Risk analysis and project evaluation tài liệu, giáo án, bài giảng , luận văn, luận án, đồ án, bài tập lớn về tất cả các...
Trang 1Risk Analysis and Project Evaluation
Campbell R HarveyDuke University
and National Bureau of Economic Research
Project Appraisal and Risk Management (PARM)
Duke Center for International Development at the Sanford Institute May 27-28, 2002
Trang 21 Cash Flow versus Discount Rate
2 Approaches to Cost of Capital Measurement
3 Recommended Framework
4 Comparison of Methods
5 Conversion of Cash Flows
6 Project Specific Adjustments
7 Conclusions
Risk Analysis and Project Evaluation
Plan
Trang 3Basic Project Evaluation:
• Forecast nominal cash flows
• Currency choice (assume US$)
• Decide what risks will be reflected in cash flows
and those in the discount rate
– Beware of double discounting
Risk Analysis and Project Evaluation
1 Cash Flow vs Discount Rate
Trang 4Simple example:
• Assume a simple project with expected $100 in
perpetual cash flows
• If located in the U.S., the discount rate would be
10% and
Value= $100/0.10= $1,000
Risk Analysis and Project Evaluation
1 Cash Flow vs Discount Rate
Trang 5Simple example:
• However, project is not located in the U.S but a
risky country
• If we reflect the country risk in the discount rate,
the rate rises to 20%
Value = $100/0.20 = $500
Risk Analysis and Project Evaluation
1 Cash Flow vs Discount Rate
Trang 6Simple example:
• If we reflect the country risk in the cash flows, the
value is identical
Value = $50/0.10 = $500
Risk Analysis and Project Evaluation
1 Cash Flow vs Discount Rate
Trang 7Our approach
• We will propose methods that deliver discount
rates that reflect country risk
• As our example showed, it is a simple matter of
shifting the country risk from the discount rate to the cash flows
Risk Analysis and Project Evaluation
1 Cash Flow vs Discount Rate
Trang 8Our approach
• Indeed, we will often do this
– That is, we will use quantitative methods to get a
measurement of country risk in the discount rate.
– Use the country risk adjustment in the cash flows (and
adjust discount rate down accordingly).
– Use Monte Carlo methods on cash flows rather than
cash flows and discount rate.
Risk Analysis and Project Evaluation
1 Cash Flow vs Discount Rate
Trang 9Many different approaches:
1 Identical Cost of Capital (all locations)
2 World CAPM or Multifactor Model
(Sharpe-Ross)
3 Segmented/Integrated (Bekaert-Harvey)
4 Bayesian (Ibbotson Associates)
5 Country Risk Rating (Erb-Harvey-Viskanta)
6 CAPM with Skewness (Harvey-Siddique)
Risk Analysis and Project Evaluation
2 International Cost of Capital
Trang 10Risk Analysis and Project Evaluation
2 International Cost of Capital
7 Goldman-integrated sovereign yield spread
Trang 11Identical Cost of Capital
• Ignores the fact that shareholders require different
expected returns for different risks
Risk Analysis and Project Evaluation
2 International Cost of Capital
Trang 12Identical Cost of Capital
• Risky investments get evaluated with too low of a
discount rate (and look better than they should)
• Less risky investments get evaluated with too high
of a discount rate (and look worse than they are)
• Hence, method destroys value
➾Avoid
Risk Analysis and Project Evaluation
2 International Cost of Capital
Trang 13World CAPM
• Sharpe’s Capital Asset Pricing Model is the
mainstay of economic valuation
• Simple formula
• Intuition is that required rate of return depends on
how the investment contributes to the volatility of
a well diversified portfolio
Risk Analysis and Project Evaluation
2 International Cost of Capital
Trang 14World CAPM
• Expected discount rate (in U.S dollars) on
investment that has average in a country
= riskfree + βι x world risk premium
• Beta is measured relative to a “world” portfolio
• OK for developed markets if we allow risk to
change through time (Harvey 1991)
Risk Analysis and Project Evaluation
2 International Cost of Capital
Trang 15World CAPM
• Strong assumptions needed
• Perfect market integration
• Mean-variance analysis implied by utility
assumptions
• Fails in emerging markets
Risk Analysis and Project Evaluation
2 International Cost of Capital
Trang 16Returns and Beta from 1970
R 2 = 0.013
-0.1
0 0.1
Risk Analysis and Project Evaluation
2 International Cost of Capital
Trang 17Returns and Beta from 1990
R 2 = 0.0211
-0.1
0 0.1
Still goes the wrong way - even with data from 1990!
