The electricity system and market operator shall be responsible for cooperating with the transmission network operator during the process of transmission grid development plan formulatio

Trang 1

THE MINISTRY OF INDUSTRY

REGULATIONS ON ELECTRICITY TRANSMISSION SYSTEM

Pursuant to the Government's Decree No 95/2012/ND-CP dated November 12, 2012, defining the functions, tasks, powers and organizational structure of the Ministry of Industry and Trade;

Pursuant to the Law on Electricity dated December 03, 2004 and the Law on Amendments to a number of articles of the Law on Electricity;

Pursuant to the Government's Decree No 137/2013/ND-CP dated October 21, 2013 detailing the implementation of a number of articles of the Law on Electricity and the Law on Amendments to the Law on Electricity;

At the request of general director of Electricity Regulatory Authority,

The Minister of Industry and Trade promulgates the Circular stipulating electricity transmission system.

Chapter I

GENERAL PROVISIONS

Article 1 Governing scope

This Circular stipulates:

1 Requirements of operation of the electricity transmission system

2 Load forecasts

3 Transmission grid development plan

4 Technical requirements and procedures for connection to transmission grid

5 Assessment of electricity system security

6 Operation of electricity transmission system

Article 2 Regulated entities

1 This Circular applies to:

a) Transmission network operator;

b) Electricity system and market operator;

i) Other organizations, individuals

2 Generating sets of a power plant with total installed capacity greater than 30 MW connected to distribution grid must meet technical requirements of equipment connected to transmission grid and other relevant requirements prescribed herein

Article 3 Interpretation of terms

In this Circular, some terms are construed as follows:

1 AGC (Automatic Generation Control) is an automatic equipment system for adjusting active power

of generating sets to maintain stability of electricity system frequency within permissible scope

according to operating principles of generating sets

2 Electricity system security is the ability of the system to supply power to meet demands for loads at

a certain point of time or for a specified period with account taken of electricity system obligations.

Trang 2

3 AVR (Automatic Voltage Regulator) is a system used to control terminal voltage of generating sets

through the impact on the excitation system of the generating set to ensure terminal voltage of the generating set within permissible limits

4 Voltage level is one of nominal voltage values of a system, including:

a) Low voltage: nominal voltage level to 01 kV;

b) Medium voltage: nominal voltage level over 01 kV to 35 kV;

c) High voltage: nominal voltage level over 35 kV to 220 kV;

d) Ultra- high voltage: nominal voltage level over 220 kV.

5 Dispatching level with control authority (hereinafter referred to as “the dispatch level”) is a

dispatching level that has the right to direct and dispatch the electricity system under the dispatching hierarchy prescribed in the Dispatch Procedure of national electricity system promulgated by the

Ministry of Industry and Trade.

6 Available capacity of a generating set is the maximum generating capacity of the generating set for

a specified period of time

7 Governor deadband is a frequency band within which any change of electricity system frequency

shall not result in reactions or impacts of the governor for adjusting primary frequency

8 Spinning reserve is the ability of a generating set operating in the national electricity system to increase or decrease generating capacity to restore electricity system frequency to permissible scope

after a single fault and restore reserve capacity of frequency control

9 Primary frequency adjustment is the process of adjusting electricity system frequency immediately

by a large number of generating sets equipped with a governor

10 Secondary frequency adjustment is the adjustment process following the primary frequency

adjustment carried out through the impact of AGC system on some generating sets specified in the system or load shedding system under the frequency or dispatching instructions

11 Electricity system dispatching is activities of directing and controlling the process of power

generation, transmission and distribution in the national electricity system according to the defined procedures, technical regulations and operation modes

12 Electricity wholesaler is the electricity unit that is granted the operation licence in electricity

wholesaling According to level of competitive electricity market, an electricity wholesaler shall be one

of the following units:

a) Electric Power Trading Company;

b) Power Corporations;

c) Other electricity wholesalers which are established according to individual levels of competitive electricity market

13 Generating unit is an electricity unit which is granted the operation licence in power generation,

possesses one or several power plants connected to the transmission grid or a power plant of over 30

MW in installed capacity connected to distribution grid

14 Electricity distributor means the electricity unit that is granted the operation licence in electricity

distribution, including:

a) Power Corporations;

b) Electricity companies of provinces, central-affiliated cities (hereinafter referred to as “provincial electricity companies”) affiliated to Power Corporations

15 Electricity retailer is an electricity unit that is granted the operation licence in electricity retailing.

16 Transmission network operator is the electricity unit that is granted the operation licence in

electricity transmission responsible for management and operation of national transmission grid.

17 Electricity system and market operator (the national electricity system dispatch center) is the unit

responsible for directing and controlling the process of power generation, transmission and distribution

in the national electricity system and conducting transactions in electricity market.

18 Reliability of a protection system includes:

a) Impact reliability of the protection system is the factor indicating ability of the protection system to

work properly on an incident within the determined scope of protection;

b) Non-impact reliability of the protection system is the factor indicating ability of the protection system

to avoid malfunctioning at the normal operation mode or any incident arising beyond the determined scope of protection

Trang 3

19 Governor is a device used to regulate rotating speed of the turbine of a generating set according to frequency changes to restore frequency to nominal electricity system frequency.

20 EMS (Energy Management System) is an energy management software system to optimize

operation of the electricity system

21 DCS (Distributed Control System) is a system of control equipment in a power plant or power

station connected to the network on the principle of distributed control to increase reliability and restricteffects caused by breakdown of control elements in the power plant or power station

22 Electricity system is a system of generating equipment, electricity network and utilities connected

to each other

23 The national electricity system is an electricity system which is managed in a uniform manner

across the country

24 Electricity transmission system is an electricity system including a transmission grid and power

plants connected to the transmission grid

25 SCADA (Supervisory Control and Data Acquisition) is a data collection system serving monitoring, control and operation of the electricity system.

26 Earth-fault factor is the ratio between the voltage on a healthy phase during a fault and value of

voltage of such phase before the fault (in case of single or double phase to ground fault)

27 Synchronization is the act of connecting generating sets to the electricity system or two parts of the

electricity system together according to synchronization conditions prescribed in the operating

procedure in the national electricity system issued by the Ministry of Industry and Trade

28 Black start capability is the ability of a power plant to restore at least one generating set to

operation from the state of complete stop and synchronize to the electrical grid without relying on transmission network in the area

29 Black start is the process of restoring all or part of an electricity system to operation from the state

of wholly or partial loss of power by using generating sets with black start capability

30 Customers using transmission grid are organizations and/or individuals possessing electrical equipment, electrical grid to connect to transmission grid, including:

a) Generating units;

b) Electricity distribution units receiving electricity direct from transmission grid;

c) Electricity retailers receiving electricity direct from transmission grid;

d) Electricity customers

31 Dispatch instruction is an order of commanding and controlling operation mode of an electricity

system in real time

32 Electrical grid is a system of transmission lines, power station and utilities for power transmission.

33 Distribution grid is a part of an electrical grid including transmission lines and power stations of up

36 Long-term flicker perceptibility (P lt ) is a value calculated from 12 measurement results of short-term

perceptibility for about two hours in following formula:

3

12 1

3

*12

P

37 Year N is the current year of operating an electricity system, calculated according to calendar year.

38 Typical day is a day that has the typical day of consumption of loads as prescribed in the contents,

methods and procedure for electrical load research issued by the Ministry of Industry and Trade Typical days include typical working days, weekends, holidays (if any) of years, months and weeks

39 Outage or reduction of power supply according to plan is the suspension of power supply to carry

out the plan for maintenance, repairs, overhaul and installation of electrical works; regulation and restriction of loads in case of a shortage according to the plan as informed by the electricity system

and market operator.

Trang 4

40 Thermo-electric plant is a power plant operating on the principle of thermal to electrical energy

conversion including biomass, biogas and solid waste power plants

41 Regulations on competitive electricity market operation are the regulations issued by the Ministry

of Industry and Trade and also the responsibility of the units in the electricity market by level

42 Load shedding is the process of cutting loads from electricity system in case of incident or lack of

electricity system security, carried out through an automatic load shedding system or dispatch

instruction.

43 Breakdown is an event or one or several equipment in the electricity system causing a disruption

of power supply or affecting safe and stable supply of power to the national electricity system

44 Single fault is a breakdown occurring in a single component of an electricity transmission system

as the electricity system is in normal operation mode.

