In this paper we review the role of post-project meetings as a tool to improve organizational learning at the group level.. Post-project reviews should aim at capturing process knowledge
Trang 1Organizational learning through
post-project reviews in R&D
Maximilian von Zedtwitz
IMD – International Institute for Management Development, P.O Box 915, CH-1001 Lausanne, Switzerland, zedtwitz@imd.ch
Post-project reviews are one opportunity to systematically improve performance in subsequent projects However, a survey reveals that only one out of five R&D projects receives a post-project review Post-project reviews – if they take place – are typically constrained by lack of time and attention as well as lack of personal interest and ability They focus mostly on technical output and bureaucratic measurements; process-related factors such as project management are rarely discussed
In this paper we review the role of post-project meetings as a tool to improve organizational learning at the group level Based on 27 in-depth interviews with R&D managers carried out between 1997 and 2001,
we categorize four classes of learning impediments These difficulties are not easily resolved, as is illustrated by examples from Hewlett-Packard, DaimlerChrysler, SAP, Unisys, the US Army, and others We propose a five-level post-project review capability maturity model, identifying some of the key capabilities that need to be in place in order to advance to the next process maturity level Most companies reside on the first or second maturity level Our conclusion is that many companies give away great potential for competence building by neglecting post-project reviews as a tool for systematic inter-project learning
1 Introduction
What do you take away from a finished project? A
product? A lesson? A bad feeling? The essence is
that most companies have not established a structured
approach to learning from projects after their
comple-tion Even worse, most projects that have been
prematurely terminated never undergo a retrospective
analysis on their causes of failure A recent survey
indicated that 80% of all R&D projects are not
reviewed at all after completion, and most of the
remaining 20% were reviewed without established
review guidelines
This paper raises the issue of organizational learning
through post-project reviews A post-project review is
here defined as a formal review of the project examining
the lessons that may be learned and used to the benefit
of future projects Post-project reviews – or
post-reviews – are more prevalent in industries where
knowledge is the main output of a project For instance, consultants regularly perform after-action reviews in order to capture lessons learned from their engagements Project reviews are commonly used as phase reviews, particularly in projects managed under the stage-gate paradigm The final review, however, is either focused exclusively on technical issues or dropped altogether due to time and management constraints Post-project reviews should aim at capturing process knowledge for enhancement of future project work, and hence differ from regular project reviews, project audits (Duffy, 1989; Neale and Homes, 1990), or project evaluations (Saladis, 1993)
In this paper we propose a five-level capability maturity model for post-project review processes in R&D Based on our review of the literature on organizational learning and R&D project manage-ment, we identify eight fundamental impediments to post-project reviews in R&D We reflect on a few
R&D Management 32, 3, 2002 # Blackwell Publishers Ltd, 2002 Published by Blackwell Publishers Ltd, 255
Trang 2observations on how to cope with these impediments
to promote organizational learning based on team
performance
2 Research methodology
At the intersection of group learning and R&D project
management practice, the study of post-project reviews
has not attracted widespread interest from R&D
management researchers until recently Little research
has been published in the academic or management
literature In addition, practitioners have repeatedly
voiced their concern about the lack of established
criteria and guidelines to conduct post-project reviews,
but their focus on future project challenges usually
distracts them from a retrospective analysis of the past
The research leading to this paper is based on a
combinative effort of doctoral research, in-depth
interviews with R&D managers, and survey
explora-tion As the goal of the paper is to identify current
R&D post-project review practices and propose
managerial recommendations on how to improve
them, we chose to begin with a broad interviewing
sample for variety and reach of insight, preparing for a
focused and limited in-depth investigation that will
eventually produce a richer and more substantiated
output in our ongoing study As our level of analysis,
we chose the boundary between individual and team
learning
Between 1997 and 2001, we conducted a total of 27
interviews with R&D managers of leading companies
from a wide range of technology-intensive industries
and geographical regions The interviews were
con-ducted according to an interview guideline that focused
on project management in R&D, specifically learning
and information sharing in R&D teams Interview
minutes were returned to the interviewees for feedback,
comments and additional interpretation Where
possi-ble, we participated in project meetings and
post-project reviews This personal observation
comple-mented the interview data well Data triangulation, as
demanded by Yin (1991), was not possible in every
instance as very little has been published by either the
interviewed companies or third parties on the
investi-gated projects However, we had access to post-project
reports of some of the studied companies
In addition to the interviews, we conducted two
surveys of R&D post-project review practice in 2000
and 2001 Sixty-three R&D directors and managers of
different organizations participated in our
question-naire of the current state of R&D post-project reviews
in their companies, including information about
frequency and motivation of post-project reviews as
well as process-related factors during their execution
As this is ongoing research, we expect our
under-standing to be refined with the progress of this work
Our analysis based on the initial survey (see Koners
and Zedtwitz, 2001) was confirmed by findings from the second survey conducted a year later Considering all currently available data, however, we are confident that the present report presents a fairly reliable picture
