Method Statements for Test Pile of Access Trestle andCoal Unloading Jetty_The purpose of this Method Statement is to describe the methodology for structural work of Method Statements for Test Pile of Access Trestle andCoal Unloading Jetty and to details out the steps to be taken in meeting the technical requirements of Van Phong 1 thermal power plant project
Trang 1
Page 1 of 31
Project Title Van Phong 1 BOT Thermal Power Plant Project
Document Title Method statements for test pile of Coal Unloading
Jetty
Document Type For Approval
No Section
/ Page
Date
Status O/C * Remarks
1 1 04/02/2020 The Contractor shall verify pile designs by installing
preliminary piles or by using permanent piles to:
• Review and check the pile lengths necessary to satisfy the Contractor’s design;
• Assess the skin friction and end bearing components of soil resistance;
• Calibrate pile dynamic testing against static test results;
• Calibrate pile dynamic driving formula against static test results, hammer types and settings and hammer energy delivered to the pile as obtained from
dynamic testing;
• Review the Contractor’s pile installation method
Those purpose of preliminary piles test shall be incorporated in this MS, and the report should clearly mentioned result of each above items
06/03/2020 Closed
26/02/2020 DHI confirmed that pile designs will be verify by preliminary pile
Trang 206/03/2020 Closed
26/02/2020
Trang 3
Page 3 of 31
3 1 04/02/2020 (1) Number of test piles, locations and theoretical
bearing capacity calculation to be provided
06/03/2020 (1) Noted
10/04/2020 (1) Cal for Prelim test pile Coal Unload Jetty&Access Trestle still not approved.
04/02/2020 (2) Item 3.2 manpower: Accuracy of test results are critical then Cvs/experiences and qualified certificate
of key persons be shown
(4) item 5.1: Provide reference for 100% and 200%
DWL And no tensile and lateral test carried out be subject to approval by the VPCL
(5) item IV Pile driving: pile driving stop criteria not clear Noted that refusal paper use for piling record should be applied to see the rebounce during final blows
06/03/2020 (2) Noted (4) Noted (5) Noted 04/02/2020 (6) Item 5.5.2: in case load reach to the maximum test load but total displacement still not reach to 10%
pile diameter, continue loading to be asked Please describe more
06/03/2020 (6) termination of loading: when load up to maximum test load but total displacement still not reach the ultimate 10% of pile diameter, it is recommended that to increase load to the failure to estimate actual
26/02/2020 (1) Number of test pile, locations and theoretical bearing capacity calculation is shown in
attachment 01, 02
29/04/2020 VP1-0-L4-C-UZR-05700 Calculation prelim TEST PILE, COAL UNLOADING JETTY AND ACCESS TRESTLE has been approved by 16 April
(2) Test will be done by laboratory staff whom has been got approved by document No VP1- MOC-003
(4) Reference for 100% and 200% DWL is shown in attachment 02 Testing pile work and due to TCVN 9393:2012
(5) This comment will be clearly by construction drawing and method for pile driving which will be submitted by separate document
(6) In case of load, DHI will be carried out following the ASTM D1143M
06/03/2020 10/04/2020
Trang 410/04/2020 (6) Noted and subject to approval of VPCL.
(7) This MS cannot used for site construction since there does not support information for quality control
of site welding for steel pile connection (if applied) as well as detail measurement of rebound value as per approved calculation.
31/03/2020 DHI has updated load up to 250% and revised
on this MS (rev c)
29/04/2020 Test pile material shall not weld at site Rebound measurement shall be conducted by total station machine/ leveling machine, Rebound record has been mention on ITP
Closed
26/02/2020 DHI has added the attachment to the MS Rev B 06/03/2020 C
Closed.
Trang 5
Page 5 of 31
5 2 04/02/2020 - Clarify the sequence of piling test: when will start
axial static test and PDA test? Which one is previous test?
- Based on result of Test, the Contractor propose the another formula (for example Hiley formular) or conventional pile refusal method to identify the pile bearing capacity without PDA test or axial static loading test that is important during mass piling work period This matter should incorporate in "Piling Criteria" document for review and approval before start driving permanent piles
06/03/2020 Closed 04/02/2020
- Axial static pile test should be performed for both of compression and tensile that depend on design (If pile foundation is under high horizontal force; it is also considered horizontal load test)
06/03/2020 Open:
Please provide more clear explanation and review Part III-2 Exhibit B1 Tech Spec Section 8, item 8.8.2 Piling
10/04/2020 Closed
- DHI will note this issue
26/02/2020
- According to calculation sheet what mention in attachment 02 the tension tests no need to carry out
02/04/2020 According to Section 9.8.4.6 of technical Specification about Pile testing where is describing the requirement for Marine work, and Contractor considered such requirement of contract
Trang 6
Page 6 of 31
04/02/2020
- Add the introduction of construction structure;
specially geology condition at pile test location;
- Pile test location is at opened sea; therefore, the working condition should be insisted clearly (wave, wind, current,) in order to ensure the high quality of test result and labour safety issues
06/03/2020 Closed
26/02/2020
- DHI has revised content of this MS, this comment will be clearly on pile driving method which will be submit in separate document
- DHI has revised content of this MS, this comment will be clearly on pile driving method which will be submit in separate document
6 3 04/02/2020 No horizontal load test for vertical pile and raking
pile?
