The purpose of this Method Statement is to describe the methodology involved in site clearance and preparation work at the approved area for site access in accordance with the technical standard and HSE requirements of Vân Phong Thermal Power Plant Project.
Trang 1
Page 1 of 2
Date
Status O/C
*
Remarks
1 Contents / Page
1 General comment: While this is a pre-construction phase document one aspect which is not addressed
and which is of concern is that of first-aid / medical care What should be reflected in this document and in other method statements is how incidents requiring first-aid or medical care will be managed
as we understand that there is currently no medical station or nurse on site
Information of first-aid / medical care has been updated on Section 7.1 Health, safety and environment management
Responsibilities Where are these documents?
Should at least be noted as reference documents
We understand that the overall HSE for the project / site will only be submitted after NTP As this is pre-construction activity, HSE could be referenced as
per section 7 below
Noted and deleted ‘safety requirements’ on this sentence Additional HSE requirement and action plan has been updated on Section 7.1
Preparation ‘providing relevant documents’ Where is this detailed? List of required relevant documents has been updated
Closed
Noted What are these "project specifications"and where can we find them?
All documents/processes NOT detailed herein need to be referenced and shall be documents the Owner has reviewed and approved of
Alternatively if this is a stand alone procedure, then please ensure that it is complete Simply deleting parts of it does not satisfy the requirement
Closed
Trang 2Page 2 of 2
4 7 Environment,
Health and Safety (EHS)
1 EHS officer shall ensure compliance with EHS requirements
2 First aid / medical station and the actions to be taken in case of an incident where someone is injured In site clearing and grubbing there are risks
of foreign objects in workers eyes, or lacerations and so on How will this be managed?
3 Environmental "damage" What is the procedure
to be followed in the event of a diesel or oil spill?
4 Who shall be informed in the event of an incident
1 Noted and modified
2 Plan for first aid and treatment including emergency hospital contact point has been updated To protect worker eyes, face mask shall be worn as described on Section 7.1
3 Procedure to be followed in the event of
a diesel or oil spillage has been updated
4 It will be reported as below sequence;
EHS officer and manager - Site manager - Owner
5
Additional Notes (if any)
* O - Open, C – Closed
Closed
Closed
Closed
Noted Accepted as temporary procedure For site work we would expect proper oil spill kits
to be kept at selected location around the site and all oil spill notified to the Owner
immediately.
Trang 3B 14-Jun-2019 For Approval JH CHOI ET KIM ET KIM
OWNER
VAN PHONG POWER COMPANY LIMITED
PROJECT
Van Phong 1 BOT Thermal Power Plant Project
OWNER ’S ENGINEER
Pö yry Switzerland Ltd
Status
□Approved
□Approved with Comment
□Not Approved
□Reviewed
EPC CONTRACTORS
IHI –TESSC–CTCI–DHI CONSORTIUM
PROJECT DOCUMENT No
VP1-1-L4-C-GEN-10003
REV
B
DOCUMENT TITLE
METHOD STATEMENTS FOR SITE CLEARANCE AND PREPARATION WORK
EPC
Doosan Heavy Industries and Construction
EPC DOCUMENT No
VP1-1-L4-C-GEN-10003
REV
B
For Approval
Documents during LNTP
Approved
Contractor to revise the correction and resubmit
Revise the correction and resubmit before proceeding
Revise and resubmit Not accepted as submitted.
Information acknowledged with no comment
Information acknowledged with comments
Information acknowledged Note: Approval or comment does not relieve the Contractor of Civil
Deemed as “AP” – For Approval DA
Resubmit For Approval (AP)
Deemed as “RE” – For Review DR
Resubmit For Review (RE)
Deemed as “I” – For Information DI
Resubmit For Information (I)
Discipline:
Date:
ü
all obligations covered under contract
PM 26.06.2019
Approved
Contractor to revise the correction and resubmit
Revise the correction and resubmit before proceeding
Revise and resubmit Not accepted as submitted.
Information acknowledged with no comment
Information acknowledged with comments
Information acknowledged Note: Approval or comment does not relieve the Contractor of Civil
Deemed as “AP” – For Approval DA
Resubmit For Approval (AP)
Deemed as “RE” – For Review DR
Resubmit For Review (RE)
Deemed as “I” – For Information DI
Resubmit For Information (I)
Discipline:
Date:
ü all obligations covered under contract
Trang 4Rev B 1 of 9
CONTENTS
1 PREFACE 2
2 SCOPE 2
3 REFERENCE DOCUMENT 2
4 SCHEDULE & EQUIPMENT 2
5 RESPONSIBILITY 3
6 PROCEDURE AND SEQUENCE 3
7 HEALTH, SAFETY AND ENVIRONMENT 6
Trang 5Van Phong Thermal Power Plant
1 PREFACE
The purpose of this Method Statement is to describe the methodology involved in site clearance and preparation work at the approved area for site access in accordance with the technical standard and HSE requirements of Vân Phong Thermal Power Plant Project
2 SCOPE OF WORK
This method statement shall apply for site clearance and preparation work in assigned area where it require
to cut and uprooting the tree, remove grass and remainig construction remains such as brick and concrete
3 REFERENCE DOCUMENTS
Exhibit B1 Technical Specifications
4 SCHEDULE & EQUIPMENT
1
1.1.1 Mobilization of equipment and manpower at site, preparation of Temp Facilities
1.1.2 Cutting trees
1.1.3 Grass and removing stubs
1.1.4 Transport cut tree and grass to disposal area
Remarks
PROJECT SCHEDULE
2019
Temp Site Office
Working Area
Spelling ?
