Sumitomo Mitsui Construction Co.,LTD Ha Noi City Ring Road No.3 Construction Project Method statement for Service road Package 2: Trung Hoa — Thanh Xuan section 1.. Ha Noi City Ring Road
Trang 3HANOI CITY RING ROAD NO.3 CONSTRUCTION PROJECT PACKAGE 2: TRUNG HOA — THANH XUAN SECTION (KM23+195 — KM 5+265)
107 Nguy Nhu Kon Tum — Nhan Chinh Ward — Thanh Xuan District — Hanoi
đa SUMITOMO MITSUI CONSTRUCTION CO., LTD
Oriental Consultants Co.,Ltd (OC) and Katahira & Engineers
in association with TEDI, APECO, ITST and VECC
Cc: Mr Vu Xuan Hoa — General Director
Mr Pham Thanh Binh, Deputy General Director
ME QSET
AI Method statement for Service Road Cc
Note:
- Refer to Technical Specification $1.14
The Engineer’s Representative
OC, KEI; TEDI, APECO,
ITST, VECC
Trang 4The Engineer's Representative Authorized Representative
Al Approval
Trang 5
Site Organization Chart
Equipment and machine
7.1 Working flow chart
7.2 Detail method statement
7.2.1, Preparation work 7.2.2 Unsuitable excavation 7.2.3, Embankment with borrow material, 50cm;
9.4 Emergency Call out Procedure HRR- PACKAGE 2
9.4.1 Initiation 13 -07- 201
9.4.2 Second Stage
9.4.3 Third Stage | RE EKEAG =
Emergency response chart
Appendix—1 Hazard analysis
Appendix—4 Plan view & Typical of cross section 12
Trang 6
Sumitomo Mitsui Construction Co.,LTD
Ha Noi City Ring Road No.3 Construction Project
Method statement for Service road Package 2: Trung Hoa — Thanh Xuan section
1 General
This method statement describes the work procedure for construction of Service road along the construction site of Ha Noi city Ring Road No.3 - Package 2 This work shail
be carried out in accordance with Technical Specification, Clause $1.14
This construction method will clarify and ascertain of above work
2 Quantity
Estimated quantity is only for reference as following The final quantity will be calculated at site
by daily contemporary record
3 Construction schedule (Please refer to appendix — 2)
4 Site Organization Chart
Senior Project Manager
——————————
Tran Van Huyen
Trang 7
Ha Noi City Ring Road No.3 Construction Project Sumitomo Mitsui Construction Co.,LTD
Package 2: Trung Hoa — Thanh Xuan section Method statement for Service road
1 Dump truck ~ | Nos | Requirement | Transporting material
6 Description of material (Black sand & Base)
- Black sand material will be transported to the site during the time of excavation work
- Base material will be transported, stored at site and sprayed water to get good moisture
content before construction ,
7, Construction Procedure
7.1 Working flow chart
Preparation work - Confirmation of plan view & typical cross section
- Establish stake at site
- Mobilization of Equipment & manpower
¥
Excavation work - Checking of working area by tape & visual
- Disposal unsuitable soil
Trang 8Ha Noi City Ring Road No.3 Construction Project Sumitomo Mitsui Construction Co.,LTD
Package 2:.Trung Hoa — Thanh Xuan section Method statement for Service road
7.2, Detail method statement
7.2.1 Preparation work
Clear up area for excavation and remove excess or any materials placed temporarily in
the working area
Manpower, materials and equipments should be mobilized as following the schedule
Proper lighting (during time of working at night shift) and safety facilities should be
furnished in the working area
Survey line marking and layout for construction road shall be established
This work shall be constructed from 2 lines: Line 1: Le Van Luong — Nguyen Trai
Line 2: Le Van Luong — Big C (Please refer to Appendix 4: Plan view & Typical Cross section)
Proceeding the survey and setting out for the construction limit
Grass and unsuitable material will be cleared by using excavators and bulldozers, and
removed material will be disposed from out of construction area by using the Dump
trucks with cover
7.2.3 Embankment work (Black sand, 50cm)
This work shall be carried out the same time of Excavation work
Before construction, the mark sticks shall be staked for control the leveling elevation
The material will be delivered by dump trucks and checked by visual during
construction
After that, the material shall be leveled by using the bulldozers and workers
The compaction work will be done by using the vibration roller and watering (if
necessary) to get the good moisture content
Thickness of embankment is 50 cm as layer
7.2.4, Base course, 30cm
Before construction, the mark sticks shall be staked for control the leveling elevation
The material will be delivered -by dump trucks and checked by visual during
construction And the material shail be stored at site, sprayed water to get good
moisture content
After that, the material shall be leveled by using the bulldozers and workers
The compaction work will be done by using the vibration roller and watering (if
Trang 9Ha Noi City Ring Road No.3 Construction Project Sumitomo Mitsui Construction Co.,LTD
Package 2: Trung Hoa.— Thanh Xuan section Method statement for Service road
Close to the manhole of crossing pipe, manhole of earth ditches will be made to collect
the water from the earth ditches Therefore, those collected water pumped to the
crossing pipe’s manhole for permanent sewerage
7.2.6 Cleaning work
Arrangement sign man, safety cone at location of entrance for control public traffic
