2 Projects and company organisational structures The hierarchical functional structure The matrix structure The problem of dual reporting The need for a corporate culture The pure projec
Trang 2Project Management and Project Network Techniques
Trang 3• •
• •
We work with leading authors to develop thestrongest educational materials in management,bringing cutting-edge thinking and best learningpractice to a global market
Under a range of well-known imprints, includingFinancial Times Prentice Hall, we craft high qualityprint and electronic publications which help readers
to understand and apply their content, whetherstudying or at work
To find out more about the complete range of ourpublishing please visit us on the World Wide Web at:www.pearsoned.co.uk
Trang 4An imprint ofPearson Education
Harlow, England· London New York > Boston San Francisco Toronto « Sydney Singapore Hong Kong Tokyo Seoul Taipei New Delhi· Cape Town Madrid Mexico City· Amsterdam· Munich· Paris· Milan
Trang 5Edinburgh Gate
Hariow
Essex CM20 2JE
England
and Associated Companies throughout the world
Visit us on the World Wide Web at:
www.pearsoned.co.uk
First published in Great Britain in 1964
Sixth edition 1996
Seventh edition 2005
© Keith Lockyer and James Gordon 1996, 2005
The rights of Professor Keith Lockyer and Dr James Gordon to be identified
as authors of this work have been asserted by them in accordance
with the Copyright, Designs and Patents Act 1998.
All rights reserved; no part of this publication may be reproduced, stored
in a retrieval system, or transmitted in any form or by any means, electronic, mechanical, photocopying, recording, or otherwise without either the prior written permission of the Publishers or a licence permitting restricted copying
in the United Kingdom issued by the Copyright Licensing Agency Ltd,
90 Tottenham Court Road, London WIT 4LP.
lSBN-lO: 0-273-69378-6
ISBN-13: 978-0-273-69378-9
British Library Cataloguing in Publication Data
A ClP catalogue record for this book can be obtained from the British Library.
Library of Congress Cataloging-in-Publication Data
A catalog record for this book is available from the Library of Congress
1098765432
09080706 OS
Typeset in Stone Serif 9.5/12.5 by 30
Printed in Great Britain by Henry Ling Ltd., at the Dorset Press, Dorchester, Dorset
The publisher's policy is to use paper manufactured (rom sustainable forests.
Trang 6To Doris and to Antoinette
Trang 8Preface
1 Introduction
Definition of a project
Revenue and capital projects
How is a project different from other operations?
Four phases of a project
Why project management?
2 Projects and company organisational structures
The hierarchical functional structure
The matrix structure
The problem of dual reporting
The need for a corporate culture
The pure project structure
3 Project organisation
The project manager
Desirable skills
The project team
4 Planning the project
Outline of planning concepts \./
Opportunity costs
The work breakdown structure
Introduction to project planning techniques
The network as a budget
Card networking/bar charting
5 Quality and reliability management in projects
The quality and reliability concepts of project management
Project quality and the parent organisation
Project processes and quality
xi
1
1
223379911
12
1314
1616
17
192121
22232425313234353737
Trang 9The following are particular to:
Activity-an-arrow (AaA) systems: Chapters 11, 13
Activity-an-node (AaN) systems: Chapters 12, 14, 15
Trang 1011 Drawing the activity-on-arrow network 94
Conventionsadopted in drawing AoA networks 95
12 Drawing the activity-on-node network 113
13 Analysing the activity-on-arrow network 122
14 Analysing the activity-on-node network 137
Trang 1119 Line of balance and elemental trend analysis 200
• Complete, downloadable Instructor's Manual
For more information please contact your local Pearson Education salesrepresentative or visitwww.pearsoned.co.uk/lockyer
Trang 12of historical interest and including practices which are of general use today Thepresent text is, as was the previous edition, intended for all those entering, orintending to enter, the fascinating and challenging field of project management.The authors have tried to produce text which is of immediate use to the reader.It
is believed that it will be of value to the increasing number of students, bothpost- and undergraduate, who seek to know something of project management
Let it be clear, neither this book, nor any other book, can create a successful
pro-ject manager Such an animal requires to have an inborn personality andresilience which will enable him or her to lead a team of individualists throughtimes which often appear traumatic The hope is that it will shed some light onareas which may not have been previously considered
The text is broadly divided into two parts The first deals with the managerialaspects of project management and has been updated to reflect the development
of the managerial aspects of projects, the second, which is a condensation of the
fifth edition of Critical Path Analysis and other Project Network Techniques, with
project management techniques and here also this edition, which is a furtherrationalisation and condensation, reflects the changes which have occurredsince the sixth edition was published Both may be read separately, and indeedthe whole book is intended to be suitable for selective reading if this is what isrequired A chapter on 'some practical considerations' which was much appreci-ated in the fifth edition and was enlarged and restructured in the sixth edition,
to take into account the problems of managing a project, is included unchanged
in this edition Two questions which both authors have been asked countlesstimes, and are still unable to answer, are treated in a brief appendix, There are,however, a set of questions, some dealing with management aspects and somewith project network techniques (PNT), for which answers to the numerical
questions will be found in the Instructor's Manual The answers to the essay
ques-tions are embedded in the main text
Itis interesting to realise that although projects have been carried out as long
as man and woman have existed, it is only within the last few decades that it hasbeen found necessary to define a project Even more recently has come the need
to recognise that there is a significant difference between managing a project andany other form of management, although recently even this has again become
Trang 13more blurred with the increasing misuse of the title Project Manager in someparts of industry For this the development of the cheap, high capacity micro-computer together with the availability of cheap software which has enabledmany to prepare network based plans - without unfortunately understandingthe underlying techniques - has in large part been responsible The microcom-puter, however, has of course been a vital element in the development of profes-sional project management