06/03/2020 Not agree, attachment 2 show the calculation of reaction pile, not test pile
10/04/2020 Closed
26/02/2020 According to calculation sheet for testing pile what mention in attachment 02 the tension tests
no need to carry out 02/04/2020
In calculation structure for piling work, the displacement and bending moment of piles have
a limitation not exceed the allowable value, therefore the lateral load test for single pile is not necessary
Test scheme is explained in 05700_A_CALCULATION FOR PRELIMINARY PILE TEST
VP1-0-L4-C-UZR-06/03/2020 10/04/2020
O
C
7 3 04/02/2020 The Testing loads for test pile shall be in accordance
to maximum Pile bearing capacity in pile design
Contractor to submit Pile design calculation report 06/03/2020
Open, it is not the calculation of bearing capacity of test pile
10/04/2020 Closed, However the test load should be refer to document
no VP1-0-L4-C-UZR-05700 which pile load capacity calculated base on soil condition
26/02/2020 DHI has submitted the calculation (refer to attachment 02) which was mention pile bearing capacity
02/04/2020 Test load is determined based on calculation structure for Coal Unloading Jetty which mention
in document No VP1-0-L4-C-UZR-05001.
06/03/2020 10/04/2020 08/05/2020
O
C
C
Trang 7
Page 7 of 31
8 3 04/02/2020 Refer to related document for Access trestle and
Coal Unloading Jetty such as design calculation, drawing, method, MAR, third-party for Testing information,
06/03/2020 Closed
26/02/2020 DHI has revised and updated on MS Rev B (Section 1.6)
9 3 04/02/2020 - Add the standard TCVN 9393:2012 Pile – Standard
test method in situ for piles under axial compression load
- Add the standard TCVN 11321:2016 Pile high strain dynamic testing for reference
- Add the standard TCVN 9394:2012 Pile driving and static jacking works – Construction, check and acceptance for reference
- Add the standard TCVN 10304:2014Pile foundation – Specification for reference
- Add the standard TCVN 9245:2012 Steel pipe pile
- Add TCVN 10318: 2014 Steel pipe piles and steel pile sheet pile for port harbor – Specification for construction and acceptance;
- Add TCVN4253:2012 Hydraulic structures – Foundation of hydraulic projects – Design standard
- Add TCXD 88: 1982 Pile method of site testing 06/03/2020
Closed
26/02/2020 DHI has revised and updated on MS Rev B (Section 1.6)
Trang 8
Page 8 of 31
10 3 04/02/2020 Please clarify what is this equipment definition based
on Vietnam Maritime Code No 95/2015/QH13 and decree No 171/2016/ND-CP, are there any other specifications, standards, regulations for this equipment, please mention for our information and supervision? How to know structural platform with the hammer assembled fit with the barge? Are there any confirmation from authority?
06/03/2020
OPEN please clarify what is this equipment (Watercraft, floating warehouse, movable platform or floating dock) based on on Vietnam Maritime Code No 95/2015/QH13? How to know structural platform with the hammer assembled fit with the barge? Are there any confirmation from authority? Please reflect it detail in this document as it it an integral part for site implementation and supervision
10/04/2020 Closed
26/02/2020
In this case, DHI has got confirmed with Authority that all document relation with each equipment definition base on Vietnam Maritime require which mention on 95/2015/QH13 and decree No 171/2016/ND-CP
02/04/2020
Base on Vietnam Maritime Code No 95/2015/QH13, Equipment for piling work is movable platform.
structural platform with the hammer is shown in the verification certification of Phu Xuan 17 which is submitted when equipment is delivered
to the site.
06/03/2020 10/04/2020
O
C
11 3 04/02/2020 Please provide more detail equipment such as
leader length of piling barge, capacity of crane on barge
How about drilling machine, drilling barge?
06/03/2020 Closed
26/02/2020 Detail equipment shall be provided on certification when equipment’s are mobilized to the site
DHI has updated Drilling machine and barge to
MS Rev B (Section III)
26/02/2020
DHI will dispatch HSE to supervise this activity 06/03/2020 C
Trang 9
Page 9 of 31
14 4 04/02/2020 Basically, the number of test pile with exactly
location, estimated pile length, tip elevation, cut off elevation should be designed and calculation first
Base on the design and soil condition, the Contractor will propose pile driving method and testing procedure to verify the calculation and decide the final pile length
06/03/2020 Closed
26/02/2020 Well note, this comment will be mention clearly
on the design document
15 4 04/02/2020 Clarify recommended for use only “Driving method
by diesel hammer machine will be applied” for Access trestle, no use “Driving – drilling – driving method”? (In the Details of test pile-Page 8, Length
of Pile test for Access trestle (50m) is longer than Wharf (42m)
06/03/2020 Closed
26/02/2020 Well note, this comment will be clearly on method of pile driving which will be submitted on
separate document
16 4 04/02/2020 Any plan to prevent oil spread to the sea due to
diesel hammer is quitted challenge during pile driving for environmental issue?
06/03/2020 OPEN Please detail what document for information, please be noted that the oil can spread to the sea in the time of test pile work due to diesel hammer so the the oil spreading prevention must be submitted pertaining to this method statement,
This are also one part of mitigation environmental control, please do not separate out of this document
10/04/2020 Closed
26/02/2020 Well note, this comment will be clearly on method of pile driving which will be submitted on separate document
29/04/2020 DHI has revised and updated on MS Rev D – Attachment 6
02/04/2020 DHI has mention on MS rev C (section 6.2, please refer)
06/03/2020 10/04/2020
10/04/2020
O
O
C
Trang 1026/02/2020 Pulling force not act on pile of Access trestle
02/04/2020 Please refer to calculation for Access Trestle
No VP1-0-L4-C-UZL-05002 which has been submitted to Owner in separate document.