45 Multi fault is a breakdown occurring in at least two components of an electricity transmission

system at the same time

46 Serious fault is an breakdown causing extensive loss of power on the entire transmission grid, or

fire & explosion which damages people and property

47 Electricity system split is a situation in which the national electricity system is separated into

disconnected small electricity systems by a fault

48 RTU/Gateway (Remote Terminal Unit/Gateway) is a device placed at a power station or power

plant serving collection and transmission of data to SCADA system of the electricity system dispatch center or control center

49 PSS (Power System Stabilizer) is a device added to the automatic voltage regulator to decrease

voltage fluctuation in the electricity system

50 Time of starting is a minimum period of time needed to start a generating set from the time the

generating unit receives the starting order from the electricity system and market operator to the time the generating set is synchronized into the national electricity system

51 N-1 criterion is a criterion for planning, design, investment, construction and operation of an

electricity system that ensures the electricity system operates normally in accordance with the

operating standards, permissible operating limits when a breakdown occurs in the system or a

component is taken from the system for maintenance and repairs

52 IEC standards are electrotechnical standards issued by the International Electrotechnical

Commission.

53 Automatic under-frequency load shedding is the act of cutting loads by frequency relays when

frequency or frequency slope of the electricity system drops below permissible limit

54 Power station is a substation, switching station or compensation station

55 Control center is a center equipped with information technology and telecommunications

infrastructure system to remotely monitor and control a group of power plants, power stations or

switchgears on the electrical grid.

56 pu is a per-unit system expressing the ratio between actual value and rated value.

Table 1

Permissible frequency band fluctuations and time for restoration of electricity system to normal

operation at other operation modes of the national electricity system

Operation

mode

Permissible frequency band fluctuations

Time of restoration since the time of fault (effective as of

January 01, 2018) Unstable status (reset mode) Restoration to normal operation mode

Single fault 49 Hz ÷ 51 Hz Two minutes to bring the

frequency to range 49.5 Hz ÷ frequency to range 49.8 Hz ÷Five minutes to bring the

Trang 5

frequency to range 49.5 Hz ÷

50.5 Hz

2 Permissible frequency band and acceptable number of beyond-the-limit times (the number of times the frequency may exceed the permissible limits) in case of multi fault, serious fault or extreme emergency mode are determined according to annual or biennial cycle in Table 2 below:

Table 2

Permissible frequency band and acceptable number of beyond-the-limit times in case of multi fault,

serious fault or extreme emergency mode

Permissible frequency band (Hz)

(“f” is electricity system frequency)

Acceptable number of beyond-the-limit times

(from the beginning of the cycle)

Article 5 Stabilization of electricity system

1 Stabilization of an electricity system is the ability of the electricity system, with predetermined initial conditions, to return to normal operation mode or reset mode after a physical impact has changed operational parameters of the electricity system Stabilization of electricity system is classified as follows:

a) Transient stability is the ability of generating sets in the electricity system to maintain consistent operational state when subjected to major disturbances

b) Small signal stability is the ability of generating sets in the electricity system to maintain consistent operational state when subjected to small disturbances;

c) Dynamic voltage stability is the ability of an electricity system to maintain steady voltage at all buseswhen subjected to major disturbances

d) Steady state voltage stability is the ability of an electricity system to maintain steady voltage at all buses when subjected to small disturbances

dd) Frequency stability is the ability of an electricity system to maintain steady frequency when disturbances have caused loss of load-generation balance

2 Sub-synchronous resonance is a phenomenon in which the resonant frequency of the turbine shaft coincides with electricity system frequency resulting in torsional stress on the turbine shaft

3 The national electricity system operating at normal operation modes or after the fault is cleared must maintain consistency and meet electricity system stability standards prescribed in Table 3 below:

Table 3

Electricity system stability standards

Transient stability Rotor angle not in excess of 120 degrees

Within 20 seconds after the fault is cleared, rotor angle fluctuationmust be stamped out

Small signal stability Damping ratio should not be less than 5%

Dynamic voltage stability Within five seconds after the fault is cleared, at least 75% of the

voltage must be restored

Trang 6

The electricity system must a reserve capacity of at least 5% in case a component is taken from the system (N-1).

Frequency stability The electricity system must meet frequency stability standards as

prescribed in Clause 1, Article 4 herein

Article 6 Voltage

1 Nominal voltage levels of a transmission grid are 500 kV, 220 kV

2 In normal operation conditions or in case of a single fault in a transmission grid, permissible voltage

at busbars on the transmission grid is prescribed in Table 4 below:

Table 4

Voltage at busbars on transmission grid

3 In case of a multi fault, serious fault, in an extreme emergency operation mode or electricity system restoration mode, permissible voltage fluctuation on the transmission grid is greater than ± 10 % to ±

20 % compared with nominal voltage

4 During the fault, voltage at the place where the fault occurs and surrounding areas may drop to 0 at phases with fault or increase over 110% of the nominal voltage at phases without fault until the fault is cleared

Article 7 Phase balance

In normal operation mode, negative sequence voltage components are not allowed to exceed 3% of nominal voltage on transmission grid

Article 8 Harmonics

1 Permissible maximum value of total harmonic distortion (based on percentage of nominal voltage) caused by high-level harmonic components to the voltage level 220 kV and 500 kv is not allowed to exceed 3%

2 Permissible maximum value of total demand distortion (based on percentage of nominal voltage) to the voltage level 220 kV and 500 kv is not allowed to exceed 3%

3 In normal operation mode, the transmission network operator shall ensure total harmonic distortion

on the transmission grid is within the range as prescribed in Clause 1, this Article

4 Customers using transmission grid shall ensure harmonics in the equipment connected to the transmission grid must not exceed the range as prescribed in Clause 2, this Article

5 If total harmonic distortion shows signs of violation of the range as prescribed in Clause 1 or 2, this Article, the customer using transmission grid or the transmission network operator has the right to order other relevant units to inspect harmonic values or hire an independent testing unit to do the job

If the result of inspection shows that the total harmonic distortion violates the range as prescribed in Clause 1 or 2, this Article, all the expenses for inspection, verification, damage and implementation of remedial measures shall be incurred by any entity that is found in breach of the regulation

Article 9 Flicker perceptibility

1 Permissible maximum flicker perceptibility in a transmission grid is stipulated in Table 5 below:

Table 5

Flicker perceptibility

Where: Plt95%, Pst95%: Threshold value of Plt, Pst respectively

2 The transmission network operator shall control flicker perceptibility on the transmission grid to ensure that the flicker perceptibility at connection point must not exceed the value prescribed in Table

5 in normal operation mode Customers using transmission grid shall ensure flicker perceptibility on the equipment connected to the transmission grid must not exceed the value as prescribed in Table 5

Trang 7

3 If flicker perceptibility shows signs of violation of the range as prescribed in Clause 1, this Article, the customer using transmission grid or the transmission network operator has the right to order other relevant units to inspect flicker perceptibility or hire an independent testing unit to do the job If the result of inspection shows that the flicker perceptibility violates the range as prescribed in Clause 1, this Article, all the expenses for inspection, verification, damage and implementation of remedial measures shall be incurred by any entity that is found in breach of the regulation.

Article 10 Voltage fluctuation

1 Voltage fluctuations at connection points on the transmission grid by fluctuating loads shall be not allowed to exceed 2.5% of nominal voltage and must be within permissible voltage values according toeach voltage level prescribed in Article 6 herein

2 If a voltage divider is operated manually, the voltage fluctuations at the points connected to loads are not allowed to exceed voltage value indicated by the transformer’s voltage divider

3 Permissible adjustable voltage level is 5% of nominal voltage to a maximum provided that such adjustment shall not cause damage to the equipment on electricity transmission system and

equipment belonging to customers using transmission grid

Article 11 Neutral grounding

1 Neutral grounding of a transmission grid is the connection of the grid direct to the ground

2 If the neutral grounding of some equipment in the transmission grid is in opposition to the provisionsprescribed in Clause 1, this Article, a written consent of the electricity system and market operator is required

Article 12 Short-circuit current and fault clearing time

1 Permissible maximum value of short-circuit current and fault clearing time by main protection on the electricity system are stipulated in Table 6 below:

circuit current (kA)

Maximum fault clearing time by main protection (ms)

