In contrast, NEPA provides a comprehensive planning process, but lacks a set of intrinsic tools for effectively implementing its procedural requirements.. These checklists have been used
Trang 1Approaches for Improving and Streamlining NEPA
This chapter describes tools, techniques, and approaches for improving and streamlining National
Environmental Policy Act (NEPA) and environmental planning problems As illustrated by the
following story, the success that an agency has in streamlining or improving NEPA is, to a large
measure, dependent on how that agency chooses to practice the Act
2.1 NEPA AND PROCESSIONARY CATERPILLARS
As many biologists will testify, processionary caterpillars meander their way through tree branches,
each one with its head fitted snugly against the rear extremity of its predecessor The long, winding
procession thus formed gives the caterpillars their aptly deserved designation
Intrigued by this behavior, the naturalist Jean-Henri Fabre lured a colony of these creatures onto
the rim of a pot In due time, the caterpillars began to snuggle up to one another, and after forming
an interconnected chain eventually began to move around in a large circle Since the chain had no
beginning or end, Fabre expected that the caterpillars would soon tire of this unceasing parade and
head off in a new direction Such was not the case
Fascinated, Fabre placed a supply of food next to them, but to no avail Undeterred by the food
that was outside the domain of their circle, the caterpillars continued on To his dismay, apparently
propelled by sheer force of habit, the creeping circle continued edging ever onward in the same
unceas-ing circle for 7 days and 7 nights Finally, exhaustion and starvation did them in The moral of the story
is that they were unable to break convention and venture out beyond their established paradigm.1
2.1.1 I MPROVING F EDERAL P LANNING
Today, federal agencies are increasingly being asked to do more with less Efficiency is vital to the goal
of successfully implementing its mission Thus, to avoid going the way of the processionary
caterpil-lars, agencies must be open to new and more effective paradigms for complying with environmental
requirements This goal requires an institutional framework within which modern methodologies can
be applied to improve the planning process Perhaps most importantly, there must be a top-down
will-ingness to accept modern tools, techniques, and approaches for improving planning processes
Once innovative approaches have been instituted, practitioners must be trained to use them For
example, the U.S Army reports that training is a particularly valuable instrument for streamlining
NEPA Professionals are kept abreast on the latest approaches for implementing its requirements
The following sections have been written to assist agencies in improving their environmental
planning and analysis processes
2.2 SLIDING SCALE AND THE RULE OF REASON
Professional judgment and common sense must be exercised in determining the appropriate scope of an
analysis Because the following two principles provide powerful tools for reducing cost, delays, and the
amount of effort expended in implementing NEPA, they will be referred to throughout this chapter
Trang 22.2.1 T HE S LIDING -S CALE A PPROACH
The sliding-scale approach recognizes that the amount of effort expended in performing an
analy-sis is a function of the particular circumstances involved in each case A sliding-scale approach is
justified based on the following regulatory directions
Impacts shall be discussed in proportion to their significance There shall be only brief discussion of
other than significant issues (40 CFR § 1502.2[b])
NEPA documents must concentrate on the issues that are truly significant to the action in question,
rather than amassing needless detail (40 CFR § 1500.1[b])
Thus, environmental issues are investigated and regulatory requirements are applied using a degree
of effort commensurate with their importance In other words, the amount of effort expended in
investigating or addressing a specific regulatory issue should generally vary with the significance of
the potential impact and its importance to the decision-making process
2.2.2 R ULE OF R EASON
Professional experience suggests that a strict or unreasonable application of a regulatory
require-ment may lead to a course of action, decision, or level of effort that is wasteful or even absurd The
Rule of Reason is a mechanism used by the courts to inject reason into the NEPA process In other
words, common sense must be exercised in determining the scope, detail, and attention devoted to
issues, alternatives, and impacts considered in the analysis
2.3 STREAMLINING AN AGENCY’S NEPA PROCESS
In the mid-1990s, a vice president of a contractor working at the U.S Department of Energy’s
Hanford Site issued a memorandum listing the top 10 processes responsible for delaying site projects
The site procurement and NEPA processes were both listed in this memorandum as significant
problems
Instead of denying that a problem existed or placing blame elsewhere, a proactive effort was
mounted to identify approaches for improving the site-wide NEPA process The author was assigned
to an interdisciplinary team (IDT) to investigate and streamline this process
Two value engineering (VE) studies were performed The first study examined the NEPA
pro-cess in an effort to identify root problems for inefficiencies and develop a list of recommendations
for streamlining NEPA A second study was then performed to determine how NEPA could be
better integrated into site planning and decision-making As it turned out, the site planning process
was complicated and was being performed by a number of independent departments The goal of
this second study was twofold: (1) to prevent project delays by ensuring that NEPA was triggered
early in the planning process and (2) to improve the effectiveness of NEPA in contributing to the
Department of Energy (DOE) decision-making process
A VE approach that was used to examine the NEPA process is briefly summarized in the next
section As described in the companion book, Environmental Impact Statements, it is important to
note that VE techniques can also be used as a tool for helping to assess the scope or issues
consid-ered in an environmental impact statement (EIS)
Data such as the length of time required to complete NEPA projects were not collected prior
to the VE workshops described above Therefore, there were no statistics available for gauging the
level of success these VE workshops attained in terms of streamlining NEPA However, there was a
general consensus among management that the VE efforts led to a substantially streamlined NEPA
process and also improved the ability of NEPA to contribute to the early decision-making process
Perhaps most important, as a result of these improvement efforts, NEPA was dropped from the list
of 10 biggest problems on the Hanford Site
Trang 3An overview of the VE process and how it can be adapted to resolve problems in NEPA are
described below
2.4 VE IMPROVEMENT PROCESS
The Society of American Value Engineers (SAVE) has revised the VE terminology, redefining VE as
the Value Methodology for which new standards have been published However, consistent with
com-mon usage in the engineering disciplines, this book will use the more traditional terminology of VE.2
A VE workshop can be an intensely focused effort, such that a large amount of work can be
accomplished in a very short period In determining the preliminary scope, the goal is to leave no
stone unturned Typically, a VE facilitator leads an IDT through a number of rigorous procedures
designed to break down preconceived and prejudicial notions and to consider new and alternative