06/03/2020 10/04/2020
O
C
04/02/2020 Please be noted that, according to "Part III-2 Exhibit B1 Tech Spec Section 9, item 9.8 Piling", one of purpose for installation preliminary piles is to review the Contractor's pile installation method In case the Contractor's proposed method is not suitable or fail, the Contractor shall propose other driving method for review and approval
06/03/2020 Closed
26/02/2020
19 4 04/02/2020 The Contractor shall keep complete and accurate
pile driving records in a standard format with all necessary information to verify the design calculation 06/03/2020
Closed
26/02/2020 DHI has noted, and this comment will be clearly
on method of pile driving which will be submitted
on separate document
20 5 04/02/2020 Is this for Access Trestle pile ?
06/03/2020 Closed
26/02/2020 This work for all pile which should be braced after first driving and this comment will be clearly
on method of pile driving which will be submitted
Trang 1106/03/2020 Closed
26/02/2020 DHI has revised and updated on MS Rev B (Attachment 02)
Design and calculation of anchor pile is shown Attachment 02
23 5 04/02/2020 The Contractor to update all figure showing actual
pile test and anchor pile arrangement for clarity 06/03/2020
Closed
26/02/2020 DHI has revised and updated on MS Rev B (section 1.4)
24 5 04/02/2020 There is no step of assemble the steel pile into the
head of the hammer, please describe this step with safety countermeasure
06/03/2020 OPEN Please be noted that there is high risk step, it is not acceptable if there is no safety countermeasure for this step in test pile time
10/04/2020 Closed
26/02/2020 The step of assemble the steel pile into the head
of hammer is shown in MS for pilling work which will be submitted in separately document
02/04/2020 DHI has been revised in Attachment 03
06/03/2020 10/04/2020
O
C
25 5 04/02/2020 drilling barge/ equipment should be mentioned in
equipment list 06/03/2020 Closed
26/02/2020 DHI has revised and updated on MS Rev B (Section III)
Trang 12
Page 12 of 31
26 5 04/02/2020 How to make sure people working here are safe,
please describe detail this step and countermeasure
06/03/2020 OPEN VP1-0-L4-H-GEN-00003 is common document, its document request you to identify the risk and safety countermeasure for this task
06/03/2020 Closed
26/02/2020
In case of safety, DHI will be implement work following HSE detail manual for L4 via VP1-0- L4-H-GEN-00003 which has been submitted to Owner
02/04/2020
DHI has been updated in Attachment 03
06/03/2020 10/04/2020
O
C
27 6 04/02/2020 Contractor to proof that the selection of hammer
12.8t is suitable for such D1000 steel pile
Calculation should be submitted and attached in this
MS 06/03/2020 Closed
26/02/2020 The calculation for hammer is shown in attachment 02 Testing pile work and attachment
02
28 6 04/02/2020 How to bracing the test pile? If brace it to the anchor
pile, mean the anchor pile should be driven before?
please show the Bracing system and correct the sequence
06/03/2020 Closed
26/02/2020 This step will be conducted for mass pile and will
be clearly on MS for pile driving which will be submitted on separate document
26/02/2020 DHI has revised content of this method, this comment will be clear on pile driving method which will be submitted on separate document
DHI has revised content of this method, this comment will be clear on pile driving method which will be submitted on separate document
Trang 1326/02/2020 DHI has revised content of this method, this comment will be clear on pile driving method which will be submitted on separate document
04/02/2020 Please show the method of cutting pile head, and how to do it on site
06/03/2020 Closed
26/02/2020 DHI has revised content of this method, this comment will be clear on pile driving method which will be submitted on separate document
32 7 04/02/2020 Number of piles to be tested: Contractor to clarify the
2 preliminary piles are test piles of both wharf and access bridge?
According to TCVN 10304-2014 Pile Foundation – Design Standard, number of test pile is about 1% of total pile, but not less than 2
According the Clause 3.6-TCVN9393:2012Pile – Standard test method in situ for piles under axial compression load, number of pile test is normally equal 1% total number of pile of jetty but no less than
2 piles
Beside, because of long structure of wharf and access bridge with much variation of soil data, the number of test pile must be increased Contractor to recheck
06/03/2020 Open Please show the total number of jetty’s pile and total number of access bridge’s pile; and explain that why there
is only 1 testing pile for jetty and 1 testing pile for access bridge And how shall the preliminary piles test result be applied for estimation of mass pile?
10/04/2020 Closed
26/02/2020 Number of piles to be tested is shown in attachment 02 Testing pile work
02/04/2020
According to detail design Rev A for Coal Unloading Jetty Total number of jetty’s pile is 317 piles and total number of access trestle’s pile is 201 piles
According to Section 9.8.4.6 of technical Specification about Pile testing where is describing the requirement for Marine work, and Contractor considered such requirement of contract
06/03/2020 10/04/2020
O
C
Trang 1426/02/2020 DHI has corrected and revised on MS Rev B (Section 4.1)
34 7 04/02/2020 Stage loading?
