Thus, wetlands expo-such as FWS and surface-flood vertical flow VF systems cannot be used in these applications, and the regulations force the designer to use HSSF wetlands or VF wetlan
Trang 1The purpose of this chapter is to provide information that
will help ensure successful outcomes for projects using
hori-zontal and vertical subsurface flow (SSF) wetlands (or
bio-solids wetlands) by discussing the internal configuration of
these systems Common construction pitfalls and start-up
errors are also discussed
Implementation of SSF wetland systems consists of the
following three stages:
1 Physical design (specification of internal components)
2 Construction of the wetland
3 Start-up (commissioning)
The sizing of the system can be done using different sizing
tools, including loading charts, scaling factors, and
first-order modeling The pros and cons of these methods have
been discussed in Chapter 20
The first implementation stage, physical design, involves
making decisions as to the number of cells, site grading,
aspect ratio, bed depth, internal piping, media size,
hydrau-lics, water level control, insulation, etc The
configura-tion of these components is then typically documented in
a set of technical drawings (engineering plans) and written
specifications
Construction of the system consists of preparing bidding
documents, retaining a contractor, and physically building
the wetland This is the most critical phase of the
imple-mentation because construction of SSF wetlands is
essen-tially a “one-way street.” Problems with site grading and
elevations become difficult and expensive to correct once
the liner (if any) is in place Problems with the liner become
next to impossible to correct once the bed media is installed
Because it is so difficult to undo construction problems, the
wetland designer is often retained in some advisory capacity
to observe and document the construction work
The final stage, commissioning, includes introducing the
flow and pollutant loading into the wetland, as well as
man-aging water levels in the wetland in a manner consistent with
vegetation establishment and regulatory compliance
The overall implementation process may seem
decep-tively simple, but it is not Determining the wetland size
is not the same as designing the system Mistakes made
in the technical drawings and specifications will lead to
serious problems down the road Mistakes made during
construction may be extremely difficult to fix, and repairs
are likely to cost many times more than the original
com-ponents Failure to understand how the wetland is
sup-posed to operate leads to start-up problems Any of these
situations is likely to lead to the intervention of regulatory
authorities
Characterization of the influent waste stream and eral site assessment issues have been previously discussed in
the necessary wetted area) have been reviewed in Chapter 20 The next stage in the implementation process is deciding how the wetland should be configured, how internal components should be placed, and how large they are Those issues are discussed in more detail here
21.1 SITING
General conditions of the potential site will have been sidered during the establishment of the basis of design There will remain a number of possibilities for the location of the system within the overall site confines These factors have been previously discussed in a general way in Chapters 16 and 18 for FWS wetlands; these also apply to SSF wetlands This chapter considers additional factors that often come into play when siting SSF wetlands These systems are typically smaller than FWS wetlands and, consequently, are often con-structed in or near existing infrastructure
con-CONSTRUCTION ACCESS
Although the as-constructed footprint area of an SSF land may be small, the designer must keep in mind that these wetland cells will be constructed with earth-moving equip-ment such as backhoe excavators The size of this equipment requires a clear perimeter area around each wetland cell; the track size of the equipment will define the minimum separa-tion distance between the wetland cell, the site boundary, and additional wetland cells Large excavators are often preferred
wet-by contractors because the long reach of these machines facilitates placement of bed media during construction An example of a construction-imposed separation distance is shown in Figure 21.1
Typical separation distances are in the range of 5–7 m around the perimeter of each wetland cell to allow access by construction equipment Designers should keep in mind that devices such as cranes (Figure 21.2) may be required to set primary treatment devices such as settling tanks, so over-head vertical clearance (from obstacles such as power lines) may be another construction access issue Excavations for tanks, pipes, wetland basins, and water level control struc-tures raise another access issue Clearly, there must be an adequate location on the site to temporarily store excavated soil With deep excavations (especially trenches), the exca-vation may have to be braced, or the sidewalls may have to
be stepped back to avoid the risk of cave-in This greatly increases the amount of site area and access needed during
Trang 2the construction period This is especially important in
sandy soils that have a low angle of repose and thus require
large excavation widths
It should be noted that heavily wooded sites will require
clearing and grubbing, as discussed in Chapter 18, and remote
sites may necessitate the construction of access roads, adding
to the overall construction cost
S LOPES
SSF wetlands require the construction of level beds On
slop-ing sites, this will necessitate terracslop-ing of the areas where
wetland beds are to be constructed On steeply sloping sites,
this will require substantial cut (earth removal) on the uphill
side and substantial fill (earth placement) on the downhill
side; this additional earthwork can far exceed the volume of
the wetland basin itself Consequently, steeply sloping sites
are often not preferred construction areas, unless no other
alternative is available
It should be noted that completely flat sites may also require substantial earthworks if gravity flow through the treatment process is desired Sites with 1–3% slopes are often the easiest to work with in terms of establishing a hydraulic profile that flows by gravity
E XISTING U TILITIES
SSF wetlands are often used for homes and villages that have previously lacked wastewater treatment Because the wetland (and any associated collection system component)
is often the last utility in the ground, there is always the risk
of hitting and damaging other underground utilities, such as water pipes, gas lines, electrical power lines, or telephone wires Most utilities in North America have a “one-call” tele-phone number to dispatch an individual to locate these utili-ties Obviously, sites with known utility conflicts should be avoided, or provisions to reroute the affected utilities must be incorporated into the design process
FIGURE 21.1 Separation distance between these two vertical flow wetland cells was dictated by the need for access by construction
equip-ment at The Preserve, Minnesota The use of such a large excavator was desirable to place gravel media in the wetland cells Alternate means
of gravel placement, such as an extendable conveyor, would decrease this separation distance.
FIGURE 21.2 Installation of settling tanks at The Preserve, Minnesota Note that construction access is needed for four different
compo-nents: (1) the truck and trailer used to deliver the tanks, (2) the crane used to set the tanks, (3) the excavation itself, and (4) the area needed
to stockpile the excavated soil Thus, the total area needed for construction is far greater than the tanks themselves.