concepts that might lead to better solutions.3 The facilitator is responsible for keeping the session
focused and for promoting an open and nonhostile atmosphere where prevailing assumptions,
mind-sets, and paradigms are challenged to identify more optimal solutions Prejudicial and preconceived
notions are openly challenged as the IDT identifies factors and solutions that might otherwise be
overlooked The typical sequence of steps is shown below
2.4.1 P RELIMINARY R EVIEW
As a first step in the typical VE process, a preliminary review or pre-study (e.g., on a specific
pro-posal, program, project, process, or design) may be useful in determining if the potential return
on investment is sufficient to justify a formal VE workshop Emphasis is placed on examining the
proposal/activity to determine if potential alternatives show promise for increasing value If a VE
study is deemed to be cost-effective, the pre-study is also used to
1 define the scope, objectives, and expected deliverables;
2 establish logistical elements necessary to ensure a successful result;
3 gather preliminary information; and
4 select the study group’s membership
If a decision is made to proceed into a formal VE workshop, a facilitator is assigned and charged
with responsibility for leading the VE team An IDT is carefully selected to include professionals
possessing a diverse range of technical expertise and experience The team challenges existing
paradigms and assumption in an effort to identify new or alternative concepts that may lead to
bet-ter solutions.3 As outlined next, the general VE process consists of a sequence of distinct steps or
phases
2.4.2 S EVEN P HASES
A standard VE study normally consists of the following seven distinct phases Each of these phases,
together with an emphasis on how they can be used to improve NEPA, is described in the following
sections:
Phase 1: Information phasePhase 2: Functional analysis phasePhase 3: Creativity phase
Phase 4: Evaluation and analysis phasePhase 5: Development phase
Phase 6: Presentation phasePhase 7: Post study/Implementation phase
Trang 4With respect to streamlining the NEPA planning process, not all of the following phases are
neces-sarily pertinent or need to be performed Professional judgment must be exercised, on a case-by-case
basis, in determining those phases that can be most effectively integrated with NEPA planning
2.4.2.1 Phase 1: Information Phase
Information pertinent to the scope of the proposal (or action under investigation) is collected and
disseminated to the members of the VE study Limitations and constraints that may affect the study
results are identified and, if necessary, ranked with an assigned value For example, information
could be shared regarding how plans are formulated and who is responsible for making certain
types of decisions
2.4.2.2 Phase 2: Functional Analysis Phase
A tool referred to as a “function analysis system technique (FAST) diagram” is frequently developed
as part of a standard VE workshop The FAST diagram can be used to critically evaluate “how”
ver-sus “why” critical functions are currently performed or would be performed For example, a FAST
diagram might be prepared to question why certain steps in the planning process are carried out
Items that have high potential for added value may be earmarked for more detailed examination in
the later study
However, a FAST diagram does not necessarily generate information useful to improving an
agency’s NEPA process Because of the amount of effort necessary to construct a FAST diagram,
its utility (with respect to improving the NEPA planning process) should be carefully questioned
before an effort is launched to prepare such a diagram
2.4.2.3 Phase 3: Creativity Phase
Team participants are encouraged to exercise creativity with the objective of identifying potential
solutions for solving a particular problem Methods such as brainstorming are used to generate
innovative ideas for more detailed consideration For example, ideas could be sought for
streamlin-ing various aspects of the agency’s plannstreamlin-ing process
2.4.2.4 Phase 4: Evaluation and Analysis Phase
In this phase, ideas generated during the creativity phase are organized into concepts possessing
similar features These can then be solidified into potential alternatives and ranked using one of a
variety of techniques
One ranking technique that has been used is referred to as “Criteria Weighting Matrix and
Evaluation Analysis Ranking.” Another ranking technique known as the “Nominal Group
Tech-nique” is described in Table 2.1 Options are then evaluated with respect to their advantages and
disadvantages For example, this phase could be used to single out ideas that show the most promise
for streamlining the NEPA process
2.4.2.5 Phase 5: Development Phase
Potential improvement options deemed to have the greatest potential for improving the NEPA
pro-cess during the analysis step are further evaluated and developed into viable, efficient, and
cost-effective options or alternatives
2.4.2.6 Phase 6: Presentation Phase
Options for improving the NEPA process are documented in a report and presented as a study
proposal
Trang 52.4.2.7 Phase 7: Post Study/Implementation Phase
The workshop recommendations are considered and evaluated by the team and management Tasks
are assigned to individuals who are then responsible for implementing the chosen recommendations
for improving NEPA
2.4.3 U SING VE IN P REPARING AN EIS
The Office of Management and Budget has directed federal agencies to apply VE in planning major
federal projects exceeding a cost of $1 million.4 As a result, both the EIS and the VE are mandated
to be performed on major federal projects However, this raises a question: Is this simply another
case where overlapping or redundant requirements have been mandated?
This question can best be answered by examining the underlying purposes of VE and NEPA
VE provides a tool box of problem-solving techniques for analyzing problems and identifying
solutions However, VE is not a planning process
In contrast, NEPA provides a comprehensive planning process, but lacks a set of intrinsic tools for
effectively implementing its procedural requirements Thus, VE offers a set of tools that, potentially,
can manage various aspects of the EIS planning process To date, this connection appears to have gone
largely unrecognized An integrated NEPA/VE planning approach for complex projects such as
pre-paring a programmatic EIS may be advantageous as it provides an efficient means for complying with
both Council on Environmental Quality (CEQ) and the Office of Management and Budget mandates
2.4.3.1 Comparison of VE with NEPA
Table 2.2 compares principal characteristics and goals of NEPA with those of VE While NEPA
and VE share strikingly similar goals and requirements, they are not redundant; in fact, not only
are NEPA and VE compatible, but also they complement each other Their commonality in goals
provides a foundation in which VE can be used as a tool for increasing the effectiveness of an EIS
planning process However, it should be noted that although VE and NEPA share many common
requirements, their underlying goals differ While VE offers many tools and techniques useful in
managing the NEPA process, its orientation is different The objective of VE is toward identifying
and solving root problems that are related to, but are not normally the underlying focus of, an EIS
scoping effort Accordingly, a successful strategy requires prudence in the selection of the
appropri-ate VE techniques that will be useful in preparing specific aspects of an EIS
TABLE 2.1
The Nominal Group Technique
Step 1: Generate ideas
The facilitator asks group members to write down the important problems or options for resolving these problems Team
participants write their ideas on note cards.
