Research Article Constructing a modern cytology laboratory: A toolkit for planning and design Isam A.. Methods: The phases of any laboratory design project are Planning, Schematic Desig
Trang 1Research Article
Constructing a modern cytology laboratory: A toolkit for planning and design
Isam A Eltoum, MD, MBA*
Address: Department of Pathology, Division of Anatomic Pathology, University of Alabama at Birmingham, USA
E‑mail: Janie Roberson ‑ jroberson@uabmc.edu; Allison Wrenn ‑ awrenn@uabmc.edu; John Poole ‑ jpoole@pooleandcompany.com; Andrew Jaeger ‑ ajaeger@hksinc.com; Isam A Eltoum* ‑ ieltoum@uab.edu
*Corresponding author
This article is available from: http://www.cytojournal.com/content/10/1/3
© 2013 Roberson, et al.; licensee Cytopathology Foundation Inc.
Abstract
Introduction: Constructing or renovating a laboratory can be both challenging and rewarding
UAB Cytology (UAB CY) recently undertook a project to relocate from a building constructed in
1928 to new space UAB CY is part of an academic center that provides service to a large set of
patients, support training of one cytotechnology program and one cytopathology fellowship training
program and involve actively in research and scholarly activity Our objectives were to provide a
safe, aesthetically pleasing space and gain efficiencies through lean processes Methods: The phases
of any laboratory design project are Planning, Schematic Design (SD), Design Development (DD),
Construction Documents (CD) and Construction Lab personnel are most critical in the Planning
phase During this time stakeholders, relationships, budget, square footage and equipment were
identified Equipment lists, including what would be relocated, purchased new and projected for future
growth ensure that utilities were matched to expected need A chemical inventory was prepared
and adequate storage space was planned Regulatory and safety requirements were discussed Tours
and high level process flow diagrams helped architects and engineers understand the laboratory
daily work Future needs were addressed through a questionnaire which identified potential areas
of growth and technological change Throughout the project, decisions were driven by data from
the planning phase During the SD phase, objective information from the first phase was used by
architects and planners to create a general floor plan This was the basis of a series of meetings to
brainstorm and suggest modifications DD brings more detail to the plans with engineering, casework,
equipment specifics, finishes Design changes should be completed at this phase The next phase,
CD took the project from the lab purview into purely technical mode Construction documents
were used by the contractor for the bidding process and ultimately the Construction phase
Results: The project fitted out a total of 9,000
square feet; 4,000 laboratory and 5,000 office/
support Lab space includes areas for Prep,
CT screening, sign out and Imaging Adjacent space houses faculty offices and conferencing facilities Transportation time was reduced (waste removal) by a Pneumatic Tube System,
This article may be cited as:
Roberson J, Wrenn A, Poole J, Jaeger A, Eltoum IA Constructing a modern cytology laboratory: A toolkit for planning and design CytoJournal 2013;10:3.
Available FREE in open access from: http://www.cytojournal.com/text.asp?2013/10/1/3/107983
Vinod B Shidham, MD, FIAC, FRCPath (WSU School of Medicine, Detroit, USA)
Vinod B Shidham,
MD, FIAC, FRCPath Wayne State University School
of Medicine, Detroit, MI, USA
For entire Editorial Board visit : http://www.cytojournal.com/eb.pdf PDFs FREE for Members (visit http://www.cytojournal.com/CFMember.asp) OPEN ACCESS
HTML format
Access this article online
Quick Response Code:
Website:
www.cytojournal.com
DOI:
10.4103/1742-6413.107983
Trang 2INTRODUCTION
Constructing or renovating a laboratory can be both
challenging and rewarding The UAB Cytology Section
recently had the opportunity to relocate services from
a building constructed in 1928 to a new space The
laboratory provides diagnostic and screening services
for UAB Medicine patients, which include a 1000‑bed
hospital and a large Outpatient Clinic Over 20,000
tests, including both conventional and liquid‑based
gynecological cases, 1000 fluid specimens, 2000 Fine
Needle Aspirations (FNA), and 1000 pulmonary cases
are processed annually Internally, the section supports
an onsite rapid FNA service for Endoscopic Procedures
(EUS) as well as for Mammography and Bronchoscopy
(EBUS) The technical and professional staff attend and
perform FNAs throughout the inpatient and outpatient
areas The laboratory serves as a clinical affiliate site for
Cytotechnology Programs, supports two Cytopathology
Fellowships, Residents, and a Professional staff, active in
research and publication As an academic institution, our
mission includes patient care, research, and education;
and our facilities must be able to accommodate these
functions seamlessly
Our challenge in the laboratory design and building
project has been to develop a plan that demonstrated
flexibility, safety, quality of environment, and cost
efficiency Flexibility is important, as laboratory testing
is constantly changing and to remain competitive, we
must be able to accommodate future growth in both
test volume and diversity Safety of the employees