Trang 3Biosolids wetlands are generally constructed to
sup-port sludge management at existing mechanical treatment
plants and are often constructed in close proximity to these
treatment works Again, knowledge of existing utilities is a
critical component of the design process
F LOODPLAINS
Siting of wetland systems in floodplains and floodways has
already been addressed in Chapter 18 It should be noted that
most flood events result in considerable sediment deposition
as flood waters recede Free water surface (FWS) wetlands
are much more tolerant of this sediment load than SSF
wet-lands, where the additional sediment could create potential
clogging issues in the wetland bed As a result, locating SSF
wetlands in floodplains requires careful consideration of the
expected frequency and severity of flooding in the project
area
Biosolids wetlands will contain organic sludge with
varying degrees of pathogens, depending on the age of the
biosolids and level of stabilization Because the potential
to export pathogenic material exists during a flood event, a
decision to locate such a facility in a floodplain would have
to be carefully evaluated
R EGULATORY I SSUES
Regulatory requirements are often a major factor in the
selec-tion of SSF technology over FWS wetlands For instance, in
the United States, approximately 25% of homes rely on
on-site (single home) septic systems (U.S Census Bureau, 1990)
There are considerable health risks associated with exposure
to raw sewage (or sewage exiting the septic tank) As a result, there is a large body of prescriptive codes that require the
treatment and disposal of the sewage without surface sure of the wastewater (U.S EPA, 2002c) Thus, wetlands
expo-such as FWS and surface-flood vertical flow (VF) systems cannot be used in these applications, and the regulations force the designer to use HSSF wetlands or VF wetlands with buried distribution piping so the water will not be exposed.Another example of regulatory requirements that dictate the wetland selection process is airports In cold climates, ice must be removed from the airplanes prior to take-off, and the associated de-icing chemicals generate stormwater run-off that is high in organic (glycol) contaminants Constructed wetlands can remove this chemical oxygen demand (COD) load However, because there is a potential for bird–aircraft strike hazard (BASH), open water bodies such as ponds and FWS wetlands are often discouraged or prohibited from being constructed near airport runways (FAA and U.S Department
of Transportation, 2004) For this reason, SSF wetlands (VF
or HSSF) are preferred for treating de-icing runoff
Siting of wetlands is also influenced by required tion distances from homes, water bodies, and other landscape features These separation distances are usually prescriptive
separa-in nature and dictated by local, state, and provsepara-incial tions In the United States, these range from approximately
regula-3 m to over regula-300 m, depending on the applicable regulations and the size of the treatment system In situations where there are limited choices for siting the wetland, these separation distances may end up not only dictating the location but also the shape of the wetland, as illustrated in Figure 21.3
Soil infiltration area
Site boundary
Dosing tank
15 m Setback
60
m S
etback
Septic tanks Sewer line
Roadwa y
House pad
Property line
15 m Setback
15 m Setback
FIGURE 21.3 The shape and location of this HSSF wetland bed in Lake Elmo, Minnesota, were dictated by regulatory setback requirements.
Trang 421.2 LAYOUT AND CONFIGURATION
Once the wetland area and location have been selected, the
designer must then make a number of decisions regarding the
layout and configuration of the wetland These include
The number of parallel flow paths
The number and type of wetlands in each flow
path
Clogging dynamics
Cell configuration (aspect ratio and bed depth)
The hydraulic profile of the wetland system
The internal configuration of the wetland cells
(flow distribution, bed depth, media size and type,
the need for insulating mulch, the water level
con-trol structures, the liner selection and type, etc.)
NUMBER OF FLOW PATHS
The decision to design the wetland system with two or more
parallel flow paths depends on several operational factors:
The need to provide operational flexibility
The need to provide treatment redundancy
The need to operate the system on a load-and-rest
basis
OPERATIONAL FLEXIBILITY
When there are multiple flow paths, one treatment train
can be taken out of service for maintenance and the flow
diverted to the other parallel wetland cells This flexibility
is a desirable attribute in a wetland treatment system, but it
comes at the added cost associated with extra berms, liner,
water level control structures, and earthwork These added
costs become especially significant for very small
treat-ment systems Let us consider the example of a single home
or 770 m2 The results of splitting this wetland into two allel beds is 40 m r 22 m, or 880 m2 In the first case, the wetland occupies 39% of the required site area; with the two parallel beds, the wetland occupies 34% of the site area, an influent splitter structure is necessary, and the outlet control structure(s) must regulate two water levels
par-Although the split-bed approach illustrated offers more operational flexibility, it comes at the cost of additional area, liner, and control structures The added costs of these com-ponents must be weighed against the alternate methods to provide operating flexibility For instance, many single-home septic tanks provide approximately three days of hydraulic retention time, so one means of taking the system out of ser-vice for maintenance or repairs would be to simply pump the septic tank This would give the operator about three days to complete the necessary work, and if additional time
is needed, the tank could be pumped again This alternate approach to flexibility is less expensive than the split-bed sys-tem, and for this reason, single-home HSSF wetlands in the United States are commonly single-bed designs
As the size of the system increases, the added cost of parallel flow paths becomes a progressively smaller compo-nent of the overall construction cost, and providing alternate means of flexibility (such as pumping of septic tanks) becomes progressively more expensive Therefore, for larger projects, two or more parallel flow paths become the preferred design approach For small community wastewater projects, systems with a design flow greater than 35 m3/d would typically have two parallel flow paths, and for larger projects, additional parallel flow paths may be warranted For instance, the HSSF wetland used to treat aircraft de-icing runoff in Edmonton, Alberta, consists of six parallel flow paths, with two cells in each flow path (Figure 21.4)
FIGURE 21.4 HSSF wetland for treatment of aircraft de-icing runoff, Edmonton, Alberta This particular system consists of six parallel
flow paths, with two treatment cells in each flow path.
Trang 5TREATMENT REDUNDANCY
Many regulatory authorities require wastewater treatment
systems to be designed to treat more than the stated design
flow and load For treatment systems in the upper midwestern
United States, a commonly used redundancy requirement is
that the treatment system must be able to treat 75% of the
influent flow and load, with one treatment train (flow path)
out of service (Great Lakes UMRB, 1997) It should be
noted that this redundancy requirement was developed for
mechanical wastewater treatment plants treating raw
munici-pal wastewater and may or may not be appropriate for
treat-ment wetlands, depending on the type and intended function
of the wetland
With a redundancy requirement, two parallel flow paths
are the minimum If the designer selects two flow paths, each
wetland flow path must be designed to treat 75% of the flow
and load, and the wetland must be designed to treat 150% of
the design (2 r 75%) In certain cases, adding a third flow
path may be advantageous With three flow paths, two
treat-ment trains will be in operation when one is out of service, so
the two trains in service must each be able to treat 37.5% (one
half of 75%) of the design flow and load So, the overall
wet-land is sized to treat 112.5% of the design (3 r 37.5%) The
designer must then evaluate whether the savings in wetland
area is sufficiently justified, given the added cost of the extra
berms and control structures
LOADING AND RESTING
Some treatment wetlands require a loading and resting
regime to function properly For these types of systems, the
loading and resting sequence will determine the number of
the parallel flow paths required
Most VF wetlands are pulse-loaded at a rapid rate to
flood the surface of the bed In between pulses, water drains
from the wetland and air is drawn into the wetland bed (see
biofilms and maintains aerobic conditions within the wetland
bed Particulate organic matter is deposited on the surface
of the bed, and microbial populations are greatest in the
upper regions of the bed, where the organic loading is the
highest (Langergraber et al., 2006b) As the loading period
progresses, this leads to the development of a clogging mat
on the surface of the bed (unless very low organic loadings
are utilized) This clogging mat blocks the movement of air
into the bed, promoting anaerobic conditions and ponding of
the bed surface (Platzer and Mauch, 1997; Hyánková et al.,
2006)
Loading and resting are used as means to avoid clogging
of the bed and associated surface ponding (EC/EWPCA
Emergent Hydrophyte Treatment Systems Expert Contact
Group and Water Research Centre, 1990; Platzer and Mauch,
1997; Molle et al., 2004a) The need for resting intervals
becomes increasingly important as the organic loading on
the VF wetland is increased For instance, in France many
VF wetlands are fed with raw sewage (no primary treatment);
to operate successfully, three VF beds in parallel are needed
in the first stage (Molle et al., 2004a) One bed is fed with raw
sewage while the other two are rested (Figure 7.31) Thus, the loading and resting operating regime of these French systems dictates that the first stage of the treatment process must con-sist of at least three parallel flow paths
21.3 NUMBER AND TYPE OF WETLANDS
IN EACH FLOW PATH
Once the number of parallel flow paths has been decided, the next question facing the wetland designer is how many cells to put in each flow path There are several scenarios that would lead the designer to consider multiple cells in series:There is a need for greater treatment efficiency (and hence greater hydraulic efficiency) to increase the
number of PTIS through the use of two or more
There is a desire for staged treatment, with ferent treatment reactions occurring in different wetland cells
dif-G REATER T REATMENT E FFICIENCY
The first case is a situation where the designer wishes to increase the overall treatment efficiency of the process—or
to provide the same level of treatment in a smaller area By combining two wetland cells in series, the number of tanks
in series (NTIS) is theoretically increased The decreasing
length-to-width ratio for each physical compartment means
that NTIS is not doubled The relaxed parameter, P, accounts for both hydraulic effects (N) and effects of pollutant weath- ering; so a decision to increase P must be based on the pollut-
ant under consideration and the best professional judgment of the designer In any case, the advantage of cells in series for HSSF wetlands is not large unless the design contemplates a
close approach to C*.