Younger readers will not be able to realise the problems early (that is to say1960s!) project managers had when, having planned a project using, say, CPA, theonly computer in the company (if there was one at all) was the vastly expensivemainframe which always seemed to be occupied by the payroll, the monthly finan-cial statements, or the chairman's statement for the AGM when the computer wasused as a 'big typewriter' The chance of getting a rerun with modifications to theoriginal network was often minimal A 'what-if' run was never heard of The onlyanalysis was provided by a printout on huge concertina sheets of paper The vision
of the project manager with piles of these printouts remains Vividly in bothauthors' minds today Itis the cheap dedicated micro which has allowed the con-sideration of the study of the art and science of project management
As far as possible, nomenclature agrees with BS 6079 - 2:2000, Project ment - Part 2: Vocabulary, a standard which now has wide international accep-tance Where words are used which do not appear in that glossary, every attempthas been made to conform to that which is in general use in the UK The onlyexception to this in the past was the use of the word 'log' in place of 'diary' in'project log' The importance of a comprehensive record of the project cannot beoverstated, and the authors felt that the word 'log' carried with it a weight, a feel-ing of importance, which was lacking in 'diary' The authors are pleased that this
manage-is now generally accepted and included in the present BS Vocabulary The
defini-tion in the Concise Oxford Dicdefini-tionary underlines the point: 'Logbook: a
perma-nent record made daily of all events occurring in the ship's voyage including rate
of progress ',
As previously, any mistakes in the present text are the responsibility of theother author
K.G Lockyer].H Gordon
Trang 14Definition of a project
No definition of a 'project' will suit every situation, but one appearing in ISOdocuments appears to be acceptable to a wide range of users ISO 9000:2000,
Quality management systems - Fundamentals and vocabularystates:
Project - unique process, consisting of a set of co-ordinated and controlled ities with start and finish dates, undertaken to achieve an objective conforming
activ-to specific requirements including the constraints of time, cost and resources
To this definition ISO, National Standards and other documents can add notes to
amplify the use of the term 'project' For instance ISO 10006:2003, Quality
manage-ment systems - Guidelines for quality managemanage-ment in projects,adds the following notes:Notes
1 An individual project may form part of a larger project structure
2 In some projects the objectives and scope are updated and the productcharacteristics defined progressively as the project proceeds
3 The project's product is generally defined in the project scope Itmay beone or several units of product and may be tangible or intangible
4 The project's organisation is normally temporary and established for thelifetime of the project
S The complexity of the interactions among project activities is not sarily related to project size
neces-Project management is thus principally concerned with the introduction andmanagement of change All projects are unique in some respect or other and maydiffer from the usual business for which the parent company exists The projectorganisation, often referred to as the project team - though this in itself is but asmall part of the total project organisation - is set up to achieve a particularobjective: the project product Teams which remain together at the conclusion of
a project and take over the next project are common in some industries but less
so in others, particularly manufacturing
Trang 15Project management and project network techniques
Common elements of a project
The project product can take many forms, from the wholly physical - the ation of a new town or the building of a new locomotive, to the virtually abstract
cre a procedure for dealing with a possible emergency Between these two extremesthere is a diversity of products each with its own particular requirements, which
in turn may require variations in the management of the project This diversity,spread over companies and industries, has impeded the recognition that thereare common elements to all projects However, they all have a:
• specification for the product;
• project plan;
• time frame;
• budget;
• cost plan;
• statement of quality required;
• identification of any areas of uncertainty;
• evaluation of possible risks and the appropriate responses
Systems must be set up to collect, in real time, the data concerning progress and
costs Facilities must be available to analyse the data and distribute the results ofthat analysis These elements are common to all projects, but their implementa-tion will depend on the product, the size of the project and the industry inwhich it is being carried out To impose a multi-thousand activity project system
on a project with a few hundred only would be absurd, losing clarity, increasingcost and wasting time
Revenue and capital projects
Projects come in many sizes, from the very small to the very large They may besimple or complex, although size and complexity are not necessarily related.Itis,however, convenient to divide them into two categories:
• Revenue projects are those for which the expenditure is treated as an expensearising during a defined accounting period
• Capital projects are those for which expenditure is capitalised, that is it isincluded on the balance sheet Investment projects should enhance the organ-isation's assets Clearly, in practice, many projects fall between these twobroad categories, and the acid test is the need to set up a special organisation
to deal with the project It is also true that capital projects always require
considerable capital investment, though this may sometimes be true of enue projects Thus, the two main characteristics of capital projects are:
rev they usually occupy considerable time;
- they always employ considerable capital
Trang 16As a consequence, they do not fit readily into a conventional organisational ture but cut across functional and time boundaries and thus require an organisa-tion particular to themselves It is with this organisation, its structure andbehaviour that this present text is mainly concerned For the sake of simplicity, theterm 'project' will be henceforth used to stand for 'capital project' Equally, theterm 'product' will be used to describe the output of a project irrespective ofwhether it is hardware, software, a service, a system or any other kind of output.
struc-A project may arise from not just one company but from several (a tium) This can raise serious problems if there is not full and free communication
consor-on all matters between the various partners Poor or limited communicaticonsor-ons canlead to distrust between partners and thus to partners taking unilateral action.The main characteristics of a project which differentiate it from conventionaloperations are:
• its uniqueness;
• its defined start and finish
Even with these characteristics it is sometimes difficult to decide whether agroup of activities is a project or not For example, the design, launch and initialproduction of a new product is a project, while the subsequent bulk production
of the product is not
How is a project different from other operations?