Risk Analysis and Project Evaluation
2 International Cost of Capital
Trang 18World CAPM
• OK to use in developed markets
• May give unreliable results in smaller, less liquid
developed markets
Risk Analysis and Project Evaluation
2 International Cost of Capital
Trang 19• Many markets are not integrated so we need to
modify the CAPM
Risk Analysis and Project Evaluation
2 International Cost of Capital
Trang 20Segmented/Integrated CAPM
• Bekaert and Harvey (1995)
• If market integrated, world CAPM holds
• If market segmented, local CAPM holds
• If going through the process of integration, a
combination of two holds
Risk Analysis and Project Evaluation
2 International Cost of Capital
Trang 21Segmented/Integrated CAPM
Estimate world beta and expected return
= riskfree + βιw x world risk premium
Estimate local beta and expected return
= local riskfree + βιL x local risk premium
Risk Analysis and Project Evaluation
2 International Cost of Capital
Trang 22Segmented/Integrated CAPM
• Put everything in common currency terms
• Add up the two components.
CC= w[world CC] + (1-w)[local CC]
• Weights, w, determined by variables that proxy
for degree of integration, like size of trade sector and equity market capitalization to GDP
Risk Analysis and Project Evaluation
2 International Cost of Capital
Trang 23Segmented/Integrated CAPM
• Weights are dynamic, as are the risk loadings and
the risk premiums
• Downside: hard to implement; only appropriate
for countries with equity markets
• Recommendation: Wait
Risk Analysis and Project Evaluation
2 International Cost of Capital
Trang 24Ibbotson Associates
(Recognized expert in cost of capital calculation)
• Approach recognizes that the world CAPM is not
the best model
• Ibbotson approach combines the CAPM’s
prediction with nạve prediction based on past
performance
Risk Analysis and Project Evaluation
2 International Cost of Capital
Trang 25Ibbotson Associates
• STEPS
1 Calculate world risk premium=U.S risk premium
divided by the beta versus the MSCI world
2 Estimate country beta versus world index
3 Multiply this beta times world risk premium
Risk Analysis and Project Evaluation
2 International Cost of Capital
Trang 26Ibbotson Associates
4 Add in 0.5 times the ‘intercept’ from the initial
regression “This additional premium represents the compensation an investor receives for taking
on the considerable risks of the emerging markets that is not explained by beta alone.”