06/03/2020 Closed
26/02/2020 DHI has corrected and revised on MS Rev B (Section 4.1)
04/02/2020 Number of testing pile and testing pile location should be distinguished between jetty and access trestle;
06/03/2020 Closed
26/02/2020 DHI has revised and updated on MS Rev B
(Section 1.4)
36 7 04/02/2020 What is this ?
06/03/2020 Closed
26/02/2020 DHI has corrected and revised on MS Rev B
(Section 4.1)
37 7 04/02/2020 Clarify Design Working Load (for the Wharf and
Access trestle) 06/03/2020 Open Please clarify Design Load (4830 kN, 4050 kN in section 1.3, page 3)
10/04/2020 Closed
26/02/2020 Design working load (for wharf and access trestle) is shown in attachment 02 Testing pile work and due to TCVN 9393:2012
02/04/2020 DHI has revised and updated on calculation for preliminary test pile, coal unloading jetty and trestles VP1-0-L4-C-UZR-05700 (jetty is 4800kN, and trestle is 3500kN)
06/03/2020 10/04/2020
O
C
Trang 15
Page 15 of 31
38 7 04/02/2020 Pile test performed before mass piling work so the
testing load should be equal 250-300% design working load
06/03/2020 Open Please refer to Section 3.1, 3.2, 3.3 and 4.4.7 of TCVN 9393: 2012
10/04/2020 Closed
26/02/2020 According to TCVN 9393:2012, applied 250~300% design load for exploration pile With test pile is applied 150-200% design working load
02/04/2020 DHI has revised and updated on MS for test pile
of access trestle and coal unloading jetty Rev C (Testing load is equal 250% design working load)
06/03/2020 10/04/2020
O
C
39 7 04/02/2020 The Contractor to confirm that all compressive test
procedure is based on ASTM D1143M
06/03/2020 Closed
26/02/2020 DHI confirmed that all compressive test
procedure is based on ASTM D1143M
04/02/2020 Tension working force may be much more when Coal vessel berth abnormally, and then tension test should be needed
06/03/2020 Open Please check what is attachment 2
10/04/2020 Closed
26/02/2020 According to attachment 02, tension test no need to carry out
02/04/2020 Based on Calculation for preliminary test pile, Coal Unloading Jetty and access trestle No
VP1-0-L4-C-UZR-05700, the tension working force is too small (0kN with Trestle and 350kN with Jetty), smaller than Pulling Resistance of Pile (7226kN with Trestle and 1663kN & 2650kN with Jetty)
DHI has revised and updated Attachment 02
06/03/2020 10/04/2020
O
C
Trang 16
Page 16 of 31
41 7 04/02/2020 Clarify why tension test no need to carry out?
(Compression/tension and number of loading cycles are as specified in the SPERW)
06/03/2020 Open Add more explanation, no description in Appendix
02 Review Part III-2 Exhibit B1 Tech Spec Section
8, item 8.8.2 Piling
10/04/2020 Closed However Lot4 will be requested to carry out the tensile strength test if the calculation of reaction show enough internal tensile strength
26/02/2020 According to attachment
02/04/2020 Based on Calculation for preliminary test pile, Coal Unloading Jetty and access trestle No
VP1-0-L4-C-UZR-05700, the tension working force is too small (0kN with Trestle and 350kN with Jetty), smaller than Pulling Resistance of Pile (7226kN with Trestle and 1663kN & 2650kN with Jetty)
DHI has revised and updated Attachment 02 Also based on Section 9.8.4.6 of technical Specification about Pile testing where is describing the requirement for Marine work, and Contractor considered such requirement of contract
06/03/2020
10/04/2020 08/05/2020
O
C
C
Trang 17
Page 17 of 31
42 8 04/02/2020 - Contractor to correct the pile toe level of pile
(01-E-76) (+4.35-42.0m=-37.65m) and also carefully correct the “,” and “.” showing in pile head and toe level of pile 02-P40B
- Add the pile arrangement plan; and mark the position of 2 testing pile
- Clarify the co-ordinates of 2 testing piles (add the survey angular, longitude, projection zone besides of VN-2000 coordinate)
- Clarify that testing pile is 1 segment or 2 welded segments;
- Pile Diameter 1000/16mm is the outside diameter (or OD 1016mm)
- Propose to perform compression, tensile axial static load and horizontal load
06/03/2020 Closed
26/02/2020
- DHI has revised content of this method, this comment will be corrected on drawing design which will be submitted on separate document
- The pile arrangement plan is shown in Attachment 01
- DHI has updated on MS rev B (Section 1.4)
- Testing pile is 02 welded segments
- Pile Diameter 1000/16 is the outside diameter
- According to attachment 02, tension test no
need to carry out
43 8 04/02/2020 Position of test piles should be shown on drawing
Please bring this information to the top of document
06/03/2020 Closed
26/02/2020 DHI has revised and updated on MS Rev B
(Section 1.4)
44 8 04/02/2020 Clarify Type of Pile STK 490?
Why it differs material spec: SKK490 in document
no VP1-0-L4-Q-GEN-10009 06/03/2020
Open Please correct remark in ATTACHMENT 01, Page
#21 10/04/2020 Closed
26/02/2020 DHI has revised and updated on MS Rev B (Section V.5.2) SKK490 due to JIS A5525
02/04/2020 DHI has revised and updated on MS Rev C
Trang 1826/02/2020
46 8 04/02/2020 No found in this MS
06/03/2020 Closed
26/02/2020
DHI has attached on MS rev B (Attachment 02) 06/03/2020 C
04/02/2020 Contractor to explain “Total loading of reaction system will be greater than 1012.8 tons”?
