Tính toán thiết kế cầu treo dây văng. Tài liệu tính toán của nước ngoài khá chi tiết. dkjádaaaaaaaaaaaaaaaaaaaaaaaaaaaaaâ dddddddddddddddddddddddddddddd dddddddddddddddllllllllllllllllllllllllllllllllllllllll
Trang 1Cable stayed bridges
D J Farquhar Mott Macdonald
Following a brief history of cable stayed bridges this chapter describes the various
materials and forms of construction that have been adopted for the major structural
components of these bridges, focussing in turn on the cable system, the pylon and
the deck By the use of examples the most appropriate use of these materials and
component forms is discussed A step-by-step approach is given for the preliminary
design of the cable stayed bridge from outline proportions of the structure to the
static and dynamic analysis including requirements for erection calculations and wind
loading on stays The dynamic behaviour for the cable stayed bridge includes the
phenomenon of stay oscillation, which is reviewed in detail including discussion of the
various types of dynamic cable response together with the available preventative
measures
Introduction
The use of inclined stays as a tension support to a bridge
deck was a well-known concept in the nineteenth century
and there are many examples, particularly using the
inclined stay as added stiffness to the primary draped
cables of the suspension bridge Unfortunately, at this
time, the concept was not well understood As it was not
possible to tension the stays they would become slack
under various load conditions The structures often had
inadequate resistance to wind-induced oscillations There
were several notable collapses of such bridges, for example
the bridge over the Tweed River at Dryburgh (Drewry,
1832), built in 1817, collapsed in 1818 during a gale only six
months after construction was completed As a result the use
of the stay concept was abandoned in England
Nevertheless, these ideas were adapted and improved by
the American bridge engineer Roebling who used cable
stays in conjunction with the draped suspension cable for
the design of his bridges The best known of Roebling’s
bridges is the Brooklyn Bridge, completed in 1883
The modern concept of the cable-stayed bridge was first
proposed in postwar Germany, in the early 1950s, for the
reconstruction of a number of bridges over the River
Rhine These bridges proved more economic, for moderate
spans, than either the suspension or arch bridge forms It
proved very difficult and expensive in the prevailing soil
conditions of an alluvial floodplain to provide the gravity
anchorages required for the cables of suspension bridges
Similarly for the arch structure, whether designed with
the arch thrust carried at foundation level or carried as a
tied arch, substantial foundations were required to carry
these large heavy spans By comparison the cable-stayed
alternatives had light decks and the tensile cable forces
were part of a closed force system which balanced these
forces with the compression within the deck and pylon
Thus expensive external gravity anchorages were not
required The construction of the modern multi-staycable-stayed bridge can be seen as an extension, for largerspans, of the prestressed concrete, balanced cantileverform of construction The tension cables in the cable-stayedbridge are located outside the deck section, and the girder is
no longer required to be of variable depth However, theprinciple of the balanced cantilever modular erectionsequence, where each deck unit is a constant length anderected with the supporting stays in each erection cycle, isretained
The first modern cable-stayed bridge was the mund Bridge (Wenk, 1954) in Sweden constructed by thefirm Demag, with the assistance of the German engineerDischinger, in 1955 At the same time Leonhardt designedthe Theodor Heuss Bridge (Beyer and Tussing, 1955)across the Rhine at Dusseldorf but this bridge, alsoknown as the North Bridge, was not constructed until
Stroms-1958 The first modern cable-stayed bridge constructed inthe United Kingdom was the George Street Bridge overthe Usk River (Brown, 1966) at Newport, South Waleswhich was constructed in 1964 These structures weredesigned with twin vertical stay planes The first structurewith twin inclined planes connected from the edge of thedeck to an A-frame pylon was the Severins Bridge (Fischer,1960) crossing the River Rhine at Cologne, Germany Thisbridge was also the first bridge designed as an asymmetricaltwo-span structure
The economic advantages described above are valid tothis day and have established the cable-stayed bridge inits unique position as the preferred bridge concept formajor crossings within a wide range of spans The long-est-span cable-stayed bridge so far completed is theTatara Bridge in Japan with a main span of 890 m At thetime of writing (2008) several other bridges are planned,
or are in construction, with main spans in excess of
1000 m, notably the Sutong Bridge (1088 m) and theStonecutters Bridge (1018 m), which are both in China
CONTENTS Introduction 357 Stay cable arrangement 358 Stay oscillations 364
Trang 2Stay cable arrangement
Two basic arrangements have been developed for the layout
of the stay cables:
1 the fan stay system (including the modified fan stay
system)
2 the harp stay system
These alternative stay cable arrangements are illustrated in
Figure 1
Fan cable system
The fan system was adopted for several of the early designs
of the modern cable-stay bridge, including the Stromsmund
Bridge (Wenk, 1954) The method of supporting the stays
on top of the pylon was taken from suspension bridge
tech-nology where the cable is laid within a pylon top deviator
saddle The floor of the saddle is machined to a radius so
that each cable stay anchored in the main span can pass
over the pylon and be anchored directly within the back or
anchor span This arrangement is structurally efficient with
all the stays located at their maximum eccentricity from
the deck and a minimum moment is applied to the pylon
The fan arrangement initially proved suitable for the
moderate spans of the early cable-stay designs, with a small
number of stay cables or bundled cables supporting the
deck There were, however, obvious difficulties, with the
corrosion protection of cables at the pylon head, their
