Lean manufacturing, sản xuất
Trang 1lean manufacturing system
Toyota Production systems
( TPS )
Prepared by : Hassan Omar Badkook
2009
Trang 2What is lean manufacturing?
Definitions :
► LM is a set of tools and methodologies that aims for the continuous
elimination of all waste in the production process.
► a system approach to identifying and eliminating waste (non-value added activities) through continuous improvement by flowing the product at the pull of the customer in pursuit of perfection
- The main benefits of LM are lower production costs , increased output and shorterproduction lead times
Trang 3Key principles of lean manufacturing
1- Recognition of waste:
- The first step is to recognize what does and does not create value from the
customer’s perspective.
- Any material , process or feature which is not required for creating value from the
customer’s perspective is waste and should be eliminated
2- Standard processes :
- Lean requires an the implementation of very detailed production guidelines, called
(standard work)
- Clearly state the content , sequence , timing and outcome of all actions by workers.
- This eliminate variation in the way that workers perform their tasks
3- continuous flow :
- Lean aims to a continuous production flow free of bottlenecks, interruption
,backflows or waiting.
- Production cycle time can be reduced by as much as 90%
4- pull-production( also called Just-in-time)
- Aims to produce only what is needed , when it is needed.
- Production is pulled by the downstream workstation so that each workstation should only produce what is requested by the next workstation.
Trang 4Key principles of lean manufacturing
5- Quality at source:
- lean aims for
- Defects to be eliminated at the source
- Quality inspection to be done by the workers as part of the in-line production process.
Trang 5History of lean manufacturing
Trang 6Key implications of lean manufacturing
Lean manufacturing
Traditional batch manufacturing
Customer driven Supply driven
Orientation
Orders are pulled through factory based on customer/downstream demand
Orders are pushed through factory based on production plan/forecast
Planning
Small large
Batch size
In-line inspection by workers
Checking of samples by QC inspectors
Quality inspection
Little or no work-in-progress between each production stage
Buffer of work-in-progress between each production stage
Handoff of works-in-process
Total production cycle shortens to approach time spent actually processing the materials
Total production cycle takes significantly longer than actual time spent processing the materials
Production cycle time
Trang 7Lean manufacturing goals
lead times
Trang 8Main kinds of waste
►Originally 7 main types of waste were identified as part of the Toyota
Production System.
►This list has been modified and expanded by various practitioners of lean manufacturing and generally includes the following :
1- Over-production waste:
▪ Unnecessarily producing more than demanded
▪ Producing it too early before it is needed
That will be:
- Increase the risk of obsolescence
- Increase the risk of producing the wrong thing
- Increases the possibility of having to sell those items at a discount or discard them asscrap
Trang 9Main kinds of waste
2 - Waiting waste:
▪ Waiting is idle time for workers or machines due to bottlenecks or inefficient
production flow on the factory floor
▪ Waiting also includes small delays between processing of units
Waiting results in a significant cost insofar as it increases labor costs and
depreciation costs per unit of output
Transportation between processing stages results in prolonging
production cycle times , the inefficient use of labor and space and can also be a
source minor production stoppages
Trang 10Main kinds of waste
- Include walking around the factory floor to look for a tool
- Difficult physical movements, due to poorly designed ergonomics which slowdown the workers
Trang 11Main kinds of waste
▪ Production to incorrect specifications.
▪ Use of too much raw materials or generation of unnecessary scrap.
Trang 12Main kinds of waste
8- Correction waste:
▪ When something has to be re-done because it wasn't done correctly the first time
▪ This not only results in inefficient use of labor and equipment but the act of
reprocessing often causes disruptions to the smooth flow of production and
therefore generates bottlenecks and stoppages
▪ Also, issues associated with reworking typically consume a significant amount ofmanagement time and therefore add to factory overhead costs
9- Knowledge disconnection:
▪ This is when information or knowledge isn't available where or when it is needed
▪ This might include information on correct procedures, specifications, ways to solveproblems, etc
▪ Lack of correct information often leads to defects and bottlenecks
▪ For example, unavailability of a mixing formula may potentially suspend the entireprocess or create defective items due to time- consuming trial-and-error tests
Trang 13JIT/Lean production
Just-in-time
- A highly coordinated production system in which processing and
movement of materials and goods occur just as they are needed (perfect timing), usually in small batches.
- Developed in Toyota® by Taiichi Ohno (Vice president of
manufacturing) in the so-called Toyota Production System (TPS).
