1. Trang chủ
  2. » Kinh Tế - Quản Lý

Thông tư Quản lí chapter8

6 115 0

Đang tải... (xem toàn văn)

THÔNG TIN TÀI LIỆU

Thông tin cơ bản

Định dạng
Số trang 6
Dung lượng 226,5 KB

Các công cụ chuyển đổi và chỉnh sửa cho tài liệu này

Nội dung

Chapter 8 - Assigning Resources to TasksIntroduction The Three Pillars of Task Scheduling: Work, Duration, and Resources How Microsoft Project Schedules a Task The Link Between the Task

Trang 1

Chapter 8 - Assigning Resources to Tasks

Introduction

The Three Pillars of Task Scheduling: Work, Duration, and Resources

How Microsoft Project Schedules a Task

The Link Between the Task and Its Predecessor

The Duration You Enter for the Task

The Resource's Working and Nonworking Time

The Resource Units You Assign to a Task

Assign One or More Resources to a Task

Control When a Resource Starts Working on a Task

Remove a Resource from a Task

Replace a Resource in One Step

Trang 2

A project plan that contains only tasks can adequately support the scope of your project You need only make sure that your plan includes all the tasks required to accomplish your goals But if you want to exercise fine control of your project both at the project level and at the task level, you should assign resources to tasks

At the project level, you can add or remove resources to bring them into balance with scope and time at any phase of your project For example, if you add a new feature to your product, thus increasing the project scope, you can add more resources Or, if your deadline is delayed by several months, you can compensate for

downtime by removing resources from your project and adding resources to a more urgent one

At the task level, you can fine-tune the trio of work, duration, and resources to schedule each task at the right time, make each task as short as possible, and use resources efficiently For example, if a task duration pushes the project

end date beyond your deadline, you can either assign more resources to the task or lengthen the work hours of assigned resources Or, if one person has too much work and another too little, you can assign one person to spend less time on tasks and the other person more time

If your project has only a few tasks requiring few resources, and you don’t need to track costs in detail, you might not need to assign resources to tasks If you don’t assign resources, you can still track task progress and some costs, but Microsoft Project won’t be able to calculate resource costs as the project progresses You’d have

to enter any updated resource costs yourself

When you do assign resources to tasks, you gain several benefits:

 Your schedule mirrors your actual circumstances more accurately

 You can assign responsibility for tasks

 You can monitor workload and make adjustments to avoid overloading resources

 You can track resource costs, often the largest portion of total project costs

Trang 3

The way Microsoft Project uses work, duration, and resources to schedule tasks is a process called effort- driven scheduling, which is the default scheduling method With effort-driven scheduling, you can see immediately the

effect of assigning a resource to or removing a resource from a task

You can manage your resources by controlling when a resource starts working on a task and by removing resources that are no longer needed

The Three Pillars of Task Scheduling: Work,

Duration, and Resources

When you assign resources to a task, Microsoft Project calculates the task’s schedule by using the work,

duration, and resources associated with the task Typically, you enter values for two of these, and Microsoft Project calculates the third

Work is the amount of effort, measured in time units (like hours or days), put into a task by a resource The total work for a task is the sum of all those time units, no matter how many resources are assigned to the task

For example, if two people each work 8 hours to complete a task, the total work for that task is 16 hours

Duration is the amount of time between the start and finish of a task Microsoft Project calculates a task’s

duration based on the number of resources and the amount of work assigned to it For a typical task, the more resources you assign to it, the shorter its duration will be

Resources are the people, equipment, office space, and so on that do — or facilitate — the work on a task

Using resources gives you further control over your schedule For instance, if you want a task or the project as a whole to decrease in duration, you can add more resources

How Microsoft Project Schedules a Task

Microsoft Project schedules a task based on information that you enter into your project plan (such as the task duration), the type of link you assign to the task, resource assignments, and constraints When you vary any one of these factors, you can affect the task’s schedule To have Microsoft Project schedule a task exactly the way you want it, you need to know how these factors do that

The following factors are used to calculate a task’s schedule

The Link Between the Task and Its Predecessor

The start date that Microsoft Project calculates for a task depends on the type of link you have assigned it For example, if it’s a finish-to-start (FS) link, the task begins as soon as its predecessor finishes With a start-to- start (SS) link, the task begins when its predecessor begins

The Duration You Enter for the Task

Microsoft Project uses the task’s duration to calculate the start date or finish date A good rule of thumb is to have a specific number of resources in mind when you enter a duration For example, if you know that a task usually takes three people 8 hours to complete, enter the duration as 8 hours When you assign resources to the task, remember to assign three of them all at once, or else change the duration accordingly

The Resource’s Working and Nonworking Time

Defined in a resource calendar, a resource’s working and nonworking days and hours let Microsoft Project know which days and how many hours per day a resource is available to work

