Master Production Schedule MPS production plan demand, engineering, supplier performance execution, each step must be tested for feasibility planning process... Master Production Schedul
Trang 2Learning Objectives
When you complete this chapter you
should be able to:
4 Determine lot sizes for lot-for-lot,
EOQ, and PPB
Trang 3Learning Objectives
When you complete this chapter you
should be able to:
Trang 4Wheeled Coach
ambulances in the world
International competitor
Trang 5Wheeled Coach
requirements of the master schedule and the capabilities of the production facility
Trang 7Dependent Demand
to the demand for another item
Given a quantity for the end item,
the demand for all parts and components can be calculated
schedule can be established for an item
Trang 8Dependent Demand
2 Specifications or bill of material
Trang 9Master Production Schedule
(MPS)
production plan
demand, engineering, supplier performance
execution, each step must be tested for feasibility
planning process
Trang 10Master Production Schedule
(MPS)
products
reasonable length of time
the near term part of the plan
produced, not a forecast of demand
Trang 11The Planning Process
Figure 14.1
Change production plan?
Master production schedule
Management Return on investment Capital
Engineering Design completion
Aggregate production plan
Procurement Supplier performance
Human resources Manpower
planning
Production Capacity Inventory
Marketing Customer demand
Finance Cash flow
Trang 12The Planning Process
Is capacity plan being met?
Is execution meeting the plan?
Change master production schedule?
Change capacity?
Change requirements?
No
Execute material plans
Execute capacity
plans Yes Realistic?
Capacity requirements plan
Material requirements plan
Master production schedule
Trang 13Aggregate Production Plan
(Shows the total
quantity of amplifiers)
Master Production Schedule
(Shows the specific type and
Trang 14Master Production Schedule
(MPS)
(make-to-order) company
(assemble-to-order or forecast) company
(stock-to-forecast) company
Can be expressed in any of the
following terms:
Trang 15Focus for Different Process Strategies
Stock to Forecast (Product Focus)
Schedule finished
product
Assemble to Order
or Forecast (Repetitive)
Schedule modules
Make to Order (Process Focus)
Schedule orders
Fine-dining restaurant Fast-food restaurant Paper
Typical focus of the
Trang 16MPS Examples
Gross Requirements for Crabmeat Quiche
Gross Requirements for Spinach Quiche
Trang 17Bills of Material
and materials needed to make product
parents
children
Trang 18Std 12” Speaker booster assembly
0
Trang 19Std 12” Speaker booster assembly
Trang 20Bills of Material
Modular Bills
components that can be assembled into multiple end items
and scheduling
Trang 21Bills of Material
Planning Bills (Pseudo Bills)
Created to assign an artificial parent
to the BOM
reduce the number of items planned and scheduled
production
Trang 22Bills of Material
only temporarily
never go into inventory
Trang 23Accurate Records
absolutely required for MRP (or any dependent demand system) to operate correctly
99% accuracy
accurately reflect quantities and scheduled receipts
Trang 24Lead Times
produce, or assemble an item
order, wait, move, setup, store, and run times
between the recognition of a need and the availability of the item for production
Trang 25C E
Start production of D Must have D and E completed here so
production can begin on B
Figure 14.4
Trang 26MRP Structure
Output Reports
MRP by period report
MRP by date report
Planned order report Purchase advice
Exception reports Order early or late
or not needed Order quantity too small or too large
Material requirement planning programs (computer and software)
Trang 27Determining Gross
Requirements
end item – 50 units of Item A in week 8
determine the week in which the order
means the order for 50 units should be released in week 7
or “time phasing”
Trang 28Determining Gross
Requirements
Item Bs – 100 Item Bs are required in week 7 to satisfy the order release for Item A
release an order for 100 units of Item B in week 5
requirements are determined by the order release of the parent(s)
Trang 29Determining Gross
Requirements
BOM one level at a time – often called
“explosion”
with multiple parents are only processed once, saving time and resources and
reducing confusion
appears at only one level in the BOM
Trang 30Gross Requirements Plan
Trang 31Net Requirements Plan
Trang 32Net Requirements Plan
Trang 33Determining Net Requirements
end item – 50 units of Item A in week 8