As discussed in Chapter 6, compartmentalization becomes
a significant aspect of the wetland sizing process when the goal is a very high level of treatment The case of providing two wetland cells in series (instead of one cell) was previously explored for biochemical oxygen demand (BOD) removal in
Tables 20.7 and 20.8 In that particular example, there was not
a dramatic reduction in the required area because the design goal (94.4% reduction in mass load) allowed an effluent con-
centration significantly above (double) the assumed C* value.
However, as the target effluent quality gets closer
and closer to C*, the hydraulic efficiency N (and hence P)
becomes an extremely important part of the sizing process, because bypassing of untreated effluent in the TIS model has
•
•
•
•
Trang 6a large impact on the effluent quality Here, we will consider
a scenario where the wetland process must deliver an effluent
quality very close to C*, where there are very large impacts
of compartmentalization on the wetland size
Tables 21.1 and 21.2 consider the case of an aerated
subsurface flow wetland (saturated flow) to remove COD
from hydrocarbons Because of the internal mixing induced
by aeration (N 3) and pollutant weathering, the wetland
is assumed to function as 2 PTIS (aerated wetlands are
addressed in more detail in Chapter 24) The spatially
vari-able flow P-k-C* model previously introduced in Chapters 17
and 20 is utilized here The influent COD is assumed to be
120 mg/L, the regulatory compliance limit is 20 mg/L, and
C* is assumed to be 10 mg/L However, because of
variabil-ity in the wetland performance, an effluent qualvariabil-ity of 11.2
mg/L is targeted as the design objective so that the system
will meet the 20 mg/L regulatory limits on a consistent basis
(90% of the time) The lower targeted effluent concentration
is not a safety factor and has nothing to do with treatment
redundancy
Further, it is assumed that there will be significant
weath-ering of the COD mixture as it approaches C*, so the two
wetland cells in series are represented by P 3 instead of
N 6
As the target effluent concentration is so close to C*, any
bypassing of untreated water (low NTIS and therefore low
PTIS) has a very large impact on treatment performance
In Table 21.1, the required wetland area is 2,400 m2; in
Table 21.2, the required wetland area is 1,500 m2 So, in this particular example, there is a large benefit in terms of size reduction (35%) if the wetland is constructed as two cells in series, even though the “benefit” of the second cell has been reduced by pollutant weathering effects
DIVIDING WETLAND CELLS BASED ON SLOPE
On sloping sites, there will be earthwork cut-and-fill costs associated with terracing the site for wetland basins How-ever, wetland designers should be aware that dividing the wetland into multiple segments may potentially have impacts
on treatment performance (as explored in Tables 20.8,
20.9, 21.1, and 21.2) If there are large topographic changes between wetland cells, this can provide the opportunity for creative design elements, such as cascade waterfall aerators (Burka and Lawrence, 1990), if these are advantageous from
a process design standpoint
MORE THAN ONE WETLAND TYPE
Another obvious situation to divide the flow path into multiple cells is when there is a desire to use more than one wetland type along the flow path This subdivision of the treatment process into unique process elements dates back to the original work of Seidel (Seidel, 1966), which
is discussed in Chapter 15 Her work eventually led to the development of the current “hybrid” wetland systems,
TABLE 21.1
COD Reduction for One Wetland Cell, PTIS 2
Input Parameters Calculated Values
Flow rate, Q 137.1 m 3 /d Volume per tank 547.2 m 3
Precipitation, P 2.2 mm/d Area per tank 1,200 m 2
ET 0.13 mm/d Influent flow, Qi 137.1 m 3 /d
Infiltration 0.01 mm/d Effluent flow, Qo 142.0 m 3 /d
Area, A 2,400m 2 Influent mass load 16,452 g/d
Porosity, E 0.38 Effluent mass load 1,591 g/d
Bed depth 1.2 m Mass percentage reduction 90.3%
C* 10 mg/L HLR based on Qavg 0.058 m/d
k 356 m/yr HLR based on PTIS 0.059 m/d
Compliance C 20 mg/L HRT based on Qavg 7.84 d
Variability factor 1.78 HRT based on PTIS 7.70 d
Target C 11.2 mg/L Liner required 3,294 m 2
Trang 7which typically employ a combination of
vertical–hori-zontal flow wetland cells (Urbanc-Bercic and Bulc, 1994;
Cooper and Green, 1995; Platzer, 1996; O’Hogain, 2003;
Obarska-Pempkowiak et al., 2004; Vymazal, 2005), or a
combination of the horizontal–vertical flows (with
recircu-lation) (Brix, 1998; Laber et al., 1999) Combination
wet-land systems of this nature are discussed in more detail in
STAGED TREATMENT
Another situation where a designer may elect to use multiple
wetland cells along the flow path is when each wetland cell
is intended to provide a different treatment function In many
situations, these wetland cells will be different types of
wet-lands, as discussed previously and in Chapter 24
However, in certain applications, the same type of
wetlands may be linked together solely based on
treat-ment function A good example of this approach is the
two-stage VF wetland systems in France (Molle et al.,
2005a) The first stage of the treatment process is often
three pulse-fed VF beds that are alternately loaded and
rested The primary function of these beds is BOD and
total suspended solids (TSS) removal The second stage
of the treatment process is typically two parallel pulse-fed
VF beds that are also alternately loaded and rested These
second-stage cells are intended primarily for BOD
polish-ing and nitrification
21.4 CLOGGING DYNAMICS
Both horizontal and vertical flow SSF wetlands rely on the ment of water through a porous media for proper functioning Both systems are susceptible to bed clogging, which restricts the flow of water through the bed media In some instances, this restriction in flow will create flooding and will be considered
move-to be a “failure” of the wetland treatment process However, the
definition of failure is qualitative and is often based on the
per-ception and expectations of local regulators, government cials, system operators, and nearby residents
offi-D EFINING F AILURE IN SSF W ETLANDS
Because failure is a subjective term in the treatment wetland
field, it is useful to define what the expectations of the tors, owners, and users of the system might be Several cases concerning hydraulic failure help to illustrate this point
regula-In Denmark, soil-based HSSF wetland technology was adopted early and spread rapidly throughout the country Although the design intent was sub-surface flow, these systems did not have sufficient hydraulic conductivity, and overland flow occurred instead (Brix, 1998) However, the treatment per-formance of these systems was satisfactory and the overland flow mode was tolerated
In the United States, regulations for single-home septic systems prohibit the surface exposure of
•
•
TABLE 21.2
COD Reduction for Two Wetland Cells in Series; PTIS 3
Input Parameters Calculated Values
Flow rate, Q 137.1 m 3 /d Volume per tank 228 m 3
Precipitation, P 2.2 mm/d Area per tank 500 m 2
ET 0.13 mm/d Influent flow, Qi 137.1 m 3 /d
Infiltration 0.01 mm/d Effluent flow, Qo 140.2 m 3 /d
Area, A 1,500 m 2 Influent mass load 16,452 g/d
Porosity, E 0.38 Effluent mass load 1,563 g/d
Compliance C 20 mg/L HRT based on Qavg 4.93 d
Variability factor 1.78 HRT based on PTIS 4.88 d
Target C 11.2 mg/L Liner required 2,107 m 2
Trang 8wastewater because of public health concerns (U.S
EPA, 2002c) HSSF wetlands that have clogged inlet
zones and overland flow (even for a small
percent-age of the wetland bed) are thus deemed “failed,”
and considerable effort and expense have gone into
maintaining these wetlands to eliminate overland