sus-ceptibility to fretting fatigue arising from bending and
hori-zontal shear stresses within the cable bundle and with the
replacement of any individual stay in the event of damage
In addition, when this arrangement was adopted for larger
spans the size of the limited number of cables increased,
eventually becoming uneconomically large and difficult to
accommodate within the fan configuration The anchorageswere also heavy and more complicated and the deck needed
to be further strengthened at the termination point
Therefore when a greater number of stays were requiredthe modified fan layout was introduced whereby the staysare individually anchored near the top of the pylon This
is now the more commonly adopted system In order togive sufficient room for anchoring, the cable anchorpoints are spaced vertically at 1.5–2.5 m Providing theanchor zone is maintained close to the pylon top there islittle loss of structural efficiency as the behaviour of thecable system will be dominated by the outermost cablewhich is still attached to the top of the pylon and anchored
at the supported end of the back span The advantages ofthis arrangement are as follows
n The large number of stays distribute the forces with greateruniformity through the deck section, providing a continuouselastic support Hence the deck section can be both lighterand simpler in its construction
n As each stay supports a discrete deck module, each module can
be erected by the progressive cantilever method without resort
to any additional temporary supports Thus increased speedand efficiency of the deck erection is possible
n The concentrated forces at each anchor point are much reduced
n With the modified fan layout it is also possible to completelyencapsulate each stay, thus giving a double protective systemthroughout its length and, should damage occur, replacement
of the stay can be undertaken as a routine maintenance task
n The large number of stays of varying length and naturalfrequency increases the potential damping of the structure
Freyssinet International has recently reintroduced theconcept of a deviator saddle at pylons in conjunction with
a modified strand system, for use in smaller-span stayed bridges and extradosed bridges The modifiedstrand, known as Cohestrand1, is protected by a poly-ethylene sheath but is filled internally with polymer resininstead of petroleum wax The resin compound is hydro-phobic, resistant to water vapour and oxygen and is capable
cable-of transferring both compression and shear forces from thepolyethylene sheath to the steel wires of the strand Thestrand can thus be continuous through the deviatorsaddle without the need to remove the polyethylenesheath This enables more slender pylons to be constructedwithout having to provide a cross-over stay arrangement.The disadvantages of earlier saddle designs have beenaddressed in that the corrosion protection of each strand
is continuous through the saddle, individual strands arenot in contact and thus not subject to fretting corrosionand the system is replaceable strand by strand The deviatorsaddle is made of a bundle of tubes placed within a largersteel saddle tube All voids between the tube bundles arefilled with a high-strength fibre concrete in the factory If
(a)
(b)
(c) Figure 1 Alternative stay cable arrangements: (a) fan stay system:
(b) modified fan stay system; and (c) harp stay system
Trang 3necessary, the external surface of the polyethylene sheath
can be locally treated, at the saddle location, to ensure
that the friction coefficient between the saddle and the
strand is greater than 0.5 The arrangement of the strands
and saddle is illustrated in Figure 2
This arrangement of multi-tube saddle and Cohestrand1
has been incorporated in a number of bridges worldwide: in
Malaysia, Vietnam, Korea, Lithuania and the Sudan A
typical design is that of the Sungai Muar Bridge, a 132 m
main span cable-stayed bridge in Malaysia
Harp cable system
With the harp system the individual stays are anchored at
equal spacing over the height of the pylon and are placed
parallel to each other This arrangement provides a visual
emphasis of the flow of forces from the back span to the
main span and, in examples that are well proportioned, is
aesthetically pleasing However, the arrangement is not as
structurally efficient as the fan layout and relies on the
bending stiffness of the pylon and/or deck for equilibrium
under non-symmetrical live loading When loading one
end only of the stay system the load may be divided into
symmetrical and antisymmetrical components of loading
The symmetrical loading will be resisted by the triangle of
forces formed by the stays, pylon and deck but the
anti-symmetrical loading can only be resisted by bending of
the deck, the pylon or a combination of both depending
on their relative stiffness This disadvantage can be
over-come by anchoring the back stay cable at approach pier
locations so that any unbalanced load is resisted by the
pier An elegant example of this arrangement is the Knie
Bridge over the River Rhine at Dusseldorf with its single
pylon and 320 m main span
Multiple span bridges
The main concern with multiple-span cable-stayed bridges
is the lack of longitudinal restraint to the top of the inner
pylons, which cannot be directly anchored to an approach
pier Without providing additional longitudinal restraint amultiple-span structure would be subject to large deforma-tions under the action of live load Increasing the stiffness ofeither the pylons or the deck can provide this additionalrestraint However, increasing the deck stiffness will beaccompanied by an unacceptable increase in the deadload and thus, the more practical approach is to stiffenthe pylon A typical example of the stiffened pylon is theA-frame braced pylon shown in Figure 3(a) However,such an arrangement requires a substantial increase in thepylon materials and a much larger foundation An alterna-tive to increasing the bending stiffness of the pylon is theintroduction of an auxiliary cable system to provide theadditional stiffness and stability Two cable systems areillustrated The first system, in Figure 3(b), connects thetops of the pylons and thus directly transfers any out-of-balance forces to the anchor stays in the end spans Thesecond system, in Figure 3(c), connects the top of the inter-nal pylons to the adjacent pylon at deck level so that anyout-of-balance forces are resisted by the stiffness of thepylon below deck level An example of this latter arrange-ment can be seen with the design of the Ting Kau Bridge,Hong Kong, which is a four-span cable-stayed bridge.The disadvantage of such an auxiliary cable system is thatthe individual cables are very long and the large sag will
