Country and Sector Background The main sector issues were identified in the Bank's energy sector report: "Fueling Vietnam's Development " April 1999 which has been discussed with the go
Trang 1Report No PID10634
Project Name VIETNAM-Vietnam Guarantee Project (@)
Region East Asia and Pacific Region
Borrower(s) SOCIALIST REPUBLIC OF VIETNAM
Implementing Agency
Address MINISTRY OF INDUSTRY Address: 54 Hai Ba Trung St., Hanoi, Vietnam
Contact Person: Mr Hoang Trung Hai - Minister
Tel: 84-4-9349411 Fax: 84-4-9349412 Email: bqlipp-bcn@hn.vnn.vn
Environment Category A
Date PID Prepared September 24, 2002
Auth Appr/Negs Date June 24, 2002
Bank Approval Date October 8, 2002
1 Country and Sector Background
The main sector issues were identified in the Bank's energy sector report:
"Fueling Vietnam's Development " (April 1999) which has been discussed with the government and the Government's strategy to respond to these issues are outlined below : The four main challenges are first, the need for large sector investments to meet the growing energy demand Energy demand has been growing 13 % faster than GDP during the last five years and continued expansion in energy and electricity supply and delivery infrastructure will enable rapid growth in the agricultural and
industrial sectors to sustain economic growth To meet the economic growth targets, electricity supplies will need to grow at about 70 % faster than economic growth rates Second, though Vietnam is a resource rich country,
it should strive to develop the energy sector along an environmentally sustainable path Recent natural gas discoveries offshore provide an
opportunity to make environmentally and economically beneficial energy use choices and the first offshore gas reserves will be piped ashore in 2002 Third, Vietnam has to invest almost 5.3 % of its GDP or twice that its ASEAN neighbors, in essential energy infrastructure Fundamental reform
of the energy tariffs with respect to both level and structure is
required to ease immediate financing constraints and ensure long-term efficiency in the investment and resource utilization decisions throughout the economy Since two thirds of the required investments will need to come from ODA, export credits and foreign direct investments, public
financial resources and government guarantees for private investment
should be selectively used Fourth, attracting foreign private investment will require the creation of a enabling environment and legal framework The Government needs to embark on restructuring and rationalization of the energy state owned enterprises, creating a regulatory system and
Trang 2the energy sector a Need for large sector investments and for
improvement in overall system efficiency: Over the past five years,
electricity demand in Vietnam has increased at an average rate of 13-15 ;
per annum This increase is typical of countries which begin from very low levels of demand To sustain an economic growth projection of about 6-8 t p.a over the next 5 years, Vietnam needs to increase its electricity supplies at the rate of about 10-13 W per annum, calling for an
investment of about US$ 8.3 billion equivalent over the period 2000-2005 This investment represents about 5 W of the projected GDP Financing this increase in electricity supplies requires a strategy to first improve the efficiency of existing systems and second to maximize the inflow of
external sources of capital within prudent limits, as well as increase the amount of self generated sectoral surpluses for investment The Government
is working towards these goals by : (a) promoting energy conservation and efficiency , (b) increasing and structuring electricity tariffs to raise internally generated surpluses; (c) involving the private sector in power
"generation" and developing natural gas supplies; and (d) promoting
equitization of distribution functions.b Low Rural Access to
electricity: Rural electrification is a critical element of the
Government's program to eliminate poverty and redress imbalances in
development Ambitious rural electrification targets have been established and work towards meeting them has commenced The key issues in rural
electricity delivery and management are: (i) securing adequate resources for investments that are economically justified but financially unviable; (ii) defining and implementing methods for rural grid and off -grid
management, maintenance and services that do not overextend central
electricity providers and maximize local participation; and (iii)
designing tariff structures that recover costs without distorting price incentives for local generation and for efficiency The Government is addressing the above issues by: (i) issuing a Rural Energy Policy Paper and preparing national decrees for implementation of the rural
electrification programs; (ii) nominating MoI to promote, coordinate and manage the renewable energy program for the country; (iii) working with the World Bank in designing investment projects for rural electrification that would address the issues noted above.c Managerially and
administratively weak sector institutions: Institutions in the Vietnam's energy sector are managerially and administratively weak Much of this weakness results from inadequate staff skills and organizational systems required to deal with and operate in an increasingly commercial
environment The Government has recognized the problem, and is making slow but steady progress: (a) the government is focusing on staff training with