only 40 are actually required – (net requirement) = (gross requirement - on- hand inventory)
week 8 is 40 units – 40 = 50 - 10
Trang 34Determining Net Requirements
the planned order release for Item A is now 40 units in week 7
80 units in week 7
the net requirement is 65 units in week 7
A planned order receipt of 65 units in
week 7 generates a planned order release
of 65 units in week 5
Trang 35Determining Net Requirements
A planned order receipt of 65 units in
week 7 generates a planned order release
of 65 units in week 5
is updated to reflect the use of the 15
items in inventory and shows no on-hand
calculation and is the third basic function
of the MRP process
Trang 36Net Requirements Plan
The logic of net requirements
Available inventory
Net requirements
On hand + Scheduled receipts
Total requirements Gross
requirements + Allocations
Trang 37Lead time = 6 for S Master schedule for S
Therefore, these are the gross requirements for B Gross requirements: B 10 40+10 =50 40 50 20 15+30 =45
Periods
Trang 38MRP Planning Sheet
Figure 14.7
Trang 39Safety Stock
and production quantities may not
Trang 40MRP Management
occur
too many changes
Pegging links each item to its parent
allowing effective analysis of changes
Trang 41MRP and JIT
does not do detailed scheduling
which might actually vary with batch size
JIT excels at rapidly moving small
batches of material through the system
Trang 42Finite Capacity Scheduling
capacity during normal planning cycles
recognizes actual capacity limits
schedule is created with feasible capacities which facilitates rapid material movement
Trang 43Small Bucket Approach
1 MRP “buckets” are reduced to daily or hourly
The most common planning period (time
bucket) for MRP systems is weekly
2 Planned receipts are used internally to sequence
production
3 Inventory is moved through the plant on a JIT
basis
4 Completed products are moved to finished goods
inventory which reduces required quantities for subsequent planned orders
5 Back flushing based on the BOM is used to
deduct inventory that was used in production
Trang 44Balanced Flow
Used in repetitive operations
executed using JIT techniques based on “pull”
principles
Flows are carefully
balanced with small lot sizes
Trang 45held in a common area often called
a supermarket
Inventory is maintained using JIT
systems and procedures
the MRP system
Trang 46Lot-Sizing Techniques
Lot-for-lot techniques order just what
is required for production based on net requirements
If setup costs are high, lot-for-lot can
be expensive
demand and MRP systems often deal with unknown and variable demand
Trang 47Lot-Sizing Techniques
Part Period Balancing (PPB) looks at
future orders to determine most economic lot size
complex dynamic programming technique
burdensome
Trang 49No on-hand inventory is carried through the system
Total holding cost = $0
There are seven setups for this item in this plan
Total setup cost = 7 x $100 = $700
Trang 50EOQ Lot Size Example
Trang 51EOQ Lot Size Example
Annual demand = 1,404
Total cost = setup cost + holding cost
Total cost = (1,404/73) x $100 + (73/2) x ($1 x 52 weeks)
Total cost = $3,798
Cost for 10 weeks = $3,798 x (10 weeks/52 weeks) =
$730
Trang 53Combine periods 2 - 5 as this results in the Part Period
closest to the EPP
Combine periods 6 - 9 as this results in the Part Period
closest to the EPP
Trang 56Lot-Sizing Summary
whenever there is a lot size or order quantity change
nervousness and instability
be used when low-cost JIT can
be achieved
Trang 57Lot-Sizing Summary
scrap, process constraints, and purchase lots
considerable distortion of requirements
at lower levels of the BOM
demand is reasonably smooth, PPB, Wagner-Whitin, or EOQ should give reasonable results
Trang 58Extensions of MRP
MRP system provides input to the capacity
plan, MPS, and production planning process
MRP system generates a load report which
details capacity requirements
This is used to drive the capacity planning
process
Changes pass back through the MRP
system for rescheduling
Trang 59Material Requirements
Planning II
data can be augmented by other useful information
Material Resource Planning
Trang 60Material Resource Planning
Week
B Units (lead time 2 weeks,
Payable: Raw material at $5 each 1,000
C Units (lead time 4 weeks,
3 each required) 300
Payable: Raw material at $10 each 3,000
Trang 61Closed-Loop MRP System
Figure 14.8
Trang 62Closed-Loop MRP System
Figure 14.8
Capacity Planning
Resource planning First cut capacity
No
Capacity requirements
(detailed)
Yes
Material requirements
(detailed)
Priority Planning
Desired master production
schedule Realistic?