be visually dominant when compared with the adjacentstay cable plane Special measures are necessary to limitthe propagation of wind-induced oscillations in these verylong stays (see the section onStay oscillations)
Number of cable planesThe cable layout may be arranged as either a single-planesystem or as a twin-plane system
Outer steel tubes
Trang 4The twin-plane system may either be formed as two vertical
planes connected from the edge of the deck to two pylon legs
located outside the bridge cross-section or as twin inclined
planes connected from the edge of the deck to either an
A-frame or inverted Y-A-frame pylon The A-A-frame pylon was
first adopted for the Severins Bridge (Fischer, 1960) The
ver-tical twin-plane system, with its tensioned stay geometry,
pro-vides considerable rigidity between the deck and pylon when
compared with the free-hanging cables of the suspension
bridge Inclined stays further increase the stiffness and
stability of the structure, with the stays and deck forming a
transverse frame Inclined stays are of particular benefit
when adopted for longer spans as they improve the torsion
response of the structure to both eccentric live load and
aero-dynamic effects When comparing the alternative stay
sys-tems, when supporting a deck with low torsional stiffness,
the inclined stay system connected to an A-shaped pylon
will have approximately half the rotation under eccentric
loading when compared with the vertical twin-plane
system The inclined stay system is also aerodynamically
superior, reducing the magnitude of vortex shedding
oscilla-tions and increasing the critical wind speed of the structure
However, the geometry of the inclined stay planes must be
carefully checked in relation to the traffic envelope and the
clearances required may result in an increase in the overall
width of the deck
The single-plane system creates a classic structural form
avoiding the visual interference often associated with
twin-cable planes However, the single plane is not able to
resist torsion loading from eccentric live loading and
there-fore this configuration requires the deck to be in the form of
a strong torsion box A deck section of this form is likely to
have excess resistance to the longitudinal bending of the
deck, particularly when a multi-stay arrangement is used
The single pylon has to be located within the central
median of the carriageway and as such an additional
width of deck is required to provide for the necessary
clearances to traffic
Two outstanding examples of cable-stayed bridges with a
single-stay plane are the Rama IX Bridge (Gregory and
Free-man, 1987) (see Figure 4) and the Sunshine Skyway Bridge
(Figure 5) The Rama IX Bridge crosses the Chao Phraya
River, Bangkok with a 450 m main span and has an
orthotro-pic steel box deck section which is 4 m deep The deck section
carries three lanes of traffic in each direction and is 33 m wide
The Sunshine Skyway Bridge crosses Tampa Bay, Florida
with a 366 m main span and a 4.27 m deep trapezoidal
concrete box deck section The deck section carries two
lanes of traffic in each direction and is 29 m wide
It is possible to combine the use of twin- and single-plane
arrangements in the single structure as incorporated into
the Rama VIII Bridge, Bangkok, completed in 2002
(Figure 6) This bridge has a single inverted Y-pylon with
twin inclined stay planes supporting a main span of
300 m, whereas the back span has a single stay planeanchored directly to a piled abutment
Stay designMany factors must be considered in the design of the staysystem including the characteristic breaking strength andthe effective stay modulus The proportion of the breakingstrength that can be realised depends on the relaxation ofthe stay under permanent loads The irreversible strainarising from relaxation increases rapidly when the perma-nent load in the stay exceeds 50% of the breaking load.The Post-Tensioning Institute (PTI) Recommendations(2001) limit, for normal load combinations, the maximumload in the stay to 45% of the stay breaking load and to50% for exceptional load combinations The French Inter-ministerial Commission on Prestressing Recommendationsfor Cable Stays (2002) limit the maximum load in thestay, at the serviceability limit state, to 50% of the staybreaking load and, at the ultimate limit state, to 70% ofthe stay breaking load This slightly higher loading is
Figure 4 Rama IX Bridge, Bangkok
Figure 5 Sunshine Skyway Bridge, Florida, USA (courtesy Parsons Brinckerhoff )
Trang 5permitted providing detailing recommendations to limit
bending effects due to eccentricity at the anchorages and
cable stay vibration are incorporated into the design
The permissible load in the stay may also be limited by the
fatigue performance of the stay under repeated live load
cycles However, this will depend on the magnitude of the
live load cycles as a proportion of the permanent loads
Thus it is only the most heavily loaded stays of a highway
structure that are possibly limited by fatigue whereas the
stays for a railway structure where the live load has greater
dominance will be much more fatigue sensitive Fatigue
endurance of a component is usually given in a plot of the
stress range () against the number of load cycles (N)
known as the Wo¨hler curve When the Wo¨hler curve is
represented on a log–log scale the plot is represented by a
series of straight lines The PTI Recommendations relate
the design limit to the test acceptance criteria of each type
of stay material, such as strand, bar or wire, and the test
cri-teria of the assembled stay The recommendations for
par-allel wire strand (PWS) and parpar-allel strand are given in
Figure 7 The fatigue endurance of the assembled stay will
not only result from variations in the applied axial
tension but also be influenced by any secondary bending
in the stay, arising from either wind- or structure-induced