flow, even when treatment performance was
sat-isfactory A similar situation exists in the United
Kingdom (Cooper et al., 2006a).
VF wetland systems in France are highly loaded with
BOD and TSS (raw sewage) in the initial treatment
stage (Molle et al., 2004a) A large component of the
initial treatment is physical filtration and deposition
of organic matter on the surface of the beds In other
words, the beds are designed to clog However, these
high loads can only be tolerated for a short time; so,
a loading and resting regime (at least three parallel
beds in the first stage) is utilized so that there is
suf-ficient resting interval to recover from the clogged
condition via drying and cracking of the cake
(Figure 7.31) Therefore, in these systems, clogging
does not equate to failure because there is a routine
operational program to address the clogging issue
However, other VF wetlands have clogged and failed
This occurs when there are insufficient beds to allow
adequate rest intervals When these beds clog, water
ponds on the surface and air movement into the
bed ceases, resulting in poor treatment (Platzer and
Mauch, 1997; Cooper et al., 1997) In extreme cases,
ponded water may essentially fill the entire basin,
requiring the entire wetland to be bypassed
Thus, it can be seen that the definition of hydraulic failure
depends on the regulatory requirements, degree of treatment
flexibility, operational regime, and local expectations These
definitions of failure may or may not involve treatment
effi-ciency issues For design purposes in this book, the following
conditions are assumed to constitute a failure mode:
An inability to meet treatment standards on a
con-sistent basis based on the regulatory compliance
interval
For HSSF wetlands, the flow should be kept within
the wetland bed When clogging occurs in the inlet
region, any overland flow path should be kept to
a required minimum This may be zero exposed
water, or some minimal length that may be
consid-ered an inlet distribution zone This defines failure
based on length of overland flow, not the area of
the bed that is clogged
For VF wetlands, the inability of the system to
hydraulically pass the design flow This will
require sufficient beds to allow adequate resting
periods to resist clogging
For biosolids wetlands, not having sufficient beds
to allow adequate resting periods to stabilize the
CLOGGING IN HSSF WETLAND BEDS
The aspect ratio (L:W) of each wetland cell is an important design decision for HSSF wetlands Longer and narrower beds increase the organic loading applied to the cross-sectional area of the bed High cross-sectional loadings will result in
a greater length of the bed operating as an overland flow tem due to the clogging mechanisms described in Figure 7.25, Chapter 7 This is likely to be unacceptable from a regulatory standpoint in the United States, and if the overland flow chan-nelizes, treatment performance will be compromised
sys-At the present time, there is considerable interest in determining whether or not a sustainable balance between solids deposition and solids decomposition/resuspension can
be reached in the inlet zone of HSSF wetlands This issue
is of profound design importance If a steady-state criterion can be identified, then HSSF wetlands can be designed with
a sufficiently conservative inlet loading criteria so as to clude the need for bed-media maintenance or replacement
pre-If bed clogging is inevitable (and merely delayed by lower inlet loading rates), then the need for scheduled bed clean-ing/replacement in the inlet zone becomes an integral part of HSSF wetland technology operation and lifecycle costs
To achieve a steady state in the inlet region, the deposited inlet-suspended solids and the microbial biomat generated
by particulate/soluble organic matter must be in equilibrium with the combined rate of organic solids decomposition and the rate of particulate matter resuspension This implies that
the rate of accumulation, A, in the inlet zone is zero This
con-dition can be represented (using terms previously presented
in Equation 7.16, Chapter 7) as indicated in Equation 21.1:
wheregeneration rate, g/m ·dsettling ra
2
G S
Reduction in the hydraulic conductivity of the inlet zone can
be attributed to a variety of mechanisms, including
1 Accumulation of mineral (biologically inert) ments associated with influent TSS
sedi-2 Accumulation of particulate organic matter ject to biodegradation) within the inlet zone
(sub-3 Formation of chemical precipitates within the land bed
wet-4 Generation of microbial biofilms in response to the combined load of the particulate and soluble organic matter
These materials combine to form a mixture that is here termed
biosolids, and the degree of biosolid accumulation depends
on all four mechanisms Because a significant portion of the incoming organic load in domestic wastewaters is present as
Trang 9decomposable particulate organic matter, depositions of this
particulate organic matter may result in organic loadings
ten-fold higher in the inlet region as opposed to the rest of the
wet-land bed (Puigagut et al., 2006) This has profound effects in
biosolid formation in the inlet zone Reductions in the
hydrau-lic conductivity from biosolid accumulations are a function of
the media size, as discussed in Figure 7.24, Chapter 7
Short-Term HSSF Inlet Zone Clogging
At the present time, there is insufficient knowledge to
quan-tify the generation G, decomposition D, and resuspension
R rates within HSSF wetland beds This is largely due to
the difficulties encountered when doing in situ sampling of
HSSF systems, as previously discussed in Chapter 7 Without
the ability to quantify the terms G, D, and R, the alternative is
to extract design information from the performance of
exist-ing HSSF wetlands, as shown in Figure 21.5
Data illustrated in Figure 21.5 suggests that HSSF
wet-land beds should be configured such that the cross-sectional
area (orthogonal to the flow) results in a BOD loading of
250 g/m2·d for bed medias with a d10 4 mm BOD has
been selected as the influent loading parameter in this case
because (1) the majority of degradable organic matter in
municipal effluents is present as particulates, (2) soluble
organic matter also contributes to inlet zone biosolids
for-mation, and (3) chemical precipitates (as represented by the
difference between COD and BOD) occur more uniformly in
the HSSF bed and are likely not restricted to the inlet zone
There are drawbacks to limiting performance
informa-tion to BOD, as illustrated in Figure 21.5 First of all, a HSSF
wetland with a high inlet flow of nonorganic (mineral) TSS
may plug at organic loads much lower than those indicated in
Figure 21.5 Secondly, the nature of the organic material must
be considered Some waste streams contain organic matter that is much more degradable than others HSSF wetlands treating soluble, rapidly degradable organic material can rea-sonably be expected to have a shorter clogged inlet zone
Long-Term HSSF Inlet Zone Clogging
Systems illustrated in Figure 21.5 generally have an tional performance history less than ten years Although reducing the cross-sectional organic loading may have short-term benefits in reducing bed clogging, the long-term viability of HSSF hydraulic conductivity remains uncertain Two factors argue against the ability to stabilize long-term hydraulic conductivity of HSSF beds These include
opera-Not all organic matter deposited in the inlet zone
is biodegradable The refractory (nondegradable) component represents a long-term accumulation of organic TSS
A certain component (variable between HSSF tems) of influent TSS consists of nondegradable (mineral) material This inert material is efficiently removed from the water column through the par-ticulate settling/filtration/interception mechanisms discussed in Chapter 7 Because these removal mechanisms are very efficient in HSSF beds, most