a view of upgrading the skills base and also to familiarize senior
government officials alternative models of governance and oversight; (b) the government has initiated plans for the equitization of communes and districts The change process is likely to be slow, but positive steps and actions have been initiated.d Lack of a Comprehensive Legal and
Regulatory Framework: Given that the structure and commercial arrangements
in the power sector are evolving rapidly and the participation of the private sector is relatively new, the legal and regulatory framework has not developed adequately to respond to these changes The creation of a credible regulatory entity and a enabling body of regulations for tariff, investment oversight, and rural electrification are key priorities The Government is giving due importance to achieving developing the needed framework and with ESMAP and ADB assistance, it is currently engaged in the (a) drafting of an Electricity Law and (b) the development of an
Trang 3institutional mechanism to perform the regulatory functions.The Project is consistent with the Bank Group's strategy in the sector, the mainstay of which is to promote reform, deregulation, and private sector investment The Government has indicated its commitment to reforming the sector, and works towards: (i) promoting energy conservation and efficiency;
(b)increasing and structuring electricity tariffs to raise internally generated surpluses; (c) involving the private sector in power generation and developing natural gas supplies; and (d) promoting equitization of distribution functions To meet increasing power demands, the Government invited private investors to bid for this generation Project under a
competitive bidding framework The Bank has supported the Government strategy of seeking private sector participation in power generation, and its support has been instrumental in ensuring a transparent framework for such private sector participation The Phu My 2-2 BOT Power Project is the first infrastructure project to be implemented by the private sector through competitive bidding process in the country.The Project is a
combined-cycle power plant to be fired with domestic natural gas and is a part of the least-cost power generation expansion plan in Vietnam It would help avoid power shortages and secure significant economic benefits for the country By enabling the Government to shift costs to the private sector, and reducing the need for public investment in the sector, this Project would help make available scarce public resources for poverty alleviation and social development needs The Project will represent one
of the largest foreign direct investment in Vietnam and should help pave the way for attracting additional private capital investment flows for infrastructure development in Vietnam
2 Objectives
The principal objectives of the Project are to (a) enable Vietnam meet its increasing power demands in a cost-effective and reliable manner, (b) mobilize private sector financing for a large infrastructure project and (c) promote Government's reform efforts by (i) demonstrating a competitive and transparent framework for private sector participation; (ii) promoting commercial discipline; and (iii) paving the way for further private
participation in the sector The proposed Project consists of a 715-MW gas-fired combined-cycle power station to be developed, owned, and
operated on a Build-Operate-Transfer (BOT ) basis by Mekong Energy Company Limited (BOT CO.), a wholly owned subsidiary of the private sponsor
consortium of EDF International (EDFI), Sumitomo Corporation and TEPCO International Under the Power Development Project (CR 2820-VN), the Bank has partially financed the first phase of the Phu My 2 power project as a public project, and has provided technical assistance support for the development of the second phase as a BOT project IDA Partial Risk
Guarantee (PRG) of up to US$75 million in support of commercial debt
financing was offered as an option in the competitive bidding to select private developer consortium for the Project, which concluded in April
1998 The EDFI-led consortium was awarded the Project in January 1999 The winning proposal included the IDA PRG as a critical core component of the financing of the Project.This operation would be the first IDA
Guarantee in Vietnam
3 Rationale for Bank's Involvement
Over a period of several years, the Bank has actively assisted the
Government in formulating a policy to promote private power development in
a transparent and competitive manner Vietnam has only limited access to
Trang 4the international loan and capital markets because of its IDA country status with non-investment grade sovereign credit rating (B1 by Moody's)
It is therefore, mainly dependent on multilateral and bilateral funds for financing infrastructure development Some oil and gas exploration
projects with high and quick returns and foreign exchange revenues have been financed by sponsor equity of international oil and gas companies However, such corporate balance-sheet funding is normally not available for lower-return infrastructure projects such as power generation
projects The limited-recourse debt financing for infrastructure projects has been extremely difficult in Vietnam, due to developing but untested legal and regulatory frameworks to deal with complex contractual
arrangement, perceived lack of creditworthiness of the Government and various agencies serving as contractual counter-parties, foreign exchange convertibility/transferability risks as well as unfamiliarity of