Operations which proceed under conventional line management are involved inwhat is normally a substantially stable situation Such changes which do takeplace are generally under the control of the line manager and the rate of change
is likely to be slow Project management, on the other hand, is concerned whollywith the introduction and management of change Such change is likely to crossconventional functional boundaries and may well be concerned with activitiesoutside those usually found within the organisation, though this last is not true
of a project-centred organisation
All projects pass through at least four identifiable phases(see Fig 1.1)
1 Conception
In many ways this is the most crucial phase of a project's life in that all that lows is determined by decisions and commitments made in this phase An ideafor a new product will be presented to the organisation, which may come inter-nally from an employee, or externally from a potential client asking if the prod-uct can be provided Assuming that the product is within the capability andethos of the organisation, then, before any decision is made on the possibledesirability of accepting the project, a comprehensive feasibility study must take
Trang 17fol-Project management and project network techniques
Fig 1.1 The four phases of a project
place This should involve, if organisationally possible, the probable projectmanager, as well as all the functions which will be involved within the organisa-tion and any external suppliers of items or services Where the project is for aconsortium, the way in which the work is to be divided between the variousmembers must be resolved This division must be accepted by the membersbefore any work on the project is undertaken
At the conclusion of the study, the following are the factors which shouldhave been determined as a minimum:
• the capability of the organisation to provide the product in the time required;
• the final price for the product;
• the costs involved;
• the budget required for the project;
• the outline specification of the product, including the quality and reliabilityrequirements;
• the ability of the organisation to support the capital outlay;
• the availability of any items or services to be procured from outside theorganisation;
• the acceptability of any geographical requirements on procurement or ecologywhich are specified in the project enquiry;
• the acceptability of any contract conditions which are specified in the enquiry
At the conclusion of the conception phase the product purpose and its design parameters must be documented in clear and unambiguous terms and agreed with the customer as the business case for the project The acceptance of the business case by the parent organisation and the customer is the point at which the projectis formally authorised This remains true irrespective of whether the projectis the subject of an external con- tract orisinternal to the organisation.
II2 Development
Assuming that the proposed new product is acceptable to the organisation, theproduct has to be designed or specified in such detail as is necessary to allow it to
Trang 18be created within the limits set in the conception phase Since the organisation isnow committed to the project, its manager should be appointed and he or shewill work closely with the customer in this and subsequent phases Considerationshould also be given to assembling at least the senior members of the projectteam A first phase Project Management Plan (PMP), as the major element in thedeveloping documentation for the project, must be drawn up under the direction
of the project manager(seeFig 1.2 for the document flow in a project)
~
rIm
100 50
Fig 1.2 The document flow in a project
Reprinted fromProject Planning and Control,4th edition, A Lester, p 354, Copyright 2003, with permission from Elsevier.
Trang 19The Project Management Plan is, or should be, alive document which is in effect,the project 'Text Book'.It is not of itself a time schedule but it contains all thetime based and other plans for the project.Itsets out the 'what', {Why', {When',
{Who', {Where', {How' and often the (How much'of the project The majority of theinformation it contains is available to the project team and the customer, butsome information, such as costs and commercial information, may be restricted
to named people Itis not a static document carved in stone: all projects sufferchange, some more than others, and any change must be documented togetherwith its authorisation
The contents and size of the document will of course relate to the size andcomplexity of the project; for a large industrial or governmental project it mayrun to several large volumes, while for a small in-house project a loose-leaf foldermay be sufficient Whatever the project, certain aspects must always be covered;
these are set out very clearly in clause 6.5 of BS 6079-1:2002 - Part 1; Guide to
pr()-jeet management, and in the 'Model project management plan suggested list' given in that document
check-3 Realisation
Once designed or specified, the project team has to turn the development intoreality An appropriate reporting system has to be provided as part of the projectplan to keep the team, top management and the customer informed on:
a regular basis, preferably daily
Note: The authors prefer the term 'log' to 'diary' since a log is something
which must be kept whereas a diary implies a degree of judgement in its upkeep.
4 Termination
An analysis of the project reports will provide invaluable information which can
be helpful in other projects This will include:
• success of methods used
• performance of team members
• reliability of suppliers
In addition to the above analyses, many projects will be completed with aresidue of capital equipment which is then surplus to the organisation's needs.This has to be disposed of as rapidly and as profitably as possible
Trang 20Each of these phases could form a project in its own right It is normal forthere to be an interval between the initial conception phase and the later phases,whilst in most cases the others overlap in time and merge into one another This
is particularly likelyifthe project request is an internal one with a vigorous ject champion Equally, although there is usually one project manager, if thephases are discrete, there may be a different project manager for each phase
pro-Why project management?
When a company which has been operating in a conventional functionallybased manner finds that the number of projects which it has to deal withbecomes uncomfortably great and large enough to require frequent board con-sultation and approval, consideration must be made at board level of the need toamend the company's existing organisational structure It is often not realisedthat the timescale implicit in such a change can be substantial Observation byone of the authors suggests that in a company of any size, three to five years arenecessary for the new organisation to settle down and people to become com-fortable with it Questions will be asked, objections to apparent loss of status will
be made, political moves worked out, and the informal structures which ease somuch of working life developed Initially, each new project will not only be seen
as a new problem to be solved but also as something to be resisted
Change is something which takes place in all organisations While it takesplace within the control of the functional manager, it will generally be consid-ered as quite normal and requiring no special steps to be taken However, oncethe rate of change increases to the extent that resources become overstretched,and/or the change involves other functions, difficulties arise It is at this stagethat the need to change to some form of 'project management' is recognised,even if it is not explicitly identified as such, and a 'project manager' is appointed.The interaction of resource requirements between the 'normal' work and the'project' is usually, and uncomfortably, complex and requests for resources to bedevoted to the 'project' are met with the 'We'll do it when we can fit it in'response This, almost always, is too late for the needs of the 'project'.Furthermore, functional managers may well believe that their authority is beingthreatened by the introduction of this new-fangled project manager This isoften resented, a resentment which is often expressed in a generally unhelpfulattitude, if not in downright covert obstruction, an attitude which is extremelydifficult to identify
Many organisations tryout 'project management' on a small scale, oftenunder the eye of top management The interest which this generates will usuallyadd such weight to the project and its management that the trial is a resoundingsuccess Project management then becomes instituted as the normal practice foranything identified as a project Sadly, unless the implications have been prop-erly digested, and the effect of top management interest realised, the extensionwill be far from successful A further pressing need for some form of manage-ment which differs from normal functional management is created by the fact
Trang 21that many projects are physically separated from the host organisation and,therefore, have no ability to call upon the functional specialists.
