Introduction The purpose of this publication is to extend the broad design intentions and considerations discussed in reference 1 in order to obtain the detailed design of various parts
Trang 1DETAILED DESIGN
OF COMPOSITE CONCRETE BRIDGE SqdPERSTRQCTdRES
A Kumar BE, PhD, CEng, MICE, MIStructE
[= bending inertia of the top slab;
I = bending inertia of the bottom slab;
I, = bending inertia of the equivalent |
length of longitudinal beam about
the Z axis;
a = spacing of the longitudinal beams
b = distance between the neutral
axes of the top and bottom slabs
Trang 2
Acknowledgements
lam most grateful to Mr E M Jones of Cleveland County Council (formerly of Staffordshire County Council) and
Mr J F White of Staffordshire County Council for checking the design calculations and making many constructive
criticisms
I would like to thank many former colleagues at the Cement and Concrete Association* who have contributed
indirectly through their discussions with me, notably Mr Tony Threlfall | am also grateful to Dr Tom Harrison
and Dr Bill Cranston for their interest and provision of the necessary facilities at the Cement and Concrete
Association to carry out this work Finally | would like to thank Mr A E Brooks for his editorial contribution to
the text
Beaconsfield
First published 1988 British Cement Association
All advice or information from the British Cement Association is intended for those who will evaluate the significance and
limitations of its contents and take responsibility for its use and application, No liability (including that for negligence) for
any loss resulting from such advice or information is accepted Readers should note that all BCA publications are subject
to revision from time to time and should therefore ensure that they are in possession of the latest version
Trang 3DETAILED DESIGN OF COMPOSITE
CONCRETE BRIDGE SũPERSTRäCTRES
A Kumar BE, PhD, CEng, MICE, MiStructE
Contents
Introduction © 0 ee cnet ee eee been bebe cece nnennes 2 Extent of design effort 20.2 0.0.02 eee eee eee beeen ee nestenas 2 Simply supported and continuous T-beam superstructures using M beams .0- 2 Inverted T-beam, solid infill superstructures 0.00000 cc ccc cece eee eee eet eeeeues 4 Pseudo-box superstructures with M beams QQQQ Q QQ Q eee e ee eennnenns 5 -beam superstructures 2.0.0.0 eee eee cence nnn e eee ennevennas 6 Box-beam superstructures 0 0 ccc ce ene en tee een ete neennnnaes 6 l-beam superstructures LG Q Q Q Q Q g0 Q TQ ng g n vn ng g ng g vn n kg v va ? S04 An nu en een e eee ee een eee ee ee nen eeneneennnnnns 7 Example A : Simply supported composite concrete superstructure 8 Example B: Continuous composite concrete bridge superstructure 49
Trang 4Introduction
The purpose of this publication is to extend the broad
design intentions and considerations discussed in
reference 1 in order to obtain the detailed design of
various parts and components of composite concrete
bridge superstructures For obvious reasons, it is not
possible to cover the detailed design of all types of
beam and their possible applications However, two
examples, representative of practical bridging
situations and utilizing the most popular of the beam
types, have been chosen for detailed design here and
are discussed on this page
Since the various types of precast beam and various
requirements of the Code'**) have many structural
similarities, only the essential ways in which other
types of superstructure differ from M-beam superstruc-
ture design are outlined on pages 4 to 7 Full details
about the standardized sections, manufacture of
beams and preliminary superstructure design are con-
tained in reference 1
Extent of design effort
Since the initial publication of the limit state Code in
1978‘, many engineers have expressed the view that
the five new load combinations and the two basic limit
states would considerably increase the analysis and
design work required for bridge design Experience has
not, however, supported this view Combination 1
remains essentially the same as in the previous ap-
proach, i.e only permanent forces and live loads need
be considered in the design Combinations 2 to 5 in the
new Code”? clearly define how the various transient
forces are to be combined This contrasts with the
previous Combination 2, in which all compatible forces
had to be considered, and yet no guidance was given on
how this was to be done, thus engendering inconsisten-
cies in bridge design practice
Additionally, separate calculations were previously
required for reinforced concrete and prestressed con-
crete, to check against the permissible overstresses®°)