sys-of the TSS reduction occurs in the early stages sys-of the wetland bed (see, for example, Figure 7.26) Long-term loading of inert TSS results in an ongo-ing reduction of the hydraulic conductivity in the inlet zone
The current understanding of HSSF wetland design does not allow a quantitative determination of the region of inlet
•
•
0 100 200 300 400 500 600 700 800
FIGURE 21.5 Flooding status of HSSF wetlands as a function of cross-sectional organic loading and bed media size (Data from Steinmann
et al (2003) Water Research 37: 2035–2042; Wallace and Knight (2006) Small-scale constructed wetland treatment systems: Feasibility, design criteria, and O&M requirements Final Report, Project 01-CTS-5, Water Environment Research Foundation (WERF): Alexandria, Virginia; Puigagut et al (2006) Size distribution and biodegradability properties of the organic matter in horizontal subsurface flow con- structed wetlands Kröpfelová (Ed.), Paper presented at the 6th International Workshop on Nutrient Cycling and Retention in Natural and
Constructed Wetlands, 31 May–4 June 2006; Trebon, Czech Republic.)
Trang 10clogging (biosolids penetration distance), although this is
believed to be related to the size of the bed media, as
indi-cated in Figure 21.5 The d10 of the media is often used to
approximate the pore volume, as only 10% of the bed media
is smaller than this size
Studies on sand clogging indicate that the clogging
dis-tance Dc, can be related to the d10 of the media: Dcy 150 d10
within the range of 5 r 10−3 mm d10 3r10−2 mm
(Blaze-jewski et al., 1994) Because this d10 is much smaller than
the media sizes used in most HSSF wetlands, the usefulness
of this relationship is limited to soil-based HSSF systems
Blazejewski et al (1994) suggested a clogging thickness of
3 cm for fine-grained HSSF beds
Bavor et al (1989) noted that clogging within a series of
long, narrow HSSF trenches (L:W ratio of 25:1) was remedied
by excavating the first 5 m of the bed and replacing with coarse
rock Kadlec and Watson (1993) provided evidence from the
Benton, Kentucky, system that the farthest biomat-penetration
distance stretched 100 m into a 300-m bed But this type of
information does not help in design unless couched in terms
of organic loadings and decomposition rates
Based on the information currently available, it appears
that bed clogging (as evidenced by overland flow length) is
reduced, or at least delayed, by minimizing the cross-sectional
loading, and using coarser bed materials in the inlet zone
However, based on the current state of the art, there is
no available evidence that argues against the phenomenon of
long-term bed clogging (A 0), even if short-term clogging
pitfalls are avoided Long-term performance information
from the United Kingdom (Cooper et al., 2006b) indicates
that HSSF systems will require some degree of inlet zone
media replacement or cleaning during the course of their
operational lives Whereas the frequency of this maintenance
is dependent on the bed clogging factors described in this
book, it appears that even well-designed, well-operated HSSF
wetlands will require inlet zone maintenance approximately
every ten years to avoid the development of large regions of
overland flow At the present time, media replacement is the
most common (and most expensive) method of maintenance
(Wallace and Knight, 2006) although trials using hydrogen
peroxide as a cleaning agent have shown promising results
(Hanson, 2002b; Behrends et al., 2006).
C LOGGING IN VF W ETLAND B EDS
VF wetlands are also subject to solids accumulation, which
can fill the pore volume within the upper region of the
wet-land bed, potentially leading to ponding and hydraulic failure
Equations describing clogging of VF wetland beds have
pre-viously been presented in Equations 2.58–2.61 in Chapter 2
The organic loading applied to the VF wetland appears to
play a large role in the clogging process For a soil/sand VF
wetland at Merzdorf, Germany, Platzer and Mauch (1997)
observed a log-linear decrease of hydraulic conductivity as a
function of the cumulative applied organic load With resting
intervals, the hydraulic conductivity of the bed was restored
to the original values
At the present time, there are two operating regimes to address the clogging of VF wetland beds:
1 Systems that are continuously operated without resting These VF wetlands are loaded at relatively low organic loads to minimize biosolids accumu-lation and associated clogging of the bed
2 Systems that employ multiple beds in a rest regime These VF wetlands are designed to clog during the loading phase; hydraulic conduc-tivity is restored during the resting phase
load-and-Because clogging and organic loading appear to be mately related, it is not possible to specify an organic load-ing rate for a VF wetland system without also specifying the resting sequence associated with that loading, as previously discussed in Chapter 20
inti-Approximately 180 VF wetlands in North America have been designed as recirculating systems, which are function-ally very similar to recirculating gravel filters (Crites and Tchobanoglous, 1998) Recirculation ratios vary depending
on design goals, but ratios of 3 to 12 times the inlet flow rate are common
An array of distribution pipes results in a nonuniform application of influent TSS and organic matter This loading
is concentrated at the discharge orifices of the distribution pipes Biosolids then preferentially form at each discharge orifice in a zone about 30 cm in diameter In extreme condi-tions, these biosolids will plug the upper layer of the wetland bed because recirculating wetlands operate at hydraulic load-ings that are much higher than the inlet flow reductions in bed porosity and loss of hydraulic conductivity can rapidly lead to flooding of the wetland bed An example is shown in
Figure 21.6.Operational experience in the United States indicates that the organic loading (as represented by BOD) should be less than 15 g/d per orifice for buried pipes to avoid biosolids clogging with bed media greater than 4 mm The equivalent BOD loading in the biosolids clogging region at the orifice is approximately 200 g/m2·d
The uniformity of application is increased and the organic loading is reduced if there is a secondary redistri-bution of the influent by splashing or spraying Figure 21.7
shows a cold-climate method of achieving this Perforated pipes are placed in infiltration chambers that are then buried
in the upper portion of the wetland Water sprays out of the distribution orifices up into the infiltration chamber, where it splashes around and undergoes secondary distribution Ori-fice shields (resembling plastic pipe caps) are commercially available for this purpose
21.5 CELL CONFIGURATION
As discussed in the previous section, clogging dynamics will often determine the number of wetland treatment cells and, for HSSF wetlands, the aspect ratio (L:W) will be a function
of the cross-sectional loading if delaying or minimizing the
Trang 11overland flow is a design goal (see Figure 21.5) Even if the
cell dimensions are governed by clogging considerations,
there are still a number of design decisions Several factors
of SSF wetland bed design warrant further consideration at
this stage; these include
The length-to-width (L:W) ratio of the wetland
cells
The depth of the wetland cells
The types and sizes of the bed media that will be
placed in the wetland cells
The overall size of the wetland cells
LENGTH-TO-WIDTH RATIO
For VF and biosolids wetlands, the aspect ratio (L:W) is
relatively unimportant, because these wetland beds are top
ing and flow velocity and, to some extent, the NTIS value.