Step 2: Record ideas
A round-robin approach is used to record the ideas generated in Step 1 This process continues until all items have been
recorded Next, to prevent confusion, the facilitator asks each participant to explain briefly the items submitted
Participants are not allowed to criticize or critique any of the suggestions during this phase.
Step 3: Polling
A potentially long list of ideas must be narrowed down to capture the most salient ideas Many methods exist for
accomplishing this task One common method is to have each participant write down three ideas considered to be the
most important These techniques are tabulated by the facilitator A second round is then conducted to prioritize the final
list of ideas.
Trang 62.5 USING VE IN DETERMINING THE PRELIMINARY SCOPE OF AN EIS
This section describes how the author used a modified VE workshop approach in performing a
prescoping effort for a complex EIS A paper previously published by the author describes this
approach in more detail.15
As described earlier, pursuing a standard VE study is deemed at times to be an ineffective use
of scarce resources A considerable degree of forethought and professional experience is therefore
required in devising a cost-effective approach for using a VE approach in scoping an EIS
Accordingly, emphasis was placed on developing an approach where VE techniques could be
used specifically to focus and manage various aspects of the prescoping effort Once a strategy had
been developed, an agenda and workshop mission statement were prepared to provide a tangible
map for implementing the strategy The following process can be modified for use in
perform-ing a public scopperform-ing process and in identifyperform-ing, evaluatperform-ing, and managperform-ing other issues in the EIS
process
Results of this prescoping workshop provided an early indication of the issues, problems, and
levels of effort that would be required if it was found advisable to prepare an EIS Determining the
preliminary scope also provided a basis for forecasting the cost and resources required in preparing
the EIS Table 2.3 provides a simplified agenda, while Table 2.4 describes the goals and objectives
for this prescoping workshop Table 2.3 should be revised, as necessary, for performing a formal
public scoping process
2.5.1 A SSEMBLING AN IDT
To ensure that all relevant planning factors were captured, emphasis was placed on assembling an
IDT of experts Approximately 10 full-time and 15 part-time members participated The prescoping
workshop ran over four consecutive days
TABLE 2.2
Comparison of VE with NEPA
VE provides management tools useful in planning NEPA is a planning process.
The Office of Management and Budget has mandated
that VE be applied to the planning of all major
projects.
NEPA is the only federally mandated planning process applicable to all major federal actions.
Uses a systematic and interdisciplinary process to
arrive at a better value solution.
Is predicated on use of a “systematic interdisciplinary”
approach 5
Provides an important tool for assessing planning
problems.
“Combines” 6 other federal planning processes during the
“early” 7 planning phase.
Based on an unbiased and rigorous process Requires the use of a “public,” 8 unbiased, 9 and “rigorous”
process 10
VE should be applied early enough to assist in
decision-making It is not intended to justify decisions already
made.
An EIS must be prepared early enough to serve as an important contribution to decision-making The EIS is not to be used to rationalize or justify decisions already made 11
VE can be used to assess planning requirements (e.g.,
cost, schedule, environmental).
NEPA allows the consideration of cost and other factors in the analysis and decision-making process.
Necessitates a full and fair analysis of alternatives to
improve the value of the final product.
An EIS analysis must provide a “full and fair discussion” of impacts and reasonable alternatives 12
Promotes consideration of all possible alternatives An EIS must explore and objectively evaluate all reasonable
alternatives 13 Alternatives form the “heart” of the EIS 14
Trang 7A kick-off meeting was held prior to initiating the VE workshop to discuss its purpose and
objectives, and to assign action items The prescoping workshop mission statement and agenda were
distributed at the meeting Certain members were identified and requested to prepare presentations
for the information sharing session to be held on the first day
TABLE 2.3
Integrated EIS/VE Prescoping Agenda
Day 1
1 Welcome and introductions (session guidelines and expectations).
2 Overview of the problem statement, agenda, VE, and EIS process.
3 Information sharing session.
4 Document potential decision-making assumptions.
5 Preparation of a FAST diagram for the no-action alternative.
Day 2
1 Brainstorming session to
identify criteria that might affect future decisions; and
identify high-level decisions that might need to be addressed by the EIS Rank decisions in importance.
2 Construction of a DIT (summarized below).
Day 3
1 (a) List, consolidate, and prioritize preliminary scope of facilities, functions, and issues to be considered in the EIS.
1 (b) Based on the key issues, develop a list of facilities and functions that would need to be analyzed in the EIS.
2 (a) De-scoping: determine issues that will not be included in the preliminary scope of the EIS.
2 (b) Document issues that are important but not included in the preliminary scope so that they can be revisited at a later
date Some issues might be flagged as candidates for later tiering.
3 Identify any outstanding issues or concerns.
4 Brainstorm ideas for reducing EIS cost and schedule in order to identify specific actions that can be taken to help
streamline the scope and EIS process.
Goals and Objectives of the Prescoping Workshop
Goals of the scoping workshop
• Determine preliminary scope of the actions, facilities, and operations requiring evaluation in the EIS.
• Identify methods for streamlining the EIS process.
• Define the scope of decisions that might need to be considered in the future.
• Reduce risk of later surprises (i.e., changes in scope resulting from inadequate communications or planning).
• Provide a basis for determining the cost and schedule of the EIS.
Objectives of the scoping workshop
• Develop a FAST diagram of the no-action alternative.
• Determine the underlying need for taking action Identify the purpose (objectives) that the proposal will need to meet.
• Construct a DIT to determine specific decisions that might need to be made (described in Chapter 8).
• Identify key issues and concerns.
• Identify factors that might influence the decision-making process.
• Determine issues that will not be included in the scope (de-scoping).