Dispose ail the debris and other materials
Cleaning the site after finishing work, specially cleaning the entrance
8 Environmental control!
The SMCC should have responsibility for surrounding environment during the
construction time with complying the Condition of Contract and Vietnam’s National Law
on Protection of Environment and other relevant legislation such as: Government
Decree No.175/CP, Government Decree on providing Guidance for the Implementation
of the Law on Environmental Protection, 1994
9 Safety control
Safety Control Plan shall be refferred to SMCC Safety method statement and shail be
part of this method statement (submitted particular)
Prior to starting of construction of Service road, the following paticular matters are to
be through to all members working in the construction site in order to complete the
work efficiently without any accident or casualty
9.1 Joint meeting
Prior to starting of construction of Service road, a joint meeting with relevant staffs has
to be held for the purpose of general explanation on whole contents of works as well as
mutual implementation of efficient work
9.2 Instruction
For new coming staffs during the work, the same instruction is to be made as it has
been explained and discussed in the above joint meeting
9.3 Prevention of accidents
To prevent injury for third party:
The safety board and safety cone will be installed the entrance of the working area and
signal man arrange during transportation of equipment and material to the site
To prevented accident during working time
Check worker's PPE before start work
Check license of operator and equipment
Install safety facilities at working area
9.4, Emergency Call out Procedure
9.4.1 Initiation
Site with staff working on night works, shall initiate the Emergency Call out Procedure
(As refer to in the Emergency response chart)
Trang 10Ha Noi City Ring Road No.3 Construction Project Sumitomo Mitsui Construction Co.,LTD
Package 2: Trung Hoa ~ Thanh Xuan section Method statement for Service road
The Site Engineer and Safety Officer (2nd Stage) will be called, and if they cannot be
contacted, their level will be skipped and the 3rd Stage will be alerted In addition, the
initiator will take prompt action to mitigate the situation When he is released he will
report on:
The situation in general in compliance with the trigger definition
The number of people killed / injured / involved
Action taken by responsible site supervisory personnel
Other vital information in brief
The Site Engineer will also report the matter to the Site Manager/Construction
Manager and contact the duty telephone on the situation
9.4.2 Second Stage
Safety Officer, upon receiving information will check the completeness and assess the
situation If necessary, he will travel to the Site to check himself Upon verification of
all information involved, he will initiate the Third Stage (3rd Stage) with given
telephone number(s)
9.4.3 Third Stage
The persons at the 3rd Stage (Project PQEHS Manager) shall assess the situation i.e
severity of accident/incident and decide whether they will proceed with Emergency Call
Out or not If the situation required, he will call
Trang 11Ha Noi City Ring Road No.3 Construction Project
Package 2: Trung Hoa —- Thanh Xuan section
EMERGENCY RESPONSE CHART
Add: 9 Tran Binh St, Cau
Giay District, Hanoi
Tell: (043) 768.3113
Viet Duc Hospital:
Add: 40Trang Thi St, Hoan
Kiem District, Hanoi
Trang 12Ha Noi City Ring Road No.3 Construction Project Sumitomo Mitsui Construction Co.,LTD
Package 2: Trung Hoa — Thanh Xuan section Method statement for Service road
APPENDIX
Trang 13Ha Noi City Ring Road No.3 Construction Project Sumitomo Mitsui Construction Co.,LTD
Package 2: Trung Hoa — Thanh Xuan section Method statement for Service road
Appendix 1:
Hazard Analysis
Trang 15Ha Noi City Ring Road No.3 Construction Project Sumitomo Mitsui Construction Co.,LTD
Package 2: Trung Hoa — Thanh Xuan section Method statement for Service road
Trang 16work (arrange safety foiites, ) excavation
wth black sand, 50cm course, 20cm Finishing work, remove safety facies and clean the site {inctuding 01 turing areal
1 work (arrange safety facies )
3 excavation
3 ‘with black sand, 80em
4) [Base course, 30em
3) work, remove safety faclities and clean the site (ncluding 04 turing area)
1) work (amrange safety facies )
2 ‘excavation 3Ị with black sand, 20cm
4} [Bane course, 30em
51 ‘work, remove salety faglfies and clean the si IP101-Pˆ2051ineruding 0% turảng area}
H work (arrange safety facies.) 2) excavation
3) ‘with black sand, Sem 4} [Base course, 30cm
9 ‘work, remove salaty faciities and elean tha sits P108-PtUs (including 01 turing area)
9 Wark (arrange safety faites.)
3 wih black sand, Soom
@) [Base course, Soom
3 ‘work, remove salety facing and clean te sta 116-422 (including 01 turing area)
1 work (arrange safety fuclties,.)