The Resource Units You Assign to a Task

Trang 4

When you assign a resource to a task, you can specify the percentage of the resource’s total daily working hours

that the resource will work on the task That percentage is known as resource units If you don’t specify

resource units, Microsoft Project assumes you want the resource to work full-time (100 percent) on the task (unless it’s a part-time resource)

Assigning a resource at 100 percent units means you want the resource to give all available working hours to the task If one resource is scheduled to work a total of 6 hours per day, then 100 percent units is equal to 6 hours For a resource scheduled to work an 8-hour day, 100 percent units is equal to 8 hours (and 25 percent units = 2 hours, 125 percent units = 10 hours, and so on)

With effort-driven scheduling, the more resources you assign to a task, the shorter the duration becomes In the Gantt Chart view, the Gantt bars decrease in length

If you want to see how these different factors — link type, duration, resource calendars, and resource units — affect the schedule of a task in your project, you can vary each factor in Microsoft Project until the task is scheduled exactly the way you want it

Trang 5

Assign One or More Resources to a Task

Keeping track of which resource performs a particular task, how much work a resource has in a certain time period, and how much your resources have cost since the project began can be difficult and time-consuming But there’s one thing you can do that enables Microsoft Project to take care of these responsibilities for you: assign resources to tasks

When you assign a resource to a task, you create an assignment You can assign any resource to any task and

change assignments at any time

You can assign more than one resource to a task and specify whether a

resource works full-time or part-time on the task by using resource units

Resource units indicate the percentage of the resource’s time allocated to the

task By default, Microsoft Project assigns 100 percent units to each resource

(unless a resource is a part-time resource) If the resource represents a

single entity, 100 percent units means the resource is working full-time on

the task If you assign a resource group — for example, a group of three

painters — at 100 percent, it means only one of the painters is assigned to

the task If you assign all three painters, it would be 300 percent

If the work assigned to a resource exceeds the daily full-time allotment

indicated in the resource’s working times calendar, Microsoft Project displays

the name of the overallocated resource in red in resource views

To assign a resource to a task

1. On the View Bar, click Gantt Chart

2. In the Task Name field, select the task to which you want to assign a

resource

3. Click Assign Resources

4. In the Name field, select the resource you want to assign to the task.

If necessary, type the name of a new resource in a blank Name field

5. Click Assign

A check mark to the left of the Name field indicates that the resource is assigned to the selected task

Control When a Resource Starts Working on a Task

When you assign resources to a task, Microsoft Project assumes by default that each resource begins working

on the task on that task’s start date But that scenario might not match reality One resource might begin work

on the start date, but another might not be available until several hours or days later

With Microsoft Project, you can specify exactly when a resource begins working on a task For example, you can stagger the times that multiple resources begin working on the same task by delaying the starting time of one

or more of the resources This is true even if you have only one resource assigned to a task When you delay the start of a resource assignment, Microsoft Project recalculates the start date and time for the resource’s work

on the task

To control when a resource works on a task

1 On the View Bar, click Gantt Chart

2 On the Window menu, click Split

3 In the Task Name field, select the task for which you want the resource’s work to be delayed

4 Click the Task Form view in the bottom pane

5 On the Format menu, point to Details, and then click Resource Schedule

6 If there is no work for the resource in the Work field, enter the work in the field, and then press ENTER

7 In the Delay field for the resource, enter the duration by which you want to delay the start of the

resource’s work

For example, type 2h for a delay of 2 hours; type 2d for a delay of 2 days

8 Click OK

9 On the Window menu, click Remove Split

Double-click a resource

in the

Resour

ce Assign-ment

dialog box to display the

Resour

ce Inform ation

dialog box

Trang 6

Remove a Resource from a Task

Just as a task can change during a project — for example, its duration can increase or decrease — so can a resource If one of your resources falls ill or becomes too busy to work on a task, you might need to remove that resource Whenever necessary, it’s easy to remove the assigned resource

To remove a resource from a task

1. On the View Bar, click Gantt Chart

2. In the Task Name field, select a task from which you want to remove a resource

3. Click Assign Resources

4. In the Name field, select the resource you want to remove, and then click Remove

Replace a Resource in One Step

You can replace a resource with someone on your resource list in one step For example, you might find a more qualified person to perform a task you already assigned to someone else Or, perhaps a piece of equipment you’ve assigned to a task breaks down Rather than removing the assigned resource and then assigning another resource in a separate action, you can simply replace one resource with another

To replace a resource with another resource

1. On the View Bar, click Gantt Chart

2. In the Task Name field, select a task with a resource you want to replace

3. Click Assign Resources

4. In the Name field, select the resource you want to replace, and then click Replace

5. In the Name field, select one or more resources to assign to the task, and then click OK

Ngày đăng: 27/08/2017, 21:58

TỪ KHÓA LIÊN QUAN

TÀI LIỆU CÙNG NGƯỜI DÙNG

  • Đang cập nhật ...

TÀI LIỆU LIÊN QUAN

w