06/03/2020 Closed
26/02/2020 DHI has revised and updated on MS Rev B (Section V.5.3.2) and Refer to Attachment 2:
Calculation Sheet for testing pile
04/02/2020 Contractor shows 04 anchor piles shall be used, please note that number of anchor pile is calculated basing on testing load and its bearing capacity
Contractor to provide calculation sheet
06/03/2020 Closed
26/02/2020 DHI has revised and updated on MS Rev B
(Section 4.1) and Refer to Attachment 2
04/02/2020
- Tolerance of calibrated displacement transducers?
- Capacity of calibrated displacement transducer 06/03/2020
Provide the quantity table of reaction piles, reference pile in detail (specification, elevation, location, ) 06/03/2020
Closed
26/02/2020 DHI has revised and updated on MS Rev B
(Section 4.1)
Trang 1926/02/2020 DHI has revised and updated on MS Rev B
(Section 1.4)
52 10 04/02/2020 - Add the figure of testing chart (including relevant
instrument and equipment: Beam and anchor piles,…);
- Notice that the distance between anchor pile, measurement equipment and testing pile must be longer than the allowable distance
- Clarify the requirement of equipment that regarding
to working pressure
06/03/2020 Closed
53 10 04/02/2020 - Mention clearly the value of 483T design bearing
capacity (compression or tensile, include or exclude safety factor)?
06/03/2020 Open Provide basis for reference, including: criteria design, design document of jetty and access bridge
10/04/2020 Closed
26/02/2020
It has mention on attachment 02, the value 483T design bearing capacity include safety factor
02/04/2020 DHI updated this information based on calculation for test pile, coal unloading jetty and access trestle No VP1-0-L4-C-UZR-05700 which has been submitted to Owner in separate document
in order to finalize this MS 06/03/2020
Closed
26/02/2020
Trang 2026/02/2020
56 10 04/02/2020 The load/unloading interval and each requirement
must follow Section 8 Procedure – ASTM D1143M
Contractor to confirm
06/03/2020 Closed
26/02/2020 The load/unloading interval and each requirement will be followed Section 8
Procedure – ASTM D1143M
57 10 04/02/2020 Clarify the basis of increasing and reducing loading
level and its period?
06/03/2020 Closed
26/02/2020 The basic of increasing and reducing loading level and its period base on TCVN 9393:2012
and ASTM D1143M
58 11 04/02/2020 Time interval between pile installation and testing:
The piles shall be tested 7 days after installation 06/03/2020
Closed
26/02/2020 DHI confirmed that the piles shall be tested 7
days after installation
04/02/2020 How to control the displacement of beam (according
to TCVN 9393:2012, the displacement of beam is not higher than 1/200L);
06/03/2020 Closed
26/02/2020 Base on calculation for beam (Attachment 02), the displacement of beam is not higher than
26/02/2020 DHI has revised and updated on MS Rev B
(Section 4.1)
Trang 21
Page 21 of 31
61 11 04/02/2020 According to ASTM D1143M, The settlement of pile
beyond the limit of 15% diameter piles, the testing is terminated Contractor to check
06/03/2020 Closed
26/02/2020 DHI has revised and updated on MS Rev B
(Section 4.1)
62 12 04/02/2020 Make clear the waiting time of project: at least 7 days
in general (Page 12); at least 7 days for piles into clay layer and at least 3 days for piles into sand layer (Page 16)
06/03/2020 Closed
26/02/2020 DHI confirmed that the piles shall be tested 7 days after installation
04/02/2020 Remind (based on Specification):
The Contractor may select any Working Pile for dynamic load testing up to a total number of 2% of piles
06/03/2020 Open Provide basis for reference, including: criteria design, design document of jetty and access bridge
10/04/2020 Closed 04/02/2020 The results of static and dynamic load tests will be used to correlate pile driving sets calculated from pile driving formula, and to establish criteria for the remaining driving operations Subsequent dynamic tests may be used to adjust these criteria
06/03/2020 Closed
26/02/2020 Frequency of Dynamic load testing for mass pile will be followed specification’s project
02/04/2020 based on calculation for test pile, coal unloading jetty and access trestle No VP1-0-L4-C-UZR-
05700 which has been submitted to Owner in separate document
Trang 22
Page 22 of 31
64 13 04/02/2020 - Add “Impact Equipment”, according to the TCVN
11321:2016 Drop weights have a mass of at least 1% to 2% of the required load capacity of the pile
- Add “The tests shall be sufficient to mobilise the full pile resistance and cause a permanent net settlement of at least 2mm after one impact of the piling hammer”
06/03/2020 Closed
26/02/2020 DHI has revised and updated on MS Rev B
(Section 4.2)
65 14 04/02/2020 Chart?
06/03/2020 Closed
26/02/2020
DHI has corrected and deleted it on MS rev B 06/03/2020 C
66 17 04/02/2020 Provide organization chart of safety department and
responsibilities of each position for test pile 06/03/2020
Closed
26/02/2020 Organization chart of safety department is included with site organization chart which mention at Section II of MS rev B
67 18 04/02/2020 Is that enough?