No Name Unit Quantity Description Remark
3 Bulldozer Nos 2 Levelling material H R R ~ P A Cc K A G E 2
= > -07- 2011
5 Water truck Nos 4 Watering
7 | Survey equipment Set 1 Survey work
//2011/8:38 PK
Trang 17KS
Ha Noi City Ring Road No.3 Construction Project Sumitomo Mitsui Construction Co.,LTD
Package 2: Trung Hoa — Thanh Xuan section Method statement for Service road
Trang 18BAN QUAN LY DU AN THANG LONG - PROJECT MANAGEMENT UNIT THANG LONG
Project (tên dy an’ Hanoi 3rd Ring road construction Project (DA Package (tên gói thầu): Package 2 ~ Trung Hoa - Thanh Xuan
XD đường vành đai 3 Hà Nội) section (Gói thầu 2 ~ Đoạn Trung Hoa -
Thanh Xuan)
CONTEMPORARY RECORDS
(Biên bản ghi chép hiện trường)
Date (d/n/y - ngày, tháng năm):
Work Item (Hang muc):
Name of the Part (Tên bệ phận):
Base on (căn cứ vào):
WarR H96 (Công việc được thực hiện)
1.No Deseription Quantity Demension/Speccification Time (Thời gian)
Trang 19BẠN QUẦN LÝ DU AN THANG LONG - PROJECT MANAGEMENT UNIT THANG LONG
Project (tên dự án) Hanoi 3rd Ring road Package (tên gói thầu): Package 2 — Trung Hoa -
construction Project Thanh Xuan section (Gói thầu (ĐA XD đường vành 2¬ Đoạn Trung Hoa - Thanh
Consultants (TV): OC, TEDI, APECO, RITST Contractor (NT): SMCC
Actual working time
Trang 20BAN QUAN LY DU AN THANG LONG - PROJECT MANAGEMENT UNIT THANG LONG
Project (tén dy an’Hanoi 3rd Ring road construction Project (DA Package (tên gói thầu):
XD đường vành đai 3 Hà Nội) Package 2 ~ Trung Hoa - Thanh Xuan
section (Gói thầu 2 - Đoạn Trung Hoa - Thanh Xuan))
(Biên bản ghi chép hiện trường)
Date (d/n⁄+y - ngày tháng năm):
Work Item (Hang muc):
Name of the Part (Tén bé phan):
Base on (cần cứ vào):
Equipment (Thiét bị)
TT (Loại thiết bị) (Thiết bị đikèm) — CAPAG (Shin (Hời Used (C.suét) liu) Htvh = gian) (chạy) (chờ) Idle
Material (Vật liệu) Quantity Unit Description Source Remark
(Khối lượng) (đơn vị) (Mô tả) (nguồn) (ghỉ chú)
Site Manager Site engineer Site manager Site Engineer
Trang 21Ha Noi City Ring Road No.3 Construction Project Sumitomo Mitsui Construction Co.,LTD
Package 2: Trung Hoa — Thanh Xuan section Method statement for Service road
Trang 22
BIG ¢ SUPER MARKET (SIEU THIBIGC)
National conference center
“Trung tâm hội nghị quốc gia
Trang 24CROSSING PILE NO.4
‘The culture center of Thanh Xuan District
‘Trung tm van ho& quan Thanh Xuan
H=1.73M (EXGAVATI Œ ION) department
Ban cdyếu chính phô
Licogi No.13 Công ty cơ khí và sấy lấp
EXISTING MANHOLE H=1.82M (EXCAVATION) ww?
Trang 25
CONSTRUCTION VAN LUONG - BIG! LINE 2
CROSSING PILE No.G
CENTER LINE OF RAILWAY
Trang 26AFC
tR- PACKAGE 2
mr
Trang 27STAZ5+062.10 2.34M (EXCAVATION)
EXISTING MANHOLE H=4.71M (EXCAVATION)
Trang 28: ¬ ưv.ư®ờớẻớ asm | aos | oma am TYPICAL CROSS SECTION (TYPE 3)
= {including 01 turing area) " BARS