is a major concern in areas with potential chemical
exposure and biohazards Additionally, there are
numerous agencies, with applicable safety mandates,
which require compliance A well‑designed, high‑quality
work environment is evidence of our commitment to
patients and employees and fosters satisfaction and
high performance among the staff As a teaching facility,
recruiting the best staff available is a priority and top‑level
facilities attract top‑level staff Cost efficiency is always
a concern and can be a limiting factor, if not carefully
monitored throughout the planning and design.[1]
METHODOLOGY
Once a project has been approved in concept, the core stakeholders must be identified and assembled as a project team The composition of this group will vary depending
on the facility type Even as academic institutions, corporate laboratories, and hospitals have variable business models, there are common roles and areas of expertise that must be represented in the composition of the project team Each member will have expectations to
be met during specific phases of the project[2] [Figure 1] The phases of project design are Planning, Schematic Design (SD), Design Development (DD), Construction Documents (CD), and Construction.[3]
PLANNING
Laboratory participation (User Group) is the most critical
in the planning phase Detailed information regarding the methodologies and scope of testing performed by the laboratory must be compiled and conveyed to the others
on the project team Administrative and facility members also participate, to ensure that the plans remain within the financial and physical constraints and are aligned with long‑term institutional strategies
Tours and high‑level process flow diagrams can bring
Figure 1: Project team composition
specimen drop window to Prep Lab and a pass thru window to the screening area Open screening
and prep areas allow visual management control Efficiencies were gained by ergonomically placing
CT Manual and Imaging microscopes and computers in close proximity, also facilitating a paperless
workflow for additional savings Logistically, closer proximity to Surgical Pathology maximized the
natural synergies between the areas Conclusions: Lab construction should be a systematic
process based on sound principles for safety, high quality testing, and finance Our detailed planning
and design process can be a model for others undertaking similar projects
Key words: Cytolaboratory design, laboratory design, lean methods, quality control, laboratory
construction, cytopathology equipments, cytopathology procedures
Trang 3an understanding of the daily work in the laboratory to
architects and engineers Awareness of the appropriate
relationships and adjacencies are essential to the design
for a smooth flow of personnel, supplies, and equipment
The strength and complexity of these relationships can be
illustrated through a bubble diagram [Figure 2]
Any discussion of an efficient facility design must
include planning for sustainable design and Lean
operations For example, materials handling is estimated
to consume 20‑50% of the operating expense in a variety
of production and manufacturing settings, not atypical
of laboratories Efficient facility design can reduce these
costs by 10‑30%; an excellent return on investment over
the life of the facility.[4] Objectives of Lean facility planning
are, obtaining a smooth work flow, reducing the walking
distances and work in progress, improving visibility for
effective management of operations, and improving the
work environment and inventory management.[5]
Along with Lean design concepts, this detailed planning
information covers personnel, equipment, and future growth
The more information compiled at this stage, the more
completely the outcome will meet the user group needs
An equipment list with specifications, including what will
be relocated, newly purchased, and projected for future
growth, ensures that utilities are matched to need The
list must include: Footprint (dimensions and weight),
electrical requirements, computer or interface requirements,
uninterruptible power supply (UPS), alarm, dedicated
circuit, emergency power, ventilation or exhaust, and a
plumbing drain or deionized (DI) water [Table 1] Cut
sheets must also be available for each piece of equipment,
conveying any information needed to install or use the
product A quantitative chemical inventory is essential
to provide the appropriate storage space This inventory
must include the chemical name, storage requirements,
and volume stored [Table 2] Storage of used reagents and residual specimen containers/fixatives must also be included in this volume The National Fire Protection Association (NFPA) provides ratings for areas based
on volume and potential hazards Anatomic pathology laboratories, because of the high volumes of xylene and formalin, are typically rated as Class A
Regulatory and safety requirements must be discussed as they relate to the specimen sources and testing to be performed
A BioSafety level is the level of bio‑containment precautions required to isolate dangerous biological agents in an enclosed facility The levels of containment range from the lowest, BioSafety level 1, to the highest, level 4 In the United States, the Centers for Disease Control and Prevention (CDC) have specified these levels.[6] Once determined, this level will dictate many of the safety requirements for the laboratory Our project and the typical cytology wet laboratory space is designated as BioSafety Level 2 (BSL2)