Making the change to project management itself is, of course, in itself a projectand should be treated as such.Ithas to be planned, implemented and monitored
as carefully as any other project After all, the future prosperity of the organisationprobably depends on its successful completion In any but the very largest organi-sations it is unlikely that the personnel skills to carry through such a change will
be available and external assistance may be required One thing is certain, thechange must be actively supported by the board and a board member shouldbecome project champion for the change itself One problem which is found instrongly hierarchical organisations is that the functional heads will see that pro-jects require resources - previously totally under their own control- to be shared
In turn this will be seen as a loss of status and security, and defensive mechanismswill be set up Careful handling and lengthy explanation are required to changesuch an attitude, a change which may never happen in some cases
Trang 22Projects and company organisational structures
Any group which comes together to make a product, be it hardware or software
or to provide a service, must form itself into an organisation with a structure.This structure will affect the way the organisation can respond to change and theintroduction of projects
The hierarchical functional structure
The majority of industrial organisations which have been set up to manufactureproducts or provide a service, develop a common form of organisation, the con-ventional hierarchical functional structure as shown in Fig 2.1
Fig 2.1 Hierarchical functional organisation
Trang 23In this form of organisation the heads of the various specialist functions reportdirectly to the chief executive who is responsible to the board for co-ordinatingthe work of the specialist functions to meet the objectives of the organisation.The functional heads in turn have the section heads within their functionreporting to them and they, in turn, have their own subordinates who report tothem This form of organisational structure has existed for a long time in indus-try because of its advantages, which include the way in which the structure:
• maintains tight control at the top;
• logically represents the functions;
• maintains the power and prestige of the functions;
• reduces any duplication of functional effort;
• allows for concentration of functional skills;
• has very simple reporting relationships;
• can achieve extremely high plant/capital utilisation
As discussed in Chapter 1, there are no problems with this structure so long asthe rate of change, which occurs in all organisations, does not overstretch thefunctional resources or cross functional boundaries When that happens, the dis-advantages of the structure become apparent These include that it may:
• cause over-specialisation;
• cause parochialism of key personnel;
• weaken co-ordination between functions;
• stifle the development of generalist (project) managers;
• limit the ability to respond in periods of fast change and diversification in themarket;
• impose an increasing burden on the chief executive as the rate of changeincreases;
• require extremely detailed pre-production planning
These problems are likely to arise when a new job requires greater resources thananyone function can provide while continuing its normal work, or is going tocut across a number of functional boundaries without belonging to anyone inparticular The chief executive, who will then have responsibility for the new job
in addition to his/her other duties, may well then decide to appoint a 'projectmanager' reporting directly to him/her This manager will, of course, requirestaff as support in managing the 'project' and this may initially be of the formshown in Fig 2.2 and would be likely eventually to be of the form shown inFig 3.1 for a full team
Even with a full team, specialist assistance may still need to be drawn from thefunctional groups for some aspects of the project For instance, in a hardwareproject, engineering design work may well be carried out in the appropriate func-tional groups The co-ordination and timing of the work however will be theresponsibility of the project teamin conjunction with the functional headto whomthe design staff report for their professional competence
Trang 24Chapter2 IIIProjects and company organisational structures
Fig 2.2 Hierarchical functional organisation with a single project
The matrix structure
These problems will continue to exist while there is only one project at a timewithin the organisation and, although they may be recognised by the chief exec-utive, it will not be worth changing the functional structure just to accommo-date one project which is known to have a limited life However, once it is clearthat projects are continuing to be carried out within the organisation, and thatthere may be several running simultaneously, a different situation arises and achange of organisational structure becomes essential.Itbecomes necessary to set
up a project management function group with its own functional staff of projectspecialists Furthermore, if many of the projects require it, it may also be neces-sary to obtain dedicated functional specialists as part of the group either by with-drawing them from the existing functional groups or by external recruitment.Ifthey are obtained internally - which if at all possible they should be - then they
must be organisationally disengaged from their previous positions. Ideally, the projectgroup should also be physically separated and located within their own area.This will have the benefit of freeing and speeding up the communication systemand increasing the feeling of commitment to the project The functional special-
ists will still be able to refer to the functional supervisors, but only for functional
technical problems.