- JIT is characteristic of lean production systems where JIT operates with very little “fat”
Trang 14Example : JIT at Hewlett-Packard
How much JIT reduced waste at Hewlett-Packard®
Scrap Setup Time
Trang 15JIT/lean streamlines production
Flow with JIT
Traditional Flow
Customers Suppliers
Customers Suppliers
Production Process (stream of water)
Inventory (stagnant
(becomes like water in stream)
Trang 16Lean manufacturing tools and methodology
►Standard work
►Communication of standard work to employees
►Standard work and flexibility
►Visual Management
►Quality and the source ( or “ Do it right the first time”)
►Value Stream Mapping
►The Five S’s
►Preventive Maintenance
►Total Productive Maintenance
►Changeover/setup time
►Batch size reduction
►Production Layout and point of use storage
Trang 17Lean/JIT Goals and Building Blocks
Trang 18Lean/JIT Building Blocks
Trang 191- product design
►standard parts
- use of standard parts leads to :
fewer parts - reduced training time and costs - routine purchasing and handling - low quality costs
Trang 201.1 standardized parts
Trang 211.2 modular design
Design modular components that can be configured into a wide variety
of end products and services
Modular Drills
Trang 221.3 quality in design
Quality function deployment (QFD) and House of quality
Voice of the customer)(
THE HOUSE OF QUALITY
Trang 23X X
X
X X
Correlation:
Strong positive Positive Negative Strong negative
B A X
BA
X B
A X
B X A BXA BAX
Trang 241.4 concurrent engineering
Trang 252 - Process design
►small batch size
►setup time reduction
Trang 262.1 small batch size
Small lots also increase flexibility to meet
customer demands
Trang 27Benefits of small lot size:
Trang 28orders 10 Lot size = 5 & number of lots = 2 Lot 1 Lot 2
Lot size = 2 & number of lots = 5
Lot 1 Lot 2 Lot 3 Lot 4 Lot 5 Reducing Lot Sizes Increases the Number of Lots
Lot size = 10
Number of lots = 1
Small lot sizes
Trang 29Effect of small lot sizes
Smaller Lot Size
TC
min
Optimal lot size
Small lots sizes increases inventory cost !
How this problem could beresolved ?
Trang 30Unless setup costs are simultaneously reduced
New optimal lot size
Trang 31Average inventory = (Lot size)/2
Effect of small lot sizes
Small lot sizes with frequent orders can reduce average inventory
Q2 when average order size=80,
average inventory is 40
Q1 when average order size=200,
average inventory is 100
Trang 322.2 Setup Reduction
►small lots leads to frequent setups.
►setups should be quick and inexpensive
►short setup require holding less inventory
►worker should be trained to their own setups
►use of standard (modular) fixtures for many type of parts
Standard and modular fixtures
Trang 33Setup Reduction
Trang 34SMED ( Single Minute Exchange Die )
►the concept arose in the late 1950s and early 1960s , when shigeo shingo , chiefengineer of Toyota, was contemplating Toyota’s inability to construct vehicles inmaximally efficient economic lots
►reduced setups – quick change over
Example: use of interrupted
screw , shigeo shingo
Trang 35Setup Reduction steps by shigeo shingo
shigeo shingo recognizes 8 techniques that should be consider
in implementing SMED.
1- separate internal from external setup operations
2- convert internal to external setup
3- standardize function , not shape
4- use functional clamps or eliminate fasteners altogether
5- use intermediate jigs
6- adopt parallel operations
7- eliminate adjustments
8- mechanization
Trang 36SMED / Quick Changeovers
Quick Changeover is a method of analyzing and reducing the time needed tochange a process from producing one good part to producing the next good part
Trang 37Benefits of setup reduction / quick changeover techniques
Trang 38Setup Reduction – Example by shigeo shingo
Machine Starts production
Changeover Time
Trang 392.3 Manufacturing cells
►JIT Objectives : reduce movement of people and material
( movement is waste!)
►JIT requires :
▪ Use work cell for product families
▪ Moveable or changeable machines
▪ Short distances
▪ Improve employee communication
▪ Little space for inventory
▪ Delivery directly to work areas
▪ Use Poka -Yoke devices
Poka – Yoke : fail – safe tools and methods to prevent mistakes
Trang 40Classification of products into families and
manufacturing cells
Products into families
Trang 41Work cell Vs process layout
Saw
Lathe Grinder
Heat Treat
Lathe
Lathe
Heat Treat
Grinder
Grinder Press
1 2
3
4 5
2
6
Saw
Press
Trang 42input
IN
OUTTPS : Toyota Production System
Trang 432-5-Quality Improvement
►Occurrence of quality defects during the process can disrupt the orderly flow of work.
►Problem solving is important when defects occur.
►Never ending quest for quality improvement.
►focus on finding causes of problems.
Trang 44Poka – yoke
Example: One way
to assemble the two
components together
www.campbell.berry.edu/pokayoke
Trang 452.6 production flexibility
►JIT Objective :
- Achieve the ability to process mix of products in a smooth flow
►Obstacle to do that:
- Bottlenecks due to overloads resulted from manufacturing some products
►Guidelines to increase flexibility in JIT:
- Reduce downtime due to changeovers by reducing changeover time
- Use preventive maintenance to reduce breakdowns
- Use many small capacities ( easier to shift capacity than small large capacities)
- Cross-train worker to help clear bottlenecks
- Use off-line buffers ( safety stock away from the production area)
- Reserve capacity for important customers
Trang 462.6 Inventory Storage
►Traditional : Inventory exists in case problems arise
►JIT objective : Eliminate inventory by eliminating problems before they
happen
►JIT inventory goal: Only have the minimum inventory needed to keep
system running
►Tactics :
- Use a pull system to reduce inventory
- Develop just-in-time delivery systems with suppliers
- Deliver directly to point of use no storage
- Perform – to – schedule
- Use group technology
Trang 47Inventory is an Asset or Evil !
