Chapter 12 Risk Topics and Real Options in Capital Budgeting and Cash Flow Estimation... The Importance of Risk in Capital Budgeting Until now we have viewed cash flows as point estimat
Trang 1Chapter 12 Risk Topics and Real Options in Capital Budgeting and Cash Flow Estimation
Trang 2Cash Flows as Random Variables
“Risk” in every day usage: the probability that something bad will happen
“Risk” in financial theory: Associated
with random variables and their
probability distributions
Trang 3Cash Flows as Random Variables
Risk – the chance that a random variable will take on a value significantly different from the expected value
– In capital budgeting the future period's cash flow estimate is a random variable
3
Trang 4Figure 12-1 The Probability Distribution of a Future Cash
Flow as a Random Variable
Trang 5Cash Flows as Random Variables
The NPV and IRR are random variables with their own probability distributions
– Actual value may be different than the mean – The amount the actual value is different
from expected is related to the variance or standard deviation
5
Trang 6Figure 12-2 Risk in Estimated
Cash Flows
Trang 7The Importance of Risk in
Capital Budgeting
Until now we have viewed cash flows as point
estimates – a single number rather than a range of possibilities
Actual cash flows are estimates, a wrong decision could be made using point estimates for NPV and IRR
The riskiness of a project's cash flows must be
considered
7
Trang 8Figure 12-3 Project NPVs Reflecting
Risky Cash Flows
Trang 9The Importance of Risk in Capital
Budgeting
Risk Aversion
Changing the Nature of a Company
– A company is a portfolio of projects
– Ignoring risk when undertaking new projects can change the firm’s overall risk
characteristics
9
Trang 11Concept Connection Example 12-1
Scenario Analysis
11
Trang 12Concept Connection Example 12-1
Scenario Analysis
Trang 13Decision Tree Analysis
Decision Tree: A graphic representation of a project in which certain events have multiple outcomes
Decision Tree Analysis – Develops a
probability distribution of NPV given the
probabilities of certain events within the project
13
Trang 14Computer (Monte Carlo) Simulation
Assume separate probability distribution for each cash flow Computer draws observation from each and calculates NPV Sort outcomes into histogram of probability distribution of NPV (next slide)
Drawbacks
– Probability distributions are difficult to estimate
– Cash flows tend to be correlated
– Interpretation of results is subjective
Trang 15Figure 12-4 Results of Monte Carlo
Simulation for NPV
15
Trang 16Figure 12-5 A Simple Decision Tree
Trang 17Concept Connection Example 12-2
Decision Tree Analysis
17
The Wing Foot Shoe Company is considering a new running shoe A market study indicates a 60% probability that demand will be good and a 40%
chance that it will be poor
C0 is $5M Cash inflows are estimated at $3M
per year for three years at full manufacturing capacity
if demand is good, but just $1.5M per year if it’s poor Wing Foot’s cost of capital is 10%
Develop a rough probability distribution for NPV
Trang 18Concept Connection Example 12-2
Decision Tree Analysis
A decision tree diagram and NPVs along each path are:
$1.5M
$1.5M
$1.5M ($5M)
$3M
$3M
$3M
3 2
1 0
The expected NPV is:
The decision tree explicitly calls out the fact that
a big loss is quite possible,
Trang 19Figure 12-6 A More Complex
Decision Tree
19
Trang 20Concept Connection Example 12-3 More
Complex Decision Trees
Wing Foot now feels there are two possibilities along the upper branch
If first year demand is good, there’s a 30% chance it will
be excellent in the second and third years, and a $1 million
factory expansion will generate cash inflows of $5 million in
Trang 21Concept Connection Example 12-3 More
Complex Decision Trees
21
The NPV for the new upper path is
Trang 22Concept Connection Example 12-3 More
Complex Decision Trees
Trang 23Concept Connection Example 12-3 More
Complex Decision Trees
23
Trang 24Concept Connection Example 12-3 More
Complex Decision Trees
The project’s probability distribution expected return are
as follows
Trang 25Real Options
An option is the right or ability to take a certain course of action
A real option is a course of action that usually
– Improves financial results under certain
conditions
– Exists in a real, physical business sense
– Frequently occurs in capital budgeting
– Generally increases a project's expected NPV
25
Trang 26The Abandonment Option
A poorly performing project can sometimes be abandoned
– Usually by redeploying project resources to another use
Avoids continuing losses along a decision tree path