This type of organisational form is shown in Fig 2.3
Such a structure is an inevitable consequence of a multi-project situation, andwhilst it may solve some problems, some remain and some new ones are created.However firmly a functional specialist is nominally disengaged from his/her
Trang 25Project management and project network techniques
Fig.2.3 Matrix organisation
previous supervisor, some latent responsibility and loyalty will always remain Inmany cases, evenifthere is a geographical separation, the functional supervisorcan still affect the functional specialist's career This can lead to a dual reportingsituation (one official, one unofficial) which can be confusing and possiblymalign For example, specialist Al may have a technical disagreement with pro-ject manager PMI which is not resolved to the satisfaction of AI In the hope ofoverturning the decision, Al may appeal to the functional supervisor SMA who,while having no authority over the project, has direct access to the chief execu-tive who does have that authority
The problem of dual reporting
A more unpleasant situation can arise if Al believes that the project manager issomehow at fault A 'word' may be passed by Al to the functional supervisorSMA which can seriously affect the behaviour of many in senior management It
is essential that the reports emanating from the project are the regular plannedprogress reports from the project manager prepared with thehelp and agreement
of the project team and directed to the chief executive Itcannot be stressed toostrongly that functional specialists, and others, within the team should not bepermitted to submit their own separate specialist reports as this will, at best, con-fuse the lines of communication and, at worst, cause the project team to fallapart with serious consequences for the project In a study of matrix organisations
Trang 26Chapter 2 III Projects and company organisational structures
(Barllett, C.A and Ghosal, S (1990) 'Matrix organisations, a state of mind',
Harvard Business Review, Vol 68 pp 138-142) the authors stated that they hadfound that' dual reporting leads to conflict and confusion'
The need for a corporate culture
The changes in managerial behaviour which are required by the adoption of amatrix organisational structure are far reaching, stretching to the board itself Toensure that different project teams react the same way to similar circumstancesand that both project managers and functional supervisors have the same view onthe priority of objectives, a powerful corporate culture must be developed This isneither an easy nor a rapid goal to achieve, probably consuming several years, butwithout its achievement there may be inconsistent behaviour between teams andfunctions which could prove embarrassing to the whole organisation.Itmust also
be remembered that project teams may be physically distant from the parent pany and each other, and that communication between them, on those non-programmable problems which are only dealt with by the use of the personalskills, experience, judgement and enterprise of the senior staff, will be difficult.The matrix organisational structure has, of course, a number of advantages in
com-an environment of chcom-ange.Itallows:
• a more rapid response to changes in demand;
• a better balance to be achieved between time, cost and resources than in thepure functional form;
• the preparation of independent policies and budgets for projects, althoughthey must not conflict with established policies and procedures;
• a clear definition of the responsibility and authority of the project manager;
• the creation of a strong base of technical expertise which is built up throughexperience in a range of projects;
• project costs to be properly identified
The disadvantages are that, in addition to the time required to reach maturity, itwill require, on the part of top management, considerable commitment andeffort to:
• define pcJlicies, procedures, responsibilities and authorities throughout the
A difficulty with this form of structure, and one reason why it is often resisted,
is that the cost of management is clearly revealed, probably for the first time for
many companies since it is normally hidden in the overheads Another ible difficulty is that, in organisations which are not completely project
Trang 27poss-Project management and project network techniques
centred, when one project is completed there may not immediately be anotherfor the project team to pick up As a result its members may be dispersed eitherback to their original function - which may prove difficult if their place hasbeen filled - or to some other part of the organisation, possibly to assist onanother project This can result in some confusion of loyalties, and beliefs thatcareer prospects are jeopardised, unless clear policies are set down and under-stood by the staff concerned
I The pure project structure
These problems tend to disappear as the organisation becomes more project tred, carrying out nothing else but projects While this is relatively rare outsideorganisations providing a service or consultancy, it does exist with advantage incompanies in jobbing production or those with a very limited product range, forexample, oil rig maintenance Such an organisation is likely to have a structuresuch as that shown in Fig 2.4
cen-Here the separate functions have virtually disappeared, the functional abilitybeing concentrated in the project teams with some reserve held as a central poolunder a manager, which is available to provide extra resources to the projectswhen required Unlike the other organisational forms, the project team is seldomdispersed but remains as a unit ready to pick up the next project which the
Process eng * Specialist lead engineers allocated
to projects as appropriate
"technical services manager
Engineering
Fig 2.4 Project organisation
Trang 28Chapter2 III Projects and company organisational structures
marketing executive will, hopefully, provide The 'top' of the organisation hasalso Virtually disappeared
While this form of organisation does not assist in the development of tional supervisors it has the following advantages over the other forms of func-tional and matrix organisation:
func-• the lines of project responsibility and authority are clearly identified;
• project budgets can be clearly defined and controlled;
• communications between the projects and top management are improved;
• managers whocanmanage change are developed;
• strong team understanding and loyalties are developed;
• the costs of management are clearly identified
Figure 2.5 shows schematically how the authority structure changes as anorganisation moves from being purely functional through a matrix to a pureproject structure
I
Matrix structure
Project with limited functional authority
Project structure
Fig.2.5 Authority relationships in organisational structures
Trang 29Project organisation
The variety of products produced by projects is immense, the connecting threadsbeing their uniqueness, the fact that each has a defined start and finish and theneed for each to be planned This diversity means that it is not possible to laydown the 'best way' in which a project should be organised, and no text canhope to cover all the possible variations of the project team organisation.However, one important difference between the organisation of hardware andinformation technology teams does seem to have emerged This difference isconcerned with the authority, responsibility and accountability of the projectmanager In hardware and most service provision projects there is invariably oneperson, the project manager, who has executive authority, within defined terms
of reference, for all aspects of the project Itappears that in IT and software jects the person appointed as project manager reports to an executive committeewhich make the executive decisions
pro-As discussed earlier, the size and detailed structure of a project team willdepend on the technology, size and cost of a project, but even at its smallestthere must always be a project manager
The project manager
The project manager for any project should be appointed as early as possible inthe life of the project, ideally in the conception phase This is not always poss-ible, so that the project manager, when appointed, may find he/she is committed
to decisions with which he/she is not in agreement This always creates problemsand the manager must formally record the problem as early as possible with aview to possible modification of the decisions The early commitments whichhave to be made in many projects will also have significant effects and the pro-ject manager, on appointment, should carry out an audit and assessment of theproject for reassurance that it is feasible within the given terms of reference Forinstance in construction projects some 80 per cent of the total project cost is inmaterials and errors in early commitments can have significant effects on prof-itability and on the project risk assessment
Trang 30Chapter 3 Project organisation
Project management is essentially team management Where the project is aconsortium project, team members may come from different cultures and speakdifferent languages so that the acceptance of the team as the driving force, ratherthan the functional and/or national interests, by all its members is particularlyimportant Optimising one part will almost inevitably result in suboptimisingthe whole
Project managers, to be successful, must possess capabilities which cannot belearnt They must be leaders, and those who are being led must respect their hon-esty, integrity and vision They will need to demonstrate drive, enthusiasm, ded-ication and humour, and a willingness to back their staff, to whom they havedelegated responsibility, when things go wrong.Ithas been said that:
To win a battle it is essential to inspire the army with confidence in itself andits general
Additionally the project managermustbe an eternal optimist!