►lower inventory level ( sea water level )
Uncover hidden problems (Rocks)
Trang 48Effect of inventory levels
Scrap
Work in process inventory level (hides problems)
High water level (inventory) hides rocks (problem)
Trang 49Effect of inventory levels
Scrap
.
A lower water level ( inventory ) Uncover rocks ( problem) ROCKS (problem)- Late deliveries
- process downtime
- Bottlenecks
- Poor quality
- waste
Trang 503.Personal / organization elements
►worker as assets
►cross-trained workers
►continuous improvement
- kaizen : continuous improvement
- Andon : system of lights used at each workstation to signal problems or
slowdowns
►cost accounting
- activity-based costing:
▪ allocation of overhead to specific jobs based on their % activities
►leadership/ project management
Trang 51Maximum height before Kaizen
Maximum height after Kaizen
Trang 52Production methods & Kaizen
Trang 53Layout before Kaizen
Layout after kaizen
Change-better
Trang 544 Manufacturing planning and control
►Level capacity loading
►Use pull systems
►Use visual systems
►Keep close vendor ( supplier ) relationships
►Reduce transaction processing
►Apply preventive maintenance
Trang 55Andon Board
Green light – Normal operationYellow light – Assistance neededRed light – Line has been stopped
Trang 564.1 level capacity loading
►JIT focuses on achieving stable , smooth production with leveled daily mixed-model schedule
Given : Daily quantity requirements of different models
JIT requires to determine :
►sequencing
►number of cycles per day
►use of small lots
►number of units per cycle for each model
Trang 57Assume the system is required to process 4 models
(A,B,C,D)
D C
B A
Model
45 50
120 100
Daily Quantity
Let the sequence is ( A-B-C-D)
Assume number of cycles = 20 cycles /day
D C
B A
Model
45 50
120 100
Daily quantity
1 3
6 5
Number of units per cycle
15 10
0 0
Extra units (inventory)
What if :
- Number of cycles = 25 or 22 or 23 ?
- Daily quantity has changed by 10 % ? Can you do any better ?
Trang 584.2 pull /push systems
- system for moving work where output is pushed to
the next station as it is completed
Trang 59Push and pull systems
Station 1 Station 2 Station 3 Station 4 Station 5
►parts enter the system from one side and exits from the other side
►when station finishes the part, it pushes it to the next workstation
irrespective is that station free ( idle, or blocked )
►if, for example , T3<T4, parts will begin to build up causing station 4
to be blocked as time passes
Trang 60Push and pull systems
Station 1 Station2Order part production from station 1 (POK)Station 3 Station 4 Station 5
Order part Retrieval from station 1 (WLK)
ProductionKANBAN
RetrievalKANBANPart processing time = Ti
PULL SYSTEM
►to prevent blocking , the successor station requests parts from the
predecessor station The predecessor station starts processing based on
that order the order is called a production ( Kanban ) ( POK ) After
processing the part, it may be ordered to move to the successor station by a
Retrieval Kanban ( WLK )
Trang 61Pull system example
Trang 624.3 Visual systems (KANBAN)
erialscard or other device that communicates demand for worker or mat
KANBAN:
►
from the preceding station
►KANBAN is the Japanese word meaning “signal” or “visible record
►Paperless production control system
►Authority to pull, or produce comes from a downstream process
Trang 63Kanban System
Trang 644.4 traditional and tiered supplier network
►suppliers do not cooperate
►each works directly with the company
►supplier have no motivation for improvement
►no distribution of responsibility
Traditional
Trang 65Tiered supplier network
First Tier Supplier
Second Tier Supplier
Third Tier Supplier
Tiered
What a tiered system would provide ?
Trang 664.5 reduce transaction processing
Trang 674.6 preventive maintenance
►maintaining equipment in good operating conditions
►replacing parts that have tendency to fail before they actually fail
►housekeeping
▪ maintaining a workplace that is clean and free of unnecessary materials
Trang 685 S’s ( workplace organization )
Self discipline
Sort
StraightenSweep
Standardize
Clean machines,
floors, walls ,and
looking for sources
Keep everything that is needed in
an orderly fashion
so that things can
be accessed easily
Trang 69Example : good housekeeping
www archive official-documents co uk
Trang 70Standardized Work
Establishing precise procedures for
each operator’s work in a production
process, based on three elements:
products must be made in a process
in order to meet customer demand
2 The precise work sequence, in which
an operator performs tasks within
takt time
3 The standard inventory, including
units in machines, required to keep
the process operating smoothly
Standard Work Board