Future utilization must be addressed through a questionnaire and/or discussions among stakeholders Even as future needs are difficult to predict, this exercise can identify the potential areas of growth and direction of technological change A universally accepted growth area
in laboratories is automation in processing and specimen tracking, which will necessitate more electrical and data capacity than in the previous workplace
DESIGN
Throughout the Schematic Design, data and information from the planning phase is used by architects and planners
to create a general floor plan This design provides the groundwork for a series of meetings, to brainstorm and modify the plan To ensure maximum efficiency, the workflow (movement of specimens) and traffic flow (movement of personnel) must be carefully evaluated during this phase [Figure 3]
Specimen preparation and result reporting are bookends to the cytological testing process, providing both pre‑analytic and post‑analytic support One of the objectives in the design of the preparation area is to allow two to three operators to effectively and simultaneously cover several instruments and functions To achieve this, handling and walking distances are minimized and open areas are provided to facilitate visual management Open work areas also allow managers to quickly assess the state of operations, inventory levels, and communication among workers, a key feature of Lean design Another key requirement of this area is broad accessibility to other functional areas, specimen couriers at all hours, pathology sign out area, cytotechnologist screening, and imaging and archive Many of the laboratory safety mandates directly impact
Figure 2: Bubble diagram illustrating strength and complexity of
relationships, both internal and external, to the laboratory
Trang 4Network connection
Dedicated Circuit
Emergency Po wer
Vent out
ocessing Biohazar
Trang 5the preparation area and must be built into the design for
appropriate plumbing and electrical support and ease of
access for staff.[7,8] A safety checklist is provided in Table 3
The Occupational Safety and Health Administration (OSHA)
regulates and the American National Standards Institute
(ANSI) provides standards (ANSI/ISEA Z358.1‑2009) for
emergency shower and eye wash station equipment OSHA’s
general regulation ([29 CFR 1910.151 (c)]) states that: “Where
the eyes or body of any person may be exposed to injurious corrosive
materials, suitable facilities for quick drenching or flushing of the
eyes and body shall be provided within the work area for immediate
In contrast to the preparation area, cytotechnologists
performing the analytic phase of testing, screening, and
diagnostics, require a workspace with more restricted access,
to minimize interruptions Multifunction workstations,
with carefully considered ergonomics, must be designed,
due to the repetitive nature of screening.[10] To reduce the
movement of personnel and specimens; the workspace is designed to accommodate both manual and automated microscopes as well as computers An open area, with individual work cubicles and a common resource area for educational materials, meets the needs of rotating trainees Slides ready to be screened are transferred from the preparation to the screening area using a ‘pass thru’ cabinet This minimizes interruptions and also helps to maintain the positive/negative airflow between the two areas Conferencing facilities are a high priority for academic institutions A multipurpose space is designed, allowing
a multihead microscope review as well as overhead projection and presentation resources A moveable wall provides the capability of separating the two functions as needed Locating this adjacent to the lounge facilitates food service, often a component of functions and conferences The Americans with Disabilities Act (July 26 1990) requires that public entities ensure that newly constructed buildings
Table 2: Chemical inventory with quantification and hazard classification
Chemical Inventory
Room #
Max In Inventory Physical State Health Flammability Reactivity
Corrosive
Thinprep® Nuclear Stain
Trang 6and facilities are free of architectural and communication
barriers that restrict access or use by individuals with
disabilities The accessibility guidelines (ADAAG) are
numerous and detailed, however, compliance is relatively
simple if addressed early in the project [Table 5].[11]
Design development, the third phase, brings more detail
to the schematic design, with addition of engineering,
casework, equipment specifics, and finishes For long‑term
savings, requirements for sustainable design and energy
efficiency must be specified.[12] Examples of this are motion
sensor, timed lighting, and planned air conditioner
zones, to accommodate the heat generating equipment
Moveable casework will allow for adaptation to changing
instrumentation Use of open casework promotes the Lean
concept of visual assessment [Figures 4‑7]
As the project moves to Construction Documents, the
work transfers from the laboratory purview to a purely