Minimum time of withstandibility of

equipment (s) Effective up to

December 31, 2017 January 01, 2018 Effective as of

2 For 110 kV busbars of 500 kV or 220 kV transformers in the transmission grid, permissible

maximum short-circuit current is 40 kA/1s

3 Total value of unsaturated sub transient reactance of a generating set (Xd’’-%) and short-circuit reactance of a terminal transformer (Uk-%) according to the per-unit system pu is not allowed to be

less than 40%

If the aforesaid requirements cannot be met, the investor shall be responsible for installing further reactance so that total value of Xd’’, Uk and electrical reactance according to the per-unit system is not less than 40%

4 If value of short-circuit current at connection point of any electrical works to an electricity

transmission system is greater than permissible maximum short-circuit as stipulated in Table 6, the investor shall take measures to restrict the short-circuit current at connection points to a level lower or equal to permissible maximum short-circuit current as stipulated in Table 6

5 Main protection of an electrical equipment is a key element of protection which is installed and set tomake initial impacts, ensuring quickness, sensitivity, selectivity and reliability of impacts of the

protection system in case of a fault within the scope of protection

6 If maximum short-circuit current exceeds the values as stipulated in Table 6, the transmission network operator or customers using transmission grid shall be responsible for reporting to the

Electricity Regulatory Authority for instructions

7 The transmission network operator shall be responsible for informing the customer using

transmission grid about maximum value of short-circuit current at connection point for coordination during the investment and installation of equipment, ensuring that the switchgears are able to de-energize maximum short-circuit current at connection point at least for the next 10 years

Article 13 Earth fault factor

Earth fault factor of a transmission grid at all voltage levels is not allowed to exceed 1.4

Trang 8

Article 14 Reliability of transmission grid

1 Reliability of a transmission grid is determined by percentage of electrical production not supplied annually due to outage or reduction of power supply outside and inside the plan, and faults on the transmission grid causing loss of power to electricity customers

2 Electrical production not supplied is calculated as the product of the load power suspended or reduced and the corresponding time of suspension, reduction in case the loss of power lasts over one minute, except for following cases:

a) Outage or reduction of power supply due to lack of power from national electricity system

b) Outage or reduction of power supply due to force majeure events

3 Percentage of electrical production not supplied annually by a transmission grid is determined in following formula:

 1( )

Where:

- kkccd: Percentage of electrical productionnot supplied in a year by a transmission grid;

- Ti: Time of outage or reduction of power supply lasting over one minute at time I is determined as the

period from the time of outage or reduction to the time power supply is restored (hour);

- Pi: Average load power suspended, reduced at time i (kW);

- n: Number of times of outage or reduction of power supply in a year;

- Att: Total electrical production transmitted through a transmission gridin a year (kWh)

Article 15 Loss of power on transmission grid

1 Annual loss of power on a transmission grid is determined in following formula:

tt received - Att

delivered

Att receivedWhere:

- ΔA: Annual loss of power on a transmission grid;A: Annual loss of power on a transmission grid;

Chapter III

LOAD FORECASTING FOR NATIONAL ELECTRICITY SYSTEM

Article 16 General provisions on load forecasting for national electricity system

1 Load forecasting for the national electricity system is forecasts on demand for loads to be supplied

by the national electricity system except loads from independent power supplies and not connected to the national grid Load forecasting for the national electricity system is grounds for making annual electricity transmission system development plans, plans and methods for operation of electricity system, electricity market

2 Load forecasting for the national electricity system includes annual, monthly, weekly and daily forecasts on loads and electricity market transaction cycle

3 Responsibility for making forecasts

a) The electricity system and market operator shall make forecasts on loads for the national electricity system, electricity systems in the Northern, Central and Southern Vietnam and connection points.b) Electricity distribution units, electricity retailers and electricity customers shall provide load forecasts

to the electricity system and market operator including forecasts on demand for loads of the entire unit and individual 110 kV transformers

c) Electricity wholesalers shall provide forecasts on exportation and importation of electricity to the electricity system and market operator including forecasts on general demand and demands of connection points serving exportation and importation of electricity

Trang 9

4 Regarding forecasts on demand of connection points and resolution of load forecasting cycle and depending on each stage of development and market demand, the Electricity Regulatory Authority shall provide instructions on implementation of this regulation.

Article 17 Annual load forecasting

1 Annual load forecasting made for next year (year N+1) and the year thereafter (year N+2)

2 Figures serving annual load forecasting include:

a) Monthly load forecasts concerning electrical energy, maximum capacity, typical daily diagrams in a 30-minute cycle for 104 weeks provided by electricity distribution units, electricity retailers and

electricity customers;

b) Monthly export, import forecasts concerning electrical energy, maximum capacity, typical daily diagrams in a 30-minute cycle for 104 weeks provided by electricity wholesalers

3 Elements taken into account for annual load forecasting:

a) Economic growth (GDP) for the next two years officially published by competent agencies;

b) Annual load forecasts and load factor under approved electricity development master plan;

c) Statistical figures on capacity, electrical energy consumed, exported and imported at least for at the last five years by electricity distribution units, electricity retailers, electricity wholesalers and electricity customers;

d) Solutions and targets of the plan for energy saving and demand management;

dd) Other necessary information

4 Results of annual load forecasting for national electricity system include: Maximum capacity, electrical energy, typical daily diagrams in a 30-minute cycle for 104 weeks of national, regional electricity systems and connection points

5 Implementation

a) Before August 01 annually, electricity distribution units, electricity retailers, electricity wholesalers and electricity customers shall provide results of annual load forecasting to the electricity system and market operator as prescribed in Clause 2, this Article

If the figures provided by electricity distribution units, electricity retailers, electricity wholesalers and electricity customers are inaccurate or inadequate according to the prescribed time limit, the electricity system and market operator shall rely on last year’s figures to make forecasts on loads for the nationalelectricity system

b) Before September 01 annually, based on the figures provided by relevant units, the electricity system and market operator shall be responsible for completing and publishing results of annual load forecasting on its website as prescribed in Clause 4, this Article

Article 18 Monthly load forecasting

1 Monthly load forecasting made for next month

2 Figures serving monthly load forecasting include:

a) Weekly load forecasts concerning electrical energy, maximum capacity, typical daily diagrams in a 30-minute cycle every week provided by electricity distribution units, electrical retailers and electricity customers;

b) Weekly export, import forecasts concerning electrical energy, maximum capacity, typical daily diagrams in a 30-minute cycle every week provided by electricity wholesalers

3 Elements taken into account for monthly load forecasting:

a) Results of monthly load forecasting in the published annual load forecasting;

b) Statistical figures on capacity, consumed, exported and imported electrical energy, maximum loads

in daytime and nighttime for the month year-on-year and the last three months provided by electricity distribution units, electricity retailers, electricity wholesalers and electricity customers;

c) Events that may cause major changes to demand for loads and other necessary information

4 Results of monthly load forecasting for national electricity system include: Maximum capacity, electrical energy, typical daily diagrams for each week with a 30-minute cycle of national, regional electricity systems and connection points

5 Implementation

Trang 10

a) Before 20 every month, electricity distribution units, electricity retailers, electricity wholesalers and electricity customers shall provide monthly load forecasts to the electricity system and market operator

as prescribed in Clause 2, this Article

If the figures provided by electricity distribution units, electricity retailers, electricity wholesalers and electricity customers are inaccurate or inadequate according to the prescribed time limit, the electricity system and market operator shall rely on last month’s figures or results of annual load forecasting to make forecasts on loads for national electricity system

b) Before the last seven days every month, based on the figures provided by relevant units, the electricity system and market operator shall be responsible for completing and publishing results of month loading forecasting on its website as prescribed in Clause 4, this Article

Article 19 Weekly load forecasting

1 Weekly load forecasting made for the next two weeks

2 The figures serving weekly load forecasting include figures on capacity, electrical energy forecasts

in a 30-minute cycle every day of the next two weeks provided by electricity distribution units,

electricity retailers and electricity customers and 110 kV transformers

3 Elements taken into account for weekly load forecasting:

a) Results of weekly load forecasting in the published monthly load forecasting;

b) Statistical figures on capacity, consumed electrical energy, maximum loads in daytime and

nighttime for the last four months provided by electricity distribution units, electricity retailers, electricitywholesalers and electricity customers;

c) Daily weather forecasts for the next two weeks, public holidays, Tet holidays and events that may cause major changes to demand for loads

4 Results of weekly load forecasting for national electricity system include: Capacity, electrical energy

in a 30-minute cycle every day of the next two weeks of national, regional electricity systems and connection points