06/03/2020 Closed
26/02/2020 DHI has revised and updated on MS Rev B
(Section 6.1.5)
Trang 23
Page 23 of 31
68 18 04/02/2020 Please describe how to manage environment
pollution during this activity (How to detail handling, storing, collecting, and treating of waste generation (including domestic, construction, and hazardous waste)
06/03/2020 Closed
04/02/2020 Please describe detail emergency response preparedness plan in this activity (Which is included emergency equipments )?
06/03/2020 Closed
26/02/2020 DHI will be conducted based on HSE detail manual for L4 via VP1-o-L4-H-GEN-00003 which has been submitted to Owner
26/02/2020 DHI has revised and updated on MS Rev B
26/02/2020 DHI will be conducted based on HSE detail manual for L4 via VP1-o-L4-H-GEN-00003 which has been submitted to Owner
Trang 24
Page 24 of 31
70 18 04/02/2020 1 Provide lifting plans as follows:
- What crane? Capacity?
- Load chart (Must be clearly marked)
- List of load (Pile )
- List of lifting gear (Capacity)
- Drawings showing the working radius and lifting area (Lifting from where to where)
- Tension force of wire rope according to the angle of lifting
- Inspection checklist for Crane and lifting gear
- List of manpower and their certificates
- Profile, 3rd party certification for crane and lifting gear
06/03/2020 Closed 04/02/2020
2 Emergency incident response flow chart and detailed communication network must be attached 06/03/2020
Closed
04/02/2020
3 Attach an emergency incident response plan (evacuation routes, boat to rescue, how to do if an incident occurs such as falling into water, cranes collapse )
06/03/2020 Closed
Trang 25- Environmental risk assessment during the test piles
- List of facilities to prevent oil spills 06/03/2020
Closed
04/02/2020
5 JSA is too sketchy: Only use JSA for each specific step in pile testing work (For example, the first day you transport the pile to the construction site, Let's
do JSA and apply it to the transport work to ensure safety)
Please provide a risk assessment (Will be much clearer and more detailed): Initial control, consequences, likelihood -> Additional measures, the likelihood of occurrence has decreased? reduced
to what extent?
Each step must be taken and clearly indicated the risks of each job step, for example:
1 Transporting piles to the construction site
2 Lifting pile to the piling barge or stock barge and arrange pile
3 Fabrication work for working platform
4 Installation of working platforms
5 Lifting pile to the working platforms
Trang 26
Page 26 of 31
71 19 04/02/2020 1 Based on EPC contractor procedure, project
specification and regulation, this document shall be added risk assessment for this task (only JSA is not acceptable)
2 There is no assessment for the dismantle and demobilization
06/03/2020 Closed
#29,…) so we highly recommend that the site control should be paid more attention, increase safety supervisor, safety devices and carry out the work step by step No night working is recommended in this Pile Test period
10/04/2020 Closed
02/04/2020 Well note, the contractor shall pay more attention, increase safety supervisor, safety devices and carry out the work step by step
Due to standard testing process must be continuous so the contractor can’t stop testing at night time, it will be affected to the testing results
There will be no test procedure due to the operation of the equipment at night, and only minimal activity related to the test will be performed
06/03/2020 10/04/2020
- pile load capacity design or calculation
And please note that there is no method for pile driving, it will be submitted separately as the Contractor mention
10/04/2020 Closed
02/04/2020
- Reaction force analyzing due to Pile testing work No VP1-0-L4-C-UZR-05700
- Pile load capacity is in Attached 02
- Method for pile driving will be submitted in separate document,
06/03/2020
10/04/2020
O
C
Trang 27
Page 27 of 31
74 3 06/03/2020 - Use ‘’Recommendation’’ or ‘’Introduction’’ to
replace ‘’Introduce’’ (Name of section)?
- Add the Figure of Master Plan (including of Coal Unloading Jetty and Access trestle) + Wind Direction Chart
10/04/2020 Closed
02/04/2020 DHI has revised and updated on MS Rev C (Section I.1.1)
10/04/2020 Closed
02/04/2020 DHI has revised and updated on MS Rev C (Section I.1.3)
02/04/2020 DHI has revised and updated on MS Rev C
(Attachment 02)
06/03/2020 10/04/2020
02/04/2020 Based on calculation for test pile, coal unloading jetty and access trestle No VP1-0-L4-C-UZR-
05700 which has been submitted to Owner in separate document the maximum loads test shall be 250%xDesign Working Load
06/03/2020 10/04/2020
O
C
78 3 06/03/2020 Clarify the basis Design Criteria to calculate for
design working load: 4830KN and 4050KN to apply
in testing 10/04/2020 Closed
02/04/2020 Based on calculation for test pile, coal unloading jetty and access trestle No VP1-0-L4-C-UZR-
05700 which has been submitted to Owner in separate document (4800kN, 3500 kN in table 1- 2)
DHI has revised and updated on MS Rev C
10/04/2020 Noted
02/04/2020 Based on calculation for test pile, coal unloading jetty and access trestle the tension working force
is too small, smaller than the self-weight of SPP, the Tension load test is suggested to neglect.