When working with HSSF wetlands, the designer is faced with two mutually contradictory design goals:
The desire to spread the influent over a very wide planar area (This delays the time to clogging.)The desire to spread the influent as uniformly as pos-sible over the vertical cross section (This improves flow distribution.)
Spreading the influent over wide areas presents a number of hydraulic challenges, especially for small systems, where the flow rate is close to zero One approach, which has been implemented in Denmark, is to divide the inlet chamber into two or more segments that can alternately be loaded to gain
•
•
FIGURE 21.6 Example of biosolids clogging in a small recirculating VF wetland This system in central Minnesota experienced rapid
hydraulic failure in response to extremely excessive BOD loadings from illegal drug manufacturing.
FIGURE 21.7 Recirculating VF wetland under construction at The Ponds, Minnesota The black infiltration chambers are used as a means
of secondary flow distribution to reduce the organic loading at the distribution orifice (This photo was taken at an intermediate stage of construction; additional gravel was later placed to bury the influent distribution chambers.)
Trang 12better control of the flow distribution (Brix, 1998) A
sche-matic of this is shown in Figure 21.8
For small-scale wetlands, flow-splitting approaches use
weirs, stoplogs, or rotating elbows if flow balancing is an
operations goal All such flow-splitting devices require
peri-odic maintenance to remove accumulated solids that may
interfere with the flow split, especially for small-scale
sys-tems with low flows
An alternate approach is to split the flow two ways using
a central effluent collection pipe with influent distribution
channels on either side of the wetland An example of this
design strategy is presented in Figure 15.5, Chapter 15
W ETLAND CELL DEPTH
HSSF wetlands were originally designed with a depth of 60
cm based on the belief that this was the maximum depth that
Phragmites root systems would penetrate (Kickuth, 1977)
However, analysis of many HSSF wetlands has indicated that
the root systems of emergent wetland plants grow
preferen-tially in the upper region of the bed; this concept is illustrated
typically being only about 30 cm Thus, deeper beds often
have a lower region without plant roots, and water flows
pref-erentially along the bottom of the wetland bed This lower
region is typically associated with more reducing conditions
and less efficient treatment
For HSSF wetlands, the designer is faced with choosing
the bed depth Some observations include the following:
1 Deeper beds promote vertical stratification of flow,
as discussed in Chapter 2 This allows bypassing
of the flow below the plant root zone (Fisher, 1990;
Pilgrim et al., 1992; Marsteiner et al., 1996; Garcia
et al., 2004b), with adverse impacts on treatment
performance
2 Shallower beds often result in better treatment (see Tables 8.14 and 9.33 for BOD and ammonia, respectively)
3 Deeper beds provide a greater cross-sectional area, which reduces cross-sectional loading (see Fig-ure 21.5) This theoretically reduces the flow velocity (in the absence of vertical stratification), resulting in less head loss through the wetland bed, which makes maintaining a uniform water surface profile easier
4 Deeper beds speculatively provide additional ume for storage of refractory and nondegradable (mineral) sediments This added storage volume would presumably decrease the time intervals between clogging and associated bed maintenance
vol-5 A deep bed speculatively allows for some ice formation at the top while still passing the water underneath the ice within the bed
From a treatment standpoint, the additional cost of the extra bed depth (e.g., 60 cm versus 30 cm) appears to add zero
or negative value to a fixed area of wetland, but there is no quantification across multiple systems Control of head loss
is better done through aspect ratio and media size If ment storage is a design consideration, more bed depth may
sedi-be warranted Ice formation can sedi-be adequately controlled via
a variety of other insulation techniques To date, virtually all HSSF wetlands have been designed with beds between 30 and 60 cm deep But, controlled field-scale research studies indicate that shallower depths provide better treatment
VF and biosolids wetlands are typically constructed to
a prespecified bed depth, 50–80 cm for VF wetlands and 50–60 cm for biosolids wetlands
Inspection port (typical)
Flow splitter to allow alternate loading and resting
Infiltration chamber
Perforated pipe
Louvered sidewall
FIGURE 21.8 Layout and design factors for a HSSF wetland utilizing an influent flow split to enhance flow distribution (From Wallace
and Knight (2006) Small-scale constructed wetland treatment systems: Feasibility, design criteria, and O&M requirements Final Report,
Project 01-CTS-5, Water Environment Research Foundation (WERF): Alexandria, Virginia Reprinted with permission.)