Trang 6Rev B 3 of 9
- Number of equipment may increase or decrease based on actual site condition
5 RESPONSIBILITIES
It is overall responsibility of Site Manager to organize resources prior to perform construction activities
as per project specification in compliance with the quality, schedule & safety requirements
HSE Manager will ensure in coordination with Site Engineer that all measure/construction taken shall be maintained till completion of job
It is the responsibility of Construction Manager/Site Engineer that construction activities are executed in accordance with this method statement and project specification
6 PROCEDURE AND SEQUENCE
6.1 Site Preparation
Prior to entering the working area, all equipment and machinery will be inspected by safety personnel Safety personnel shall be responsible for preparing and providing relevant documents such as related certificate and insurance document for equipment prior to entering into the site
Provide all necessary Personal Protective Equipment (PPE) to the manpower and enforce them to wear
Remark
CONSTRUCTION EQUIPMENT
2019
Site Survey
Cutting Tree & Grass
Collect Tree, Grass and Household Waste
Remove Tree, Grass and Household Waste
Trang 7Van Phong Thermal Power Plant
and use this at all times during the work Worker for tree cutting shall wear face mask to protect eyes to avoid any risks of foreign objects into workers eyes
All machineries, equipment and material shall be access through the designated entrance gate
Temporary container site office together with its machinery storage area will be setup at the designated location shown on 1 PREFACE
6.2 Survey
Check existing bench marks where have been installed during soil investigation period
Install pole with flag on the site boundary
6.3 Cutting Tree and Grass
The bulldozer cuts small trees and grass and uses cutting saws and excavators to cut large trees
Cut tree and grass will be collected and temporary stocked at site until approval of disposal area by
Ninh Phuoc PC and Ninh Hoa district (expected temporary stockpiling period : 1~2 month)
6.4 Analysis for Erosion Risk by Storm Water
Considering site elevation is high along existing public road, storm water will not flow to outside project
Instead it will flow to south-east direction
Trang 8Rev B 5 of 9
In addition, tree cutting will not make any influence on erosion, because density of tree along public
road is quite low
During heavy rain at site, the Contractor shall keep monitoring site condition not to make water ponding
near slope, and take immediate action by excavator, if any damage detected
Sloped protective devices such as slope cover sheets and temporary open trenches shall be considered
in the following cutting and filling steps
Expected flow of storm water
6.5 Transportation of grass and tree to disposal area
Cut tree and grass will be transported to the proposed disposal area and the area shall be approved by the local authorities prior to commence disposal activities
6.6 Household waste at site
There are household waste at site in many different location, and those wastes will be collected and treated by licenced waste treatment company
Public Road
Trang 9Van Phong Thermal Power Plant
7 HEALTH, SAFETY AND ENVIRONMENT (HSE)
7.1 Health, safety and environment management
• HSE Officer shall monitoring and corporate with Site Engineer to ensure that all work is undertaken
following HSE Regulation
• HSE officer shall ensure that all new manpower understand the health and safety general requirements and
attend HSE induction training prior to being allowed to commence work
• All personnel should be aware of assembly points, escape routes, emergency contact numbers A notice
board with site map, relevant special locations and emergency evacuation route be placed at site by the
Contractor
• Site Engineer shall carry-out daily tool box meeting and safety talks with Safety Staff assisted
• Personal Protective Equipment (PPE) shall be worn at all times during the working shift
• Material, equipment transfer to the site shall be stock tidily at the designed area Housekeeping activity is
applicable to all personnel at site to reduce the risk of injury and create safe working conditions
Housekeeping shall be monitored by the HSE officer, and work will be temporary stop until completion of
housekeeping, if HSE officer has found any failure to fulfill this obligation
• Oily material shall be stored with tray and fire extinguisher at the restricted designed area If leaks occur
while filling the fuel, it shall be reported immediately to the Owner and resolved with care Contaminated
soil is collected after removing oil and/or fuel through sand and adsorbent, and is disposed by a hazardous
waste disposal company
• Construction wastes shall be segregated and disposed to an approved dump yard area
• Ensure all workers and equipment working overtime are properly accounted and obtained permit/approval
from HSE Manager prior to carry-on works
• Prior to commencement of Work, the Contractor shall monitor and report the status of existing houses,
garbage, waste materials, farms, any activities of cultivation, etc to the Owner and related local authorities
Pls attach Organisation chart of HSE team
Pls submit license/ permit for dumping yard before dump-ing work.