in the materials of up to 30% of the basic values when
HB load was present on the bridge deck In the new
Code! this is no longer the case, although some com-
plication is caused by the requirement to check crack-
ing in reinforced concrete and tensile stresses in
prestressed concrete under serviceability Combination
1 for 25 units of HB, compared with 45 or 37.5 units of
HB (depending upon the class of the road) forthe rest of
the design
The two detailed design examples included in this
publication are intended to illustrate that an adequate
design complying with the Code can be obtained with-
out either an excessive amount of computer analysis of
the superstructure or lengthy hand design calculations
If more precision is desired or the behaviour of the
superstructure is not well known, additional loading
cases for the computer analysis are recommended In
time, with the accumulation of experience with the new
2
Code, engineers will be able to discern the critical
loading conditions more readily and take short cuts, as they have done in the past, to arrive at satisfactory designs
Simply supported and continuous T-beam superstructures using
M beams
To illustrate the design procedure and compliance with
the Code, two representative examples of the cesign of
a composite concrete superstructure have been in-
cluded at the end of this publication Both examples utilize M beams in the form of a T-beam superstructure construction (there is no bottom-flange in situ con- crete) Example A deals with the design of a single- span simply supported superstructure using (a) fully bonded, (b) part debonded or (c) part deflected tendon configurations in the precast beams Example B deals with the design of a two-span live load continuity-type superstructure (as described in reference 1) using part deflected tendons in the precast beams
Example B has been extended to deal with the design of the continuity moments over the middle support in the design of the middle diaphragm The end diaphragms, the links in the precast beams and the top slab are also designed for this second case (design for the simply supported case will be broadly similar) References to various parts of BS 5400 and clause numbers are indicated in the left-hand margin of the examples for the benefit of the reader
For both these examples, substantial diaphragm members exist at the support positions which are shown to possess sufficient strength for separate bear- ings to be provided under alternate beams only During the construction period, each beam will obviously be provided with a separate temporary bearing until the diaphragms are cast
The Department of Transport have issued imple- mentation documents for the Code"®) and these have also been taken into account in the detailed design cal-
culations of Examples A and B Table 1 indicates the
values of Y, to be used in the calculations for these examples The section properties for the precast M beams are given in references 1 and 9 The section properties for the composite section using M beams
with 160 mm top slab are given in Table 2
In the context of live load continuity in composite
construction, the Code gives some guidance (Part 4,
Clause 7.4.3.5.) and formulae (Part 4, equations 33 to 35) for estimating continuity moments It should be noted that the hogging restraint moment due to differ- ential shrinkage, M,, given by equation 33, is only correct for a large number of spans made continuous
by this method For only two spans, this restraint mo- ment should be increased by 50%
Trang 5Table 1 Loads to be taken in each combination with appropriate Y,,
deck surfacing (LS† 17500 061.75 1/75 -175 1.75
SI.ST 1.20 1.20 1.20 120 1.20
SLS 1.00 1.00 1.00 1.00 1.00 5.1.2.2 & Reduced load factor for dead and superimposed qLS 1.00 1.000 1.00 1.00 1.00 5.2.2.2 dead load where this has a more severe total effect
5.8 Earth pressure: retained fill and/or live load surcharge aLs 1.50 1.50 1.50 1.50 1.50
SLS 1.00 1.00 1.00 1.00 1.00
6.8.1 Vehicle collision load with bridge parapets and associated Sẽ
SLS | 36 1.20
6.8.2 for global effects with containment parapets: se
* 1, shall be increased to at least 1.10 and 1.20 for steel and concrete respectively to compensate for inaccuracies when dead loads are not accurately assessed
+ T, may be reduced to 1.2 and 1.0 for the ULS and SLS respectively subject to approval of the appropriate authority (see Clause 5.2.2.1 of BS 5400 : Part 2)
t This is the only secondary live load to be considered for foot/cycle track bridges
NOTE For loads arising from creep and shrinkage, or from welding and lack of fit, see Parts 3,4 and 5 of BS 5400, as appropriate.