It usually takes planning early in a project’s life
to preserve an abandonment option
Trang 27Valuing Real Options
Real Options usually
– have definite costs early in projects
– Create additional income along only one path
– The chance of more income increases NPV
An option’s value is at least the increase in NPV less the option’s cost
– But the real option may be worth more if it also reduces project risk (e.g abandonment )
Trang 28Valuing Real Options
The Risk Effect is Tricky –
– Not all real options have a risk effect
– To lower risk an option has to reduce a potential loss not make a success better
– A case by case analysis is necessary
An Approach Through Rate of Return
– If lower risk is associated with a lower rate of return
Trang 29Designing Real Options into Projects
Abandonment option
– Usually increase NPV and lower risk
– Contract obligations can make abandonment tough
Expansion options
– Often require little or no early commitment
– Should be planned in whenever possible
Investment timing options
– Permit delaying investment until more certain about surrounding issues
Flexibility options
– Preserve ability to respond to changing business conditions
29
Trang 30Incorporating Risk Into
– For IRR– Compare IRR to k
A higher k leads to a lower chance that IRR>k reducing probability of project acceptance
The cost of capital (k) plays a key role in both NPV and IRR
Trang 31Incorporating Risk Into
Capital Budgeting
Riskier Projects Should Be Less Acceptable – Using a higher, risk-adjusted rates for risky projects lowers their chance of acceptance
The Starting Point for Risk-Adjusted Rates is the firm’s current risk level reflected in its cost
of capital
31
Trang 32Incorporating Risk Into
Capital Budgeting
Relating Interest Rates to Risk
– Interest rates are comprised of a base rate plus a risk premium
– Investors demand a higher risk premiums higher interest rates
if they are to bear more risk
Trang 33Incorporating Risk Into
Capital Budgeting
Choosing the Risk-Adjusted Rate for Various Projects
– An arbitrary, subjective process
Three categories of increasing risk
– Replacements – low risk, use cost of capital
– Expansion projects - slightly more risky than the current level
– New ventures – generally involve a lot more risk
33
Trang 34Estimating Risk-Adjusted Rates
Using CAPM
The project as a diversification
– If viewed as a collection of projects, a new venture diversifies the firm
– A new venture also diversifies the
stockholders’ investment portfolios
Trang 35Estimating the Risk-Adjusted Rate
Through Beta
The Security Market Line (SML) can be used to determine
a risk-adjusted rate for a new venture
SML: kx = kRF + (kM - kRF) bX
– bX = beta = the measure of a company's systematic risk
If a project is viewed as a business in a particular field, use
a beta common to that field to estimate a risk-adjusted rate for project analysis
35
Trang 36Estimating Risk-Adjusted Rates
Using CAPM
The project as a diversification
Diversifiable and non-diversifiable risk for projects
– Projects have two levels of diversifiable risk
Some risk diversified away within the firm's
Trang 37Figure 12-7 Components of Project Risk
37
Trang 38Concept Connection Example 12-6
Risk-Adjusted Rates - SML
Orion Inc makes radio communications equipment
beta = 1.1 cost of capital = 8%
Considering a venture into risky military radios
Military radio market is dominated by
Milrad Inc - 60% market share, beta = 1.4
Antex Radio Corp - 20% market share, beta = 2.0
Both make only military radios
kM = 10% , kRF = 5%
C0 = $10M, Ci= $3M n = 5 years
Should Orion undertake the project?
Trang 39Concept Connection Example 12-6
at best.
Trang 40Problems with the Theoretical Approach
It is often difficult to find a pure play firm from which to obtain an appropriate beta
– If a pure play division is found within a corporation, estimate the beta of that division using the
accounting beta method
Systematic risk may not be only important risk
– If total risk is important, an even higher
risk-adjusted rate would be appropriate
Trang 41Certainty Equivalents (CE)
For every cash flow management develops a lower risk free (certain) figure that is as attractive as the
forecast risky figure
– Then calculate a risk adjusted NPV or IRR with those cash flows
Alternatively choose a CE factor (0< 1) for each cash flow and multiply
– CE factors generally decline as they proceed
further into the future
Trang 42A Final Comment on Risk in Capital
Budgeting
Virtually every firm of any size uses
capital budgeting techniques
– But few explicitly include risk
Business managers do recognize risk but they do it through subjective
judgments