vibrations at the anchorage or bending of the stay in a
saddle The response to these factors is extremely important
though complex and varies according to the manufacturing
characteristics of the stay and its anchor Because of this the
PTI Recommendations propose that at least three
represen-tative samples of the stay assembly to be used in a project be
fatigue tested Testing is usually undertaken over two million
cycles The stress range depends on the generic type of stay
being tested but the upper limit of the stress range is always
taken as 45% of the breaking load Acceptance criteria for
the test are based upon a limit to the number of individual
wires in the stay that may break and that a tensile test,
undertaken after the fatigue test, achieves at least 95% ofthe guaranteed breaking load of the stay
The French CIP Recommendations for Cable Stays (2002)include the effect of coincident bending through a modifiedfatigue test whereby the cable specimen is made to deviatesinusoidally from the anchorage centreline at the samefrequency as it is being subject to an axial stress variation.Stay types
Problems arose with the stays of early cable stay bridges as
a result of deficiencies with the anchorage design, steelmaterial problems and inadequate corrosion resistance.The development of modern stay systems has largelyovercome these problems providing designs that minimisebending of the stay at the anchorage face and incorporate
a double corrosion protection system throughout able stay systems include:
Avail-n locked coil (prefabricated)
n helical or spiral strand (prefabricated)
Locked coil stays
Locked coilstays have been incorporated into many of theearliest cable-stay bridges The stays are factory produced
on planetary stranding machines, each layer being applied
in a single pass through the machine and contra-laidbetween each layer The core of the stay is composed
of conventional round steel wires while the final layers
Figure 6 Rama VIII Bridge, Bangkok (courtesy A Yee)
Trang 6comprise Z-shaped steel wires which lock together creating
an extremely compact stay cross-section A typical example
of a locked coil stay is illustrated in Figure 8 Modern
locked coil stays provide all the wires in a finally galvanised
condition and will achieve a tensile strength of up to
1770 N/mm2 The stays are commonly anchored by
zinc-filled sockets although sometimes stays that are sheathed
with a polyethylene protection have their sockets filled
with epoxy resin The largest locked coil stays
manufac-tured to date are the 167 mm diameter stays supplied for
the Rama IX Bridge over the Chao Phraya River, Bangkok
Helical or spiral strand stays
Helical or spiral strandstays, which are illustrated in Figure
9, are also factory fabricated on a planetary stranding
machine similar to the locked coil stay but are entirely
manufactured from finally galvanised round steel wires
The wires are usually of 5 mm diameter with a tensile
strength of either 1570 N/mm2 or 1770 N/mm2 The largestspiral strand stays manufactured to date are 164 mmdiameter, as supplied for the Queen Elizabeth II Bridgeover the River Thames at Dartford
Bar bundlesBar bundles contain up to ten threaded steel bars with atensile strength of 1230 N/mm2 coupled together in 12 mlengths The bars have been conventionally placed within
a steel tube and protected with a cement grout The use ofcouplers connecting the bars will give a much reducedfatigue resistance when compared with the equivalent wire
or strand systems Coupled bar systems are thus rarely usedwhere significant variations in the stay load are likely tooccur Tests have also been undertaken to assess the effective-ness of cement grout as a protective medium These testsconcluded that transverse and longitudinal cracking of thegrout rapidly develops due to temperature effects, live loadstrains and wind vibration It may be assumed that thecement grout provides little protection against corrosion
Parallel wire strand stays
Parallel wire strand (PWS) most commonly comprises
7 mm diameter finally galvanised round steel wires with atensile strength of 1570 N/mm2 PWS stays may either beprefabricated or assembled on site, the wires being installedwithout a lay or helix within a polythene tube and injectedwith cement grout or wax When manufactured without alay the prefabricated stays are difficult to handle and coil
on to the reel and the system also suffers from the doubtsassociated with grouted stays
New parallel wire strand stays
The new PWS system, as illustrated in Figure 10, was oped with a tensile strength up to 1770 N/mm2 The stay isprefabricated and with a long lay helix to improve coiling
devel-on to the reel The largest stays can cdevel-ontain up to 400wires and a coating of high-density polyethylene (HDPE)
is applied in the factory using the continuous extrusionprocess The stays can be socketed using a patented
Figure 8 Locked coil cable (courtesy Bridon International Ltd)
Figure 9 Spiral strand cable (courtesy Bridon International Ltd)
Trang 7system such as BBR’s DINA or HiAm anchorages The
individual wires within these anchorages incorporate
button heads transferring the full load to the anchor The
socket is then filled with a proprietary epoxy compound
that is claimed to enhance the fatigue resistance of the
stay Other manufacturers provide these stays with
con-ventional socketed anchorages filled with zinc or epoxy resin
Parallel strand stays
Parallel strand stays are usually manufactured from
15.7 mm (or 15.2 mm) diameter seven-wire strands, which
are usually galvanised and have a tensile strength of
1770 N/mm2, to give a characteristic breaking load per
strand of 265 kN Some manufacturers also supply strand
with a tensile strength of 1860 N/mm2 The strand bundle
can typically comprise up to 110 strands and anchoring is
by means of a pre-stressing anchor head with individual
strands gripped by wedges In order to provide adequate
fatigue resistance it is essential that rotation of the strands
at the face of the wedge grips, due to changes in stay load or
wind oscillation, is minimised Guides or dampers located
some distance in front of the anchor face provide the
necessary restraint (see the section on Stay flexure at the
anchorage) An outer polyethylene tube covers the strand