of the fundamental issues of managing post-project R&D reviews
3 Post-project reviews in organizational learning and R&D management
3.1 Defining post-project reviews
According to the great satirist and critic George Bernard Shaw, ‘we learn from experience that men never learn anything from experience’ Luckily, re-search in organizational learning over the past decades shows an improving understanding of how people and
organizations learn (see Easterby-Smith et al (2000)
for a concise and recent review) Among a number of important mechanisms, the post-project review is one
of the most structured and most widely applicable approaches to passing on experience from one team to the next
We define a post-project review as the final formal review in the course of a project that examines any lessons that may be learned and used to the benefit of future projects (see also the projectnet.com definition and Wideman, 1992) This section, as well as the following section on team learning (including Figure 1 and Table 1), is strongly based on the contribution of Ursula Koners to our joint publication reporting findings from the initial post-project review survey (Koners and Zedtwitz, 2001) The main objective of post-project reviews is to initiate and facilitate continuous learning on all levels within an organiza-tion Learning effectively protects and enhances an organization’s competitive advantage (e.g
Wheel-wright and Clark, 1992; Johannessen et al., 1997;
Gupta, 1998; Drejer and Riis, 1999; Takeuchi and Nonaka, 1986)
Learning is critical in R&D organizations since it is the precondition for sustaining significant improve-ments over long periods of time The body of knowl-edge on learning in R&D and New Product Development has been growing in recent years, but the variety of learning concepts studied is immense and the underlying processes are still scarcely known (e.g Reger and von Wichert-Nick, 1997) One major drawback is the absence of investigations on learning
in R&D after a project is actually finished Most of the existing literature on post-project reviews in R&D repeats their importance and the fact that few organizations conduct post-project reviews regularly Generally, the final phase of an R&D project concentrates on issues like the financial closure, the project appraisal and the reallocation of equipment and workforce to future projects (EIRMA, 1998) This
Trang 3paper wants to advance the discussion further in the
direction of inter-project learning capabilities – and
barriers – in post-project reviews in R&D
3.2 From team learning to organizational
learning
Argyris (1977) defined organizational learning as ‘a
process of detecting and correcting error’ The notion
of organizational learning has since evolved (see e.g
Crossan and Guatto, 1995; or Garvin’s (1993)
defini-tion of ‘an organizadefini-tion skilled at creating, acquiring
and transferring knowledge and at modifying its
behavior to reflect new knowledge and insights’)
We distinguish between three levels of learning:
individual learning, team and group learning, and
organizational learning (see Figure 1) At the basis of
all learning is the individual (e.g Barker and Neailey,
1999, p 60) Individual learning is the domain of
psychology and cognitive science; organizational
learn-ing is studied by social psychologists and organization
theorists In this context, team learning may have a
pivotal role in distributing, processing and interpreting
individual experience for organizational memory and
knowledge
Post-project reviews focus on the link between team
and organizational learning, and – as we will discuss
below – on the link between individual and
organiza-tional learning The process of organizaorganiza-tional learning
through team learning is best described in Argyris and
Scho¨n’s (1978) concept of single-loop and double-loop
learning Single-loop learning pertains to the detection
and correction of mismatches between experience and
a reference system without questioning or altering the
values of the system Double-loop learning takes place
when a mismatch is detected and used to adapt and
correct the reference system
Post-project reviews (should) focus on double-loop
learning After the completion of the project – when
the project team is ready to step back and reconsider
what it has done and what has happened – the team is
in the best position to review cause-and-effect relation-ships and should be required to propose improvements for the management and execution of future projects Unfortunately, for a number of reasons which we outline further below, few teams find the appropriate amount of time for this exercise Most learning is confined to individual learning, and substantial poten-tial for group learning is missed Although individual learning is an important ingredient of organizational learning, both the depth and reach of individual experience are on average more limited
3.3 Learning in the life of an R&D project
A review is certainly not the only way to learn in or from a project Although learning and knowledge accumulation in R&D are at the core of R&D, knowledge dissemination to other scientists and R&D managers is poorly facilitated and supported Learn-ing, state Ayas and Zeniuk (2001, p 64), ‘is not a natural outcome of projects knowledge created within a project is not always diffused, and lessons learned may not be shared across projects’
Learning through reviewing is one of the most frequent approaches to capitalizing on previous experience, and many R&D project management concepts (such as stage-gate (O’Connor, 1994; Cooper and Kleinschmidt, 1991) or milestone techniques) are based on formal points of reflection.1 Figure 2 illustrates a schematized phase model of R&D project reviews (Balanchandra and Brockhoff, 1995, p 32)
It would be dangerous, however, to focus exclusively
on formal methods of learning and neglect other informal and tacit means of knowledge and experience building Some of the greatest advances in R&D management in the 1990s have been soft and informal management techniques, which tend to be extremely effective at the individual learning level However, they are difficult to systemize and replicate
For example, SAP carries out a number of different reviews over the course of an R&D project Reviews
Individual Learning
Team/Group Learning
Organizational Learning
Levels of Learning How does learning occur?
