What is Line Balancing ?? Assigning each task to a work within an assembly line in order to meet the required production rate and to achieve a minimum amount of idle time.. Line balan
Trang 1ASSEMBLY LINE
BALANCING
MODUL 7
Trang 2What is Line Balancing ??
Assigning each task to a work within an
assembly line in order to meet the required production rate and to achieve a minimum amount of idle time
Line balancing is the procedure in which
tasks along the assembly line are assigned
to work station so each line has
approximately same amount of work
Trang 3Terms Defined
Delay/idle time of a workstation: the
difference between the cycle time (CT) and the station time (ST)
Cycle time (CT): the time between the
completion of 2 successive assemblies,
assumed constant for all assemblies for a given conveyor speed
Trang 4Terms Defined (Cont.)
Line efficiency (LE): the ratio of total station time to the cycle time multiplied by the number of workstations
Balance Delay
Balance Delay
Work element: a part of the total work content in an assembly process
Trang 5Terms Defined (Cont.)
Smoothness index (SI): an index to indicate the relative smoothness of a given
assembly line balance A smoothness index
of zero indicates a perfect balance
Workstation (WS): a location on the
assembly line where a work element or
elements are performed on the product
Trang 6Precedence Constraint
Precedence Constraint is a restriction on the order of execution of work elements
There are two conditions taht usually
appear in assembling process:
1 There is no dependency of the components
in the works
2 If a component has been selected to be
assembled, then the sequence begins to assemble other components.
Trang 7Precedence diagram
Precedence diagram: a diagram that describes the ordering in which work elements should be
performed It shows that some jobs cannot be
performed unless their predecessors are
completed The layout of workstations along the assembly line depends on the precedence diagram
Presedence diagram symbols:
Symbol element
Relationship between symbols
Trang 8Precedence Diagram
Trang 9Zoning Constraint
Allocation of work elements at the work
station is also limited by zoning constraints
that preclude or require grouping of certain elements of the work on a particular
station
Trang 10Line Balancing Methods
Helgeson dan Birnie / Ranked Positional Weight (RPW)
Kilbridge and Wester Heuristic (Region Approach)
Largest Candidate Rule
Trang 11Helgeson dan Birnie / Ranked
Positional Weight (RPW)
Step 1- Calculate the weight of the position of each work
elements.
Step 2- Sort the elements according to the weight of the
position of the largest to the smallest.
Step 3 -Calculate the cycle time.
4 Place the working element with the greatest weight on all the workstations do not violate precedence relationships and time station does not exceed the cycle time.
5 Repeat step 4 until all the elements are placed.
6 After forming a work station consisting of its elements, then specify the value of efficient, balance delay, and its smoothest index.
Trang 12Kilbridge and Wester Heuristic
(Region Approach)
Create precedence diagram of the problems faced Separate work elements in the diagram in columns from right to left.
2 Determine the cycle time (TC) of primes total time working elements, and specify the number of work stations.
3 Place the work elements to work stations such that the total time working element does not exceed the cycle time Remove elements of work that has been placed on the list of work elements.
4 When an element of work placement resulted in a total time of work elements exceeds the cycle time working elements are placed in the next work station.
5 Repeat steps 3 and 4 until all work elements are placed.
6 Determine the value of efficient, balance delay, and smoothness index
Trang 13Largest Candidate Rule
The basic principle is to combine the processes of sorting
operation on the basis of the largest processing time to the
smallest elements of the operating time
Steps:
1 Starting from the top, select the element to be assigned to the first station, which meets the requirements of precedence and does not cause the total amount exceeds Tek on stretcher station Ts.
2 If there are no other elements that can be assigned without
exceeding Ts, then move on to the next station.
3 Repeat steps 1 and 2 for the other stations until the completion
of all elements assigned.
4 Determine the value of efficient, balance delay, its smoothness index.