Government bodies towards private project finance and resulted long
delays.The IDA Guarantee would assist the debt financing and therefore the actual implementation of the Project, and would encourage private
participation into the power and other infrastructure sectors where such has been very difficult By guaranteeing the contractual obligations of the Government and its agencies for the Project, the IDA PRG would
mitigate sovereign and political risks for commercial lenders and thereby facilitate the mobilization of long-term debt capital necessary to
implement the Project and offer competitive tariffs The IDA Guarantee would allow for allocation of only non-commercial risks to the Government and commercial risks to the sponsors, unlike sovereign borrowing where the Government takes on all the risks The IDA Guarantee would not create any additional liabilities for the Government other than limited
non-commercial risks already undertaken in the project agreements
Following the Sponsors' request for a Guarantee, and in keeping with IDA's 'lender of last resort' role, BOT CO was asked to maximize other possible sources of finance such as export credits and multilateral programs
without a government counter-guarantee with a view to minimizing IDA
support for only the balance of the financing The IDA Guarantee will help catalyze the largest limited-recourse project finance commercial debt package to date for Vietnam IDA PRGs, compared with IDA credits, are
particularly suited to help governments transition from public to private finance through political risk mitigation and effective risk sharing with project sponsors and lenders The IDA Guarantee, by catalyzing commercial finance, would reduce the amounts of fund resources required by
governments for critical infrastructure investments such as the Project and enable the Government to free more resources to meet other social projects.The IDA Guarantee, in a limited but significant way, has
contributed to the sector reform dialogue in terms of helping to establish
an enabling and sustainable framework for private power projects by
raising the awareness of the stakeholders in the Government toward the need for sector reform
4 Description
The proposed Project consists of a 715-MW gas-fired combined-cycle power station to be developed, owned, and operated on a Build-Operate-Transfer (BOT) basis by Mekong Energy Company (BOT CO.), a wholly owned subsidiary
of the private sponsor consortium of EDF International (EDFI), Sumitomo Corporation and TEPCO International
5 Financing
Trang 5Total ( US$m)
BORROWER $0.00
IBRD
IDA
ASIAN DEVELOPMENT BANK $75.00
IBRD GUARANTEE $75.00
EXPORT CREDIT (UNIDENTIFIED) $190.00
FOREIGN PRIVATE COMMERCIAL SOURCES (UNIDENTIFIED) $140.00
Total Project Cost $480.00
6 Implementation
The Project will be implemented by Mekong Energy Company (BOT CO.), a private company incorporated under the laws of Vietnam by the Sponsors The Government, coordinated through MOI, has negotiated and will finalize the various project agreements EVN will purchase the Project's power capacity and output for resale to users through its distribution PCs PV will supply gas fuel to the Project The Government, through MPI, will provide necessary assurances and guarantees to the Project
7 Sustainability
The sustainability of the Project will be underpinned through a
combination of the following factors: (i) economic benefits to the
Government from the Project with a competitive tariff and which would help
to address needs for increased power generation capacity to sustain
economic growth; and (ii) private sector operation backed by firm
financing commitments and commercial and financial benefits to the
Sponsors
8 Lessons learned from past operations in the country/sector
Learning from the experience with IPPs in other countries, certain
safeguards have been incorporated in the Project design with respect to mitigating sectoral and macroeconomic risks
9 Environment Aspects (including any public consultation)
Issues : The Project is an expansion of the Phase 1 of Phu
My 2 power project financed by IDA under the Power Development Project (CR
2820 of February 1996), for which an EA was previously prepared by IDA The Project does not involve any land expropriation or resettlement Under the RFP of the Project, the Sponsors were required to produce an
environmental impact evaluation report with respect to the facility in accordance with World Bank Guidelines and the Laws of Vietnam The
Sponsors and their consultants have completed a detailed EA in accordance with World Bank Guidelines and submitted such to the Bank for review The
EA will be publicly disclosed and discussed in Vietnam A copy of the EA will be released through the Bank's InfoShop in October 2001
10 Contact Point:
Task Managers
Anil Kumar Malhotra /Suman Babbar
The World Bank
1818 H Street, NW
Washington D.C 20433
Telephone: 84-4-9346600 (Hanoi); 202-473 2029 (Washington)
Trang 6Fax: 84-4-9346597 (Hanoi); 202-477 0218 (Washington)
11 For information on other project related documents contact:
The InfoShop
The World Bank
1818 H Street, NW
Washington, D.C 20433
Telephone: (202) 458-5454
Fax: (202) 522-1500
Web: http:// www.worldbank.org/infoshop
Note: This is information on an evolving project Certain components may not be necessarily included in the final project
This PID was processed by the InfoShop during the week ending
September 27, 2002