Knowledge acquisition
Information Distribution Information Interpretation
Organizational Memory
How is knowledge embodied?
•Personal memory
•Personal experience
•Notes
•Individual capabilities
•Networks
•Reports
•Products
•Team-specific expertise
•Technologies
•Stories / Anecdotes
•Databases
•Procedures
•Processes
•Core competencies
Figure 1 From team learning to organizational learning (based on Huber, 1991).
Trang 4can be held as specification reviews, design reviews,
coding reviews, and even reviews of online
documenta-tion Reviews are designed to ensure that everyone has
access to the same project-critical information;
infor-mation that is important for discussing problems and
finding solutions, discovering potential risk areas,
status tracking, introducing new design proposals,
coordination with other groups, and success checks
Reviews are not necessarily formalized and are
some-times held in small, informal group meetings
How-ever, the results of reviews should always be recorded
in project documentation
Learning from reviews is not limited to the life-time
of an R&D project While a final post-project review
closes out the current project, it may also create the
grounds for a new project For instance, after the
development of a client=server wholesale banking
software product by Unisys, a post-project meeting
(post-mortem in their terminology) was called
includ-ing the programme manager, the customer project
manager, the responsible Unisys International Engi-neering Center project manager, the Unisys Interna-tional Banking Service Center development director, its support manager, and its GUI engineer, the product’s marketing representatives, and the European marketing manager Based on reviews carried out by the Engineering Center the future benefits of lever-aging the development work, including process improvements for future projects and specific require-ments for product internationalization, the Engineer-ing Center and the BankEngineer-ing Service Center agreed to collaborate on a localization project of the banking software Here the post-project review was not only a triggering event to identify additional market potential for the just completed development project, but was also a means to help marketing people use engineering information for future project bids
Post-project reviews thus help improve learning from one R&D project to the next Post-project reviews introduce a systematic way to double-loop learning by making project-specific knowledge and
Idea
Stage I:
Feasibility
Stage II:
Development
Stage III:
Test Market
Stage IV:
Commercialization
Review
Review
Review
Review
Project
Graveyard
Figure 2 Stages in the life of an R&D project (source:
Balanchan-dra and Brockhoff, 1995, p 32).
Organizational and Technical Knowledge Pool
Idea
Stage I:
Feasibility
Stage II:
Development
Stage III:
Test Market
Stage IV:
Commercialization
Review
Review
Review
Review
Idea
Stage I:
Feasibility
Stage II:
Development
Stage III:
Test Market
Stage IV:
Commercialization
Review
Review
Review Review
Post-Project
Double-Loop Learning
Single-Loop Learning
Figure 3 Double loop learning through post-project reviews in R&D projects.
Table 1 Differences between single- and double-loop learning
Characteristics * Occurs through repetition and routine * Occurs through use of insights and non-routine
* Occurs at all levels in organizations * Occurs mostly in upper levels Consequence * Behavioural outcomes * Insights and collective consciousness
Examples * Institutionalizes formal rules * New missions and new definitions of direction
* Adjustments in management systems * Agenda setting
* Problem-solving skills * Problem-defining skills
* Development of myths, stories and culture Application in
post-project
reviews
å Discussion of variances in expenditures, missed deadlines etc å Suggestions for the application of lessonslearned to future projects
å Retrospective analysis of major obstacles experienced
å Deep analysis of cause-effect relations regarding major obstacles experienced
Source: adapted from Fiol and Lyles (1985, p 810).