Trang 6Table 2 Section properties of composite M beams, beam spacing 1 m, modular ratio = 1.0
M2 850 467 650 429.3 42.98 102.16 147.84 164.86 100.11
M3 930 499 650 474.37 54.49 119.59 167.33 184.31 114.86 M4 1010 531 650 517.98 67.69 137.57 186.98 203.87 120.68 M5 1090 506 050 553.00 81.82 152.37 201.04 217.04 147.96 M6 1170 538 050 601.21 98.80 173.70 225.16 241.69 164.34 M7 1250 570 050 649.10 135.79 225.97 288.36 307.98 209.20 M8 1330 544 450 675.84 135.31 206.84 258.14 273.81 260.20 M9 1410 576 450 727.29 158.56 232.25 286.87 303.34 218.01
Restraint moments due to prestress and its profile,
and dead load, both modified by creep, should also be
calculated (no expressions are given in the Code) The
creep modification factor for these latter effects sug-
gested in the Code is given by equation 35 but assumes
that continuity is established at the time of prestressing
the beams This could result in seriously overestimat-
ing the support sagging moments, since much of the
prestress and dead-load creep would have taken place
prior to the establishment of continuity For this reason,
the approach used in Example B is based on ‘first
principles’ and only involves the residual creep due to
prestress and dead load at the time of establishing con-
tinuity Some information on the background of the
Code equations can be found in reference 10
Inverted T-beam, solid
infill superstructures
The live loading on an inverted T-beam superstructure
with solid infill concrete will be resisted by the rectangu-
lar composite section and this should be reflected both
in the analysis and in the design of the superstructure
The design of diaphragms and top slab will be replaced
by the design of transverse reinforcement through the
web holes for the whole length of the span If no
longitudinal bars (parallel to the beams) are placed at
the bottom of the in situ concrete between the beams,
the crack width for the transverse bars only needs to be
4
checked at a nominal cover away from the surface of these bars Longitudinal steel, if required at this posi-
tion, should be placed on either side of, not directly
above, the gap between the bottom flanges This will avoid contravening the crack-width limitations of the Code for these bars (see Figure 1)
As indicated elsewhere"), lightweight-aggregate concrete is sometimes used as an in situ infill medium with this form of construction in order to reduce the dead load of the structure The Code does not ceal with
the use of such concrete as prestressed members in
highway structures However, as an in situ infill me-
dium, this concrete is only reinforced in the transverse
direction and can be dealt with under the provisions of the Code In the longitudinal direction, the lightweight-
aggregate concrete acts compositely with the prestressed member
Trang 7For stress analysis of the composite section for the
serviceability limit state, the lightweight part of the
section can be transformed on the basis of the modular
ratio of the two concretes According to the Code, the
modulus of elasticity of lightweight-aggregate concrete
is related to that of normal-weight concrete of the same
grade by the square of the ratio of their dry densities
For the flexural strength of the composite section at the
ultimate limit state, the modular ratio will not be appli-
cable, and the grades of two concretes will determine
their contribution to the compressive force in the sec-
tion Shear strength of composite sections can be
determined as for normal concrete superstructures,