5 Implementation

a) Before 10:00 every Tuesday, electricity distribution units, electricity retailers, electricity wholesalers and electricity customers shall provide weekly load forecasts to the electricity system and market operator as prescribed in Clause 2, this Article

If the figures provided by electricity distribution units, electricity retailers, electricity wholesalers and electricity customers are inaccurate or inadequate according to the prescribed time limit, the electricity system and market operator shall rely on last week’s figures or results of monthly load forecasting to make forecasts on loads for national electricity system

b) Before 15:00 every Thursday, based on the figures provided by relevant units, the electricity systemand market operator shall be responsible for completing and publishing results of weekly load

forecasting on its website as prescribed in Clause 4, this Article

Article 20 Daily load forecasting

1 Daily load forecasting made for the next two days

2 Elements taken into account for daily load forecasting:

a) Results of daily load forecasting in the published monthly load forecasting;

b) Figures on capacity, electrical energy of the electricity system of the last seven days or the holidays,Tet holidays of last year if the figures fall within public holidays, Tet holidays;

c) Weather forecasts of the next two days and other necessary information

3 Results of daily load forecasting for national electricity system include: Capacity, electrical energy in

a 30-minute cycle of national, regional electricity systems and connection points

4 Before 10:00 every day, the electricity system and market operator shall be responsible for

completing and publishing results of daily load forecasting as prescribed in Clause 3, this Article

Article 21 Load forecasting in a electricity market transaction cycle

1 Load forecasting made for next transaction cycle and eight cycles thereafter

2 Elements taken into account for load forecasting in a transaction cycle:

a) Results of load forecasting from the published daily load forecasting and the electricity market transaction cycle previously published;

b) Figures on capacity, electrical energy of the same period of last week;

Trang 11

c) Weather forecasts;

dd) Other necessary information

3 Results of load forecasting in a electricity market transaction cycle include:

a) Capacity and production of the national electricity system and regional electricity systems in a minute cycle of the next transaction cycle and eight cycles thereafter;

b) Capacity and production at each point connecting the transmission grid and distribution grid in a minute cycle of the next transaction cycle and eight cycles thereafter

30-4 At least 15 minutes before the next transaction cycle, the electricity system and market operator shall be responsible for completing and publishing results of load forecasting of a transaction cycle as prescribed in Clause 3, this Article

Chapter IV

TRANSMISSION GRID DEVELOPMENT PLAN

Article 22 General principle

1 Annually, the transmission network operator shall be responsible for making a transmission grid development plan for next year (year N+1) with account taken of the year thereafter (year N+2)

2 Annual transmission grid development plans shall be made based on:

a) Published annual load forecasting plans;

b) Approved national electricity development plans, provincial electricity development planning and signed connection agreements;

c) Requirements for operation of the electricity system prescribed in Chapter II and technical

requirements of connection points prescribed in Chapter V herein;

d) Demand for loads and requirements for electricity system and market operation; ensuring the national electricity transmission system operates in a safe, reliable and stable manner

3 The electricity system and market operator shall be responsible for cooperating with the

transmission network operator during the process of transmission grid development plan formulation toensure investment, connection and operation of the power generation and electrical grid works meet the requirements prescribed in Clause 2, this Article

Article 23 Content of transmission grid development plan

The transmission grid development plan includes following subject matters:

1 Assessment of performance of the transmission grid to the end of June 30 of the current year

2 Load forecasts in each point of delivery between the transmission grid and distribution grid for the next year with account taken of the year thereafter

3 Assessment of implementation of investment and estimated implementation of investment in the list

of transmission grids according to the approved transmission grid development plan until the end of December 31 of current year

4 List of power generation projects connecting to the transmission grid for next year with account taken of the year thereafter accompanied by planned connection points, connection agreements for these power generation projects

5 List of information system works, SCADA system, RTU/Gateway, measurement system, data collection system serving electricity market and electricity system operation and dispatching

6 Results of calculation of reset modes of the electricity transmission system for each month next year, dry and rainy seasons of the year thereafter including results of calculation of methods and assessment of ability of the transmission grid to meet N-1 criterion

7 Results of calculation of short-circuit current at 500 kV, 220 kV, 110 kV busbars on the transmissiongrid in which the positions where maximum value of short-circuit current exceed 90% of permissible maximum value as prescribed in Article 12 herein must be determined

8 Results of calculation and analysis of stability of the electricity transmission system

9 Results of calculation of reactive power compensation on the transmission grid

10 Determination of obligations and constraints on the transmission grid that may have effect on safe and stable operation of the electricity transmission system including effects on requirements for stability of the electricity system as prescribed in Article 5 herein

11 Proposals for norms of reliability and loss of power of the transmission grid for the next year according to Article 14 and Article 15 herein

Trang 12

12 Analysis of ability to meet operational requirements of the electricity system prescribed in Chapter

II and technical requirements of connection points prescribed in Chapter V herein, and proposals for solutions to meet the prescribed requirements

13 Analysis and selection of methods of investment in the transmission grid to ensure transmission of all the power from power plants meeting demand for loads, technical requirements and lowest costs

14 Lists and schedules of construction of transmission grid items by month of next year and by quarter of the year thereafter Fund plan for each project

15 Proposals (if any)

Article 24 Responsibility for supplying information serving formulation of transmission grid development plan

1 Generating units shall be responsible for supplying following information:

a) Lists of new power plants planned to be connected to the transmission grid in the next year with account taken of two years thereafter, progress of investment and connection, and expected date of operation of such power plants

b) Main parameters of power plants shall be connected to the electricity transmission system and information about connection points are stipulated in Annex 1B enclosed herewith;

c) Changes related to connection to existing power plants in the next year with account taken of two years thereafter

2 Electricity distribution units, electricity retailers and electricity customers shall be responsible for providing following information:

a) Lists of connection points in the next year with account taken of the year thereafter; lists of

transmission grid projects to be invested and constructed;

b) Planned progress of energizing new connection points;

c) Maximum load capacity at new connection points and information about connection are specified in Annex 1C enclosed herewith;

d) Expected proposals for changes to existing connection points in the next year with account taken of the year thereafter

3 The electricity system and market operator shall be responsible for providing following information:a) Results of annual load forecasting as prescribed in Article 17 herein;

b) Expected demand for ancillary services in next year with account taken of the year thereafter;c) Plan for mobilization of power supplies in the next year with account taken of the year thereafter

4 Electricity wholesalers shall be responsible for supplying following information:

a) Exported, imported capacity and electrical energy;

b) Progress of putting new power generation projects into operation in the next year with account take

of two years thereafter

Article 25 Procedures for formulation, approval and public announcement of transmission grid development plans

1 Before August 01 annually, the transmission network operator shall be responsible for delivering requests for supply of information and time limit of supply of information to the electricity market and system operator, electricity wholesalers and customers using transmission grid (including customers who need to establish new connections)

2 Before September 01 annually, the electricity system and market operator, electricity wholesalers and customers using transmission grid shall be responsible for providing sufficient information as prescribed in Article 24 herein to the transmission network operator

3 Before October 15 annually, the transmission network operator shall be responsible for completing draft plans for transmission grid development in the next year with account taken of the year

thereafter, and submitting requests to the electricity system and market operator for suggestions on assessment of impacts of expected transmission grid projects on safety, stability and reliability of the electricity transmission system

4 Before November 01 annually, the transmission network operator shall be responsible for

completing the plan for transmission grid development in the next year with account taken of the year thereafter and reporting to Vietnam Electricity

Trang 13

5 Before November 15 annually, the transmission network operator shall be responsible for submittingthe plan for transmission grid development in the next year with account taken of the year thereafter approved by Vietnam Electricity to Electricity Regulatory Authority.