Trang 5experience available to a corporate-wide pool of
organizational and technical knowledge (see Figure 3)
But few companies have achieved double-loop
learning with the help of post-project reviews
Post-project reviews can limit double-loop learning if they
are too inward-oriented and focused on a reactionary
agenda Table 1 illustrates the differences between
what constitutes single-loop and double-loop learning
in current PPR practices Most can be generally
described as ‘single-loop’ and are therefore restricting
their inherent learning potential
4 A review of current post-project review
practices in R&D
4.1 Results from an exploratory survey on
R&D post-project reviews
Although most R&D organizations seem to
under-stand the potential benefit of post-project reviews, they
still do not make full use of this learning opportunity
We conducted two surveys among a group of R&D
directors and senior R&D managers on the extent and
quality of R&D post-project reviews in which they had
participated The venues were two executive training
events on innovation management held at a business
school in September 2000 and October 2001 We
collected a total of 63 valid responses This number is
too low to warrant in-depth statistical evaluation, but
it does allow some interesting observations about the
state of R&D post-project reviews
On average, 19.4% of R&D projects in which the
respondents had participated had been post-reviewed
Although post-project reviews were conducted in
almost every company and within most departments
represented, post-project reviews were conducted
mostly on an ad hoc basis or after particularly large
projects Only 12 (of 63) respondents indicated that
their companies tried to post-review as many projects
as possible, and 55.6% of the respondents stated that
their companies had not established formal guidelines
on how post-project reviews were to be conducted
17.5% of the respondents indicated that post-project
reviews followed similar practices to those employed in
earlier projects, and only 11.1% of the respondents’
companies had defined review practices
The most popular means of disseminating know-how
between projects was through individuals moving to
new projects (52.4%) or through written documentation
(39.7%) Just eight of 63 respondents claimed that
post-project review results were effectively used to improve
project management or were an integral part of
inter-project learning 39.7% stated that their review focused
mostly on technical criteria, and just 6.3% found that
their companies applied sound and consistent criteria to
every post-project review The complete questionnaire
and its results can be found in the Appendix
Our survey confirms a benchmarking study of 79 highly regarded R&D organizations conducted by Menke (1997) who stated that less than a quarter of the 79 organizations made full use of post-project reviews (see also Kumar, 1990) However, we are aware of the limitations of our investigation due to the restricted scope and sample of the survey But even with these considerations in mind we must conclude from our survey that great learning potential is lost by not taking formalized team learning seriously enough Among the 63 valid respondents, 59 indicated they would prefer to see more post-project reviews to follow
up on completed R&D projects This is no easy task, as
we will see from the following chapter
4.2 Post-project reviews in industrial R&D
What post-project review practices have been estab-lished in R&D-intensive companies, and have any of them best-practice character? Considering the low attention and time that R&D management devotes to post-project reviews, and the multitude of difficulties and obstacles faced in executing these reviews, we were expecting that only a few companies would have developed all-encompassing approaches that could serve as leading examples for their peers
We collected a number of examples that illustrate how some companies have addressed specific problems
of post-project reviews Hewlett-Packard (HP) is one of the companies that has been heralded for its fairly consistent and established implementation of post-project reviews Some of its business units do not only have official project closure meetings but also ‘retro-spective’ project meetings looking exclusively at the development process and potential improvements Their main aim is to gather root causes for problems witnessed during the project and then to make recommendations on how such events can be avoided
in future projects This effort is based on an HP-wide project management initiative established in 1989 and later reinforced in a 1993 HP project management council Since then, HP has been striving to develop project management as a company-wide core compe-tence This strategic emphasis on project management helped to accommodate post-project reviews despite the additional administrative requirements Special review facilitators focus on coaching post-project review meet-ings Still, the frequency of post-project review varies between business units The need for reviews has not yet trickled down into every R&D department, and the quality and result of each post-review meeting depends
on the skills and talents of the review facilitator Most companies rely heavily on personal networks
to disseminate experiences from project management, including all forms of personnel rotation, temporary project assignments and core team hand-overs Some companies also establish central service centres within their central R&D whose members are in effect human
Trang 6dissemination tools for project experience
Daimler-Chrysler, for example, offers support and coaching
staff to its R&D project managers from its FTK=P
department These coaches are not involved in the
technical work of the project but support the project
team in all questions concerning the project execution
and facilitation process Depending on the size and
strategic importance of the projects, these coaches are
responsible for up to five projects and are able to
capture and re-apply their in-depth knowledge to
future assignments and fellow project members