albeit that the reduced Code values apply for the
lightweight component Alternatively, as for all forms
of composite construction, the precast units them-
selves can be designed to resist the entire shear force
on the composite sections, as indicated in the Code
For the analysis of the superstructure, the stiffness
values calculated for the individual members should be
based on the transformed concrete section in both di-
rections, to reflect the lower modulus of elasticity of the
lightweight-aggregate concrete
Pseudo-box
superstructures with
M beams
For pseudo-box superstructures with M beams, the live
load on the deck will be resisted by the pseudo-box
section, the properties of which should be considered in
the grillage analysis and may be calculated as follows
The longitudinal flexural inertia of the composite
section may include full contribution from the in situ
concrete on the bottom flanges, as shownin Figure 2"),
The transverse flexural inertia of each strip equal to the
spacing of the web holes may be calculated by replac-
ing the whole of the bottom in situ concrete and the rein-
forcement by an area of concrete which is 4D horizon-
tally and 2.5D vertically, where D is the diameter of a
single equivalent bar equal in area to that of the
transverse reinforcing bars through the hole This is
indicated in Figure 3"),
The longitudinal torsional inertia for a single cell
should be calculated using the thin-wall formula by
Transverse section
Figure 3 Section for transverse stiffness evaluation
considering half the thickness of the beam webs in con- junction with the top slab and the bottom in situ
concrete taken uniform of its maximum thickness,
which occurs mid-way between the bottom flanges as shown in Figure 42):
4A2
ý ds
t area inside the median line of the concrete; and
sum of the lengths of the sides around the median line each divided by the appropriate wall thickness
Torsional inertia, C = where A
Trang 8
equivalent closed box section and then applying the
thin wall formula
The thickness ¡ of the equivalent continuous side
wall for the idealization shown in Figure 5 is given by the
formulat1?):
where I = bending inertia of the top slab;
s ° bending inertia of the bottom slab;
I,, = bending inertia of the equivalent length of longitudinal beam about
the Z axis;
a = spacing of the longitudinal beams
b = distance between the neutral axes of the top and bottom slabs
The method of calculating torsional inertias in the two
directions for a pseudo-box, M -beam superstructure is
illustrated with the help of a numerical example in
Appendix 1 of reference 12
The superstructure is acting both ways simultane-
ously and the longitudinal torsional inertia calculation
is more likely to be an accurate assessment of the total
torsion stiffness of the superstructure The longitudinal
value should therefore be split into longitudinal and
transverse components in proportion to originally cal-
culated values in the two directions, for in-putting into a
grillage analysis program This procedure is discussed
by West in reference 12 The contribution to transverse
stiffness from the diaphragms should be included in the
support edge members of the grillage
The presence of the bottom in situ concrete is usually
~ Spacing of transverse grillage members
ments Crack control forthis bottom flange steel can be handled in the same way as for the inverted T-beam
superstructures, except that the simplified equation for
flange in over all tension, given in the Code, should be
slab, will be very substantial Also, unlike the T-beam