• Document issues that are important but not to be included as part of this scope, so that these issues can be revisited at
a later date (i.e., later tiering).
Trang 82.5.2 I NFORMATION P HASE
The prescoping workshop began with a review of the workshop mission statement and an
explana-tion of the process and techniques used The workshop then proceeded to the informaexplana-tion phase,
which was used to gather and share information that might have a bearing on determining the
preliminary scope Issues such as other ongoing NEPA activities, inconsistencies, gaps in NEPA
documentation, related documents and studies, and other related or planned projects were identified
during this phase Information such as keywords, memories (e.g., ideas and concepts), issues and
concerns, and assumptions were captured on flip charts The facilitator was responsible for keeping
the session focused on schedule Except for cases where unusual circumstances exist, it is
recom-mended that this phase be limited to no more than a few hours
An exercise was performed to identify key planning assumptions A brainstorming exercise
then followed in which the facilitator challenged the group to identify assumptions important to
this planning effort Assumptions identified during the remaining portion of the workshop were
Similarly, an exercise was performed to identify principal planning documents and studies that
might have a bearing on the preparation of the EIS Capturing such information at this early
plan-ning phase is important, not only because it may affect the scope, but also because it could prevent
duplication and wasted effort
A flip chart list was also maintained for capturing special issues and concerns raised throughout
the workshop Such a list should be referred to both in preparing the formal EIS scoping process and
in preparing the actual analysis
2.5.3 D ECISION -I DENTIFICATION P HASE
An EIS cannot properly support subsequent decision-making if it does not correctly anticipate and
address decisions that might require future consideration While such an observation appears
obvi-ous, it is not uncommon to find that the EIS has been completed only to discover that it does not
adequately anticipate the types of decisions that actually needed to be considered Such
discrepan-cies frequently result from disconnects between the scope of the analysis and the actual
decision-making that follows This observation is particularly true when dealing with complex actions or
dynamic circumstances
For this reason, the prescoping workshop used a systematic approach developed by the author
and referred to as decision-based scoping (DBS) and decision-identification tree (DIT), which is in
marked contrast to the way most scoping efforts are typically conducted A DBS approach is
espe-cially well suited for large or complex EISs, and in scoping programmatic EISs The DIT provided
a systematic methodology for identifying and mapping potential decisions that might need future
consideration by a decision-maker and which therefore need to be addressed in the scope of the EIS
The DBS and DIT are both detailed in Chapter 8
2.5.4 U NDERLYING N EED AND P URPOSE : D EFINITION
In support of the DBS approach, an effort was mounted to define the underlying need for future
action in a succinct manner Identifying and properly defining the “need” for taking action can be
deceptively complicated The need might at first appear intuitively obvious, yet on closer
inspec-tion confusion or differing views as to its true meaning may arise Note that Webster’s Dicinspec-tionary
defines “need” as “a want of something requisite, desirable, or useful.”
To this end, the group was challenged to identify the underlying need(s) Responses voiced by
the participants were recorded on a flip chart by the facilitator Next, the group reviewed, sorted, and
consolidated these responses to develop the required succinct definition of the primary or
underly-ing need Similarly, an exercise was conducted to determine potential objectives to aid in
identify-ing the underlyidentify-ing purposes As detailed in the companion text, Environmental Impact Statements,
continuously added to the flip chart list
Trang 9precise definition of the underlying need is an important first step to take because it can drive the
range of alternatives that will be investigated later.16,17 Not surprisingly, even a small change in the
definition of need can have profound implications on the alternatives that are eventually chosen for
analysis Thus, correctly defining the need at this early stage can substantially improve the
effec-tiveness of the planning process that follows
Once consensus was reached regarding the need, the IDT was tasked with defining the
pur-pose for taking action The term purpur-pose should not be confused with the term need “Purpur-pose” is
defined in Webster’s as a “goal” or “object” to be obtained.
2.5.5 E NHANCING E FFECTIVENESS OF THE EIS P ROCESS
An effort was also mounted to identify methods and approaches for reducing cost and expediting
preparation of an EIS Brainstorming techniques were used to elicit ideas from participants in an
attempt to investigate every conceivable method for improving the efficiency and effectiveness of
the potential EIS The facilitator recorded suggestions offered by the participants on flip charts
Special VE techniques were used to evaluate these suggestions The evaluation consisted of three
distinct stages or rounds
In the first round, the group reviewed all the suggestions in an attempt to eliminate those that
were clearly unreasonable or of little value Item by item, the facilitator led the IDT through each
suggestion in an attempt to identify which of them could be dropped The rule used in this round
was that unanimous consensus had to be obtained before an item could be eliminated
Because of time constraints, the second and third rounds that followed were actually combined
into a single round for this EIS effort Normally, the second round consists of consolidating and
combining suggestions into manageable categories The third and final round normally involves the
use of matrix weighting methods, such as a nominal group technique, in an effort to generate a final
list of concepts On completing this task, the team formulated specific recommendations that could
be undertaken to expedite preparation of an EIS As a final step, success-oriented criteria (e.g., cost
and schedule considerations, ease of implementation, and budget constraints) were used to prioritize
the recommendations for consideration by decision-makers
2.5.6 I NVESTIGATING THE N O -A CTION A LTERNATIVE
Where an EIS is being prepared for a complex proposal or program, the IDT might also want to
consider preparing a FAST diagram to assess activities currently being conducted as part of the
no-action alternative The FAST diagram technique is founded on the observation that a rigorous
evaluation of functions underlining a particular process provides a basis for evaluating problems
and alternatives The FAST diagram provides a systematic tool for identifying these functions
Process functions were first identified and described using sentences containing active verbs
and proper nouns Using these functions, a diagram was constructed illustrating “how” and “why”
particular functions are conducted Scanning the diagram from right to left reveals “why” particular
functions are performed Conversely, scanning the diagram from left to right reveals the sequence
of “how” functions are conducted When completed, the sequence of how functions are conducted
should be internally consistent with the reason why each function is conducted
Next, an effort was undertaken to identify methods for improving or optimizing a program
func-tion A FAST diagram can provide a useful tool for understanding the current baseline, identifying