Trang 13T YPE AND SIZE OF BED MEDIA
Whereas HSSF beds almost always use coarse stone in the
inlet and outlet regions, a variety of materials are used for
the main bed media
The original HSSF beds utilized sand in the Max Planck
Institute Process (MPIP) system (Seidel, 1966) and soil in the
root zone method beds (Kickuth, 1977) Many more of the
root zone method systems were constructed, despite
signifi-cant problems with the hydraulic conductivity and associated
problems of overland flow (Brix, 1998)
The response to the overland flow problem was to design
HSSF beds with coarser materials so that the water could flow
through the wetland bed Different countries took various routes
in the development of HSSF wetland technology, and there are
regional differences in the size and type of the bed media
Perusal of Table 10.14, Chapter 10, will provide an indication
of the wide variety of bed medias that have been evaluated In
certain cases, the use of media with specific chemical
proper-ties, such as phosphorus sorption or a high cation exchange
capacity (for ammonia retention), may be desirable Examples
of bed media and size gradations that have been used in HSSF
wetlands are summarized in Table 21.3
Finer materials have a greater surface area for
micro-bial biofilms and may result in better treatment, as indicated
more prone to clogging and associated hydraulic problems,
as illustrated in Figure 7.23, Chapter 7 The use of coarser
material in the first part of the HSSF wetland bed and finer
material closer to the outlet has been proposed as a
com-promise between these two competing design objectives
(Wallace and Knight, 2006) The type of wastewater may
also be a factor, because biosolids production and/or
distri-bution appears to be a function of the organic loading With
lower organic loadings, finer bed medias could conceivably
be used without clogging for the same time period as coarser materials with higher loadings, as proposed in the Austrian design guidelines (ÖNORM B 2505, 2005) and summarized
in Table 21.3
Economics, availability, and local design practices cally dictate what material will be preferred for the wetland bed To date, medias in the size range of 8 to 16 mm have been most commonly used in HSSF wetlands (IWA Specialist Group on Use of Macrophytes in Water Pollution Control, 2000)
typi-VF wetlands typically use a layered approach to the bed, with fine material (typically sand) at the top of the wetland bed and progressively coarser materials lower in the bed—down to the drainage layer It has long been recognized that the composition of the sand layer is critical; the material must be fine enough to trap TSS on the surface of the bed but coarse enough to allow water movement without clogging (Cooper, 2003) Depending on the level of pretreatment, finer bed media may be warranted; the French systems use coarser bed material in the first VF stage (which treats raw sewage) and finer bed material in the second VF stage, which pro-
vides COD polishing and nitrification (Molle et al., 2004a).
Biosolids dewatering wetlands typically have a fine layer (sandy loam or sand) with an underlying drainage layer (Nielsen, 2002) However, it has been noted that it is important
to maintain continuity of capillary suction to facilitate flow through the various drainage layers; otherwise, the result will
be “hanging water” as evidenced by a lack of sludge ing (Nielsen, 2004) So, large differences in the size range between adjacent drainage layers should be avoided
dewater-Different bed media and layering for VF wetlands are summarized in Table 21.4
EC/EWPCA (1990) 3–6; or 5–10 mm Gravel 86 m/d 50–200 mm stone
TVA (1993) 3–6 mm Gravel 2,600 m/d (secondary effluent)
260 m/d (primary effluent)
50–100 mm stone
ATV (1998) 0.2–1.0 mm Soil/sand
k(d10)2100
where k is in m/s and d10 is in mm U.S EPA (2000a) 20–30 mm Gravel 100,000 m/d 40–80 mm stone
5–20 mm top layer 10,000 m/d inlet region IWA (2000) 8–16 mm Gravel k D
P
12 600 , 1 9
where k is in m/d and d10 is in cm use 10% of this value in the inlet region
75–100 mm stone
ÖNORM B2505 (2005) 0–4 mm (gray water)
1–4 mm (secondary influent) 4–8 mm (primary influent)
Sand Gravel Gravel
Use the saturated hydraulic conductivity;
head loss is sized on 1/10 of the daily flow being delivered in 1 hour
16–32 mm gravel or gradated bands of 8–16 and 4–8 mm gravel
Wallace and Knight (2006) 4 mm Gravel 260 m/d 25–50 mm gravel
Trang 14SSF WETLAND CELL SIZE
Another factor enters into the design process when
determin-ing the footprint area of individual wetland cells, specifically
the construction equipment that will be used to place the
bed media Even large excavators have a maximum reach of
approximately 10 m (see Figure 21.1) Therefore, SSF
wet-land cells greater than about 20 m wide cannot be filled with
standard excavators, and the remaining construction options
consist of
Allowing equipment to operate inside the
wet-land basin (typically, skid-steer loaders for small
basins, or bulldozers for large basins)
Using a specialized piece of equipment, such as an
extendable conveyor, to place the bed media
The pros and cons of these different approaches are
dis-cussed under the SSF wetland construction section of this
chapter However, the designer should give thought to
con-struction methods and the type of concon-struction equipment
locally available when determining the dimensions of
indi-vidual wetland cells
The overall hydraulic profile for the treatment cess, including frictional losses within the wetland bed
pro-Distribution of the influent flowCollection of the effluent flowWater level control
Gravity flow through the treatment process is the preferred situation from an operations and reliability standpoint Pumping of the flow is less desirable because of the reliabil-ity, maintenance, and power consumption issues associated with wastewater pumps On very flat sites, grading the site
to achieve the “stair-step” configuration needed for gravity
Summary of Bed Materials Used in VF Wetlands
Source Wetland Type Layer Thickness Media Size Material
EC/EWPCA (1990 Pulse-fed Surface layer
Second layer Third layer Drainage layer
Sharp sand Pea gravel Round gravel Round gravel ATV (1998 Pulse-fed Main layer 80 cm 0.2–1.0 mm Soil/sand
Molle et al (2004a) Pulse-fed (First stage) Surface layer
Second layer Drainage layer
30 cm 10–20 cm 10–20 cm
2–8 mm 5–20 mm 20–40 mm
Fine gravel Gravel Coarse gravel
Molle et al (2004a) Pulse-fed (Second stage) Surface layer
Second layer Drainage layer
30 cm 10–20 cm 10–20 cm
0.25 d10 0.4 mm 3–10 mm 20–40 mm
Sand Gravel Coarse gravel ÖNORM B2505 (2005) Pulse-fed Surface layer
Second layer Third layer Fourth layer Drainage layer
10 cm
50 cm 5–10 cm Separation fabric
20 cm
8–16 mm 0–4 mm 4–8 mm
— 16–32 mm
Gravel Sand/gravel Gravel 2.5-mm mesh Gravel NAWE (2006) Recirculating Main layer
Drainage layer
75 cm
15 cm
12–15 mm 16–40 mm
Gravel Coarse gravel Nielsen (2002) Biosolids dewatering a Surface layer
Second layer Third layer Drainage layer
5–10 cm
15 cm Separation fabric 30–45 cm
— Sandy loam
Sand
— Pebble gravel
a Sludge dewatering effectiveness is dependent on maintaining continuity of the capillary suction under unsaturated flow Therefore, large transitions in the size range of adjacent drainage layers should be avoided, especially between the overlying biosolids material and the top layer of the filter (Nielsen, 2006).