6 Before December 15 annually, the Electricity Regulatory Authority shall conduct assessment, grant approval and publish on its website the plan for transmission grid development in the next year with account taken of the year thereafter

7 Within 15 working days since the plan for transmission grid development is approved by Electricity Regulatory Authority, the transmission network operator shall be responsible for publishing the plan onits website

Chapter V

CONNECTION TO TRANSMISSION GRID

Section 1 GENERAL PRINCIPLE

Article 26 Connection point

1 Connection points are the points connecting equipment, electrical grids and power plants of

customers using transmission grid with the electricity transmission system

2 Depending on structure of the electrical grids and connection lines, connection points shall be determined as follows:

a) Regarding overhead lines, connection points are the end points of the suspension string for

outgoing feeders connected to the disconnect switches of the substation or distribution area of the power plant

b) Regarding underground lines, connection points are the cosse of disconnector insulators on the outgoing side of the substation or distribution area of the power plant

3 Any connection point which is in opposition to provisions prescribed in Clause 2, this Article shall beagreed by the two parties

4 Connection points must be detailed in relevant drawings, diagrams and explanations in the

connection agreement or power purchase agreement (PPA)

Article 27 Borders of assets and operation management

1 Borders of assets between the transmission network operator and customers using transmission grid are connection points

2 Assets belonging to each party at connection point must be detailed and accompanied by relevant drawings and diagrams or power purchase agreement (PPA)

3 Each party shall be responsible for investing, constructing and managing assets of its own in accordance with standards and laws unless otherwise agreed

Article 28 General requirements

1 The transmission network operator shall be responsible for developing transmission grids according

to approved electricity development planning and investment plan, ensuring transmission grid facilities meet requirements of the electricity system as prescribed in Chapter II herein and technical

requirements of connection points prescribed in this Chapter

2 Connecting electrical equipment, electrical grids and power plants of customers using transmission grid with the transmission grid must be consistent with the electricity development planning approved

by competent state agencies, ensuring transmission grid facilities meet requirements of the electricity system as prescribed in Chapter II herein and technical requirements of connection points prescribed

in this Chapter

3 The transmission network operator shall be responsible for making notification to the electricity customer of any connection proposed by such customer which is in opposition to the approved electricity development planning Any customer who needs to get connected shall be responsible for submitting an application for grant of approval for adjustments and supplements to the planning according to the regulation on contents and procedures for formulation, assessment, approval and adjustment of electricity development planning issued by the Ministry of Industry and Trade before taking next steps

4 The transmission network operator and customer that request connection must execute a

connection agreement according to the form prescribed herein including following information:

a) Position of connection point;

b) Technical information related to connection point;

c) Progress of connection;

Trang 14

d) Responsibility for investment and operation management;

dd) Terms and conditions of the connection agreement

5 The transmission network operator is entitled to reject proposals for connection in following cases:a) Customer’s electrical equipment, grids fail to meet operational and technical requirements

prescribed herein and other relevant technical regulations;

b) Proposals for connection are inconsistent with the approved electricity development planning

6 The transmission network operator is entitled to disconnect the customer from its transmission grid

if such customer violates technical and operational requirements as prescribed herein or violates the regulation on safety and operation of its assets The procedures for settlement of dispute prescribed inChapter IX herein shall apply if the two parties fail to reach an agreement on the disconnection

7 If any change or upgrading of equipment or change of connection diagram by the customer using transmission grid within its scope of management affects safe operation of the electricity transmission system or electrical equipment belonging to the transmission network operator at connection point, such customer must make a written notification to the transmission network operator and the dispatch level before implementation

8 Any change related to connection point during the investment and operation must be updated in the dossier of connection point and signed connection agreement

9 The customer using transmission grid shall be responsible for storing figures concerning working modes, operation and maintenance and incidents on the components within its management for a period of five years As requested by the transmission network operator, the customer shall provide adequate information related to the incident on the components within its management For any connection serving purchase and sale of electricity between power plants overseas or outside the territory of Vietnam and the national electricity system, the technical and operational requirements of the equipment connecting to the transmission grid shall be in order of priority as follows:

a) Be conformable with regulations, international agreements and commitments of which Vietnam is a signatory;

b) An agreement between relevant parties must be reached to meet all the technical requirements andtechnical regulations on each country’s electricity system and ensure that the operation of the

electrical grids is safe, reliable and stable

Section 2 GENERAL TECHNICAL REQUIREMENTS FOR EQUIPMENT CONNECTING TO

TRANSMISSION GRID

Article 29 Requirements for connecting equipment

1 The diagram of main connection point shall represent all the electrical equipment from voltage to super high-voltage levels and connectivity between the electrical grid of the customer using transmission grid and the transmission grid The electrical equipment must be described in symbols, standard signs and numbered by the dispatch level according to the operating procedure of the national electricity system issued by the Ministry of Industry and Trade

middle-2 Circuit breakers directly related to connection points accompanied by protection, measurement and control systems must be capable of de-energizing maximum short-circuit current at connection point, meeting the electrical grid and power generation development diagram under the approved electricity development planning at least for the next 10 years

3 Equipment connecting directly to the transmission grid shall be fully capable of withstanding

possible maximum short-circuit current at connection points according to the calculations by the transmission network operator, meeting the electrical grid and power generation development diagramunder the approved electricity development planning at least for the next 10 years

Article 30 Requirements for protective relay system

1 The transmission network operator and the customer using transmission grid shall be responsible for designing, installing, setting and testing the protective relay system within their own management

to meet requirements for quickness, sensitivity, selectivity and reliability in case of fault clearance to ensure safe and reliable operation of the electricity system

2 Coordination in installing protective relay equipment at connection points must be agreed between the dispatch level, the transmission network operator and the customer using transmission grid The transmission network operator or the customer using transmission grid shall not be allowed to change its own protective relay equipment and installation parameters without consent of the dispatch level

3 The dispatch level shall be responsible for issuing relay setting notes within scope of transmission grid belonging to the transmission network operator and granting approval for the relay settings of the protective relay equipment belonging to the customer using transmission grid

Trang 15

4 Maximum time limit for fault clearance through main protection on the components of the electricity system belonging to the customer using transmission grid is not allowed to exceed the values

prescribed in Article 12 herein

5 If the protection equipment belonging to the customer is required to connect to the transmission network operator’s protection equipment, such equipment must meet requirements of the transmissionnetwork operator for connection and be approved by the dispatch level

6 If the electrical grid belonging to the customer using transmission grid has a problem, the protective relay equipment in the electrical grid may send commands to disconnect circuit breakers on the transmission grid with consent of the transmission network operator and the dispatch level with regard

to these circuit breakers

7 Reliability of impacts of the protective relay system shall not be less than 99%

8 In addition to requirements prescribed from Clause 1 to Clause 7, this Article, the protective relay system belonging to the customer using transmission grid and the transmission network operator mustmeet following requirements:

a) Power plants must be equipped with synchronization system;

b) Power plants must be equipped with a GPS

c) Power plants with total installed capacity from 300 MW and on must be equipped with a phasor measurement unit (PMU) and a GPS Power plants with total installed capacity less than 300 MW, equipment of PMU must follow calculations and requirements of the electricity system and market operator;

d) The transmission network operator and customer using transmission grid other than generating units shall be responsible for installing a GPS, PMU according to requirements of the dispatch level, ensuring compatible, reliable and stable connection to the GPS and PMU located at the electricity system and market operator The dispatch level shall be responsible for integrating the GPS and PMU

of the transmission network operator and customer using transmission grid to the system located at the dispatch level;

dd) During operation, in case of upgrading or changing the GPS and PMU, the transmission network operator and customer using transmission grid shall be responsible for making notifications and entering negotiations with the dispatch level before implementation;

e) The transmission lines from 220 kV and over connecting to generating sets or distribution area of the power plant must be equipped with two independent communication channels serving

transmission of signals of protective relay between two ends of lines (transmission time no more than

20 ms);

g) Electricity customers shall be responsible for investing and installing low-frequency relays within scope of automatic load shedding management according to calculations and requirements of the dispatch level

9 Scope, positioning and technical requirements of protective relay equipment for generating sets, transformers, busbars and lines connecting to the transmission grid shall be conformable with the regulation on technical requirements of protective relay and automation system in the power plant and transformer issued by Electricity Regulatory Authority

Article 31 Requirements for information system

1 The customer using transmission grid shall be responsible for investing, installing and managing theinformation system and ensuring it is connected to the information system belonging to the

transmission network operator and the dispatch level Means of communications serving dispatching and operation include direct communication channel, telephone and facsimile

2 The information system belonging to the customer using electrical grid must be compatible with that

of the transmission network operator and the dispatch level

The customer may negotiate an agreement for use of information system of the transmission network operator or other suppliers to connect to the information system of the dispatch level to ensure

continuous and reliable communication serving electricity system and market operation

3 The transmission network operator shall be responsible for investing and managing the information system of its own to serve electricity system and market operation; cooperating with the dispatch level

in establishing a information transmission line to the dispatch level

4 The dispatch level shall be responsible for providing requirements for information data, data

transmission and necessary information interface serving electricity system and market operation to the transmission network operator and customer using transmission grid

Trang 16

5 The dispatch level and the transmission network operator shall be responsible for cooperating with the customer using transmission grid in testing, inspecting and connecting the customer’s information system to the existing information system managed by the units.