In order to retain and develop a cadre of highly
skilled global R&D project managers, Hoffmann-La
Roche’s Pharma Division instituted an ‘International
Project Management Department’, coordinating a
resource pool of about 50project managers for all
R&D projects worldwide (see also Gassmann and
von Zedtwitz, 1998) The members of this ‘virtual’,
geographically decentralized department are also
assigned as managers to projects as part of a global
programme to ensure standards in quality and project
procedures Upon completion of these projects, project
managers return to the virtual resource pool Since
there are more projects in the pipeline than there are
potential project managers available, they are
imme-diately reassigned to new projects
Since the director of this department reports
directly to the corporate board, the internal political
position of R&D project managers has been improved
recently The director of the ‘International Project
Management Department’ is also on the International
Project Committee, which decides over the
approxi-mately 60global R&D projects at Roche Pharma The
director assumes a role as interpreter or liaison
between project managers and top management, thus
representing the interests of international project
management at Roche This virtual pool promotes
the project management idea Experienced project
managers are dispersed around the world and wander
from project to project – no matter where the project
will be conducted Roche thus manages to retain
much of the valuable procedural know-how to
conduct and lead international projects not only
inside the company, but also in a position where it
can be reapplied when needed
Although top-management support is important in
recognizing the strategic significance of post-project
reviews, it is not always beneficial that top
manage-ment personally participates in them Depending on
the company culture, the presence of research directors
might prevent open and frank discussions of
experi-enced problems DaimlerChrysler, on the other hand,
classifies R&D projects into ‘A’, ‘B’ and ‘C’ projects
(depending on their budget and strategic importance);
‘A’ projects are reviewed in front of the CTO, ‘B’
projects with the relevant R&D director, etc However,
the higher the hierarchical level of participants, the
more likely it is that the post-project review develops
into a marketing event rather than an analysis of the finished project
DaimlerChrysler introduced a new review proce-dure in R&D in 1998, giving directions on the format
of Powerpoint slides as well as details on mandatory information to be given Agilent stresses the impor-tance of cross-functional participants to enhance the array of issues raised during the post-review (see also the Unisys example above), underlining that ‘low-key’ events also help to achieve generally more honest results than formal meetings A similarly informal approach is adopted by many software development companies (e.g., SAP), although some of them regard post-reviews as wild brainstorming sessions without fixed agendas Professional networks and clubs at Dow Corning and DuPont also provide platforms for informal know-how exchange of project management Sinofsky and Thomke (1999) have collected a number
of hands-on guidelines on how to conduct a post-project review session Again, the approach chosen depends heavily on the existing company culture and underlying motive for conducting post-project re-views
Some companies insist on maintaining the post-review as a completely internal meeting with no outsiders present Others, for instance Novartis and Hewlett-Packard, opt for external facilitators in order
to profit from the perspectives of an objective outsider
to the project External facilitators may come from an internal coaching or quality management department, like at DaimlerChrysler FTP=K or Agilent, or hired externally to do the job These outside facilitators are usually consultants specialized in process develop-ment
Obviously, post-project reviews take place after a project is finished The time span between project closure and the post-review meeting, however, varies considerably Some companies choose to conduct post-reviews immediately after the delivery of the last project milestone when the memory is still fresh and most project members still present Other companies prefer to wait until after market introduction, when customer feedback can be taken into account as well Schindler, for example, waits approximately two years after the actual product launch before conducting the post-project review
While all these examples show that current post-project review practices in R&D are quite hetero-geneous, it does not seem to be appropriate to impose
a single best practice of post-project reviewing Different objectives and needs, different markets and industries, different cultural contexts, and differ-ing degrees of innovation all influence the way post-project reviews need to be conducted But before we propose a framework to develop better (rather than best) review practices, we must understand some of the underlying resistances to reflective learning for future projects
Trang 75 Resistance to learning from post-project
reviews
If post-project reviews were simple, few companies
would pass up the chance for additional systematic
learning However, a number of factors both at the
individual and the group level prevent the free flow of
information and the retention of critical project
knowledge for future use
Based on research done by Ursula Koners at
Cranfield University (see also Koners and Zedtwitz,
2001, p 128 – 131), we identified eight major problem
factors, which we grouped in four areas as barriers to
learning from post-project reviews (Figure 4):
1 Psychological barriers;
2 Team-based shortcomings;
3 Epistemological constraints;
4 Managerial problems
5.1 Psychological barriers
There is no organizational or team learning without
individuals creating and sharing information All
hu-man beings are limited in their capacity to learn based
on their experiences Our minds are programmed
through the process of evolution to a certain balance