technical mode At this point, due to costs, design changes
must not be made Architects and engineers provide more detail and specifications to allow qualified contractors to participate in the bid process
During the construction phase, architects and engineers serve as liaisons between the construction team and owners, to ensure compliance with the construction documents The user group tours the space periodically
to verify that the construction meets the expectations of the planning and design phases Change orders may be generated during this phase, however, they add to the project cost and must be minimized
Although not a phase of construction and beyond the scope of this article, it must be noted that detailed plans for the actual move‑in must begin early, as they can significantly impact the workflow and the project budget Vendors must be notified well in advance for quotes and schedules for equipment transport and set up Carefully developed detailed crosswalks from the old to the new
Figure 3: Schematic design illustrating movement of people and materials
Trang 7Table 4: Eyewash and emergency shower specifications
Eyewash and Emergency Shower Specifications Plumbed Eyewash
Station
Plumbed Emergency Shower
Heads - Positioned 33"—45"
from floor
- Positioned 6" from wall
or nearest obstruction
- 0.4 gallons per minute (GPM) for 15 minutes (provides flushing fluid
at 30 PSI)
- Positioned 82"—96" from floor
- Spray pattern will have
a minimum diameter
of 20" at 60" above the floor
- Flow Rate=20 gallons per minute (GPM) at 30 pounds per square inch (PSI)
- Center of the spray pattern at least 16 inches from any obstruction Valves - Activate in 1 second or
less
- Stay-open valve (leaving hands free)
- Activate in 1 second or less
- Stay-open valve (no use
of hands) Valve remains on until the user shuts off Installation - Requires no more than
10 seconds to reach
- Located in a well-lit area and identified with
a sign
- Located on the same level as the hazard
- Requires no more than
10 seconds to reach
- Located in a well-lit area and identified with a sign
- Located on the same level as the hazard
Mainte-nance and Training
- Activated weekly to verify correct operation
- Training for all employees who might
be exposed to a chemical splash
- Inspected annually to ensure ANSI Z358.1 compliance
- Activated weekly to verify correct operation
- Training for all employees who might
be exposed to a chemical splash
- Inspected annually to ensure ANSI Z358.1 compliance
Table 5: Americans with disabilities act
requirements
Doorways
32” with the door open 90º degrees
Wheelchairs
Single wheelchair passage 32”at a point and 36”continuously
Turning space-60” clear space for 180º turn
Reach
Forward 15”-48”
Side (parallel approach) 9”-54”
Sinks and fountains
Spouts 36” maximum
Lavatories 34” maximum, at least 29” to the bottom of the apron
Knee clearance 27” high, 30”wide, and 19” deep underneath
sinks
Table 3: Safety checklist and BLSI 2
requirements
Requirements
Automatic fire extinguishing
system
Two exit access doors, if required
Audible automatic fire detection
and alarm system
Fire alarm station
Portable fire extinguishers
Emergency lighting
Flammable and combustible liquid
storage
Acid and base storage
Emergency eye wash
Hand washing sink
Emergency Shower
PPE Storage
BioSafety Cabinet Requirements
Negative and Positive
Pressurization areas
Chemical ventilation
BSL 2 Requirements
All BSL1 Requirements Gloves
Facial protection Hand washing with anti-bacterial soap
Disinfect all exposed surfaces of the lab Specific training in handling pathogenic agents directed
by scientists with advanced training
Limited access to the laboratory
Extreme precautions are taken with contaminated sharp items
Use of biological safety cabinets or other physical containment equipment when infectious aerosols or splashes may be created
space for phones and computers, ensure a seamless transfer
of this equipment Customers and supply chains must
be informed of the potential interruption of service The
vacated space must be cleared of all chemical and biological
hazards as well as any Protected Health Information (PHI)
RESULTS
At completion, the project fitted out a total of 9000 square
feet; 4000 square feet of laboratory space and 5000 square feet of office/support space The laboratory space included areas for preparation, CT screening, sign out, and imaging The adjacent space housed faculty offices, support staff, and conferencing facilities
Our objectives for building a Lean facility were essentially met The workflow was improved by moving specimens and their derivatives in a linear motion, from receipt to final verification Walking distances (transportation) were greatly reduced by the installation of a Pneumatic Tube System (PTS), specimen drop window directly into the Prep area, and a pass thru cabinet to the screening area Logistically,
Trang 8Figure 4: Gyn-cytology processing elevation
Figure 5: Accessioning and staining coverslipping in an open work area
Trang 9Figure 6: Accessioning, staining, flammable cabinet, and refrigerated storage
Figure 7: Elevation 07: Non-Gyn processing
Trang 10closer proximity to Surgical Pathology maximized the natural
synergies between these areas Open floor plans for the main
functional areas and screening and preparation, improved