06/03/2020 10/04/2020
08/05/2020
O
C
C
Trang 2802/04/2020 Fresh time after pile driving is 7 days which is shown in section IV.4.1.3
02/04/2020 Reference pile is the pile to fix the Dial gauge 06/03/2020
10/04/2020 Open
It is unclear, please provide the detail drawing of reaction structure, joint between anchor pile and beam; and how percentage of counterweight from concrete block and from anchor pile?
02/04/2020
Please see Attachment 01 – Drawing of Static Pile load test and PDA test
29/04/2020
DHI has revised and updated on Attachment
01– Drawing of Static Pile load test and PDA test Percentage of counterweight from concrete
block (100%-1220T) and from anchor pile (20%
-if necessary) is shown in Bearing capacity of
anchor pile calculation in Attachment 02
08 reaction piles and 04 Reference piles) 10/04/2020
Closed
02/04/2020 DHI has revised and updated on MS Rev C (Section IV) There are 08 reaction piles and 04 Reference piles
06/03/2020
10/04/2020
O
C
84 17 06/03/2020 This is for reminder that you may misunderstand
what is job safety analysis
10/04/2020 Closed
Trang 2910/04/2020 Closed
02/04/2020 DHI has revised and updated on MS Rev C (grade of steel pipe pile is SKK490)
10/04/2020 Closed
02/04/2020 DHI has revised and updated on MS Rev C (Section I.1.6)
06/03/2020 Clarify the “Assumed Load Bearing Capacity of Pile”
of 483T, 405T for Hammer calculation?
Clarify the “Assumed Load Bearing Capacity of Pile”
of 483T, 405T for Hammer calculation?
10/04/2020 Closed
02/04/2020 DHI has revised and updated on MS Rev C
06/03/2020
- Add the figure to describe the length of anchor pile (include of length under seabed and free length);
- Add the steel grade of anchored pile
- Add the checking of anchor pile section 10/04/2020
Closed
02/04/2020 The length of anchor pile (include of length under seabed and free length) is shown in Attachment 02
06/03/2020
10/04/2020
O
C
Trang 30- Clarify the flexible length of Anchor pile?
- Internal force of anchored pile shall be used to check the capacity of section
10/04/2020 Closed
02/04/2020 The contractor calculated for beam system which is supported for counterweight so in model link between beam system and ground is anchored steel piles same as bearing point In this case internal force of beam system shall be bigger and it’s more safety for calculation
DHI has revised and updated calculation with updated Designed Verification Load on MS Rev
10/04/2020 Closed
02/04/2020 DHI has revised and updated on MS Rev C
Trang 31
Page 31 of 31
91 1 11/05/2020 DHI proposed Option 1 & 2 for Jetty structure on
27th April, 2020 which included raked pilea with large tension force This document including Static Load Test shall be revised.
DHI will not change document, it is including in static formula,
- No specification for tension test applied on preliminary pile as shown on 9.8.4.5 and 9.8.4.6 in Exhibit B1, Technical Specifications:
“A minimum number of two static compressive load tests shall be done in accordance with international standards and codes” is required only
- This comment has been verify on document
“CALCULATION FOR PRELIMINARY TEST PILE, COAL UNLOADING JETTY AND ACCESS TRESTLE” (VP1-0-L4-C-UZR-05700- Rev C) which has been approved by Owner
-It also has verified by site test pile (PDA and static load test) which determine the pile bearing capacity for both of compression and tensile Load (see document VP1-0-L4-Q-GEN-10043- Test Report For Offshore Piling Initial)
Additional Notes (if any)
* O - Open, C – Closed
Closed
Trang 32P a g e | 1
METHOD STATEMENTS FOR TEST PILE OF ACCESS TRESTLE AND COAL UNLOADING JETTY EPC
Doosan Heavy Industries and Construction
EPC DOCUMENT No
Contractor to revise the correction and resubmit
Revise the correction and resubmit before proceeding
Information acknowledged with no comment
Information acknowledged with comments Note: Approval or comment does not relieve the Contractor of
Trang 33VAN PHONG 1 BOT THERMAL POWER PLANT PROJECT
Table of Contents
I GENERAL 3
1.1 I NTRODUCTION 3 1.2 T HE P URPOSES OF THE TEST 3 1.3 S COPE OF WORK 4 1.4 L OCATION OF TEST PILE 4 1.5 T ESTING S EQUENCE 5 1.6 R EFERENCE 6
II SITE ORGANIZATION 7 III TESTING EQUIPMENT AND SCHEDULE 7
3.1 Schedule 7 3.2 Equipment and mobilize plan 8
IV TESTING METHOD 8
4.1 S TATIC PILE LOAD T EST 9
4.1.1 Introduction 9 4.1.2 Testing Equipment’s 9 4.1.3 Testing Step 10
4.2 H IGH S TRAIN P ILE D YNAMIC L OAD T EST (PDA) 13
4.2.1 Introduce 13 4.2.2 Objective, method and standard for the test 13 4.2.3 Testing Equipment’s 14 4.2.4 Test procedure 14 4.2.5 Test Report 15
V QUALITY CONTROL 15
VI HEALTH, SAFETY AND ENVIRONMENT 16
6.1 S ITE S ITUATION R ESPONSE AND E MERGENCY R ESPONSE 16
6.1.1 Site response 16 6.1.2 Emergency and contact information 17 6.1.3 Medical Emergency Response Plan 18 6.1.4 Personal Protection equipment (PPE) 19
6.2 J OB SAFETY ANALYSIS 19 6.3 R ISK A SSESSMENT 22
VII ATTACHMENT 22
Trang 34VAN PHONG 1 BOT THERMAL POWER PLANT PROJECT