bundle, providing protection against impact damage and
prevents dynamic oscillation or rattling of the individual
strands Early designs filled the tube with cement grout or
wax as corrosion protection but in later designs each
strand is manufactured with a continuously extruded
HDPE coating over a corrosion-inhibiting petroleum
wax With this level of protection further cement or wax
injection is unnecessary European and Japanese practice
has been to use galvanised strands but some American
bridges have been constructed using epoxy-coated strand
The risk with epoxy-coated strand is that small pinholes
or minor damage can propagate corrosion, forming a
notch in the strand, which will create a local stress
concen-tration The use of Galfan, a licensed zinc and aluminium
mixture, gives two to three times the protection for the
equivalent weight of zinc coating, but the fatigue properties
of the strand are reduced
The outer covering to the stay has conventionally been
manufactured from steel or polyethylene pipe Where
polyethylene pipe is used, UV resistance was achieved by
the use of carbon black pigment in the material The
design temperature differential between the stays and the
deck or pylon can vary considerably The PTI
Recom-mendations (2001) note that values of 98C and 228C have
been used for white painted or taped stays and black
stays respectively The use of black stays is not preferred,
particularly in tropical zones where there is a high solar
gain Early attempts to wrap the stays, as in the case of
the Pasco-Kennewick Bridge over the Columbia River
USA, where a white plastic wrapping was used, were
unsuccessful as the coating deteriorated within a fewyears Later coverings using Tedlar, as in the case of theSecond Severn Bridge (Mizon et al., 1997), have beenmore successful Subsequently a range of light-colouredpolyethylene pipe has been developed with a high UV resis-tance The pipe is manufactured in a bi-extrusion processwhere a thin coating of light-coloured polyethylene isextruded over a black pipe core
Advanced composite stays
Advanced compositestays are manufactured from aromaticpolymide fibres, abbreviated to arimid, developed byDupont in the 1970s under the trade name Kevlar Kevlar
is manufactured in three grades and has an exceptionallygood strength-to-weight ratio The structural grade
‘Kevlar 49’ has a tensile strength in the range 3600–
4100 N/mm2 and a density of 14.4 kN/m3 Due to its goodresistance to corrosion the material has found favour inthe manufacture of rope for use in a marine/offshoreenvironment An experimental cable-stayed footbridgehas also been constructed in Aberfeldy, Scotland Thestructure, which has a main span of 63 m, utilises Kevlararamid stays, protected with a low-density polyethylenecoating For further information on the use of non-metallicstay systems reference should be made to the chaptertitled Advanced fibre polymer composite structural systemsused in bridge engineering
Stay behaviourThe behaviour of the stay under load must be represented inthe analysis of the structure The modulus of the stay underload is a characteristic of the stay manufacture and a non-linear variation with respect to both stay length and axialtension When comparing the modulus of various types ofstay that are manufactured, parallel wire strand (PWS)achieves the highest modulus at 205 kN/mm2 This isclose to the modulus of the steel wire itself Seven-wirestrand achieves a modulus of some 195 kN/mm2whilelocked coil will be approximately 155 kN/mm2 Themodulus of helical strands will be within the range 155–
175 kN/mm2 The modulus of both locked coil and helicalstrands is variable depending on the lay angle, the galvanis-ing and the stay diameter Factory-produced locked coiland helical strand cable, which are pre-stressed as part ofthe manufacturing process, will give the stays a predictableelongation in service Pre-stressing, where the cable issupported in a bed and preloaded, is the method used toremove the non-elastic stretch, resulting from the initialcompaction of the strand Pre-stressing is not required forPWS or parallel strand stays The non-linear behaviour ofthe stay may be represented by an equivalent modulustaking into account the sag or catenary effect in theloaded stay The variation in the equivalent modulus ofelasticity of the stay (Eeq) is given in Figure 11 and may
Trang 8where E is the guaranteed modulus of the straight stay, L is
the horizontal length of the stay, is the specific weight of
the stay and is the tensile stress in the stay
Allowance must be made during the erection of the deck
for the dead load extension of the stay In the case of a
prefabricated stay this is achieved in manufacture, by
reducing the stay length to compensate for this extension
In the case of the stay fabricated on site, using a strand
system, the calculated extension of the stay is taken up
within the anchorage The length of the stays will also vary
with changes in temperature and it is therefore necessary to
measure the temperature of the stay and deck at the time of
stay installation and calibrate the stay load accordingly
Stay flexure at the anchorage
Some stay systems are designed with rotational adjustment,
through a pin and clevis arrangement, which assists with the
proper alignment of the stay during its erection However,
when the cable is subject to small angular deviations in
ser-vice the inertia of the anchorage components will inhibit the
cable end from rotating and thus the anchorage connection,
whatever arrangement is adopted, should be considered
fixed ended Angular deviations at the anchorage may
arise through a number of cumulative effects as follows:
n installation error when the anchorage is built into the structure
n vibration of the cable stay due to wind and other effects causing
an oscillating rotation at the anchorage
n structural displacements causing a varying rotation of the
anchorage with respect to the stay cable
n varying load in the stay cable due to the effect of imposedloading on the structure causing varying rotation of the staycable at the anchorage due to the catenary effect
When no guide is installed to limit the rotation of the staythe maximum bending is at the face of the anchorage anddecreases exponentially over a characteristic length, whichdepends upon the bending stiffness of the cable Thebending stresses at the face of the anchorage are high, arelocated where they are most damaging, and are typically