Trang 15flow must be weighed against the construction and
opera-tions costs of pumping For countries with a high level of
infrastructure support, such as the United States, pumping
is perceived as less expensive than extensive earthwork
dur-ing construction For developdur-ing countries, the inverse may
be true
The hydraulic profile for a wetland system results from
a number of different calculations Major components of the
hydraulic profile for SSF wetlands typically include:
The driving head needed to distribute the influent
flow
Frictional losses (head loss) in conveyance piping
Elevation differences between different stages of
the treatment process
Frictional losses in the wetland bed (HSSF
wetlands)
If the bed is intended to completely drain, the
depth of the bed
The elevation and hydraulic characteristics of
water level control devices such as weirs or
standpipes
Separate calculations are made for each unit process,
resulting in a stair-step diagram describing the relative
elevations of the water surface profile (and for pumped
systems, the hydraulic grade line) Typically, calculations
are made at different flow rates, such as the average daily
flow, the minimum flow rate, and the peak daily or hourly
flow rates The peak flows should include the capture of
water from rainfall events; often a 10-year or 25-year
storm event is used for this purpose, depending on the
regulatory jurisdiction
For very small wetland systems, the low flow at night
will be zero due to the diurnal fluctuation in water use
pat-terns This can create a number of design challenges in terms
of flow distribution and, in very cold climates, freezing of
pipes Specific design challenges for small-scale wetland
systems have been addressed in the literature (Wallace and
Knight, 2006)
Generally speaking, the larger the system, the more
important detailed hydraulic calculations become For SSF
wetlands, these calculations must also address anticipated
phenomena such as bed clogging (see Chapter 7) The
pre-ferred design practice for SSF wetlands is to make each bed
completely drainable and also to have a discrete elevation
drop between cells (often, a minimum drop of 0.3 m is
desir-able, unless the site cannot support this elevation change
or hydraulic calculations indicate that this differential is
insufficient)
Hydraulics of HSSF Wetlands
For HSSF wetlands, the water surface profile within the
wetland bed is assumed to be governed by frictional losses
within the wetland bed If flow is within the laminar range,
a simple relationship such as Darcy’s law can be used to
H k
yydraulic conductivity, m/d
This is the one-dimensional version of Darcy’s law It is restricted to the laminar flow regime At higher flow veloci-ties, there will be a turbulent component to the flow, which must also be considered (see Equations 2.44, 2.46, 2.47, Chapter 2) The use of these friction-loss equations are only the start of the hydraulic design process, because what is of most use to the wetland designer is the longitudinal depth profile This is typically a nonuniform profile due to changes
in the flow rate (gains or losses from precipitation, tion, and ET) and hydraulic conductivity of the wetland bed Calculation procedures have been previously established in Equations 2.48–2.54, and the results of such calculations are illustrated in Figure 2.26
infiltra-These calculations are typically performed by dividing the wetland bed into subunits (each with its own hydraulic conductivity) and calculating the head loss across each sub-unit The standard procedure is to start at the effluent end of the bed (the tailwater condition) and work backwards to the inlet
Here, we explore the effects of design parameters on the water surface and its relation to the media surface The goals
of hydraulic design for HSSF wetlands are to convey the design flow within the wetland bed without surfacing while providing an acceptable hydrologic environment for the sur-vival of emergent wetland plants Two philosophies may be used to achieve these goals:
1 A management-intensive scheme, in which tors compensate for hydraulic upsets through oper-ational adjustments
opera-2 A design-intensive scheme, in which the design is made sufficiently conservative so as to eliminate the need for most operational adjustments
In either case, the overall wetland footprint area is presumed
to be set from the treatment requirements as previously cussed in Chapter 20
dis-Normally, the requirement for treatment performance will provide a specification of either the hydraulic load-ing rate or detention time In turn, these combine with the required volumetric flow rate to determine either the volume
of water in the bed or area of the bed However, it must be recognized that many wastewater sources create flows that vary considerably on both diurnal and seasonal time scales Neither the minimum nor the maximum anticipated flow should cause hydraulic failure
Trang 16The requirements for stable water depth and controllable
water flow for creating proper vegetation conditions serve to
further restrict the geometry of the bed and the size of the
media
These requirements can be summarized as
1 Anticipated design flows must pass through the
bed without overland flow or flooding
2 Anticipated design flows must pass through the
bed without stranding the plants above water; i.e.,
there must not be protracted, excessive headspace
that results in desiccation and die-off of wetland
plants
3 Operation should remain acceptable in the
inevi-table event of changing hydraulic conductivity,
especially in the inlet zone As the bed clogs with
roots and microbial biofilms it should not flood
4 The bed should be drainable
5 Water levels within the system should be fully
controllable through the use of inlet and outlet
structures
6 The configuration must fit within the available site
area in terms of project boundaries and hydraulic
profiles
There are often serial and parallel arrangements of
individ-ual wetland cells within a system In the present discussion,
attention is restricted to individual cells and to simple
rectan-gular geometries The variables that may be chosen to satisfy
these considerations are: length (L), bottom slope (Sb), and
the media (D or k) Bed depth (D) is usually in the narrow
range of 30–60 cm and is therefore set by the desire for plant
root penetration within the HSSF bed rather than hydraulics
The width of the system is scaled by the need to carry the full
design flow and by clogging concerns.
There is no theoretical need for a slope to the top of the
bed If water level control is to include the ability to totally
inundate the bed for vegetation management, then a top slope
is detrimental
Because the media is likely to undergo significant changes
in hydraulic conductivity, its frictional resistance cannot be
relied upon for control of the water depth This implies that the conductivity of the media must be large enough, or the water travel distance short enough, to sustain a nearly level pool condition controlled by the elevation of the wetland out-let control structure
In certain cases, it may be desirable to be able to drain the HSSF wetland bed In this case, the bottom slope should
be set to provide for complete bed drainage Normally, a few centimeters of elevation differential allows for this require-ment The wetland bottom slope cannot be considered as the design driving force for water movement The reason is that designs based on bed slope are excessively sensitive to chang-ing conditions of flow and hydraulic conductivity Dry-out or flooding are virtually certain to occur with such designs
Headspace Considerations
Under conditions of very low flow, the water surface will be a horizontal level pool controlled by the elevation of the outlet structure It is necessary that this condition should not create
a dry zone of excessive depth (headspace, f ) (Figure 21.9),
which would occur due to a tilt of the upper bed surface If the top and bottom of the HSSF wetland are both sloped, it creates a condition very conducive to overland flow within the system, as illustrated in Figure 21.10
However, many old HSSF systems have been built to specifications that require uniform bed depth and a signifi-cant bed bottom slope Indeed, early design guidance docu-ments recommended high bottom slopes: 0.5–2.0% (TVA,
1993); 1–5% (Cooper et al., 1996) Another early guideline
was established for Danish systems, namely, restricting the bed surface slope to no more than a 30-cm drop, thereby ensuring that plant roots could reach water even under level pool conditions (Johansen, 1994)
The effect of bed slope is seen in Figure 2.26, Chapter 2, for the Benton, Kentucky, system There, a 0.1% bed slope over 334 m ($B 33 cm) results in a drained bed water ele-vation that is not compatible with the hydroperiod needs of emergent wetland plants at low flow conditions The result was unsuitable water conditions for the target wetland plant
species (Scirpus validus).
Low Flow or High Hydraulic Conductivity with Large Sb
Design intent S = SbActual water surface profile, S
Raising water level
to support plants at inlet causes outlet flooding
Dead plants at inlet due to drought stress
FIGURE 21.9 Water level problems occurring in sloped HSSF wetland beds under conditions of low flow (From Wallace and Knight
(2006) Small-scale constructed wetland treatment systems: Feasibility, design criteria, and O&M requirements Final Report, Project
01-CTS-5, Water Environment Research Foundation (WERF): Alexandria, Virginia Reprinted with permission.)