Article 32 Requirements for connection of SCADA system

1 Transformers from 220 kV and on, power plants with installed capacity greater than 30 MW and power plants connected to the transmission grid which is not yet connected to the Control Center must

be equipped with a Gateway or RTU with two ports connecting directly, simultaneously and

independently to the SCADA system of the dispatch level

2 Power plants with installed capacity greater than 30 MW and power plants connecting to the transmission grid which is connected to the Control Center must be equipped with a Gateway or RTU with one port connecting directly to the SCADA system of the dispatch level and two ports connecting directly to the Control Center Transformers from 220 kV and on which is connected to the Control Center must be equipped with a Gateway or RTU with two ports connecting directly to the Control Center

3 If a power plant, transformer has multiple dispatching levels with control authority, such dispatching levels shall be responsible for sharing information to serve electricity system operation coordination

4 The transmission network operator and customer using transmission grid shall be responsible for investing, installing and operating the RTU/Gateway within management or hiring the data

transmission lines from service providers to ensure continuous and reliable connection to the SCADA system of the dispatch level and the Control Center

5 Technical characteristics of RTU/Gateway belonging to the transmission network operator and customer using transmission grid must be compatible with the SCADA system of the dispatch level and the Control Center (if any)

6 The dispatch level shall be responsible for integrating data according to the list of data agreed with the transmission network operator and customer using transmission grid to its SCADA system The transmission network operator and customer using transmission grid shall be responsible for

cooperating with the dispatch level in configuring and setting database on its system to ensure

compatibility with the SCADA system of the dispatch level and control system of the Control Center (if any)

7 If the SCADA system of the dispatch level has had some technological changes approved by competent agencies after the connection agreement is signed resulting in changes or upgrading of thecontrol system, RTU/Gateway of the transmission network operator and customer using transmission grid, the dispatch level, the transmission network operator and customer shall be responsible for making necessary adjustments to ensure that the equipment belonging to the transmission network operator and customer using transmission grid is compatible with changes of the SCADA system The transmission network operator and customer using transmission grid shall be responsible for investing and upgrading the control system and RTU/Gateway to ensure compatibility with the SCADA system

of the dispatch level

8 During operation, in case of upgrading or expansion of the control system, RTU/Gateway, the transmission network operator and customer using transmission grid shall be responsible for entering negotiations with the dispatch level before the upgrading or expansion is carried out

9 Requirements on lists of data, technical requirements of RTU/Gateway are detailed in the regulation

on technical requirements and SCADA system operation management issued by the Electricity Regulatory Authority

Article 33 Neutral grounding in transformers

Neutral grounding in transformers must ensure value of earth fault factor does not exceed the value prescribed in Article 13 herein

Article 34 Power factor

1 In normal operation mode, electricity distribution units and electricity customers must maintain a power factor (cosS) at key measuring positions from 0.9 and over in case of receiving reactive power and from 0.98 and on in case of transmitting reactive power

2 The customer using transmission grid must provide parameters of reactive power compensation equipment in its electrical grid (if any) to the transmission network operator and the dispatch level, including:

a) Rated reactive power and adjustment range;

b) Principle of reactive power adjustment

Article 35 Load fluctuation

Trang 17

The speed of changing power consumption by electricity customers in a minute is not allowed to exceed 10% of power consumption in normal operation mode unless the electricity customer adjusts demand as requested or under an agreement with the electricity system and market operator.

Article 36 Automatic frequency load shedding system

1 The customer using transmission grid shall be responsible for cooperating with relevant units in unifying the installation of the automatic frequency load shedding system and ensuring that it operates

in accordance with calculations and requirements of the dispatch level

2 The system must be designed to meet following requirements:

a) Reliability not less than 99%;

b) Any unsuccessful load shedding must not affect operation of the entire electricity system

c) Load shedding procedures and amount of shed power must be in compliance with level of

distribution by the dispatch level and must not be changed in any case without consent of the dispatch level

3 Low-frequency relays must be installed and put into operation at the request of the dispatch level

4 Load recovery procedures after frequency is restored to normal operation mode must be in

compliance with dispatch instruction of the dispatch level

Article 37 Requirements of Control Center

1 General technical requirements

a) Monitoring, control and information systems installed in the Control Center must be equipped to ensure safe and reliable operation of power plants, substations;

b) The Control Center’s monitoring and control systems must be technically compatible and ensure stable, reliable and continuous connection of power plants, substations and switchgears to SCADA system of the dispatch level;

c) The Control Center must have a backup power supply to ensure normal operation in case of loss of power from the national electricity system

2 Requests for connection from Control Center

- There are two independent data transmission lines to be connected to the information system of the dispatch level If multiple dispatching levels with control authority exist, an information sharing method must be agreed by all the dispatching levels;

- There are two data transmission lines to be connected to the control and information system of power plants, substations remotely controlled by the Control Center;

- Means of communications serving dispatching and operation include direct communication channel, telephone, facsimile and computer network

b) Requirements for connection to SCADA system

- There are two ports connecting directly, simultaneously and independently to SCADA system of the dispatch level If multiple dispatching levels with control authority exist, a common information sharing method must be agreed by all the dispatching levels;

- There are ports connecting to RTU/Gateway, control system of power plants, substations and switchgears on the electrical grid remotely controlled by the Control Center

c) The Control Center must install a monitoring screen connected to the surveillance camera at power plants, substations and switchgears on the electrical grid

3 Power plants, substations or switchgears on the electrical grid remotely controlled by the Control Center must be equipped with a control and surveillance camera system to establish stable, reliable and continuous connection to the Control Center meeting requirements prescribed in Clause 1 and Clause 2, this Article

Section 3 TECHNICAL REQUIREMENTS FOR CONNECTION TO HYDRO POWER PLANTS AND THERMO POWER PLANTS

Article 38 Requirements for generating sets’ power control

1 Power plants with installed capacity over 30 MW must be equipped with facilities, control systems , AGC system to ensure stable and reliable connection to a generating set’s power control system of theelectricity system and market operator serving remote control of the generating set’s power according

to dispatch instruction of the electricity system and market operator Particular technical requirements for connection of the generating set's AGC system to SCADA/EMS of the electricity system and market operator are prescribed in the regulation on technical and operation requirements of SCADA system issued by the Electricity Regulatory Authority

Trang 18

2 The generating set of a power plant must be capable of generating rated active power in a power factor from 0.85 (corresponding to reactive power generation mode) to 0.9 (corresponding to reactive power receiving mode) in accordance with characteristics of the generating set’s reactive power.

3 The generating set must be capable of adjusting primary and secondary frequency as prescribed in the national load dispatch process issued by the Ministry of Industry and Trade and controlling voltage

in the electricity system through continuous adjustment of active power and reactive power of the generating set

4 In normal operation mode, voltage changes at connection point to transmission grid within

permissible scope prescribed in Article 6 herein must not affect amount of active power generated andreactive power generation capability of the generating set

5 The generating set of a power plant must be capable of generating rated active power continuously within frequency band 49 Hz – 51 Hz In a frequency band from 46 Hz to under 49 Hz and over 51 Hz, level of power reduction must not exceed value according to frequency reduction ratio of the electricity system Minimum time to maintain operation of power plants with installed capacity over 30 MW or power plants connected to the transmission grid in proportion to frequency bands of the electricity system is specified in Table 7 below:

Table 7

Minimum time to maintain power generation in proportion to frequency band of the electricity system

Hydro power plants Thermo power plants

From 49 Hz to 51 Hz Continuous generation Continuous generation

6 Generating sets of a power plant must be capable of withstanding level of voltage symmetry loss in the electricity system as prescribed in Article7 herein

7 Generating sets of a power plant must be capable of working continuously in following modes:a) Unbalanced three-phase loads from 10% and under;

b) Indicator of response of the exciter in a synchronous generating set greater than 0.5%;

c) Negative sequence current is 5% less than rated current

Article 39 Excitation system of a generating set

1 The excitation system of a generating must ensure that the generating set can operate in a power factor range prescribed in Clause 2, Article 38 herein The excitation system must ensure the

generating set operates at a rated apparent power (MVA) within the range ± 5 % of rated voltage at the generating set’s terminal posts