of the same order as those for live loading However, theyare identical whether the stay is monolithic, such as with
a spiral or locked coil strand, or is composed of separatetensile components that can slide over each other, such asparallel strand or parallel wire stays Monolithic staysvary from separate tensile components in that the charac-teristic length is much longer and this has to be consideredwhen designing any guide system
To limit these harmful bending effects a guide systemshould be provided at a distance from the anchor face Theguide, acting as a simple support, is usually located at theend of the anchor pipe that is an integral part of the bridgepylon or girder, so that the stay is subject to continuous bend-ing over the guide When adopting a rigid guide, subject to itbeing located a sufficient distance from the face of the anchor,the moment will be reduced by half the original moment atthe face of the anchor However, by manufacturing theguide from an elastic material, typically poly-butadiene,with an optimum spring stiffness designed for each individualcable arrangement, the bending stress in the cable can befurther reduced to a third of the original moment Thiseffect is illustrated in Figure 12
Stay oscillations
A phenomenon peculiar to cable-stay bridge construction isthe effect of stay oscillation During cantilever erection aslender deck may be particularly prone to wind-inducedmovement This can in turn excite the stays, producingviolent oscillations which, in some projects, have had to
Figure 12 Effect of guides on stay anchor bending
Trang 9be restrained with temporary straps In service the
wind-induced vibration of stay cables has also occurred on a
range of cable-stayed bridges under a variety of wind and
traffic conditions Both standing waves and travelling
waves have been observed and these oscillations can reach
amplitudes of more than a metre This behaviour was
reported to have occurred with the Helgeland Bridge
(Svensson and Jordet, 1996)
A cable’s natural frequency for the fundamental mode
may be calculated from the following:
is the cable tension and m is the cable mass per unit length
(Note: It is normal to provide an anchor guide system
which gives an apparent fixity to the cable In this case
the chord length of the cable may be assumed to be the
length between guides at the top and bottom of the cable.)
Cable vibrations can occur as a result of a number of effects
which can be categorised under the following headings:
appropriate measures need to be planned to suppress cable
vibration due to these phenomena
Vortex shedding
This effect is due to the alternate shedding of vortices from
opposite sides of the strand, inducing a periodic load in the
cable As steady wind is required for this effect to occur, the
most damaging vibrations generally occur at low wind
velocities They can be mitigated by reducing or eliminating
the underlying excitation along the lengths of the stay
cables that drives stay oscillation by introducing
projec-tions, or texturing, of the stay pipe This roughens the
surface of the cable and presents an irregular surface to
the wind flow
Vortex shedding is expected to occur when its frequency
becomes approximately the same as the natural frequency
of a stay, that is to say, a wind velocity approaching the
reso-nance-inducing velocity In order to avoid this phenomenon
the French CIP Recommendations for Cable Stays (2002)
require that the natural frequency of stays should not be
the same as the vortex-shedding frequency described below:
where U is the wind velocity, D is the outer diameter ofthe stay and Stis the Strouhal number 0.20 for a circularcable
Wake-induced vibrationsWake-induced vibrations occur when the leeward stay lies
in the wake of a windward obstacle, such as another stay.This effect has most often occurred in moderate winds,which are not turbulent, and the effect is sometimes related
to rain or ice accretion The effect can be mitigated byimproving the cable system stiffness through tying thecables together using cross-cables These couple themodes of the different stays and thus stiffen the combinedcable system so that any excitation causes less oscillationand self-excited modes are avoided This method of mitigat-ing cable oscillation was employed on both the Normandyand Helgeland Bridges
Rain–wind instabilityRain–wind instability results from perturbing the smoothsurface of a stay and has occurred when water rivuletsform on the top and bottom of a stay, with wind in thedirection of the span, and for stays that slope downwards
in the direction of the wind, as illustrated in Figure 13.The French CIP Recommendations for Cable Stays (2002)note the results of research which show there is a possibility
of rain–wind excitation if the steady wind velocity is in therange 8–15 m/s The wind must be from an oblique direc-tion, between 308 and 808 from the perpendicular to thecable, so that the wind will tend to lift the cable Thefrequency of the cable oscillation is typically 1–3 Hz.Below the stated wind speed range, the top rivulet doesnot form because the wind is insufficient to prevent itfrom running down the side of the stay Above the range,the wind forces tend to blow the rivulets off the stay.Wind turbulence also prevents the rivulets from forming
In order to avoid the onset of rain–wind oscillation it hasbeen suggested that the Scruton number (Sc) for the stayshould be at least 10 according to the following formula
Trang 10specified in the PTI Guide Specifications (2001):
m
where m is the mass per unit length of the stay, is the
damping ratio (typically in the range 0.5–1%), is the
density of air and D is the outer diameter of the stay
Rain–wind excitation is therefore unlikely to occur if the
damping ratio satisfies the above formula Where stay cable
pipes have effective surface texturing it has been suggested
that the above requirement may be relaxed such that
Sc55 However, this conclusion is based on limited testing
of regularly spaced stay arrangements and a study by
Jones et al (2003) recommends that a careful case-by-case
evaluation of the above limits be undertaken
Cable galloping