superstructure using M beams, the torsional liriks in the
webs can be spaced further apart because of “he good
proportions of the sides of these sections and the Code
requirements in this respect
The section properties forthe composite section with
CU beams and 160 mm top slab are givenin Table 3 The
unsupported webs of these beams are vulnerable to mishandling and shock loads; therefore, during the manufacture, lifting and transport of these beams, some temporary bracing of the webs is often necessary
to avoid overstressing the junction of the webs with the bottom flange
Box-beam superstructures
Box-beam superstructures are only provided with a
nominal thickness of levelling screed with mesh rein-
forcement; their transverse distribution properties emanate from post-tensioning through transverse dia-
phragms The precast box beams therefore carry the
entire longitudinal effects themselves, while in situ infill concrete (between the beams) combined with post- tensioning, handles the load distribution and the result- ing transverse effects Thus, any structural contribu-
tion from the screed or topping which may be provided
is ignored, both in the analysis and in the design of this
type of superstructure Vertical shear due to live loads
and longitudinal shear due to a component of trans- verse prestress in skew bridges (if prestress is applied parallel to the supported edges) should be checked at the vertical interface of the precast and the in situ
concretes
Trang 9
Table 3 Section properties of composite C beams; beam spacing 2 m, modular ratio = 1.0
dl 960 786 450 568.62 82.87 211,75 358.17 145.75
q5 1160 852 450 685.87 136.31 287.49 433.01 198.73 ũ7 1260 885 450 743.83 169.29 327.98 475.32 227.59
| - be a m 5 DEPARTMENT OF TRANSPORT Reinforced concrete
2 for highuuau structures London, 1973 BS 1/73
su p erstructures 6 DEPARTMENT OF TRANSPORT Prestressed concrete
for highway structures London, 1973 BS 2/73 This type of superstructure is essentially similar to the ;
T-beam construction using M beams, except that there @, DEPARTMENT OF TRANSPORT Loads for highway are in situ transverse diaphragms acting compositely bridges: use of BS 5400: Part 2: 1978 London with the top slab, which must be considered both in the BD 14/82: 1982 and its Amendment No 1 :
analysis and in the design of this type of superstructure 1983
8 DEPARTMENT OF TRANSPORT Design of concrete bridges: use of BS 5400: Part4: 1984 London
9 PRESTRESSED CONCRETE ASSOCIATION,
1 KUMAR, A Composite concrete bridge _ Prestressed concrete bridge beams Second
superstructures Wexham Springs, British edition Leicester, 1984 7 pp + folder
Cement Association, 1988 46 pp Publication
46.505 10 CLARK,L.A Concrete bridge design to BS 5400
London, Construction Press, 1983 186 pp
2, BRITISHSTANDARDS INSTITUTION Steel, concrete
and composite bridges Part 2: Specification for 11 MANTON, B.H and WILSON, C.B MoT/C&ECA
loads London 46 pp BS 5400 : Part 2:1978 standard bridge bears: prestressed inverted
T beams for spans from 15m to29m London,
3 BRITISH STANDARDS INSTITUTION Steel, concrete Cement and Concrete Association, 1975 20 pp and composite bridges Part 4: Code of practice for Publication 46.012
design of concrete bridges London 68 pp
BS 5400: Part 4: 1984 12 WEST,R CGCA/CIRIA Recommendations on the
4 BRITISH STANDARDS INSTITUTION Steel, concrete
and composite bridges Part 4 : Code of practice for
design of concrete bridges London 48 pp
BS 5400: Part 4: 1978