The dimensions of 02 mooring dolphin are: LxBxH = (12x12x2) m; crest elevation: +6.50m; bottom elevation: -18.31m Structure of Mooring dolphin is the RC block on steel pipe pile D1000 system
The length of trestle is about 1150m with the width of trestle is 12m; from axis 44 to axis 48 the width of trestle is 17m Above the trestle is technological trench with the width is 5m and from axis 44 to axis 48 is 10m Structure of trestle is the RC beam and RC slab system on steel pipe pile D1000 system
Figure I-1 General view of access trestle and coal unloading jetty
1.2 The Purposes of the test
Determine the characteristic value of the single pile vertical bearing force;
Provide the dynamic force test parameters for the engineering pile by the high straining dynamic force test and comparison with the results of static load test;
Trang 35VAN PHONG 1 BOT THERMAL POWER PLANT PROJECT
No Description D (mm)
Steel grade
Length (m)
Thk (mm)
Q’ty (Pile)
Design load (KN)
Testing load (KN)
Table I-1 List of test pile
1.4 Location of test pile
Figure I-2 Location of test pile for Jetty
Trang 36VAN PHONG 1 BOT THERMAL POWER PLANT PROJECT
Trang 37VAN PHONG 1 BOT THERMAL POWER PLANT PROJECT
1.6 Reference
Technical documents:
Drawing:
Drawings of Jetty: From VP1-0-L4-C-UZN-05104 to VP1-0-L4-C-UZN-05137
Drawings of Trestle: From VP1-0-L4-C-UZN-05501 to VP1-0-L4-C-UZN-05526
Documents:
Part III-2 Exhibit B1 Tech Spec Section 8, item 8.7 Steel work
Part III-2 Exhibit B1 Tech Spec Section 8, item 8.8.2 Piling
Part III-2 Exhibit B1 Tech Spec Section 9, item 9.8 Piling
Design Criteria No VP1-0-L4-C-UXU-00002
Code and standard:
Standard test method for high-strain dynamic testing of piles, ASTM D4945-00
Standard Test Methods for Deep Foundations Under Static Axial Compressive Load, ASTM D1143
Section B16 and Section B17: The specification for the piling works is the “UK Institution of Civil Engineers (ICE) Specification for Piling and Embedded Retaining Walls, Third Edition 2017, (SPERW)”
Standard TCVN 9393:2012 Pile – Standard test method in situ for piles under axial compression load
Standard TCVN 11321:2016 Pile high strain dynamic testing for reference
Standard TCVN 9394:2012 Pile driving and static jacking works – Construction, check and acceptance for reference
Standard TCVN 10304:2014 Pile foundation – Specification for reference
Standard TCVN 9245:2012 Steel pipe pile
Standard TCVN 10318: 2014 Steel pipe piles and steel pile sheet pile for port harbor – Specification for construction and acceptance;
Standard TCVN 4253:2012 Hydraulic structures – Foundation of hydraulic projects – Design standard
Standard TCXD 88: 1982 Pile method of site testing
Trang 38VAN PHONG 1 BOT THERMAL POWER PLANT PROJECT
II SITE ORGANIZATION
Figure II-1 Site organization chart
3.1 Schedule
Table III-1 Schedule of testing pile work
Trang 39VAN PHONG 1 BOT THERMAL POWER PLANT PROJECT
3.2 Equipment and mobilize plan
I Static Loat Test
2 Oil Pressure Pump + Pressure
Table III-2 Equipment Mobilization plan
Please find attachment 05 Detail of equipment’s for testing
IV TESTING METHOD
Static loading test by reaction Pile Method and concrete block load provides the relationship between loads - settlement of the pile to determine the axis bearing capacity of the pile working in the soil by using 08 anchor piles and 04 reference pile These 08 anchored piles shall be working piles of Platform
Piles are tested by the method loading each level up to maximum loading
Trang 40VAN PHONG 1 BOT THERMAL POWER PLANT PROJECT
Pile settlement is monitored by meter system setting at four positions on the head pile, matching symmetric through the pile center The meters are mounted on the stand independent to testing pile
LAS-XD236 is approved for carry out testing pile as document No VP1-MOC-003 (See
Attachment 04 – Certificate Eligible for construction specialized testing of LAS-XD236)
4.1.2 Testing Equipment’s
a Loading part
Hydraulic jack synchronization system consists of the specialized hydraulic, the total lifting capacity ensure larger than 150% largest testing load Hydraulic system is put on the head pile through the steel pad to ensure loading evenly on the head pile Center of Hydraulic system coincides with pile center
Pumping station is manufactured synchronization with Hydraulic system Pressure - meter type 70MPa or equivalent
All devices are on the certificate verification period effect
b Reaction System
The reaction system contains test beams, loading frames, anchor piles The loading frame is constructed by a system of cross beams The following reaction system will be used:
- 2 Longitudinal beam I600x200x11x17mm, length L = 12m
- Cross beam I800x300x14x26mm, length L = 12m
- Test beam I1300x550x30x85mm, length L = 12m
Refer to ‘Attachment 02: Calculation Sheet for test pile’
- 8 anchor piles without side diameter is 812.8mm;
- Total loading of reaction system will be greater than 1,1520 KN