Production plan
Planning
Trang 63Input/output report
Is average capacity adequate
?
Dispatch list
Is specific capacity adequate
?
Trang 64Resource Requirements Profile
Lot 1
Lot
2 Lot 4
Lot 7
Lot 8 Lot
3 Lot 5
Lot
10 Lot 13
Lot
9 Lot 12
Lot
14 Lot 16
Lot 6
Lot 15
Lot
11 Available capacity
Capacity exceeded
in periods 4 & 6
Lot 1
Lot
2 Lot 4
Lot 7
Lot 8 Lot
3 Lot 5
Lot
10 Lot 13
Lot
9 Lot 12
Lot
14 Lot 16
Lot 6
Lot 15
Lot 11
Available capacity
Lot 6 “split” Lot 11 moved
Trang 65Resource Requirements Profile
Figure 14.9
Lot 1
Lot
2 Lot 4
Lot 7
Lot 8 Lot
3 Lot 5
Lot
10 Lot 13
Lot
9 Lot 12
Lot
14 Lot 16
Lot 6
Lot 15
Lot
11 Available capacity
Capacity exceeded
in periods 4 & 6
Lot 1
Lot
2 Lot 4
Lot 7
Lot 8 Lot
3 Lot 5
Lot
10 Lot 13
Lot
9 Lot 12
Lot
14 Lot 16
Lot 6
Lot 15
Lot 11
Available capacity
Lot 6 “split” Lot 11 moved
Trang 66Smoothing Tactics
Sends part of the work to following
operations before the entire lot is complete
Reduces lead time
Sends the lot to two different machines for
the same operation
Shorter throughput time but increased setup
costs
3 Order or lot splitting
Breaking up the order into smaller lots and
Trang 67MRP in Services
directly linked to demand for other services
demand services or items
Trang 68Uncooked linguini
Helper one;
Work Center #2
Asst Chef;
Work Center #3
Cooked linguini
#20002 Spinach #20004
Prepared veal and sauce
#20003
(a) PRODUCT STRUCTURE TREE
Veal picante
#10001
Figure 14.10
Trang 69MRP in Services
(b) BILL OF MATERIALS
Part Number Description Quantity Measure Unit of cost Unit
20003 Prepared veal and sauce 1 Serving —
Trang 70MRP in Services
(c) BILL OF LABOR FOR VEAL PICANTE
Labor Hours Work Center Operation Labor Type Setup Time Run Time
3 Cook veal
and sauce Assistant Chef .0125 .0500
Trang 71Distribution Resource Planning
(DRP)
Using dependent demand techniques
through the supply chain
become gross requirements
customer service levels
Trang 72Enterprise Resource Planning
(ERP)
tie in customers and suppliers
many business processes
business practices
supplier evaluation to customer
Trang 73Enterprise Resource Planning
(CRM)
Trang 74ERP and MRP
Figure 14.11
Trang 75Sales Order (order entry, product configuration, sales management)
Trang 76Table 13.6
Bills of Material
Work Orders
Purchasing and Lead Times
Routings and Lead Times
Master Production Schedule
Inventory Management
ERP and MRP
Figure 14.11
MRP
Trang 77ERP and MRP
Figure 14.11
Supply Chain Management
Vendor Communication (schedules, EDI, advanced shipping notice,
e-commerce, etc.)
Trang 78Accounts Receivable
Payroll Accounts Payable
Trang 79© 2008 Prentice Hall, Inc. 14 – 79
Enterprise Resource Planning
(ERP)
meet specific business requirements
Enterprise application integration
software (EAI) allows ERP systems
Trang 80Enterprise Resource Planning
(ERP)
information
Facilitates a strategic emphasis on
JIT systems and integration
Trang 81Advantages of ERP Systems
production, and administration
collaboration between business units and sites
Trang 82Disadvantages of ERP
Systems
more so to customize
in the company and its processes
adjust to it
completed, process for implementation
problems
Trang 83ERP in the Service Sector
for health care, government, retail stores, hotels, and financial
services
Also called efficient consumer
response (ECR) systems
Objective is to tie sales to buying,
inventory, logistics, and production