use of grillage analysis for slab and pseudo-slab bridge decks London, Cement and Concrete Association, 1973 24 pp Publication 46.017
Trang 10EXAMPLE A: Simply supported composite
concrete superstructure
End support and điaphragm section .- eee ee tte teen ene 2 Deck section and grillage idealization .- -.- ee eee ete 3 Stiffnesses for grillage analysis - Examples A andB 2 et eee 5 Live load patterns 2.00 ee ee nee ee eee eee eee 7 Basic load cases for grillage analysis 2.0.0 cc eee eee eee ete hà ki mi ng 10 Longitudinal moments in precast beams 2.0 ee eee ee eee 11 Section properties .0 0.0 ee eee ee ee eee eee eens 14
Allowable stresses in precast concrete 1.2 0 cee ce ee ee ee eee eee ene 15
Stresses due to dead load and live load 1 2 Lee ee nee teen eens 16 Temperature difference stresses (PTD and NTD) ee eee nee 17 Differential shrinkage stresses (DSH) Q HQ HQ HH hy hy hà 20 (A) Precast beams with straight fully bonded tendons Ặ ẶQ Q HS 21 Differential creep stresses (DC) Q Q Q LH Q HQ HQ Q H ng HH n HH gà H ĐH nà kà kh kh va 25 Final stress checks Q Q Q HQ HQ HQ HH HH HH Ho gu Hy ng kg Hy kg k KV Hy kg eens 28 (B) Precast beams with straight part debonded tendons 29 (C) Precast beams with straight part deflected tendons -.-ẶVẶẶ VỤ 38 ULS checkS 2 ee ee ee ee ee ee ee ee 40
8
Trang 11Spare 18:1 we Sify snppeortiol
Ấy» foofhattsonr both sides
SD wm nde chia plriatrns sahishying the web hole clearances, Cost whew the beand
were 3 do tt mentee old
C(AsfoVC k4 n/f Orn cas.Á (vxvÀ⁄«na(2
dc 17 M3 beams af (wm conics wit
O-3m x 2:3 panopel bint cash write
the deck , see Fig 2/A
Gril Nine lonpitrGralty at cevbus of
alkramak M beams representinp (T/y x
single been shiffrts Nine transversely vepreserhing /8-‡/2= 2-4 alors the Yaar,
spacer ak- 781/8 = 2-2625 Diadehang més
and fasrafect plinths wers treludd with
Based or Weak recommentahions (
prbbeakon 46017) amd ab ivdircatiol on
fapes S and C/A
Soy dens oye od od FR we ete 5 ray, eR RTE PRK EE ey
PERRET EX CICS AAAS TOIY) RS Ae La ON Ld er kd A SS = sits
Trang 12Project Job ref
Part of structure £A/ b> SUPPORT AND Calc sheet no rev
Drawing ref Calc by Date Check by Da-e
TAH EY EOS Y soma cam DMARD To Qt OAS LS RL NA KÝ
Trang 14Project Job ref
The CAR Epler hey ca, J Ibm wrtl
be iwiced afro Lno 3'25munde mithiernel loo Sec ha 3/A
HA YP = 9123 kM/m`
HÀ kế = 120 EA /inre width
2 lames of HA + DOHA in the rot
xe cv CC S50] am
Inti, Coretta HOM nn
fy : H4EO Nome y = 5 = 200 kn] mon”
IS*2 mm Twine shandenel stone
Be = 195 kA/ÌmuÈ
Sp = 6†o N fm
Thao fot procticah kvubrav2 He
the poll tendon frre 10 mutable
the wa 55m “f beams,
Trang 15Project Job ref
Drawing ref Calc by Date Check by Date
Ref Calculations Output
Ref 12
Ref (2
hLongitrGinehL JT Reeastond rss conerde
for infer emote
10 NG vase theredere Here i6 no
nacol or teen Êaee2
&tehiow Pri M2 bean wilh
x0'U + 02382016 x 0335
% O25
+ 0'291x 0°185°% 0-95 )= 0:0076 mat
[ecco pet ““2 2> conaictti2ad fe
art tA th eof IM bens ord,
Trang 16“Freaminae L Lf m OBS wm LOT] m ý
ceri eT 1 conaidosd to act with he
Top tab (proving ob pth bute
T= 0:0465 mt
3 7/N&¬-£vtx2c € C= OIG XO-8S * O77 4 OSX 0:33
The C8td 22 2c mit int , shrears amd
/xtre+.4 Pr metre with al the nodal potions
Trang 17Project Job ref Part of structure /,/V/£ LOAD PATTERNS Calc sheet no rev
frduer Tha wed” “fect:
nor ann
ko en ÀL Z/¿{&, fewer
Aeslt na an ^eÍep.sÉc 420v
prehow, bk synte a node exists
Fig, #4 Maxi minrn long hGined "9 reement
a mie - San proition
avemgement of Fig s/4 distance anny fom the rete Spare,
Trang 18
Š LA ¡
Drawing ref Cale by Date Check by Date
camse the worst offeet- IF