Desirable skills
The desirable skills of a good project manager are:
1 Technological understanding Since the project manager will have to ate, possibly without recourse to assistance from the parent company, techni-cal proposals and recommendations, including an assessment of any risksinvolved in the use of new or untried technologies, an adequate technologicalunderstanding of the project is vital Since, by their very nature, projects tend
evalu-to be multi-disciplinary some of this understanding will probably come fromthe project manager's basic discipline and training; the rest rriay have to belearned very rapidly Itis, however, undesirable for the project manager to be
a specialist in the project technology, as he/she may tend to get involved inthe technology to the detriment of the management of the project
2 An understanding of project economics This will require a thoroughunderstanding of the customer's totalview of the project and its subsequentoperation or use This will require financial skills applied to the project andthe use of such techniques as life-cycle costing
3 A knowledge of man management techniques This will include a ledge of and the ability to use:
know-• payment and bonus systems;
• interviewing techniques;
• team building and motivation;
• industrial relations legislation and its application in the project environment;
• the health and safety at work regulations and their application to the project
4 A competence in systems design and maintenance This includes edge of, and the ability to implement, appropriate office and technologicalsystems for both the project team and the project
Trang 31knowl-Project management and project network techniques
S A competence in planning and control A sound knowledge of all the niques for planning and controlling projects, with the ability to decide which
tech-is the most appropriate to use as circumstances artech-ise
6 Financial competence The ability to read and understand companyaccounts, together with an understanding of the various financial accountingtechniques including:
• setting and controlling budgets;
• cost control;
• variance analysis;
• cash flow statements and earned value;
• discounted cash flow methods (DCF);
• net present value (NPV);
• credit control;
• loan and interest repayment systems;
• risk analysis (financial);
• lifecycle costing
7 A competence in procurement This will include knowledge of:
• contract law;
• techniques for the procurement of goods and services;
• costs of holding stock;
• expediting;
• materials control
8 Good personal communication abilities The project manager will often becalled upon to address meetings, both business and public, on a variety ofmatters concerning the project Additionally, there will be the need to teachproject and customer's staff on the use of techniques and methods and toassess training needs and courses
These issues are summarised in Table 3.1
Table 3.1 Desirable skills of the project manager
• Understanding of project economics
• Knowledge of man management
Trang 32Chapter3 Project organisation
The project team
The size of the project team will naturally be related to the size of the project sothat in a small project it may only have one full-time member, the project man-ager, who draws on others for specialist assistance when required(seeFig 2.2) Asthe size of the project grows so does the team until a complete team structureemerges For larger projects still it is the numbers in the team that change, notthe structure of the team A full project team will be made up as in Fig 3.1
As discussed earlier, even with a full project team, assistance from the tional specialists may be required for many aspects of the project These special-ists then have a dual responsibility which is at the heart of many of the problems
func-of project management in functional industry Staff who are seconded to a ject have in effect two supervisors:
pro-1 the head of the function who is their normal supervisor and is the one towhom they look for salary, promotion and career prospects; and
2 the project manager to whom they are responsible for their work in the ject and who will report on that work, and their general conduct, to theirfunctional head
pro-This inevitably leads to divided loyalties and problems as a result, particularlywhen staff are seconded full-time to the project and may be physically absentfrom the function office at the time of annual reviews and similar occasions and
so feel that they do not receive the recognition that their work on the projectdeserves Oddly enough, this problem appears to be at its worstif the physicalseparation is so slight that communications appear to be easy and no formalstructure is set up A distant location forces the setting up of formal communica-tions channels Equally, when a problem, not necessarily technical, arises con-cerning some aspect of the project, to whom do staff turn? They are in aninvidious dual reporting situation, and to whomsoever reference is made, theother 'supervisor' will feel aggrieved
Level1 Project manager
1
-Procurement officer
Level 2 Project
accountant
Project co-ordinator(s) (Engineer(s))
1
-Level 3
Level 4
Assistant accountants
Project planners (Network analysts)IAssistant planning analysts
Functional specialists
Fig 3.1 Structure of a full project team
Trang 33As a project of any size progresses the project team membership will change asfunctional specialists enter and leave the team in response to the changing tech-nical demands of the project Some people will stay with the project throughoutits life; others will be concerned only with a particular phase and on its comple-tion will return to their functional group in the parent company or transfer toanother project It is a major part of the project manager's job to ensure thesmooth integration of these people into the project team to progress the work asharmoniously as possible.
As with the project manager, in addition to their technical skills, the personalskills of the members of the project team are of considerable importance Projectscan become very demanding and lack of harmony in the team can be disastrous.For this, if for no other reason, the project manager must be involved in theselection and appointment of, at the very least, the two top levels of the team.The project manager should aim to build a team in which people will:
• behave innovatively, if necessary, and generally adopt a problem-solvingapproach;
• openly discuss ideas before they are adopted;
• communicate freely between functions;
• sell the ideas and work of the team;
• obtain co-operation from people outside the team;
• ensure that work is progressed at an acceptable level;
• assess their own and other people's work pragmatically;
• remain cohesive as a group even when things go wrong
The team must be aware of the need for good communications both within thegroup and with others Communication is a two-way process - the project notonly requires information, it must also supply it The formal reporting systemsand regular meetings are only one aspect of the communication network Thecustomer and other interested parties, suppliers of goods and services, and otherswho have only transitory links with the project should be encouraged to raiseproblems and concerns as early as they become aware of them Discussions and,when necessary, actions can then be taken to resolve the difficulties Commercialand Official Secrecy requirements must, of course, be respected and, as discussedearlier, the dangers of dual reporting well understood and avoided
Trang 34Planning thep.roject
Any endeavour should be planned and, the larger or more complex or uncertain
it is, the more essential a plan becomes This is particularly true of projectsbecause of their uniqueness and, except for very small projects, the planningactivity needs to be formalised Even small projects can be complex and requirecareful planning to resolve the interactions between the various jobs or activitieswhich make up the work in the project
I Out.llneofplanning concepts
Present decisions affect both present and future actions and,ifimmediate, term decisions are not made within the framework of long-term plans, then theshort-term decisions may effectively impose some long-term actions which areundesirable but inescapable Military writers categorise these long- and short-term plans as:
short-• strategic plans - which are those made to 'serve the needs of generalship';
• tactical plans - which are those made 'when in contact with the enemy'.