All site personnel must be trained
as per application law's require-ments (E.g.Decree No 44/2016/ ND-CP) before commences of work
Trang 10Rev B 7 of 9
• The Contractor shall install sign board of construction notice and control site access to avoid any conflict and accident with local people Watchman will be arranged near working boundary area
• The VP1’s target is zero incidents and accidents to achieve the objective of no harm to people In case any incident or accident is detected at site, it shall be immediately reported to HSE officer and manager It is recognized that incidents will occur, and any incidents that do occur will be investigated by the management and a report issued, but the objective is clear, zero harm to people and to prevent recurrence
Reporting line : Incident / accident HSE officer and manager Site manager Owner
• For minor accidents in the field, the medical kit is placed in the container field office Accidents more than normal injuries are sent to the following hospital according to the degree of accident
Trang 11Van Phong Thermal Power Plant
7.2 Job Safety Analysis
Safety regulation non-compliance Choose competent personel with full personel
documents required Roofcause for accident Conduct oriental and specialize training for task Cause harm to workpartner Issue and guide with SWP for safety executing
Provide PPEs and inspected-tools for task Mobilized Equipment
lacking quality Accident roofcause
Choose suitable equipments with full documents and certicates Pre- inspection before allow entering the site Roofcause for accident Check operator status and his certificates
obstruct and damage/ harm personel Stocpike materials tidyly in a designed area, secure.
Put sign board if possible
Slip, trip and fall Do not stack material obstruct the convoy or walkway
Stab and cut Tidily and tie if required Cover the sharp-side expose Unproper Access Personel Injury Ensure safe access is provided to personel, use
barricades , sign board Vehicle Collision, hit Set individual convoy route Set Sign board and
warning board if possible Securing the executing area with barricades
Bankmen and Operators using equipment to be advised
of any personel within excavation area
Personel injury
Set bankman / flagman for the crowed workforce with workers and vehicles execute together
Executing under the working range of the excavator is prohibilatied
Set barricades with signboard to prevent any intruders
if possible
Property loss, accident, collission, hit
Operator must pre-check equipment before starting workingshift
Repair or maintenant any damage or broken
Keep focus only for job and retrict using phone
Follow guiding signals from bankman/ flagman if present
Vehicle lean , stuck or turn over Loss property, damage
Engineer must inspect the site condition and situation and set proper plan for vehicle travel and operate
Any risk or hazard area like deephole, un-balance area must be inform at the TBM to the operator
Operator must keep clear vision and focus on their job
Phone using during the operating is retricted
Material stockpike hazard
Unproper Convoy
Vehicle collision, hit personel
Mobilized Laborers untrain and unskill
The maintenance act should
be located at designated
area with proper
environ-ment protection measure
Roofcause?
oriental?
Designated?
Improper
Convoy?
Personnel? or Personal?
Spelling
Shall be STRICTLY
FORBIDDEN This is
ille-gal in Vietnam and should
be illegal on site Anyone found breaking this rule shall be immediately re-moved from site and not allowed to return
Trang 12Rev B 9 of 9
Oil / fuel leak Environment Contamintion
Pre-inspection vehicle before entering the site Precheck vehicle before start workingshift
Repair and maintenant any damage or broken
Oil/ fuel musst store at an individual area with driptray Refill act must using a funnel-sharp inlet and prepare a plastic sheet or tray beneath to collect any leaking
Chermical -absorbed material must be collected right away in an individual pack and treat it follow Hazardous waste method
falling to deephole Personel Injury
Work area must be isolated to prevent any intruders after excavate to remove the root Backfill and level the excavated hole after removing root if possible
Snake attack Poison , body injury
Set recon team / watch team with safety boots and long stick to make sound and tremor rapidly to chivy snakes
Safety boots and hard gloves is only option for manual activity
Bust and cut tree shall be gathered as sum and loading righ way
If bush and cut tree be stock at site overnigh, Loading
to truck must cary out by excavator; manual disposal not allow
Nighshift 's manual activity not allow
In case of snake bite occupation, Tightly tie the upper part and sent the victim to the nearest merdical center / hospital ( 15 mins away ) for emergency medical treatment
Fire and burning Body injury , loss property
Smoking is restrict at workforce Every vehicle must have been supplied fire extingguishers to prevent and stop any flak or pre-burn case
First Aid Case Minor Personnel injury
Prepare a Medical Kit at site office Any personel got any minor injury must come to the office to report and get the First aid tratment
Medical treatment case Personel Injury
Founder contact to report righ away to the Site management Board
Send the victims/ Injuried Person to the nearest Medical center / hospital
Oil fueling act should be used oil tank truck with electrical pump or manual pump and
How would you "isolate" a hole?
In the case of snake bite,
it is useful to identify the
snake as this aids in
treat-ing the victim If possible
a photograph of the snake
would be useful
The site should be a
non-smoking area with
desig-nated smoking areas at
various locations around
the site This way the
problem is avoided
Spelling
Spelling