Risk Analysis and Project Evaluation
2 International Cost of Capital
Trang 27Ibbotson Associates
• Gives unreasonable results in some countries
• Only useful if equity markets exist
• Ibbotson Associates does not even use it
➙Recommendation: Do not use this version Ibbotson has alternative methods available
Risk Analysis and Project Evaluation
2 International Cost of Capital
Trang 28CAPM with Skewness
• For years, economists did not understand why
people spend money on lottery tickets and horse betting
• The expected return is negative and the volatility
is high
• Behavioral explanations focused on “risk loving”
Risk Analysis and Project Evaluation
2 International Cost of Capital
Trang 29CAPM with Skewness
• But this is just preference for positive skewness
(big positive outcomes)
• People like positive skewness and dislike negative
skewness (downside)
Risk Analysis and Project Evaluation
2 International Cost of Capital
Trang 30CAPM with Skewness
• Most are willing to pay extra for an investment
that adds positive skewness (lower hurdle rate), e.g investing in a startup with unproven
technology
Risk Analysis and Project Evaluation
2 International Cost of Capital
Trang 31CAPM with Skewness
• Harvey and Siddique (2000) tests of a model that
includes time-varying skewness risk
• Bekaert, Erb, Harvey and Viskanta detail the
implications of skewness and kurtosis in emerging market stock selection
Risk Analysis and Project Evaluation
2 International Cost of Capital
Trang 32CAPM with Skewness
• Model still being developed
• Skewness similar to many “real options” that are
important in project evaluation
➙Recommendation: Wait
Risk Analysis and Project Evaluation
2 International Cost of Capital
Trang 33• This model is widely used by McKinsey, Salomon
and many others
• Addresses the problem that the CAPM gives a
discount rate too low
• Solution: Add the sovereign yield spread
Risk Analysis and Project Evaluation
2 International Cost of Capital
*J.O Mariscal and R M Lee, The valuation of Mexican Stocks: An extension of the capital asset pricing model to emerging markets, Goldman Sachs, June 18, 1993.
Trang 34• The sovereign yield spread is the yield on a U.S
dollar bond that a country offers versus a U.S Treasury bond of the same maturity
• The spread is said to reflect “country risk”
Risk Analysis and Project Evaluation
2 International Cost of Capital
Trang 35STEPS
• Estimate market beta on the S&P 500
• Beta times historical US premium
• Add sovereign yield spread plus the risk free
Risk Analysis and Project Evaluation
2 International Cost of Capital
Trang 36Risk Analysis and Project Evaluation
2 International Cost of Capital
Trang 37Real Yields and Institutional Investor Country Credit Ratings from 1990 through 1998:03
Risk Analysis and Project Evaluation
2 International Cost of Capital
Trang 38Goldman-Integrated-EHV Hybrid
• You just need a credit rating (available for 136
countries now) and the EHV model will deliver the sovereign yield
Risk Analysis and Project Evaluation
2 International Cost of Capital
Trang 39Goldman-Integrated-EHV Hybrid
capital that is unreasonably low in many countries
• While you can get the yield spread in 136
countries with the EHV method, you can only get risk premiums for those countries with equity
markets
Risk Analysis and Project Evaluation
2 International Cost of Capital
Trang 40• Main problem is the beta
• It is too low for many risky markets
• Solution: Increase the beta
Risk Analysis and Project Evaluation
2 International Cost of Capital
Trang 41• Modified beta=standard deviation of local market
return in US dollars divided by standard deviation
of the US market return
• Beta times historical US premium
• Add sovereign yield spread
Risk Analysis and Project Evaluation
2 International Cost of Capital
Trang 42• Using volatility ratio implies that the Correlation=1 !!
World
i World
i World
i
dev Std
dev
Std n
Risk Analysis and Project Evaluation
2 International Cost of Capital
Trang 43• No economic foundation for modification
• No clear economic foundation for method in
general
➙Recommendation: Not recommended
Risk Analysis and Project Evaluation
2 International Cost of Capital
Trang 44E[ri]=SYi + βi{E[rus-RFus] x Ai} x Ki
• SYi = brady yield (use fitted from EHV)
• βi = the beta of a stock against a local index
Risk Analysis and Project Evaluation
2 International Cost of Capital
L Hauptman and S Natella, The cost of equity in Latin American, Credit Swisse First Boston, May 20, 1997.
Trang 45E[ri]=SYi + βi{E[rus-RFus] x Ai} x Ki
• Ai =the coefficient of variation (CV) in the local market divided by the CV of the U.S market)
where CV = σ/mean
• Ki =“constant term to adjust for the
interdependence between the risk-free rate and the equity risk premium”
Risk Analysis and Project Evaluation
2 International Cost of Capital
Trang 46• No economic foundation
• Complicated, nonintuitive and ad hoc
➙Recommendation: Avoid
Risk Analysis and Project Evaluation
2 International Cost of Capital
Trang 47make it more like an equity premium rather than a bond premium
Risk Analysis and Project Evaluation
2 International Cost of Capital
A Damodaran, Estimating equity risk premiums, working paper, NYU, undated.