Ideally, of course, strategic plans are mll.?e beforethe start of an operation and,
by following them, the operation is successfully concluded Inevitably, however,tactical decisions will have to be made and these can only be successfuliftheyare made within the context of the strategic plan
To permit effective tactical decision making, it is necessary for the strategy to
be expressed in a form that is:
• explicit;
• intelligible;
• capable of accepting change;
• capable of being monitored
Itmust be realised that there is no absolute definition of strategy and tactics: atanyone level in a hierarchy a tactical plan should be made to fit the needs of thestrategy received from a higher level and this tactical plan then becomes the
Trang 35Project management and project network techniques
strategy for a lower level Freedom to make appropriate decisions must be given
to those who will be held responsible for performance and, if these decisions are
to be meaningful in a larger context, then it is imperative that this larger context
be known Freedom 'within the law' is as important a concept in management as
in the community Too often tactical decisions are taken to meet the needs ofimmediate expediency without reference to the strategic plan, and the resultsmay well be disastrous in the long term
- sacrificed - is £100, so the opportunity cost of the 'box under the bed' policy istherefore £100
This concept can be widely applied Thus, for example, at a project milestone
it is forecast that the project will overrun by one week and the penalty clausestates that for each week of overrun a penalty of £1000 will be levied The oppor-tunity cost of not taking any corrective action to pull the project back by oneweek is £1000, and this will give an idea of the extra cost which can be economi-cally incurred to avoid the overrun
A second example concerns procurement Suppose a piece of capital ment is to be hired for use on the project at a weekly rate of £1000 Itis brought
equip-on to site three weeks before it is needed The opportunity cost of this earlyhiring is £3000 plus any financing charges and the weekly cost of storage andinsurance Equally, material which is over-ordered or delivered early will attract
an opportunity cost which is often alarmingly high
Itshould be noted that opportunity costs do not show up in the final projectaccounts, being absorbed in the general financing Thus, in the example above ofthe piece of equipment brought on site early, the hiring cost will appear as oneitem A declaration of the extra costs involved by bringing the equipment on sitebefore it was needed is a statement which is outside the experience of eitherauthor It is also true that opportunity cost may not be the sole criterion inmaking a decision Itmay be that other commercial considerations outweigh theopportunity cost but it must always be taken into account
Trang 36Chapter 4 Planning the project
I Elements of project planning
The earliest attempt at aformalplanning system was the Gantt chart which was
derived from the simplebarchart.The use of the term 'bar chart' is now so versal for referring to either form that it has been used throughout this text,except in this chapter where 'Gantt charts' and 'bar charts' are discussed
uni-A project plan in its simplest form is an attempt at a ti.rrLetable for all the ities which make up the project.Itforms the first major step in the projectman-agement j.)rocess, and sets out 'hg,w', 'who does what' and 'when' At the nextstage of sophistication it will also state to 'what level of performance and quality'and at 'whatcost' At a yet higher stage of sophistication it will also be related tothe availability of the resources required to carry out the activities As each stage
activ-is considered, it may be necessary to reconsider and modify the preceding ones.The process ofq~51~!.lga projectmanagement plan is the responsibility of theproject manager and the projectteam, with the advice and assistance of the pro-ject sponsor, the customer and other interested parties The preparation of a pro-
ject management plan is an iterative process (see Fig 1.2).Itneeds to be reviewedand updated as information becomes available throughout the life of the project
It is never a static document and it forms the base against which all progress inthe project is measured Itmust therefore be as accurate and up-to-date as is pos-
sible No plan should ever be regarded as set in concrete - it is a working tool.