The possibility of galloping oscillations of either single
cables or groups of cables should also be investigated
The PTI Recommendations (2001) propose the following
equation to check if cable galloping occurs:
where c¼ 40 (PTI) and 35 (CIP) for circular cables
The French CIP Recommendations for Cable Stays (2002)
raise doubts as to the validity of the above formula;
how-ever, no other advice is given Clearly, as the wind speed
increases there could be instances of cable galloping
occur-ring, but usually increasing wind speed is accompanied by
the wind becoming more turbulent and in this state the
likelihood of galloping will be reduced
Parametric excitation
Parametric excitation can occur when the frequency of an
applied load, derived from either vehicular or wind
excita-tion of the girder/pylon, causes small vibraexcita-tions of the deck
or pylon cable anchorages which match a stay frequency or
any multiple (harmonic) thereof Stays with an oscillation
amplitude of several metres can occur although these
more pronounced effects are usually when the deck is
poorly streamlined, such as when twin I girders are
adopted The deck anchorages are usually the main driver
for such oscillations but it is possible for an unbraced
pylon to vibrate under wind loading The Øresund Bridge
for example, is reported to have experienced stay
oscilla-tions due to this phenomenon The new Stonecutters
Bridge in Hong Kong has 300 m high pylons which were
originally conceived as tapered tubular steel members
above the deck level However, the transverse frequency
of the pylons was found to be close to the cable frequencies
and consequently vulnerable to parametric oscillation
under longitudinal wind conditions The pylons were
modified to concrete construction, with a composite steelskin, in order to increase the pylon mass and hence their fre-quency It is therefore possible to set limits on the wind-induced motions and frequencies of the girder and pylon
so as to limit or preclude objectionable parametric tion of the stays, by ensuring separation between thedeck/pylon frequencies and the stay frequencies
excita-Rattling
A stay that is made up of a bundle of sheathed strandsexperiences aerodynamic interaction whereby the outerstrands will move in and out of the bundle and slap againstthe inner strands, eventually initiating a general motion ofthe whole cable The solution is to encase the strandbundle within an HDPE pipe and this forms an integralcomponent within all modern stay cable designs
Methods of damping stay oscillationsThere are three methods of damping stay oscillations:
1 incorporating internal and external damping mechanisms
2 texturing the external surface of the cable cover
3 installing stabilising cables
Dampers
The damping ratio of a cable stay is the sum of its intrinsicdamping, which will vary according to the type of stay andthe aerodynamic damping which increases with increasingwind speed The intrinsic damping of a cable stay is lowwith a typical range of 0.1–0.3% (logarithmic decrement
of 0.6–1.8%) Wind–rain instability can be avoided if thetotal stay damping exceeds 0.5% (logarithmic decrement
of 3.0%)
Various devices are available to supplement the cabledamping External dampers are hydraulic devices whichapply a transverse damping force to the stay and aremounted on structures which are fixed to the deck close
to the stay anchorages Internal dampers are ring shapedand placed between the stay and the steel anchorage tubewhich is built into the structure Internal dampers use thedistorsion of a dissipating material (specially formulatedneoprene) or viscous friction or dry friction The object of
a damper is to minimise the amplitude of any cable stayvibration However, unlike a guide, which would com-pletely inhibit cable displacement, a damper must permitsome displacement if it is to effectively dissipate energy
Texture of the stay pipe
Applying a texture to the external surface of the stay isalso an effective method of preventing wind–rain instability
as it helps prevent the rivulets forming long continuouslengths Initially on Japanese bridges longitudinal finswere adopted but when this type of profile is adopted thedrag coefficient increases dramatically to 1.35 Later helical
Trang 11ribs, as illustrated in Figure 14, or a series of random
dimples were used and tests have confirmed that the
recommended drag coefficient of 0.7 is still appropriate
Tests have shown that the helical ribs are more effective
in preventing wind–rain instability than the random
dimples
Stabilising cables
Stabilising or secondary cables stiffen the stay cable array
and can also provide additional damping They are
how-ever of limited effectiveness in preventing wind–rain
instability but can successfully inhibit vertical vibration
modes of the stays arising from parametric excitation
They are less effective in reducing transverse vibration
modes Stabilising cables must be sufficiently pre-stressed
such that they do not de-tension under extreme variations
in structure loading Failures occurred in early designs,
with insufficient pre-stress, where they were subject to
repeated shock following unloading The trajectory of the
stay cables will be modified by the stabilising cables so
kinking of the stay cable at the anchorage will occur The
setting of the rigid anchor tubes at deck and pylon needs
to be corrected so that they follow the modified cable
geometry
Stabilising cables cannot therefore be easily used as a
remedial measure when cable vibration arises, as only
lim-ited pre-stressing of the stabilising cables is possible without
unacceptable modification of the stay geometry of the main
cables leading to anchorage kinks
Summary of preventive measures
Wind and rain instability should be avoided by the
inclu-sion of suitable texturing of the stay cable pipe together
with a minimum Scruton number between 5 and 10,achieved by the installation of suitable damping devices.Long stays (more than 80 m) should have dampersinstalled such that the stay has at least 0.5% damping.Parametric resonance should be assessed at the designstage, by a study of the eigenmodes of both the cablesand the structure When the cable and structure frequencyare close (within 20% of each other) the use of stabilisingcables should be considered