functional requirements and relationships, and challenging preconceived assumptions and ideas
Where appropriate, other planning considerations such as resource and infrastructure requirements
may also be identified
As described in Section 2.4.2.2, preparation of a FAST diagram can be resource intensive,
con-suming a substantial amount of a scoping workshop schedule And, as previously stated, in some
cases a FAST diagram might contribute valuable information, whereas in other cases little or no
Trang 10benefit would be derived from its construction Lacking a clear and specific objective for its use,
practitioners are ill-advised to devote scarce resources constructing a FAST diagram For this
rea-son, it is well to reiterate that prudence and professional judgment must be exercised in determining
the appropriate use and application (if any) of a FAST diagram with respect to scoping
2.5.7 E LIMINATING I SSUES FROM THE S COPE
One of the principal objectives of the scoping process is to eliminate unimportant issues De- scoping
is a powerful method for reducing the cost of an EIS and it is a requirement that is often
underuti-lized.18 Efforts should be focused on eliminating insignificant or irrelevant issues Properly applied,
such a method can substantially reduce time and resources required in preparing an EIS
Partly for this reason, an effort was mounted to identify candidate issues for elimination
dur-ing the formal scopdur-ing process Emphasis was placed on documentdur-ing issues that were considered
important but eligible for deferral from the immediate scope of this EIS These issues could thus be
revisited, if necessary, at a later date (some issues might be flagged as candidates for later tiering)
2.5.8 I DENTIFYING O THER R ELATED R EQUIREMENTS
Regulatory requirements can profoundly influence cost, schedules, and the direction of future
actions For this reason, it is recommended that an exercise be performed to identify other related
environmental and regulatory drivers
For example, a preliminary matrix might be prepared of potential regulatory requirements
versus potential alternatives that eventually would be analyzed A regulatory compliance matrix
provides a “heads-up” so that the agency is not surprised by unanticipated requirements that may
emerge later The stage is now set for presenting the results
2.5.9 F INALIZING THE P RESCOPING E FFORT
The final phase involved is presenting the results of the prescoping workshop Focused toward peer
review, this phase allows the agency and decision-maker(s) to review the potential scope to
deter-mine if issues that have not been addressed remain
In this case, the general consensus was that construction of the DIT, in conjunction with the
VE workshop, had been very effective in identifying what was otherwise a rather enigmatic set
of potential issues and actions With only one exception, the prescoping workshop successfully
identified principal issues and actions considered essential for analysis
It is important to note that at this stage the scope is still preliminary and may evolve once
addi-tional information or public scoping comments are received Still this effort was very effective in
providing an early indication of the scope, which was useful in planning the public scoping process,
identifying agency consultations, preparing cost estimates and schedules, and developing
prelimi-nary engineering and environmental support studies
Once this step has been completed, the stage is now set for preparing and issuing a notice of
intent (NOI), which completes the prescoping phase
A facilitated workshop approach such as the one described above may also offer a useful tool for
effectively managing and performing formal public scoping sessions Such an approach also has the
advantage of ensuring that each participant has an opportunity to provide feedback and voice opinions
2.6 A STRATEGY FOR EFFICIENTLY IMPLEMENTING A POLLUTION
PREVENTION PROGRAM
In 1990, the U.S Congress passed the Pollution Prevention Act.19 President Clinton issued an
executive order instructing federal agencies to implement pollution prevention (P2) measures in
1993.20 Similarly, the International Organization for Standardization (ISO) has developed a series of
Trang 11environmental management, auditing, and performance standards known as the ISO 14000 series;
the ISO 14000 series speaks to the merits of pollution prevention, particularly from the standpoint
of establishing a top-level policy committed to pollution prevention
The following section describes a systematic strategy developed by the author for effectively
integrating P2 objectives with DOE Hanford Site projects and operations This integrated NEPA/P2
strategy received two Secretary of Energy commendations The purpose of the following example
is to illustrate how a federal facility’s NEPA planning process can be used to efficiently implement
a P2 program
Because project requirements, procedures, operations, and the details of each agency’s NEPA
process vary, the readers should consider this example from the perspective of how it can be adapted
to their own specific internal projects and programs
2.6.1 NEPA P ROVIDES AN I DEAL I MPLEMENTATION M ECHANISM
With very few exceptions, all proposed federal actions are potentially subject to NEPA’s
require-ments For this reason, NEPA provides the ideal mechanism or framework for efficiently reviewing
new (proposed) federal actions that may present opportunities to reduce pollution and waste
gen-eration While P2 is not specifically mentioned, its inherent objectives are captured in the purpose,
goals, and requirements of NEPA, and its implementing regulations Significant cost savings may
be realized by properly integrating NEPA with P2
NEPA regulatory direction is consistent with the purpose and goals of an integrated NEPA/P2
strategy (Table 2.5) Table 2.6 shows that NEPA’s policy is consistent with that of P2 As indicated
TABLE 2.5
NEPA’s Regulatory Direction is Consistent with an Integrated Pollution Prevention Act
• Ultimately, of course, it is not better documents but better decisions that count NEPA’s purpose is not to generate
paperwork—even excellent paperwork—but to foster excellent action (§ 1500.1[c])
• The NEPA process is intended to help public officials make decisions that are based on understanding of environmental
consequences, and take actions that protect, restore, and enhance the environment (§ 1500.1[c])
• Use all practicable means, consistent with the requirements of the Act and other essential considerations of national
policy, to restore and enhance the quality of the human environment and avoid or minimize any possible adverse effects
of their actions upon the quality of the human environment (§ 1500.2[f])
TABLE 2.6
NEPA’s Policy is Consistent with the Pollution Prevention Act
• “…to promote efforts which will prevent or eliminate damage to the environment and biosphere and stimulate the
health and welfare of man; to enrich the understanding of the ecological systems and natural resources important to the
Nation … (Sec 2 [42 USC § 4321])
• use all practicable means [to:]
fulfill the responsibilities of each generation as trustee of the environment for succeeding generations;
assure for all Americans safe, healthful, productive, and aesthetically and culturally pleasing surroundings;
attain the widest range of beneficial uses of the environment without degradation, risk to health or safety, or other
undesirable and unintended consequences;
achieve a balance between population and resource use which will permit high standards of living and a wide sharing
of life’s amenities; and
enhance the quality of renewable resources and approach the maximum attainable recycling of depletable resources.”