There will always be several levels within the project management plan At thehighest level it will be a summary showing key events and milestones in the pro-ject as an executive overview for senior management In a consortium project,the plan will indicate the agreed division of work between the members of theconsortium The lower levels will have increasing amounts of detail with thelowest giving activity lists for task owners who are responsible for activities in aparticular cost centre or function
The plan will always include a timetable for the work to be done This mayonly be in bar chart form but should preferably be a network, which has beenanalysed to obtain the start and finish data for all the activities As the projectproceeds the planning documents will also contain progress information show-ing the current state of the project against the plan In a long duration projectthe amount of detail included in the plan should vary with time In the shortterm, which may be three to six months or in some cases more, there should bethe full expansion of detail with progressively less from there on The short-termhorizon is, of course, moved forward at each update or at pre-planned times sothat detail increases as the project moves forward
The project management plan will include the bu? &tlfor the project andfinancial statements showing expenditure, income and n~tcash flQ}Vs adjusted
to net present values As noted earlier this part of the project management planmay be restricted to certain levels of management or in some cases named indi-viduals, as may other parts if they contain confidential information
Contained within the project plan there will also be plans for c~ge and figuration management, for quality and for procurement together with a risk
Trang 37con-Project management and project network techniques
assessment showing both financial and technical risks and their possible impact
on the project These may be the work of separate groups within the parent isation which specialise in the appropriate techniques, but for the project theyreport to the project manager who has to agree and approve their plans.Ifseparategroups exist they will probably second a member to the project team to supportthe appropriate activities.Ifthe project is large or is taking place physically distantfrom theoriginatingorganisation, there will probably be support teams, as part ofthe project team, for some or all of these aspects of the project plan
organ-I The work breakdown structure
Concurrently with the time-based plan a work breakdown structure (WBS) should
also be produced and included in the project management plan, which will vide all those involved in the project with a hierarchically structured division ofthe work required in the project The WBS can be structured in a number of alter-native ways depending on the use to which it is to be put Common ways are bydivision of the product into major components which are then split into sub-assemblies and so on down to components, by a functional breakdown or bycost centre code The way chosen is usually related to the type of project and theindustrial or public sector in which it is taking place
pro-In all cases, the lowest level in the WBS comprises groups of activities bined as a work package - or single activities ifthey are large enough - whichare the responsibility of a named individual - the task owner The task owner isresponsible for identifying, estimating, planning, executing and reportingprogress on the work in accordance with the project plan The task owner isalso responsible for the quality of the inputs to the project plan and for ensur-ing the progress data is accurately obtained and provided on time as required inthe plan
com-For each task a 'statement of work' (SOW) is required which describes theactivities in the task in sufficient detail to provide an unambiguous statement ofthe task owner's commitment to the project and thus enable the activity list data
to be complete The data required will include estimated durations together withthe resources required, costs, measures of performance including how any statedquality requirements are to be assessed, any risks and uncertainties and details ofreporting procedures
When the identified task is a subproject in its own right so that the task ownerbecomes a supplier to the project, the statement of work may need to take theform of a legal contract This will certainly be so ifthe task owner is external tothe parent organisation
The project manager must assess and discuss the statements of work supplied
by the task owners before agreeing the assignment of the work Implicit in theagreement is the ability of the task owner to fulfil the commitment, as defined inthe statement, at the time specified in the project plan The task owner is thuscommitted to provide the required resources at the right time without interferingwith other work
Trang 38Chapter 4 Planning the project
Concurrent with the WBS, the logical relationships between project activitiesshould be planned through the use of bar charts (where the logical relationshipsare difficult to express) or, preferably, through network diagrams in which theinclusion of the logical relationships is a part of the technique, whichever of thetwo types of diagram - of activity-on-arrow (AoA) or activity-on-node (AoN) - isused Both bar charts and project network techniques (PNT) are presented indetail in later chapters and discussed further below
There are differences of opinion among practitioners as to which comes first,the WBS or the network or an activity list Your authors do not feel stronglyabout it and would suggest that whichever is most convenient for the project iswhat comes first Whatever happens, the result is the same - the project logicplan and all that goes with it is produced
Introduction to project planning techniques
II The bar chart
When attempting to determine the completion date for any project, whether it
be the building of a bridge, the mounting of a sales conference, the re-layout of ashop, the designing of a new piece of equipment or any other project, it is neces-sary to_~ableall the activities that make up the task, that is to say aplanmust
be prepared The need for planning has always been present, but the complexityand competitiveness of modern undertakings now requires that this need should
be met rather than just recognised The first attempt at a formal planning systemwas theGantt chart.
In the Gantt chart the time that an activity should take is represented by ahorizontal line, the length of that line being proportional to the duration time ofthat activity In order that several activities can be represented on the samechart, a framework or ruling is set up, giving time flowing from left to right, theactivities being listed from top to bottom(seeFig 4.1)
Trang 39Project management and project network techniques
Assume, for the sake of simplicity, that there are three activities, A, Band C,which must be carried out in sequence and that the duration times are:
To show how work is actually progressing, a bar or line can be drawn withinthe uprights of the activity symbol; the length of the bar representing theamount of the work completed Thus, if 50 per cent of an activity is complete, abar half the length of the activity symbol is drawn (seeFig 4.3) This gives a verysimple and striking representation of work done, particularly if a number ofactivities are represented on the same chart
Ifthis chart has been correctly filled in and is viewed at the end of week 7, that
is 'time now' (denoted by two small arrows at the top and bottom of the chart asshown in Fig 4.4), then the following information is readily apparent:
ActivityA should be complete and, in fact, is so
Activity B should be 50 per cent complete, but, in fact, is only 17 per cent finished
ActivityC should not be started and, in fact, is not started
Activity 0 should be 62 per cent complete and, in fact, is only 50 per cent finished
Activity E should be 17 per cent complete and, in fact, is 50 per cent finished
Activity F should be complete and, in fact, is not started
ActivityG should be 87 per cent complete and, in fact, is complete
Fig.4.2 Three sequential activities
Fig 4.3 Representation of50per cent of activity complete
Trang 40Chapter 4 • Planning the project
Fig 4.4 Representation of progress
Thus we see that incomplete bars to the left of the cursor line mean fulfilment, while those to the rightmean over-fulfilment By the use of codesand/or symbols the reasons for any delays can be displayed and the whole chartcan be very succinctly informative, combining both planning and the recording
under-of progress For many tasks the Gantt chart is unsurpassed, and its use has beenvery highly developed
Though valuable, the Gantt chart presents three major difficulties; one cerning the problem of interrelationships, the second that of needing to take sev-eral decisions simultaneously and the third the problem of modifying the chart
con-The problem of interrelationships
Consider activity F in Fig 4.4 Itis shown here to start at the beginning of theproject However, it may be that there is another requirement, namely that itmust be completebeforeactivity C can start This means that activity F can in fact'slide' five weeks without detriment to the whole project There may also beanother activity, K (not shown in Fig 4.4), which can startonlywhen F is com-plete How can these interrelationships be displayed? It is possible, in a small-scale work, to 'tie' bars by dotted lines but, if more than a few activities areconcerned, the chart becomes so muddled as to be useless
The problem of simultaneous decisions
Locating an activity on a Gantt chart requires three simultaneous decisions to
• Resources: locating an activity in position implies that resources are available
to carry out the activity at that time