of reflection and action Given the complexities and
challenges of our lives, particularly under high pressures
in modern society, it seems understandable that our
commitment to reflection on the past – particularly with
no immediate benefits to oneself – is rather limited This
mechanism is effective at the conscious as well as the
subconscious levels Here we focus on two impediments
pertaining to post-project review management:
1 The disinclination of team members to objectively
reflect upon past actions and their consequences,
particularly their own actions;
2 The bias to remember easy-to-categorize incidents
and the tendency to repress ambivalent experiences
5.1.1 Inability to reflect. The business life of today is generally not based on reflections of the past One popular ‘excuse’ is based on the claim that past models and experiences do not apply if circumstances change (Kransdorff, 1996) Most often it is found that managers have little awareness of past actions and rationales According to Busby (1999) the idea that
‘experience is a teacher in its own right’ is very dominant In other words, one should not be surprised that people find it difficult to communicate about the past since the past is not the objective of management Another reason for this inability to reflect is based
on the fact that traditional approaches to project management do not treat learning and reflection as central (Ayas, 1997); and consequently these activities are not considered as a vital part of the project management task In R&D, blue-sky researchers are the ones most likely to engage in learning and reflection for its own sake, but they are in the minority compared to product-oriented development engineers and scientists working on problems in applied research Once learning and reflection become a means and not
an end of a process, they are more easily forgotten
5.1.2 Memory bias and ambivalent experiences. Be-sides the selectivity of reflection, man is confronted with the selectivity of memory Psychology and psychoanalysis have made great advances in our understanding of why the human mind remembers certain things and forgets others Several layers of memory have been identified Repression is commonly considered to apply to unpleasant experiences, forcing
us to forget the actual incident that led to the experience but leaving us with a mental imprint influencing future behaviour
What is the role of repression of group experiences? Unpleasant experiences are not really forgotten and are often very present However, it is the ambivalent experiences that – both at the individual and the group level – become those memories that pose the greatest
Team-based
• Reluctance to blame
• Poor internal communication
Difficult to generalize Tacitness of process knowledge
Epistemological
•
•
• Time constraints
• Bureaucratic overhead
Managerial
Inability to reflect Memory bias
Psychological
Barriers to Learning from Post Project Reviews
•
•
Figure 4 Four major barriers to learning from post-project reviews.
Trang 8threat to the comfort of people, and are hence
repressed unless they are (at least at the group level)
raised and discussed Since our world is not
black-and-white, most of our experiences are ambivalent If we
were not able to prioritize which experiences to discuss
and which to repress, we would spend all day debating
and interpreting our experiences and possibly stalling
any progress whatsoever Repression is a natural way
of limiting everyday complexity
Repression or selective memory in projects can
override potentially important and valuable information
for future use Future project teams, creating a new team
spirit and a new moral understanding, may understand
this experience in a completely different perspective It is
therefore important to analyse what repressions may
have taken place at the group level to carry over any
underlying experiences from a previous project
5.2 Team-based shortcomings
While team members are put together to work
hand-in-hand towards the same common goal, they are often
poorly suited to stand up face-to-face and give each
other a piece of their mind Frank feedback may hurt
and potentially affects the relationship between
in-dividuals for years: many people choose not to risk
their social networks for the sake of project quality
At the same time, much neutral information is not
passed on because its importance is undervalued or its
perceived validity limited:
1 The reluctance of individual team members to
blame other team members or their direct superiors,
and to take accountability;
2 Poor team-internal communication and the failure
to share different interpretations of common
experiences
5.2.1 Reluctance to blame. One explanation why
reviewing past projects does not always lead to a
successful learning experience is that it necessarily
involves looking back at problems and critical events
in the past Although Gulliver (1987) established in his
in-depth case study of the BP organization that people
genuinely want to help the company grow more
profitable by reviewing past behaviours, reviews often
suffer from the reluctance to allocate blame and
criticism since they might uncover cynical or
embar-rassing events
Unfortunately, this reluctance can be stronger than the
realization that the organization has a potential to learn
constructively from a project team’s experience
(Krans-dorff, 1996) In extreme cases, project members deflect
the blame away from themselves, citing unclear goals,
insensitive and unfair leaders, and ignorant clients
(Barry, 1991) By the same token, individuals are
unwilling to take accountability for failure, either because
failure may have a negative impact on their career record,
or because they are embarrassed to acknowledge failure
in front of others Research in this area is difficult to generalize beyond the particular case, and the degrees of reluctance and accountability probably depend on specific company culture and incentive systems
5.2.2 Poor team-internal communication. Excellent communication has always been held as critical for
effective R&D teams Tushman (1979), Allen et al.