Vier urene no feotpatts ý ức
PAH EOUY SOO CUPPA Mey y
V3) N ASL và Wee TRAST LAE ES
Trang 19
Project Job ref
Part of structure Cale sheet no rev
Q 1A I
Drawing ref Cale by Date Check by Date
Ref Calculations Qutput
Max shead “tự fel loool pat hạ
Trang 20Project Job ref
Drawing ref Calc by Date Check by Date
Ref Calculations Output
The briotre otek t2 anny 502
fot he fe Lenstrng foc ad ca ws,
PL vf prwat Aianis ef § 23 EN / ne an >
msit, conerele >⁄ 3 Sy kN fon Re sisted by
ANE precant btanes And caleLs biol by hen),
over The 44 A-rtas
Lk of AA / a on the necVsede footpath
Trang 21Ca rvza2-tvt sš#rt +22 fet a romwhrnahens (as
xe of 72 ) “o be Len thar the atlersale ,
Tatle 1 mrdceates brild- op ef moments alm
Node 39, SH wao ebeenvtel from the tombal
art pot- tral” seme repetive momen erenrcol
mm te enck Hie of the sam These mamenti af
the fare of the daaphregr (Team 2) were abort to)
of the mid shaw valnes (Tate 1) Mee the mum ots
at tre ymarter spam (TeAte 3) rere abenl- bof of tre
rid- shaw valves, fev SA 200052 the dedeorhs of
fll brihd-np of values at these brahions have
beer Omitted Unkss additonal Lad cess art denis, the mements ot thease (tan bald be
comseriahicly estimated The variahen of mam enti Aas been arsnmeel + be Anes atthe erds ard furebolic
nv the nnd shaw reg ones , ek “2 ?/A
Project Job ref
Part of structure LOWG/TUDINAL MOMENTS Calc sheet no rev
IN PRECAST BEAMS fof AT]
Drawing ref Calc by Date Check by Date Ref Calculations Output
Botk fet ULE anol AS Nocte 39 Is the mat ential
fr tre hal fatteins of Fig Ff:
de Lim tet dy Chie I ana fet Gowt.3 (4s
braids of “., by Clare IL Aag ad re ments,
Trang 22Nominel lambs Comp) |Gome.t(tens)| Comb, 3 | Comb.? | Come 3
Moment Foedorcd Fac+oxc3 Factovc Fectover | Feetored
po Ye Moment} ft Mom ent] "Pe planet T° Moment FFL Moment
Table 3) Estimakd moments at grater shan FC sen
SDL can be sub-divided mto Surfacing and othey loads and thtn
Fe applied separa kh,
Trang 23Project Job ref
Part of structure Calc sheet no rev
13) AY
Drawing ref Calc by Date
\ parabolic
/462
Hogeing moments due to LL only
Sagging moments ane to DL +LL,
Fig Y Bending moments envelope fer SLS L¢e3
momerk values enerreel 2» Yhe Have
VBLLONS maxima may Otows ir 2x
writerbers of the nhanh a
Trang 24
Part of structure SECT/ON PROPERTIES Calc sheet no rev
/ 1A |
Drawing ref Calc by Date Check by Date
Fibves fancl 2 refer bo the preeail bears soffit
avd tof and frres 3 ancl 4 vi» fo ne
Sept and tp af the ania wreck shed
Subroripts onde olenete fpreeacl and
cư kệ section wopectirey
Table 4 chen prepotic
Trang 25Project Job ref
Partofstructure ALLOWABLE STRESSES IN
Xe sec 0 te Charl fot Gwb.t (herr)
L-32Y inne bt Claas I for low-b 3
ru
(amjvvzưưv€ sheva 0-5fe, Ott ¿.e 20 | ron”
Tenwile stess fi! Nm for Comes f
+- 0-45 fon Ue =2-Ệ§ Ms Tai Comb.3
Lith, any ky or Aan dein SWtv2x⁄2
whieh the preceat- nits vn AZ be subjected + y
—F Maw being otrerely pri” from Hrnmeger
Her ve nid fratew novia gated “`, ¬ 5 = ey
Trang 26
Project Job ref
Partofstructure STRESSES Duc TO DEAP | Cale sheetno rev
LOAD AND LIVE LOAD fo, A |
Drawing ref Cale by Date Check by Date Ref Calculations
NI, dernoks momends rensead fy precast beams only
My clmolea mements wiisted by combs silt section
Table SA SLS rid spam Sr/aes
Trang 27Project Job ref
ResAtaned ý, SAW? = 33x/0% /2 xio® O:396 “fon
Trang 28
J8 | 8 J
Drawing ref Calc by Date Check by Date
- 0:16 x0-2x0-75 (4p- 185-200/s)} = - 24 kN mn
Reshornss are new relerard & per
LemhPhe cs AAS AAS VAS MESA 3š vO ¬ — Ầ VỀ ed ts x