visibility for a more effective management of operations The
overall work environment was improved with better lighting,
aesthetics, conferencing facilities, information technology,
and employee comforts Inventory management was more
efficient, with accessible areas appropriate for short‑term
and long‑term storage Security was managed by key‑code
and card access entry and the slide archive area could only
be accessed by authorized individuals Surveillance cameras
were also strategically located for added security Efficiencies
were gained by ergonomically placing manual and imaging
microscopes in customized work cells for cytotechnologists
Location of computers in close proximity and the addition
of bar code scanners facilitated a new paperless workflow
for additional savings
SUMMARY
For Cytology, the past decade has brought tremendous
technological change to what for half a century, has largely
experienced predictable and constant practice Automated
stainers and cover slippers, liquid‑based processors, and
imaging systems are now a standard of practice in most
laboratories These advances in instrumentation require bench
space and facility modifications not seen in traditional cytology
laboratories With the expected decrease in volume of routine
Pap tests and growth and integration of molecular testing,
future cytology laboratories will demand an increasingly more
technologically sophisticated workplace Planning, design,
and construction must incorporate the flexibility to allow
this change at a minimal time and cost Infrastructure and
information technology must be able to support networked
instruments, mobile devices, wireless connectivity, digital
projection, and high quality audio‑visual technology
Successful laboratory construction must be a systematic
process, based on sound principles, to provide flexibility,
safety, quality of environment, and cost efficiency
Throughout the project, decisions must be driven by data
gathered in the planning phase This careful planning and
design can ensure that the laboratory we build today will
adapt to the laboratory we need tomorrow
COMPETING INTEREST STATEMENT BY
ALL AUTHORS
The author(s) declare that they have no competing interest
AUTHORSHIP STATEMENT BY ALL
AUTHORS
All authors declare that we qualify for authorship as defined by
ICMJE http://www.icmje.org/#author Each author aknowledges
that this final version was read and approval.
ETHICS STATEMENT BY ALL AUTHORS
This article content does not require approval from Institutional Review Board (IRB) at out institution Authors take responsibility
to maintain relevant documentation in this respect.
REFERENCES
1 Research Laboratory Design Guide, Department of Veterans Affairs Office
of Research and Development, Office of Facilities Management September
30, 1995 Available from: http://www.wbdg.org/ccb/VA/VADEGUID/lab.pdf [Last accessed on 2012 Jan 18].
2 Mortland K Laboratory Design for Today’s Technologies, MedTechNet East Amherst, NY; May 1997 p 1-14.
3 Clinical and Laboratory Standards Institute Laboratory Design; Approved Guideline ‑Second Edition CLSI document GP18-A2 [ISBN 1-56238-631-X]
Clinical and Laboratory Standards Institute 940 West Valley Road, Suite 1400 Wayne, Pennsylvania 19087-1898 USA, 2007.
4 Joseph T Design Your Laboratory of the Future Available from: http://www sprickstegall.com [Last accessed on 2011 Sept].
5 Lean Boot Camp: CLMA Immersion Day, presented by Susan Stegal www sprickstegall.com
6 Centers for Disease Control and Prevention, Summary of BioSafety Levels-1 and 2 http://emergency.cdc.gov/documents/PPTResponse/table3abiosafety pdf [Last accessed on 2012 Jan 18].
7 College of American Pathologist http://www.cap.org Lab General Checklist 7/11/2011
8 NCCLS Clinical Laboratory Safety: Approved Guideline‑Second Edition NCCLS
document GP17-A2 [ISBN 1-56238-530-5] NCCLS 940 West Valley Road, Suite 1400 Wayne, Pennsylvania 19087-1898 USA; 2004.
9 Eyewash and Safety Shower Requirements Available from: http://gesafety com/ansi/index.shtml Last accessed 02/2013.
10 Ergonomics Checklist Available from: http://www.ehs.ucr.edu/ehsacademy/ presentations/ergonomicslaboratorychecklist.pdf [Last accessed on 02/2013]
11 Available from: http://www.ada.gov/2010ADAstandards [Last accessed on
2011 Aug].
12 Supporting Integrated Design through Interlinked Tools: The Labs21 Toolkit Available from: http://www.labs21century.gov/ [ Last accessed on 2012 Jan 18].
EDITORIAL / PEER‑REVIEW STATEMENT
To ensure the integrity and highest quality of CytoJournal publications, the review process of this manuscript was conducted under a double blind model (authors are blinded for reviewers and vice versa) through automatic online system.
www.cytojournal.com
Peer-reviewed academiccytopathologyjournal
The FIRST Open Access cytopathology journal
Publish in CytoJournal and RETAIN your copyright for your intellectual property
Become Cytopathology Foundation Member to get all the benefits
Annual membership fee is nominal US $ 50 (US $ 1000 for life)
In case of economic hardship it is free For details visit http://www.cytojournal.com/CFMember.asp
PubMed indexed
FREE world wide open access Online processing with rapid turnaround time.
Real time dissemination of time-sensitive technology
Publishes as many colored high‑resolution images
Read it, cite it, bookmark it, use RSS feed, &