(1980), and Katz and Allen (1982) described how team-internal communication affects the productivity of the
R&D function Imai et al (1985) or Dimanescu and
Dwenger (1996) are mentioned here, in lieu of many others who underlined the importance of cross-functional communication for new product develop-ment teams While this is a significant step forward, in practice internal communication across functions and groups is hindered by team-internal regrouping: Some people get along better with each other, being able and willing to share information more easily with some than with others In pathological situations, team-internal factions intentionally hide critical information
in order to gain unfair advantage in performance recognition or promotions Teams separated by physical distances have usually little opportunity to meet in person; they are hence restricted to electronic
or written communication Team members with different technical, functional, or cultural backgrounds
do not share the same vocabulary or referential context, which leads to misunderstanding and reduced knowledge exchange While there are great advantages associated with the inclusion of people from different backgrounds, locations, and cultures, team-internal communication is certainly not enhanced
5.3 Epistemological barriers
Even if human beings had the time and interest to fully devote their attention to the reflection and analysis of what happens around them, they would still find it difficult to grasp the most important issues and draw important conclusions for future behaviour all by themselves The human intellect is limited At the same time, certain kinds of experiences are inherently hard
to express and hence not easily shared with colleagues Group-based discussion on commonly shared experi-ence may thus be the only way to bring forth distributed key lessons for future project teams:
1 The difficulty of abstraction from single occur-rences and events to formulate more general recommendations;
2 The inherent difficulty of articulation of tacit knowledge and the precise formulation of ambig-uous assumptions and beliefs
5.3.1 Difficulties in generalizing from specific projects.
Abstract knowledge may be the basis for competitive
Trang 9advantage if it is well embodied in an organization
(Hamel and Prahalad, 1994) Generalizing from
context specific project experiences is one of the main
hurdles and difficulties for post-project reviews in
general The human mind is not made to abstract
experiences to a general level so that they can be
applied to a wide range of future projects
Further-more, project results (no matter if they are positive or
negative) are often naively extrapolated in a simple
linear fashion The reality, however, is much more
complex, so that the outcome of a project depends on a
whole variety of interlinked variables which again are
very difficult to generalize
5.3.2 Tacitness of process knowledge. The nature of
process-related knowledge, experiences and insights
implies that they cannot be shared in the same way as
information stored in reports, databases or prototypes
Polanyi (1966) refers to this phenomenon as ‘tacit
knowledge’ and describes the underlying problem of
organizations: ‘We know more than we can tell’
Durrance (1998) draws from Polanyi, Takeuchi and
Senge’s work and claims that especially Western
cultures still prefer explicit knowledge, which is
quantifiable and definable Despite increasing
aware-ness of the difference between tacit and explicit
knowledge, companies are still struggling to convert
tacit into explicit knowledge so that it can be shared by
the entire organization Senge (1990) suggests
reflec-tion or careful observareflec-tion – a task mainly found in
post-project reviews
5.4 Managerial constraints
R&D is, like any other corporate function, under
constant performance pressure This pressure leaves
little time to step back and reassess a project that has
occurred in the past Furthermore, researchers are
known to shun guidelines and project management
rules imposed by a central department These
require-ments are often interpreted as unnecessary and
obstructive to the actual R&D work Hence we have:
1 Lack of time to deal with the past in a business that
typically looks three to five years ahead;
2 Reluctance to comply with bureaucratic and
admin-istrative requirements in association with following
up on post-project reviews
5.4.1 Time constraints. The most often stated reason
why post-project reviews are not conducted is lack of
time People are unlikely to devote time and effort to
yesterday’s problems since natural incentives favour
moving ahead to the next problem instead of spending
valuable time on reviewing a just completed project
This has been verified by Kotnour (1999) who – based
on results from his questionnaire survey of 43
experienced project managers – states that ‘most
project managers viewed producing lessons learned as
a valuable and important exercise However, they felt they did not have enough time to complete a formal lessons-learned process’
Particularly in an economy more and more deter-mined by Internet-speed competition, time will be increasingly short An R&D manager of a large IT company declared that ‘if you have the time to think, you’re doing something wrong’ When time is a critical resource, retrospection and contemplation are left to others
5.4.2 Bureaucratic overhead. Corporate control sys-tems tend to concentrate on budget, time and output Not surprisingly, if post-project reviews are conducted
at all, a substantial part of each review is devoted to complying with these control demands Particularly when post-project reviews are considered as additional bureaucratic chores imposed by a central project management department, project teams rarely have the necessary enthusiasm to engage in additional review work Moreover, the information requested