(NEPA, Sec 101 [42 USC § 4331][b], 1969)
Trang 12in Table 2.7, NEPA is to be combined and integrated with other environmental requirements and
processes whenever practical; and, as demonstrated in Table 2.7, NEPA provides both an effective
and efficient environment framework for incorporating P2 objectives into new actions
2.6.2 NEPA P ROVIDES A C OMPREHENSIVE D ECISION -M AKING P ROCESS
A component essential to NEPA as well as to some aspects of P2 is a requirement to rigorously
analyze environmental impacts, alternatives, and mitigation measures As depicted in Table 2.8, the
NEPA regulations provide specific direction for analyzing actions such as P2 measures
NEPA provides decision-makers with many advantages not found in other environmental
pro-cesses Moreover, while NEPA mandates rigorous requirements for performing environmental
analyses, it places no substantive restrictions on agencies regarding the final decision that may be
reached NEPA only requires that the final decision has been adequately investigated, such that a
decision-maker can make an informed decision regarding the course of action to be taken NEPA,
therefore, allows decision-makers to consider many diverse factors, such as environmental impacts,
economics, schedules, technology, risk, and other practical considerations, in reaching a final
decision
Although P2 is often touted as a cost savings measure, some waste reduction actions may
actu-ally result in cost increases In practice, decision-makers may be faced with having to make difficult
tradeoffs between the goals of P2, other environmental requirements, scarce resources, cost, and
agency requirements Fortunately, NEPA provides decision-makers with a flexible and analytical
planning process for evaluating such tradeoffs and resolving dilemmas in an effort to reach a
ratio-nally based and legally defensible decision
2.6.3 P ROCESS FOR I NTEGRATING NEPA AND P2
A set of checklists has been prepared by the DOE for assessing a diverse range of activities in terms
of potential P2 measures These checklists have been used by employees to identify measures that
TABLE 2.7
Integrating NEPA with Other Environmental Processes
• Integrate the requirements of NEPA with other planning and environmental review procedures required by law or by
agency practice so that all such procedures run concurrently rather than consecutively (§ 1500.2[c])
• Integrating NEPA requirements with other environmental review and consultation requirements (§ 1500.4[k])
• Combining (combine?) environmental documents with other documents (§ 1500.5[i])
TABLE 2.8
NEPA Direction for Analyzing Actions such as Pollution Prevention Measures
• Use the NEPA process to identify and assess the reasonable alternatives to proposed actions that will avoid or minimize
adverse effects of these actions upon the quality of the human environment (§ 1500.2[e])
• Study, develop, and describe appropriate alternatives to recommended courses of action in any proposal which involves
unresolved conflicts concerning alternative uses of available resources as provided by Section 102(2)(E) of the Act.
(§ 1501.2[c])
• To assess the adequacy of compliance with Sec 102(2)(B) of the Act the statement shall, when a cost-benefit analysis
is prepared, discuss the relationship between that analysis and any analyses of unquantified environmental impacts,
values, and amenities (§ 1502.23)
• Rigorously explore and objectively evaluate all reasonable alternatives … (§ 1502.14[a])
Trang 13could be taken to implement specific P2 measures It is important to note that P2 measures may be
applicable to a proposed action even though the action may not result in a significant impact
Figure 2.1 depicts a high-level integrated strategy developed for the U.S Department of
Ener-gy’s Hanford Site The NEPA process provided the framework for efficiently implementing a
com-prehensive P2 program Figures 2.2 through 2.4 describe the details of implementing the integrated
NEPA/P2 strategy.21 The readers should consider how this site-specific strategy could be modified
and adopted to other sites or programs
The following discussion focuses on describing the implementation of a P2 program rather
than describing specific aspects of the NEPA process itself As depicted in Figure 2.1, an integrated
NEPA/P2 process begins with identifying a need to take action
Identify need for taking action
Is categorical exclusion applicable?
Prepare EA?
Some entity such as a P2 Program Office reviews the proposal for P2 measures
See Figure 2.3
Prepare NEPA request form
Review proposed action:
- Identify preliminary P2 measures
NEPA determination meeting:
- Determine NEPA level
- Provide initial P2 guidance
Figure 2.4
See Figure 2.2
Trang 142.6.3.1 Categorical Exclusions
Typically, a review is performed to determine if a proposed action can be categorically excluded
from further NEPA review Specific details of a categorical exclusion (CATX) process may change
from agency to agency, depending on an installation’s internal procedures, requirements, and
con-straints Consequently, this section will not dwell on the specific implementation details of the
inte-grated NEPA/P2 process that was developed for the Hanford Site Instead, readers should consider
how a P2 program can be adapted to their specific internal CATX process A generalized summary
of the integrated NEPA/P2 process is described below
The CATX response is depicted by the diamond labeled “Is categorical exclusion applicable?”
in Figure 2.1 If the response is “yes,” the reader is directed to Figure 2.2 Figure 2.2 details the
process used in determining if and when P2 measures are applicable to an action that is eligible for
Submit CATX to agency’s NEPA
office for approval
Prepare and attach P2 checklist
to CATX Transmit copy of P2
checklist to some oversight
entity such as a P2 program
Office for review
Are P2 measures applicable?
Pursue action
FIGURE 2.2 Process for integrating pollution prevention measures with the CATX process.
Trang 15Some agencies recognize two types of CATXs: (1) documented and (2) nondocumented This
step is depicted by the diamond labeled “Documented CATX?” in Figure 2.2 If the CATX requires
no documentation (“no” path, diamond labeled “Documented CATX?”), this strategy assumes
that the action and its impacts are essentially trivial, and it is therefore not practical to review the
action for potential P2 measures If the CATX requires documentation (“yes” path, diamond labeled
Scoping direction
Prepare P2 checklist
Transmit copy of P2 checklist to some entity such
as a P2 Program Office for review
Describe and analyze P2 measures in EA
Incorporate P2 into mitigation measures
Submit EA for review and approval
Append P2 checklist to EA
Document in EA that no
“reasonable” P2 measures were identified
Is P2 applicable?
