2013b)[31]for an
in-depth description of this method
Similarly, Flora et al.[17]proposed an alternate formulation to
predict the average diameter of jet grout column infine-grained soils
formed using conventional jet grouting systems:
Da¼ Dref αΛE0n
7:5 10
qc
1:5
−0:25
ð3Þ
where Da= average calculated diameter of column; E′ = specific
ener-gy at the nozzles;α = parameter relating to the jet interaction with the
surroundingfluid (either grout spoil or air): i) α = 1 for single fluid jet
grouting where no air shroud is used, ii)α N 1 for double and triple fluid
jet grouting;Λ⁎ = parameter relating to composition of the eroding
fluid (either water or grout); Dref= reference diameter obtained with
singlefluid jet grouting having the water-cement ratio of eroding fluid
ofω = 1, and corresponding to E′ = 10 MJ/m and qc= 1.5 MPa The
reader is referred to Flora et al (2013) for further details of this method
[17]
In adopting Eq.(2)for the present trial parameters, a predicted
diameter of 1.04 m (i.e Rj= 0.52 m) The alternate prediction using
Eq.(3)gave a diameter of Da = 1.13 m These predicted diameter
are a little bit smaller than the measured diameters of 1.1 m to 1.4 m
observed in the trial columns[24] This shown that removal of spoil
increases the erodibility of jetting, which was considered in the
theoret-ical prediction equations
5 Conclusions
Newly designed automatic pressure-control equipment has been
developed to reduce construction related ground movement and
environmental impact during horizontal jet grouting operations The
applicability of this new equipment was verified through a case study
in a well consolidated soil strata with over-consolidation ratio greater
than unity Detailed conclusions can be drawn as follows:
1) The innovative elements of the horizontal jet grouting equipment
include: i) multiple-functional monitor, ii) pressure control system,
and iii) spoil discharge system
2) The developed automatic pressure-control jet grouting equipment is
based on the concept of self-balanced pressure and automatic spoil
drainage During jet grouting, the construction parameters,
includ-ing water pressure, groutinclud-ing rate, and retractinclud-ing velocity can be
detected, recorded and controlled automatically The generated
spoil can be removed from the stratum to maintain the stability of
the ground and to effectively reduce environmental impact
to ensure the spoil path out road during jet grouting Thus, the clogging of gap between diameters of monitor and rod should be avoided There are two possible reasons for clogging: collapse of soil strata and large diameter of soil particle (e.g gravel particle) The factor influence of clogging may include stress state of soil, par-ticle size of soil and size of the gap, which need to be investigated further in the future to develop universal applicable equipment in various soil strata
Acknowledgements The authors thank Dr Anil Misra for assistance in review and proof-read the manuscript for improvement of the quality of the manuscript
in both English and technical aspect The research work described herein was funded by the National Nature Science Foundation of China (NSFC) (Grant No 41372283) and National Basic Research Pro-gram of China (973 ProPro-gram: 2015CB057806) Thisfinancial support
is gratefully acknowledged
References
[1] T Yahiro, H Yoshida, Induction grouting method utilizing high-speed water jet, Proceedings of 8th International Conference on Soil Mechanics and Foundation Engineering, Moscow 1973, pp 402–404.
[2] C.E Ho, Analysis of deep jet groutingfield trial in clay, Contemporary Topics in Ground Modification, Problem Soils, and Geo-Support, Geotechnical Special Publication No.187, American Society of Civil Engineers, Reston 2009, pp 233–240.
[3] Z.F Wang, S.L Shen, C.E Ho, Y.H Kim, Investigation of field installation effects of horizontal twin-jet grouting in shanghai soft soil deposits, Can Geotech J 50 (3) (2013) 288–297.
[4] Y.X Wu, S.L Shen, Y.S Xu, Z.Y Yin, Characteristics of groundwater seepage with cut-off wall in gravel aquifer I: field observations, Can Geotech J 52 (10) (2015) 1526–1538.
[5] Y Tan, X Li, Z Kang, J Liu, Y Zhu, Zoned excavation of an oversized pit close to an existing metro line in stiff clay: case study, J Perform Constr Facil 29 (6) (2014) 04014158.
[6] N Eramo, G Modoni, M Arroyo Alvarez de Toledo, Design control and monitoring of
a jet grouted excavation bottom plug, in: Viggiani (Ed.), Proc of the 7th Int Sympo-sium on Geotechnical Aspects of Underground Construction in Soft Ground, TC28 IS Rome, Taylor & Francis Group, London, 2011.
[7] S.L Shen, Q.L Cui, E.C Ho, Y.S Xu, Ground response to multiple parallel microtunneling operations in cemented silty clay and sand, J Geotech Geoenviron Eng 142 (4) (2016) 04016001.
[8] M Ochmański, G Modoni, J Bzòwka, Numerical analysis of tunneling with jet-grouted canopy, Soils Found 55 (5) (2015) 929–942.
[9] A Davia, M Marotta, G Peach, High pressure jet grouting for a collapsed tunnel — a case study, International Conference and Exhibition on Tunnelling and Trenchless Technology Selangor 2006, pp 143–155.
[10] N Zhang, S.L Shen, H.N Wu, J.C Chai, Z.Y Yin, Evaluation of effect of basal geotextile reinforcement under embankment loading on soft marine deposits, Geotext Geomembr 43 (6) (2015) 506–514.
[11] H.N Wu, S.L Shen, L Ma, Z.Y Yin, S Horpibulsuk, Evaluation of the strength increase
of marine clay under staged embankment loading: a case study, Mar Georesour Geotechnol 33 (6) (2015) 532–541.
[12] G Modoni, J Bzòwka, Analysis of foundation reinforced with jet grouting, J Geotech Geoenviron Eng 138 (12) (2012) 1442–1454.
[13] I.K Mihalis, G Tsiambaos, A Anagnostopoulos, Jet grouting applications in soft rocks: the Athens metro case, Proc Inst Civ Eng Geotech Eng 157 (4) (2004) 219–228.
[14] H.N Wu, S.L Shen, S.M Liao, Z.Y Yin, Longitudinal structural modelling of shield tunnels considering shearing dislocation between segmental rings, Tunn Undergr Space Technol 50 (2015) 317–323.
[15] P Croce, A Flora, Analysis of single-fluid jet grouting, Geotechnique 50 (6) (2000) 739–748.
[16] P Croce, G Modoni, Design of jet grouting cut-offs, Ground Improv 11 (1) (2007) 1–9.
[17] A Flora, G Modoni, S Lirer, P Croce, The diameter of single, double and triple fluid jet grouting columns: prediction method and field trial results, Géotechnique 63 (11) (2013) 934–945.
[18] S Coulter, C.D Martin, Effect of jet-grouting on surface settlements above the Aescher tunnel, Switzerland, Tunn Undergr Space Technol 21 (5) (2006) 542–553.
Trang 10Eng Geol 196 (2015) 59–70.
[26] Y.X Wu, S.L Shen, Z.Y Yin, Y.S Xu, Characteristics of groundwater seepage with
cut-off wall in gravel aquifer II: numerical analysis, Can Geotech J 52 (10) (2015)
1539–1549.
[34] M Ochmański, G Modoni, J Bzòwka, Prediction of the diameter of jet grouting columns with artificial neural networks, Soils Found 55 (2) (2015) 425–436.