Trang 48Country Sovereign Equity std dev equity = yield x - premium spread Bond std dev.
Risk Analysis and Project Evaluation
2 International Cost of Capital
Trang 49use the bond yield spread as a plug number
in the CAPM
for stocks and bonds must be the same in any particular country.
Risk Analysis and Project Evaluation
2 International Cost of Capital
Trang 50Country Risk Rating Model
• Erb, Harvey and Viskanta (1995)
• Credit rating a good ex ante measure of risk
• Impressive fit to data
Risk Analysis and Project Evaluation
3 Recommended Framework
C.B Erb, C R Harvey and T E Viskanta, Expected returns and volatility in 135 countries, Journal of Portfolio Management, 1995.
Trang 51Country Risk Rating Model
• Erb, Harvey and Viskanta (1995)
• Explore risk surrogates:
– Political Risk,
– Economic Risk,
– Financial Risk and
– Country Credit Ratings
Risk Analysis and Project Evaluation
3 Recommended Framework
Trang 52Country Risk Rating Model
Sources
• Political Risk Services’ International Country Risk Guide
• Institutional Investor’s Country Credit Rating
• Euromoney’s Country Credit Rating
• Moody’s
• S&P
Risk Analysis and Project Evaluation
3 Recommended Framework
Trang 53Political risk International Country Risk Guide
% of Individual % of
Economic expectations vs reality 12 12% 6% Economic planning failures 12 12% 6% Political leadership 12 12% 6%
Trang 54Financial risk International Country Risk Guide
Financial
Loan Default or unfavorable loan restructuring 10 20% 5% Delayed payment of suppliers’ credits 10 20% 5% Repudiation of contracts by governments 10 20% 5% Losses from exchange controls 10 20% 5% Expropriation of private investments 10 20% 5%
Total Financial Points 50 100% 25%Risk Analysis and Project Evaluation
3 Recommended Framework
Trang 55Economic risk International Country Risk Guide
Economic
Debt service as a % of exports of goods and services 10 20% 5% International liquidity ratios 5 10% 3% Foreign trade collection experience 5 10% 3% Current account balance as a % of goods and services 15 30% 8% Parallel foreign exchange rate market indicators 5 10% 3%
Total Economic Points 50 100% 25%
Risk Analysis and Project Evaluation
3 Recommended Framework
Trang 56International Country Risk Guide Risk Categories
Very High Risk 0.0-49.5
High Risk 50.0-59.5
Moderate Risk 60.0-69.5
Very Low Risk 85.0-100.0
Risk Analysis and Project Evaluation
3 Recommended Framework
Trang 57Institutional Investor’s Country Credit Ratings
3 Recommended Framework
Trang 58Ratings are correlated:
0 10 20 30 40 50 60 70 80 90 100
S&P Sovereign Ratings
Risk Analysis and Project Evaluation
3 Recommended Framework
Trang 59Ratings are correlated:
0 10 20 30 40 50 60 70 80 90 100
S&P Sovereign Ratings
Risk Analysis and Project Evaluation
3 Recommended Framework
Trang 60Ratings are correlated:
0 10 20 30 40 50 60 70 80 90 100
S&P Sovereign Ratings
Risk Analysis and Project Evaluation
3 Recommended Framework
Trang 61Ratings are correlated:
Risk Measure Changes
II CCR ICRGC ICRGP ICRGF ICRGE
Risk Measure Levels
Risk Analysis and Project Evaluation
3 Recommended Framework
Trang 62ICRG ratings predict changes in II ratings:
Attribute Coefficient T-Stat R-Square
Trang 63Ratings predict inflation:
Trang 64Ratings correlated with wealth:
Trang 65Switzerland Italy Kuwait Argentina
Risk Analysis and Project Evaluation
3 Recommended Framework