Recognizing threshold investments, economies of scale, multiple goals and investment risk... More Activities and Constraints: this notion deals with more complex resource mixes, and
Trang 1Ch 12: More Advanced Linear Programming Concepts and
Methods
Applying Linear Programming to
Those Investments in Which The
Simplifying Assumptions of Basic
LP Analysis Do Not Hold.
Trang 2Simple Application of L P.
In Chapter 11, Linear Programming was
applied to those investments satisfying the following assumptions:
1 Additivity within activities: resource
consumption is constant per unit of
output; there are no economies of scale.
2 Divisibility within activities: partial
investments can be implemented There
is no requirement to accept equipment in discrete sizes.
3 Independence of activities: there is no
recognition of productive or financial
Trang 3Extensions to the Basic
Application of L.P.
This chapter extends the basic applications of L P, to allow investment analysis where projects take on a more ‘real word’ flavor: ie, where some simplifying assumptions are relaxed.These extensions include:
1 Allowing more activities and constraints
2 Recognizing indivisible investments
3 Allowing inter-year resource borrowings and
transfers
4 Recognizing interdependent projects
5 Treating mutually exclusive investments
6 Recognizing threshold investments, economies
of scale, multiple goals and investment risk.
Trang 4Explanations of the
‘Extension’ Ideas I.
More Activities and Constraints: this notion deals with more complex resource mixes,
and more constraints, or combinations of
projects
Indivisible Investments: Most projects are
not physically divisible For example, power stations are not divisible, although they can vary in size as to scale.
Inter-Year Transfers: Capital and supplies
may become available at different times, or surplus amounts may be able to be
transferred between years.
Trang 5Explanations of the
‘Extension’ Ideas II.
Interdependent projects: projects may provide mutual support and
resources, or infrastructure to each
other.
Mutually Exclusive Investments: A
casino built on a site will preclude the construction of an hotel or sporting
facility Only one of these projects can appear in the LP solution.
Trang 6Explanations of the
‘Extension’ Ideas III.
Threshold Investment, Economies of Scale,
Multiple Goals, and Risk:
Projects may have a fixed scale: eg a
single large airplane, requiring a fixed
amount of capital.
Projects may generate scale of production
economies with increased size.
Projects may have to satisfy conflicting
wealth, environmental and social concerns
All analyses must recognize risk.
Trang 7Advanced LP Techniques Applied to
A Complex Investment Problem :
An Example, ‘Power Gen Inc’.
Power Gen Inc has identified this set of
alternative power generating
proposals:-Constraint or Hydro- Natural Gas Natural Gas Wind - Biofuel Solar
Objective power Site A Site B Farm Panels
Capital Outlay ($M) $400 $170 $150 $100 $50 $120 Power Output (MW) 420 250 200 70 50 90 NPV ($M) => $180 $100 $80 $50 $7 $20
Alternative Generating Technologies
Power Gen Inc: Electricity Generating Investment Problem
Trang 8Advanced LP Techniques Applied to A Complex Investment Problem :
An Example, ‘Power Gen Inc’.
In maximizing total NPV by choosing a mixture of these generating alternatives, Power Gen Inc faces these
constraints:-At least 100 MW have to be
produced from renewable
resources.
At least 200 MW have to be
produced from natural gas.
Total cash and credit available is
Trang 9The LP Solution For ‘Power Gen Inc’.
Constraint or objective
Hydro-power
Natural gas, site A
Natural gas, site B Windfarm Biofuel
Solar panels
Resource use Sign
Resource supply
Activity Level: Chosen 0.7 1 1 1 0 0
Capital outlay ($M) 400 170 150 100 50 120 $700 $700 Renewables output (MW) 420 70 50 90 364 100 Nat gas output (MW) 250 200 450 200
Formatted Problem and LP Solution For Power Gen Inc.
Trang 10Notes On The LP Solution For
‘Power Gen Inc’.
The chosen generating methods are:
Hydro 70% of project adopted,
Natural Gas, Site A 100% of project adopted,
Natural Gas, Site B 100% of project adopted,
Windfarm 100% of project adopted,
Biofuel 0% of project adopted,
Solar Panels 0% of project adopted.
Total NPV from this selection is $M356
Calculated as:
(0.70 x $180) + (1 x $100) + ( 1 x $80) +
Total capital outlay for this selection is $M700
Trang 11Notes On Constraints For The LP Solution For ‘Power Gen Inc’.
Output from renewable resources at 364MW is greater than the required minimum of 100MW.
Output from natural gas at 450MW is greater
than the required minimum of 200MW.
All projects were artificially constrained at a
maximum of 1 unit, so that more than one
project of any technology could not be chosen This constraint has been satisfied.
Capital outlay at $M700 is equal to the
maximum allowed of $M700.
Trang 12Note On Output For The LP
Solution Of ‘Power Gen Inc’.
The solution shows that only 70% of the Hydro scheme is to
be adopted Such a scaled down scheme may not be
acceptable To ensure that projects are either accepted or rejected in their entirety, Mixed Integer Linear Programming can be used
‘Integer’ settings such as 0,1,2,3… allow discrete zero or
multiple selection of projects.
‘Binary’ settings with levels of 0 or 1 allow discrete zero or unitary selection of projects.
MILP is invoked by selecting either ‘bin or ‘int’
Trang 13Setting Integer and Binary
Constraints.
‘Binary’ constraint selected via the Solver ‘sign’ dialog box.
‘Integer’ constraint selected via the Solver ‘sign’ dialog box.
Trang 14Other LP Formulations
Mixed Integer Linear Programming can be used
to solve other complex investment problems by
careful specifications of the goals, and
imaginative definitions of the constraints.
For example:
Inter-Year Capital Transfers Introduce activities
for borrowing and capital transfers.
Contingent Projects introduce permission
constraints which allow one activity to proceed only
if another is adopted.
Mutually Exclusive Projects introduce constraints
in which the total number of activities is below or
Trang 15Other LP Applications
Threshold investment levels – the threshold
level is set up as a binary constraint.
Economies of Scale – particular scale levels are set up as independent activities with binary
constraints.
Multiple Goals - each goal is set up as a
constraint goal, or each goal can be individually weighted in a total goal measure.
Risk Analysis – risky alternatives could be
constrained in the product mix; or an overall risk measure such as ‘variance could be targeted and minimized.
Trang 16Advanced LP Applications:
Summary
Linear programming can be used to solve selection problems from amongst competing investment
alternatives in the face of complex constraints.
These constraints mirror real world problems, and present a more realistic picture of actual
investment behavior, than that assumed in base level LP analysis
This higher level of analysis requires imaginative definitions of both goals and constraints, and an appreciation of Linear Programming methodology.