2 The generating set must be equipped with AVR which operates continuously and is capable of maintaining deviation of terminal voltage within ± 0,5 % of rated voltage in the entire permissible working band of the generating set

3 AVR must be capable of making up for voltage drop on terminal transformers and ensure stable distribution of reactive power among generating sets connected to a common busbar

4 AVR must be installed with following limits:

a) Minimum excitation current;

b) Maximum excitation current

5 When terminal voltage of a generating set is in a range from 80 to 120% of rated voltage and the system frequency is in a range from 47.5 to 52Hz in a maximum of 0.1 second, the excitation system

of the generating set must be capable of increasing the current and excitation voltage to following values:

a) For a generating set of a hydro power plant: 1.8 rated value;

a) For a generating set of a thermo power plant: 2.0 rated value;

Trang 19

6 Change of excitation voltage is not allowed to be less than 2.0 rated excitation voltage/second when

a generating set carries the rated load

7 A generating set with a capacity over 30 MW must be equipped with a PSS capable of dampening 0.1 Hz – 5 Hz frequency fluctuation contributing to improvement of the electrical system Generating units must install and set parameters of the PSS according to calculations by the electricity system and market operator to ensure dampening ratio of the PSS is not smaller than 5% For generating setsequipped with PSS, the generating units shall be responsible for putting the PSS into operation at the request of the dispatch level

it is not required

3 The governor must be capable of setting value of static coefficient less than or equal to 5% Set value of static coefficient shall be determined by the electricity system and market operator

4 Apart from add-on generating sets of combined cycle power plants, minimum value of a dead-band

in the governor must range within ± 0,05 Hz Value of dead-band of the governor of each generating set shall be calculated and determined by the electricity system and market operator during

connection and operation

5 The governor control system must be installed with following limits and anti-over speed control as follows:

a) For steam turbines: From 104% to 112% of rated speed;

b) For gas and thermo power turbines: From 104% to 130% of rated speed;

c) If the generating set in the grid area is temporarily disconnected from the national electricity

transmission system but keeps supplying power to customers, the governor system of the generating set must maintain frequency stability for such grid area

Article 41 Black start

1 In some important positions in electricity transmission system, some power plants must be capable

of black starting Requirements for installation of black start capability must be stated in the connectionagreement

2 The electricity system and market operator shall be responsible for determining important positions

in the national electricity system for the construction of power plants capable of black start and

cooperate with the transmission network operator, generating units in determining specific

requirements for black start of individual power plants

Section 4 TECHNICAL REQUIREMENTS OF WIND AND SOLAR POWER PLANTS

Article 42 Technical requirements of wind and solar power plants

1 Wind and solar power plants must be capable of maintaining generation of active power within frequency band from 49 to 51 Hz in following modes:

a) Free generation mode

b) Generating capacity control mode

Wind and solar power plants must be capable of adjusting generation of active power as commanded

by the dispatch level in accordance with change of primary sources no more than 30 seconds with tolerance within ± 01 % of rated power, specifically as follows:

- Generation of power in accordance with dispatch instruction in case primary sources are equal or greater than forecast value;

- Generation of possible maximum power in case primary sources are lower than forecast value

2 In normal operation mode, wind and solar power plants must be capable of generating active power and ensure no negative effect is caused by change of voltage at connection point within permissible band prescribed in Article 6 herein

3 Wind and solar power plants must be capable of maintaining generation of power for a minimum period of time in proportion to frequency band prescribed in Table 8 below:

Table 8

Minimum time to maintain power generation in proportion to frequency band of electricity system

Trang 20

Frequency band Minimum time

20 n m

f x

P P

Where:

- ΔA: Annual loss of power on a transmission grid;P: Level of active power reduction (MW);

- Pm: Active power in proportion tothe point of time prior to power reduction (MW);

- fn: Electricity system frequency prior to power reduction (Hz)

5 Wind and solar power plants must be capable of adjusting reactive power and voltage as follows:a) If a power plant generates an active power greater or equal to 20% of rated active power and voltage in normal operation band, such power plant must be capable of adjusting reactive power continuously in a power factor from 0.85 (corresponding to reactive power generation mode) to 0.95 (corresponding to reactive power receiving mode) at connection point in proportion to rate power;b) If a power plant generates an active power less than 20% of rated power, such power plant may reduce ability to receive or generate reactive power in accordance with characteristics of the

generating set;

c) If voltage at connection point is within ± 10 % of rated voltage, the power plant must be capable of adjusting voltage at connection point with deviation no more than ± 0,5 % of rated voltage in

permissible working band of the generating set;

d) If voltage at connection point varies beyond ± 10 % of rated voltage, the power plant must be capable of adjusting reactive power to the minimum of 2% compared with rated reactive power in proportion to each per cent of voltage varying at connection point

6 Wind and solar power plants at every time of connection to the grid must be capable of maintaining generation of power in proportion to voltage range as follows:

a) Voltage less than 0.3 pu, minimum time is 0.15 seconds;

b) Voltage from 0.3 pu to under 0.9 pu, minimum time is calculated in following formula:

Tmin = 4 x U – 0.6Where:

- Tmin (second): Minimum time to maintain power generation:

- U (pu): Actual voltage at connection point (pu)

c) Voltage from 0.9 pu to under 1.1 pu, wind and solar power plants must maintain continuous

negative phase sequence components up to 03% of rated voltage for voltage from 220 kV and on

8 Total harmonic distortion caused by wind, solar power plants at connection point is not allowed to exceed 03%

Trang 21

9 Flicker perceptibility caused by wind and solar power plants at connection point is not allowed to exceed the value prescribed in Article 9 herein.

Section 5 PROCEDURES FOR CONNECTION AGREEMENT

3 After receiving the application, the transmission network operator shall:

a) Review requirements concerning the equipment expected for connection;

b) Preside over assessment of effects of connection of equipment, electrical grid, power plants of customers on transmission grid including following subject matters:

- Calculate reset modes of regional electrical grids under requests for connection in the next 10 years including calculation of all alternatives and assess ability of regional transmission grid to meet N-1 criterion;

- Calculate and assess short-circuit current at connection points to the transmission grid;

- Determine obligations and constraints from new connections that may have effects on safe and stable operation of electricity transmission system;

- Assess ability to meet requirements for operation of the electricity system prescribed in Chapter II herein and technical requirements of connection points prescribed in this Chapter;

c) Prepare a draft connection agreement according to the form in Annex 2 enclosed herewith and submit it to customers who need to get connected and the dispatch level;

d) After 15 working days at the latest since receipt of the application for connection from customers, the transmission network operator shall submit a written request to the dispatching with control authority and relevant units for official suggestions as follows:

- Assessment of impacts of connection on the electricity transmission system;

- Technical requirements of equipment at connection points, requirements of operation and

dispatching of generating sets, requirements of frequency load shedding system of electricity

customers to ensure compliance with technical and operation requirements prescribed in Chapter II and Chapter V herein;

- Draft connection agreement in accordance with provisions prescribed in annexes enclosed herewith

4 The dispatch level shall be responsible for cooperating with the transmission network operator in assessing effects of connection on the electricity transmission system as prescribed in Point b, Clause

3, this Article

5 Customers who need to get connected shall be responsible for providing other necessary

information to the transmission network operator and the dispatch level for determination of technical characteristics and other technical requirements to ensure safe, reliable and stable operation of the electricity transmission system

6 Within 20 working days since receipt of request from the transmission network operator, the

dispatch level and relevant units shall be responsible for delivering suggestions in writing on issues prescribed in Point d, Clause 3 and Clause 4, this Article to the transmission network operator

7 Upon receipt of suggestions from the dispatch level and other relevant units, the transmission network operator shall be responsible for completing the draft connection agreement

8 The connection agreement shall be made into four copies Each party keeps two copies The transmission network operator shall submit a copy to the dispatch level, relevant units for cooperation during construction, energizing and official operation

9 Time for review of the application, negotiation on relevant issues and execution of the connection agreement is prescribed in Article 44 herein

Trang 22

10 A customer who needs to get connected to the electrical grid or equipment of the customer using transmission grid shall be responsible for making direct negotiation with this customer Before

reaching an agreement for connection plan with the customer who needs to get connected, the customer using transmission grid shall be responsible for cooperating with the transmission network operator and the dispatch level in ensuring that the equipment of the customer meets technical requirements of the equipment at connection points prescribed herein The customer using

transmission grid shall be responsible for updating connection-related issues to the connection

agreement signed with the transmission network operator

11 In case of connection to 110 kV or medium-voltage busbars belonging to transformers 500 kV or

220 kV within management by the transmission network operator, the procedures for execution of the connection agreement are prescribed in Clauses 1 to 9, this Article