Determine applicability of P2
Review proposed action Figure 2.3
No
Mitigated EA?
Input from P2 entity such as a P2 Program Office
Document adopted P2 measures in FONSI
Incorporate P2/mitigation into EMS (if practical)
Yes
Yes
No
Input Input
Issue FONSI
FIGURE 2.3 Process for integrating pollution prevention measures into EAs.
Trang 16“ Documented CATX?”), a review is performed to determine if P2 measures are applicable to the
proposed action
The action is pursued if no practical P2 measures are identified (“no” path, diamond labeled
“Are P2 measures applicable?”) If practical P2 measures are identified (“yes” path, diamond labeled
“Are P2 measures applicable?”), an appropriate P2 checklist(s) is prepared and attached to the
docu-mented CATX for review If appropriate, the P2 Program Office (or equivalent) provides input and
Prepare P2 checklist(s) Transmit copy of P2
Checklist to P2 office
Public P2 input
Identify, screen, and describe reasonable P2 measures
Review reasonable alternatives for potential P2 measures
Begin internal scoping Figure 2.4
Some entity such as a P2 Program Office
Document adopted P2 measures in the ROD
Begin public scoping.
Request comments on P2
Review P2 scoping comments
Analyze P2 measures for
proposed action, alternatives, and mitigation
measures
Finalize EIS
Implement adopted P2 measures using EMS (if applicable)
P2 Post-EMS monitoring and auditing
Input
Input Input
FIGURE 2.4 Process for integrating pollution prevention measures into EISs.
Trang 17assistance in preparing the P2 checklist A copy of the completed P2 checklist is transmitted to
some responsible entity such as a P2 Program Office Where practical, any adopted P2 measure
could be implemented and monitored through an environmental management system (EMS), such
as the one outlined in Section 2.7
2.6.3.2 Environmental Assessment Process
A different strategy is followed for actions involving preparation of an environmental assessment
(EA) This process might be triggered by filling out a NEPA request form (see box labeled “Review
proposed action,” Figure 2.3) The NEPA request form could be modified to require an initial
screening for potential P2 measures; a review is then performed to determine the applicability of
P2 measures The proposed action is reviewed to identify potential measures for achieving NEPA/
P2 goals such as reducing or preventing pollution, waste minimization, and energy conservation
Where appropriate, the P2 office assists in identifying potential P2 measures
If no P2 measures are considered practical (“no” path, diamond labeled “Is P2 applicable?”),
this fact is documented in the EA; the EA then continues along the standard NEPA path
If P2 measures are deemed to be applicable (“yes” path, diamond labeled “Is P2 applicable?”), a
P2 checklist(s) should be prepared indicating methods that can be implemented to minimize waste
and to prevent pollution A copy of the completed P2 checklist(s) is transmitted to the P2 office or
equivalent
As appropriate, P2 measures identified in the P2 checklist(s) are incorporated into the
descrip-tion of the proposed acdescrip-tion and reasonable alternatives described in the EA Any applicable P2
measures should then be reviewed to determine their effectiveness
If a mitigated EA is prepared (“yes” path, diamond labeled “Mitigated EA?”), applicable P2
measures could be incorporated into the mitigation measures
The P2 checklist(s) is appended to the final EA to be submitted for review and approval If the
EA is eligible for a finding of no significant impact (FONSI), the decision to adopt any applicable
P2 measures described in the EA should be documented in it Where practical, any adopted P2
measures could be chosen through the NEPA process (e.g., FONSI/record of decision [ROD]) and
implemented/monitored with an EMS
2.6.3.3 EIS Process
Where a proposed action involves preparation of an EIS (Figure 2.4), an effort could be performed
during the internal scoping process to identify potential P2 measures for achieving NEPA/P2 goals
such as reduction or prevention of pollution, waste minimization, and energy conservation Where
appropriate, the P2 office (or equivalent) provides assistance in identifying potential measures
As indicated in the box labeled “Prepare P2 checklist(s)” in Figure 2.4, a P2 checklist(s) can be
filled out indicating potential methods that could be implemented to minimize waste and prevent
pollution A copy of the completed P2 checklist(s) should then be transmitted to the P2 office
Potential pollution prevention measures identified in the P2 checklist(s), combined with input
obtained from the public scoping process, are reviewed to identify specific P2 measures for
investigation Reasonable P2 measures should then be incorporated into the description of the
pro-posed action, and reasonable alternatives described in the EIS The measures are then analyzed to
determine their effectiveness and potential impacts The analysis should also consider options and
costs for implementing P2 measures
The P2 checklist(s) is archived as part of the administrative record and the completed EIS is
submitted for review and approval The decision to adopt any of the P2 measures investigated in
the EIS would be documented in the ROD Where practical, any adopted P2 measures could be
monitored and implemented through an EMS The EMS could be used in a monitoring and auditing
capacity to ensure that the P2 measures are correctly implemented
Trang 182.7 NEPA AND ISO 14001
The effectiveness of NEPA as a planning tool is sometimes diminished because it has not been
properly either implemented or integrated into agency’s planning process In 1996, the author began
investigating commonalities and similarities which existed between NEPA and the relatively new
ISO 14001 EMS A final report was issued to the President of the National Association of
Envi-ronmental Professionals (NAEP) in 1997, outlining a process for integrating NEPA with an ISO
14001 EMS, which was published in 1998.*,22 In 2000, this report was reviewed and approved by the
NAEP Board of Directors and issued to the Council on Environmental Quality (CEQ) as a strategy
that should be promoted to federal agencies The following section summarizes this strategy
Although this strategy is directed at integrating NEPA with an ISO 14001 certified EMS, it can
also be integrated with any EMS that is consistent with the ISO 14001 standard Hence, as used in
this chapter, the term EMS is interpreted to mean an EMS consistent with the ISO 14001 series of
standards This strategy has since been generalized to describe a process for integrating any
envi-ronmental impact assessment (EIA) process with an EMS.23
2.7.1 A N ISO 14001 C ONSISTENT EMS
The ISO 14000 environmental management standards define specific procedures to assist an
orga-nization in complying with applicable statutes, regulations, and environmental requirements;
min-imizing how the organization’s activities negatively affect the environment, and for continually
improving on the above ISO 14000 is similar to the ISO 9000 quality management system in that
both focus on the management process used (e.g., how a product is produced) rather than on the