in a post-project review is often incompatible with information solicited during the execution of the project, and hence undermines the confidence of the team in the entire control system
As a consequence, the purpose of a post-project review is often reduced to ensure that the project complied with all bureaucratic procedures, and the important inter-project learning function is neglected
If learning is on the review agenda, it is often for the benefit of the team members only Kotnour (1999) discovered that the learning goals of project managers focus on costs, scheduling, performance and customer satisfaction – in line with what most corporate incentive systems favour In combination with time constraints, the disinclination of project teams to comply with bureaucratic procedures tends to keep the effort spent on post-project reviews to a mini-mum
6 A capability maturity-based model for organizational learning through post-project reviews in R&D
There is a growing body of evidence that projects may prove immensely beneficial to the long-term success of companies when these companies systematically in-corporate reflective practices into their project man-agement processes (DeFillippi, 2001, p 6) In the two previous chapters we have outlined why post-project reviews have been difficult to conduct, and how selected companies have found formalized ways and means to gain insight from R&D projects despite these obstacles
Overall, we have not been able to find a single best practice in post-project reviews in R&D Individual
Trang 10approaches tend to be company-specific and optimized
to problems perceived to be most urgent by each
organization
A number of methodologies for structured learning
from projects have been formulated to provide R&D
managers with practical guidelines (e.g Collier,
De-Marco and Fearey, 1996; Barker and Neailey, 1999;
Kearth, 2000) If these methodologies were embraced
by R&D organizations, post-project reviews would be
conducted with greater consistency and greater
applic-ability of their outcomes to other R&D projects
However, the introduction of a new reflective
process, which is typically not perceived to add value
to current business activities, is resisted unless the
organization has reached a level of maturity that is
receptive to company-wide knowledge sharing
In the field of software engineering and
develop-ment, a capability maturity model (CMM) has been
proposed by the Software Engineering Institute to
describe the capabilities of software development
organizations and to provide guidance on how to
establish and improve software development processes
(see Carnegie-Mellon University, 1995) Analogous to
CMM, we propose a five-level capability maturity
model for post-project reviews Our post-project
review maturity model is designed as a framework
allowing the progression from an immature
unrepea-table review process to a mature, well-managed review
process (see Figure 5)
The maturity model is organized into five levels:
Initial; Repeatable; Defined; Managed; Optimizing
Each level is described in terms of key processes that
contribute to the degree of implementation and
institutionalization of the review processes in place
6.1 Level 1: Initial
Organizations at this level of process maturity
char-acterize post-project reviews as ad hoc or even chaotic
If a review process has been defined, then its success depends heavily on the skills and talent of individuals who conduct it Reviews are seldom planned but triggered rather in reaction to a major project-related event, such as a complete failure or a particularly successful project Because the review process is poorly defined and its execution not standardized, its outcome
is unpredictable and incomparable to other review results
Most organizations still appear to be at this level Our survey indicated that one in eight companies never conducts post-project reviews, and that half of the remaining companies use arbitrary or random selection criteria to review projects More than half of all respondents stated that their companies have no post-project review guidelines in place, and about a quarter responded that the review quality was based mostly on the capabilities of the team members
6.2 Level 2: Repeatable
The organization has established post-project review guidelines and sound review practices: the review process is repeatable and comparable to previous reviews Managing and planning of new reviews is based on experience with similar reviews, although specific review practices may differ With principal review policies in place, major disasters in review sessions or in review outcomes may be avoided
A simple example of a repeatable review practice is a post-completion report, which is usually based on a report template to ensure inclusion of relevant project improvement areas Such written reports, however, focus mostly on quantifiable and explicit data, such as costs, scheduling and technical=design deviations Nevertheless they provide a good means for transfer-able recommendations for corrective action, if these suggestions are made available at the group or management level
Maturity of Post-Project Review Processes
Optimizing
Managed
Defined
Repeatable
Initial
• Ad hoc PPR
• Reaction-driven reviews
• Based on capabilities of project individuals 1
2
3
5
• Establishment of PPR policies
• Introduction of sound review practices
• Based on experience with similar reviews
• PPR process standardized
• Establishment of sound and consistent review criteria
• PPR responsibility assigned to a unit
• PPR goals quantified and measurable
• Corrective action can be taken
• Quality of transferable knowledge predictable
Post-Project Review Capabilities
4
• Organization-wide PPR
• Consistent inter-project learning
• Proactive review of PPR pro-cesses
Figure 5 A capability maturity model of post-project review (PPR) processes.