In order to avoid the visual concern of the user it isrecommended in the French CIP Recommendations forCable Stays (2002) that the amplitude of the stays shouldalso be limited Ratios of amplitude to stay length (L) inthe range L/1000 to L/1600 have previously been adopted.Pylons
The pylon is the main feature that expresses the visual form
of any cable-stayed bridge, giving an opportunity to impart
a distinctive style to the design The design of the pylonmust also adapt to the various stay cable layouts, accom-modate the topography and geology of the bridge site andcarry the forces economically
The primary function of the pylon is to transmit theforces arising from anchoring the stays and these forceswill dominate the design of the pylon The pylon shouldideally carry these forces by axial compression wherepossible, such that any eccentricity of loading is minimised.Steel pylons
Early cable-stay pylon designs were predominantly structed as steel boxes, and bridges such as the StromsmundBridge (Wenk, 1954) took the form of a steel portal frame,which was intended to provide transverse restraint to thestay system However, this restraint is largely unnecessary
con-as sufficient transverse restraint can be provided withinthe stay system itself When a single mast supports eachstay plane, any lateral displacement at the top of the mast
is accompanied by a rotation of the stay plane This tion of the stay plane ensures, for the simple fan layout ofstays attached to the top of the mast, that the resultantreaction from the main span and back span stays cableswill pass through the pylon foot The weight of the pylonwill remain vertical but the reaction from the stays willnevertheless be dominant Thus the effective length of themast in buckling will not be that of a simple cantilever,twice times the height (2H), but equal to the height (H).This effect is illustrated in Figure 15 With the harplayout of stays, the loads will be applied at various levelsalong the pylon but similar principles apply An example
rota-of the harp layout is the Theodore Heuss Bridge (Beyerand Tussing, 1955) where one slender strut supports eachcable plane When considering the buckling behaviour ofsuch a pylon, allowance must be made for constructional
Figure 14 Outer sheath for parallel strand stay with helical ribs (courtesy
BBRV Systems Ltd)
Trang 12inaccuracies; typically an eccentricity of 100 mm of the stay
reaction is adopted
In the longitudinal direction the main and back stay
cables will restrain the pylon against buckling providing
the deck, to which the stays are anchored, is adequately
restrained against longitudinal movement The pylon
beha-viour when the deck is allowed to float is illustrated in
Figure 16 When the deck is unrestrained any disturbing
forces can only be resisted by the pylon acting as a
canti-lever with maximum bending at the base Thus the effective
length of the mast in buckling will be twice the height (2H)
When the deck is effectively restrained at either an
abut-ment or at one of the pylons the top of the mast is held in
position by the stays and the effective length of the mast
in buckling will be approximately 0.7 times the height
Con-necting the back stays to an independent gravity anchorage
is an equally effective solution Early cable-stay pylon
designs, such as for the Stromsmund Bridge (Wenk,
1954), incorporated a pin at the pylon foot so as to
ensure that the mast did not have to be designed for large
bending moments Later designs have adopted a fixed end
cantilever mast, which is simpler and also more stable
during erection Nevertheless, the effect of a frictionlessbearing can still be achieved with a fixed end mast providingthe member is sufficiently slender, such that the maximumaxial load approaches the buckling capacity of the mast
in free cantilever As the axial load increases to oneeighth of the buckling capacity, the location of the maxi-mum moment will move up from the base and the basemoment will tend to zero In this condition the mast willoffer no resistance against a longitudinal displacement atthe top In practice the adoption of a particular slendernessmay be limited by the need to maintain stability of the pylonduring construction when restraint from the stays is notavailable
For the single mast pylon supporting a single plane ofstays two methods have been used to connect the mast atits base
1 It can be constructed encastre into a transverse girderforming part of the deck In this case a bearing isrequired on top of the pylon foundation immediatelybeneath the mast and two further bearings at each end
of the transverse girder so as to provide the necessarytorsional restraint to the deck and pylon forces
2 Alternatively the mast can pass directly through thedeck to sit upon the pylon foundation In this caseonly bearings at each end of the transverse girder arerequired and these only have to provide the resistance
to the deck forces
Method 2 is the more efficient of the two and has beenuniversally adopted in more recent designs An example
of the use of this method of support is in the design of theRama IX Bridge (Gregory and Freeman, 1987)
Concrete pylonsConcrete is very efficient when supporting loads in axialcompression Advances in concrete construction andmodern formwork technology have made the use ofconcrete increasingly competitive for pylon construction,despite the much greater self-weight when compared with
a steel alternative Concrete has proved particularly ble to the more complex forms of pylon Many varied types
adapta-of pylon have been developed to support both the verticaland inclined stay layouts These include H-frame, A-frameand inverted Y-frame pylons as illustrated in Figure 17.With the H-frame pylon the stay anchors are normallylocated above the level of a crossbeam and with themodified fan arrangement of stays this crossbeam locationwould be between mid-height and two-thirds of the pylonheight above the deck When the harp arrangement ofstays is adopted the anchors are distributed over the fullheight of the pylon above the deck Therefore, as in thecase of the Øresund Bridge between Denmark andSweden, a crossbeam can only be provided, in practice,below the deck level
H
Figure 15 Transverse deflection of a simple pylon
Figure 16 Longitudinal restraint of the pylon by the anchor stays