Article 44 Time limit for execution of connection agreement

Time limit for negotiation and signing of the connection agreement is prescribed in Table 9 below:

Table 9

Time limit for review and signing of connection agreement

Submit an application for

Examine the application, prepare

a draft connection agreement and

deliver it to other units for

collection of suggestions

No more than 35 working days since receipt of the application

The transmission network operator shallpreside over and cooperate with the dispatch level and relevant units

Complete the draft connection

agreement, negotiate and sign

the connection agreement

No more than 20 working days since receipt of suggestions from relevant units

The transmission network operator and customers who need to get connected

Section 6 IMPLEMENTATION OF CONNECTION AGREEMENT

Article 45 Rights to get access to equipment at connection points

The transmission network operator and customers who need to get connected shall have the rights to get access to the equipment at connection points during survey process to make plans for connection, construction, installation, testing, replacement, removal, operation and maintenance of connection equipment

Article 46 Dossier for inspection of energizing conditions

1 Dossier serving general inspection of energizing conditions (technical documents confirmed by customers who need to get connected and certified copy of legal documents) includes:

a) Written records of inspection of individual parts and whole of connection equipment, transmission lines and transformers (according to technical standards of Vietnam or international standards

applicable in Vietnam and technical requirements of connection equipment prescribed in this Chapter);b) Approved technical documents, amendments and supplements (if any) to initial design including following documents:

- General explanation, electrical equipment layout;

- Schematic diagrams of protective relay, automation and control system that represents circuit breakers, current transformers, voltage transformers, lightning arrestor, disconnect switches …;

- Secondary diagrams of protective relay, automation and control system;

- Diagrams detailing connection to the transmission grid and parameters of transmission lines;

- Other relevant diagrams (if any)

c) Documents concerning technical parameters and operation management including:

- Technical parameters of equipment including parameters of transmission lines;

- Documents concerning primary energy system, excitation systems, governors, simulation modeling, PSS, Laplace transform diagram together with other installation values (for construction of new power plants);

- Instruction manuals for setting of protective relays, automation, specialized software;

- Instruction manuals for equipment operation and other technical documents

d) Calculations and proposals for trial operation, energizing and putting the plant into operation

Trang 23

2 Unless otherwise as agreed, customers who need to get connected shall be responsible for

providing all the documents prescribed in Clause 1, this Article to the dispatch level and the

transmission network operator serving energizing as follows:

a) At least three months prior to date of initial trial operation of the power plant;

a) At least three months prior to the date of initial trial operation of the power plant;

3 The dispatch level shall be responsible for making plans for energizing and putting the power plant into operation, ensuring safety and reliability of the equipment of the national electricity system Customers who need to get connected shall be responsible for cooperating with the dispatch level in formulating methods of energizing the power plant

4 Within 20 working days since receipt of the documents, the dispatch level shall be responsible for delivering following documents to the customer:

a) Equipment numbering diagram;

b) Requirements for methods of receiving dispatch instruction;

c) Settings of protective relays of the customer from connection points; protective relay settings note within transmission grid and other settings related to protective relays of the customer;

d) Agreed energizing method;

dd) Requirements for testing and calibration of equipment;

e) Requirements for establishment of communication system serving dispatching;

g) Requirements for connection and operation of SCADA, monitoring equipment, PMU and PSS;h) Requirements for installation of information technology system and other necessary infrastructure serving electricity market operation;

i) Procedures related to electricity system and market operation;

k) Lists of relevant officials and dispatchers accompanied by phone and facsimile numbers

5 Within 20 working days prior to the date connection points are energized, customers who need to get connected must reach an agreement with the dispatch level for trial operation schedules, methods

of energizing and putting electrical equipment into operation

6 Within 15 working days prior to the energizing day, customers who need to get connected must provide followings to the transmission network operator:

a) Trial operation schedules, methods of energizing and putting the electrical equipment into operationagreed with the dispatch level;

b) Agreement for assignment of responsibility of relevant parties for management and operation of connection equipment;

c) Internal regulation on safe operation of connection equipment;

d) Lists of qualified operators as prescribed in the national electricity system dispatch procedure issued by the Ministry of Industry and Trade including full name, professional title, responsibility, phone number

7 Within 15 working days prior to the date connection points are energized, customers who need to get connected must provide information as prescribed in Points b, c, d, Clause 6, this Article and information as prescribed in Point a, Clause 6, this Article to the dispatch level and electricity

wholesalers respectively

Article 47 Inspection of conditions for energizing connection points

1 Within five working days prior to the date connection points are expected to energized, customers who need to get connected shall be responsible for negotiating with the transmission network operator

on the date for physical inspection of connection points

2 The transmission network operator shall be responsible for presiding over and cooperating with relevant units in negotiating with the customer on procedures for inspection of dossier, written record

of inspection and installation of equipment at connection points

3 If connection points or electrical equipment of the customer fail to meet conditions for energizing as notified by the transmission network operator, the customer must carry out adjustment, supplement or replacement as requested and re-negotiate with the transmission network operator on the time for nextinspection

4 If the dispatch level provides warnings about negative impacts of energizing on safe, reliable and stable operation of the electricity transmission system or equipment of the customer, the customer must cooperate with the dispatch level and the transmission network operator in re-inspecting matters

Trang 24

related to the warnings and reaching an agreement for settlement method and re-negotiating with the transmission network operator on the time for next inspection

5 If the customer detects possible effects of energizing on safe and reliable operation of its

equipment, the customer shall make proposals to relevant units for handling and re-negotiating with the transmission network operator on the time for next inspection

6 The transmission network operator, customers who need to get connected and relevant units shall

be responsible for signing the written record of inspection of conditions for energizing connection points (hereinafter referred to as “the written record of inspection”)

Article 48 Energizing connection points

1 After the written record of inspection is signed, customers who need to get connected shall be responsible for delivering an application for energizing accompanied by following documents to the dispatch level:

a) Written confirmations of fulfillment of legal and technical procedures:

- Equipment within the scope of energizing that meet operational and technical requirements at connection points;

- Copy of the written record of inspection;

- Measurement system completed as prescribed, electrical meter indicators finalized;

- Signed power purchase agreement (PPA) or any agreement for power purchase;

- Dossier of work acceptance according to the law on construction:

- Primary equipment numbered according to the primary diagram issued by the dispatch level;

- Protective relay, automation, control, excitation and governor systems that have been installed and set in accordance with requirements prescribed herein and by the dispatch level;

- Lists of qualified operators as prescribed in the national electricity system dispatch procedure issued

by the Ministry of Industry and Trade including full name, professional title, responsibility, phone number

- Means of communications serving dispatching as prescribed in the national electricity system dispatch procedure issued by the Ministry of Industry and Trade;

- Connection to SCADA, monitoring system, PMU and communication system of the dispatch level fully completed;

- Operation coordination procedure agreed between the generating unit and the dispatch level

2 If the energizing of connection points of customers has impacts on operation mode or in case of separation of equipment on the transmission grid from operation, the transmission network operator shall be responsible for delivering an application for separation of equipment within management to the dispatch level

3 Within five working days since receipt of the application, the dispatch level shall be responsible for making notification to the transmission network operator and customers who need to get connected of the time and method of energizing connection points

4 The transmission network operator and customers shall be responsible for coordinating energizing connection points according to the method notified by the dispatch level

Article 49 Trial operation, acceptance and official operation of equipment behind connection points

1 During trial operation, acceptance and official operation of the equipment behind connection points, customers who need to get connected must appoint dispatchers and competent officials for keeping watch round the clock and send the list of officials with phone numbers to the transmission network operator and the dispatch level if need be

2 Procedures for trial operation and acceptance shall be conformable with the manufacturer’s

instructions and applicable regulations (if any)

3 During trial operation and acceptance, customers who need to get connected shall be responsible for cooperating with the transmission network operator, the dispatch level and relevant units in

minimizing effects of new equipment in trial operation on safe and reliable operation of the national electricity transmission system

4 After the process of trial operation and acceptance is completed, customers who need to get connected must provide confirmations and following information to the dispatch level and the

transmission network operator:

a) Technical specs of electrical equipment, transmission lines, transformers and generating sets;