Trang 29Project Job ref
Freq, [2 Ssse4 dine +o megatie remnp differen ceS.INTD }
Poy ehreys Cyr otios
Trang 30Project Job ref
Assuwe Yoo- tirds vf Cota potential
pleee pr the Arccaalhramd Wher ingthe
slab > cart Thougere 200x160"
Aaffran bok Z2 eke/< of tre slab cyÊ set
rer affect the confers CC section mom he
Trang 31Project Job ref
Part of structure (A) FRE CAST REAMS WITH
STRAIGHT FULLY BONDED TENDONS Calc sheet no 2! 1A | rev
Assunieé 2o? le20 ef prCrrw drbsernend do 6 xxx,
71A^§t#@kt tr bolleriy fibre at wn d- share
SBiv2209 oltre te otiffferenbal c^+zZ are net brown
ok thar Stage brit art enpecteol to be of ruhevirg
> -~Í
natant Thin in olemansHalerl tater
Tran sfr conciter is heart ne mort riheal,
Assume a lo 2 hewn tf free pret to And anAvg
shussing , therefere Jrckirg fre
Trang 32Project
Use 23 [15:2 tam Mindared shrrwdls wit an
bon fal fore of OFS fe proving
Fy = O75 xZ23Bx 232 = 4ooz ka/ anil
2x6o + 6X llO + x!éO+ 2x 430 + 2x S550
€ - 37D - _— ,
23
= 810 — Ííô = /42 mm
e - v
transfer ano Anat: Shortening Ar tuUns
Trang 33
inital stemig due do dead ford and ÂytA #22
ef ma- pan are at Sharm om fg 1S /A
Fig IS/ Stresses a transfer art mid shan
22/1 A I
Drawing ref Calc by Date Check by Date
Trang 34
Project dob ref
Part of structure Calc sheet no rev
fib 2 = ~O8325x OSB 2 -O-4E ad
Ref Calculations Output
Lea of f etl Ar Fhe (eng (Fone:
t/6-722 Cu» va we fost x 0:02 (Say) ¥ 4002 = 8OkN
724 — Shninkare lots ( Eos Es Abs)
= 300x10 195%23%/39= IRTEN
Yenrs| Gap bors (6 foo ks ops)
+ z4 obmg “fo the Dt meme , te to
faas revll vary along Me bean, Wre fol
trké t2 thea tere buen daa ew -2/4A—
Mew conchbin xx Ac memder, “test Frese
be brad ew cv, sÊxae alan whe, Cops fe beau,
‘ ae oy ean owe § - awe a ae oe SR RY
Tair py nek gamail cam Le SP Ryas ALAA xŠ MAP DCSE Wet be
Trang 35
Project Job ref
Partof structure D/FFERENTIAL CREEP Calc sheet no rev
Ref lo
% Tạ 10
Basis af tale lation (See comments on Faae 3)
Asse YLat Aso - Wk As “f up ont +o
pr lirse ancl enon self magi Hake 7 pee frieg +o The coctimp of fp Hab( sory
ak 180 dogs ) powdfere the Aciiaduval eed
for bees = x GE The Lame neers
factor can fe Adcumed fer the slab ⁄
he flal clad Lond ord us afphcd
ot “ 160 Mays whew the beam conn i
cen aiclr.ably mre mats han al Rewmsfr
Assume tet tyo-tivels ef the total di
od preatres ag ti Coop vi k2 plac “ee
«4/46 n cook, tharspere Fey= Fat t(P-Fe)
Fesheus, C force dp rear nt xen ial ‹ ~ee/
Are Ýo kh‹Z +2 F p= — fe;.Poah
Eecenti city of prtcael- earn cerlisad to
the NI nước centrerd “¿¿= 7Ø - 3!0= 164 mm
Nlom wn abart Preceat tram tentreiad to
Pustornr bnrvadirr clre Có Afperentiol reef
= (Rye- My, ) Bees ?
Trang 36Kelhinze re amd memint on the Compote
seetrer, witt therefore be — Fran of
Ay mid — spam a con fartooive strez of
O-4Y Nim” exists ot feel
wea
|
Ề
Trang 37a7 iA |
Drawing ref Calc by Date Check by Date
Trang 38
Project Job ref
Partofstructure Fyng/ Stress Checks Calc sheet no rev
Trang 39Project Job ref
Part of structure ( 6 ) PRECAST BEAMS WITH
STEM GHT PRET PEBENPtbD TENDONS
Calc sheet no rev
p2i/A
Assume 207, Lew of prusburr subacg nent fo
3, 337 _ s z
A ergy = 337 Nim at fins 1 and 2
ropectirely ak grantor, Sion powtens Tare fare
Allowing 107 Loss of preshrss Cefore amd during |
Tams fer ; ®e</me respec d Be 2980 LM
TAL 22 xaxrv2 at a stor of 075 Ton br ^<:pC 20 strandsI7! 7, f5:2 Mw, StandarA `
Trang 40
30, A |
Drawing ref Cale by Date Check by Date
to oblav~ Stine peri bilirs in hitondhing ) |
Fry the skand petierar of Fig 1e/A
Fig 18) SMa ol pettan with de bonded t-dons |
YY