ultimate quality of the product itself
An EMS is part of an organization’s management system The EMS specifies requirements and
procedures for implementing the organization’s environmental policy ISO 14001 provides an
interna-tionally accepted specification for the EMS The ISO 14001 EMS has the following five components:
Detail procedures for defining an environmental policy with a commitment to pollution prevention, continual improvement, and compliance with relevant environmental legisla-tion and regulations
Specific procedures for identifying an organization’s (products/services/activities) mental aspects, legal and other responsibilities, and environmental management programs
environ-Implementation and operation procedures; includes identification of responsibilities, ing and awareness, documentation, and operational controls
train-Developing measurable targets for meeting environmental objectives; verification and rective action procedures; includes monitoring and measuring performance to meet targets for continual improvement
cor-Review by management to ensure that the EMS is addressing changing conditions and information
Presidential Executive Order 13148 directed federal agencies to develop EMSs by the year
2005.24 As explained in more detail later, strong parallels exist between the goals and requirements
of NEPA and the specifications for implementing an EMS Because there is a general expectation
under an ISO 14001 EMS that action(s) will be taken to improve environmental quality,
perfor-mance of an integrated NEPA/EMS can provide a mechanism for infusing NEPA’s substantive
national policy goals into federal decision-making
Figure 2.5 shows a simplified process for implementing an EMS The EMS provides a
struc-tured system (plan-do-check-act) in which a set of management procedures is used to systematically
* Eccleston C.H., “ A Conceptual Strategy for Integrating NEPA with an Environmental Management System,” issued to
the President of the National Association of Environmental Professionals, 1997 Issued to CEQ, 1990/2000.
Trang 19identify, evaluate, manage, and address environmental issues and performance The EMS provides
organizations with a mechanism which helps ensure that necessary actions are taken to integrate
environmental safeguards and compliance into day-to-day operations and long-term planning with
respect to an organization’s (e.g., including federal facilities) activities, products, and services
As depicted in Figure 2.5, the EMS employs a rigorous monitoring cycle for managing and
con-tinually improving an organization’s (federal facility) environmental performance The continuous
improvement cycle is achieved by identifying how the organization’s activities affect environment
quality This is accomplished through
assessing an organization’s environmental aspects (described later),establishing defined environmental targets and objectives,
training staff and defining departmental and personal responsibilities,cyclical monitoring and implementing corrective actions as necessary to avoid or mini-mize impacts, and
instituting procedures and controls for responding to emergencies
An EMS provides an effective mechanism for tracking, monitoring, and improving the
implemen-tation of the agency’s selected alternative, including mitigation measures and other commitments
established in final NEPA documents; monitoring such commitments can support internal auditing
requirements and identification of appropriate corrective actions
Both NEPA and EMS processes involve a review of activities to identify those with potentially
significant environmental impacts and to implement measures to avoid, minimize, or eliminate
the causes of adverse environmental impacts For reasons such as these, an integrated NEPA/EMS
methodology can substantially improve an agency’s environmental performance and thus
environ-mental quality and may reduce the cost of complying with NEPA and EMS requirements Some of
the key advantages of an integrated NEPA/EMS system are
incorporating NEPA documents and schedules into EMS objectives and targets;
archiving the NEPA administrative record and NEPA documents as part of the EMS tem for maintaining records;
sys-integrating NEPA mitigation commitments with other related regulatory requirements and EMS objectives and targets;
Develop plan to implement the policy
Implement the plan/policy
Monitor and develop a plan for correcting deficiencies in the policy
Review performance of the plan/policy
Revise plan/policy
FIGURE 2.5 Simplified overview of a typical EMS.
Trang 20including NEPA impact assessments as part of the process of identifying the tal aspects under an EMS; and
environmen-monitoring the implementation of the selected NEPA alternative and applicable mitigation and monitoring commitments
Some agencies have already begun pursuing an integrated NEPA/EMS strategy For example,
new Forest Service planning regulations require 126 Forest Service administrative units to
imple-ment EMSs containing procedures for identifying and monitoring environimple-mental conditions The
preamble to the Forest Service regulations declares that:
… through the implementation of EMS, administrative units will be continually collecting and
evalu-ating the data necessary to create any document that may be required by NEPA This will make the
creation of accurate and relevant NEPA documents more efficient.25 (emphasis added)
2.7.2 W HY NEPA AND ISO 14001 C OMPLEMENT E ACH O THER
As depicted in Table 2.9, each system has its strengths and weaknesses; moreover, a weakness in
one system tends to be offset by the strengths of the other
Some of the principal characteristics outlined in Table 2.9 are described below
•
•
TABLE 2.9
How an ISO 14001 Consistent EMS and NEPA Complement Each Other
Substantive mandate Substantive actions are expected to be taken
which lead to continual improvement in environmental performance (and thus environmental protection).
Lacks a legally binding substantive mandate to protect the environment.
Goal ISO’s goal is to provide environment
protection by identifying impacts Its continual improvement system is used to reduce these impacts and improve performance
NEPA’s goal is to provide environment protection by ensuring
that environmental factors are considered during the early planning process.
Planning function A planning function is required which
provides a system for ensuring that decisions are appropriately implemented However, ISO 14001 does not prescribe a detailed process for performing the planning function.
Specifies detailed direction for performing an analysis of direct, indirect, and cumulative impacts.
Life cycle Details how to perform a life-cycle analysis
(ISO 14040 series).
An analysis of reasonably foreseeable impacts over the life cycle of the action
is required.
Significance Lacks detailed direction for interpreting
or determining the meaning of significance.
In addition to the context, 10 specific factors are detailed in the NEPA implementing regulations for determining the significance of environmental impacts.
planning process is defined, but it lacks