Table 2.4: Comparison of Defined Terms Owner Architect/Engineer Contractor Subcontractor The Project Approved Provide Specifications Requirements Drawings Final Completion Governmental A
Trang 1Washington University in St Louis
Washington University Open Scholarship
All Theses and Dissertations (ETDs)
January 2010
Front End Specifications and the Propagation of Construction Claims
Sidney Hymes
Washington University in St Louis
Follow this and additional works at:https://openscholarship.wustl.edu/etd
This Dissertation is brought to you for free and open access by Washington University Open Scholarship It has been accepted for inclusion in All Theses and Dissertations (ETDs) by an authorized administrator of Washington University Open Scholarship For more information, please contact
Trang 2WASHINGTON UNIVERSITY IN ST LOUIS School of Engineering and Applied Science Department of Civil Engineering
Dissertation Examination Committee:
Dr Thomas Browdy, Chair
A dissertation presented to the School of Engineering
of Washington University in partial fulfillment of the
requirements for the degree of DOCTOR OF SCIENCE
December 2010 Saint Louis, Missouri
Trang 3copyright by Sidney J Hymes
2010
Trang 4
ABSTRACT OF THE DISSERTATION
Front End Specifications and the Propagation of Construction Claims
by Sidney J Hymes Doctor of Science Washington University in St Louis, 2010 Research Advisor: Professor Thomas Browdy Front End Specifications represent the administrative, organizational, performance and payment requirements for construction projects The vast majority of construction contracts use Front End Specifications, either from an independent source or prepared in-house In spite of the crucial role of Front End Specifications, little is known regarding whether Front End Specifications increase or decrease claims in construction Further, no published reports
to date have investigated whether construction claims are systematically related to Front End Specification complexity, partnering, business size or document authorship
In the present quantitative study, participants (n = 150) from the construction industry, including contractors, subcontractors, designers and owners, completed an on-line survey of sixteen multi-part questions detailing common Front End Specifications and the impact of those specifications on claims
Results indicate that disputes and claims from Front End Specifications impose significant costs on construction projects, with scheduling specifications/requirements, summary
Trang 5iii
(scope) of the work and coordination being the most common causes of claims Perceptions
of claims were not related to business size or document authorship Partnering participants trended towards perceiving Front End Specifications as decreasing claims Regulatory
Requirements were generally perceived as too complex and participants who perceived Front End Specifications Regulatory Requirements as too complex were significantly more likely to believe that Front End Specifications would cause more claims
Results are discussed in the context of ConsensusDOCS® library of construction forms, practical implications for construction project management, limitations of the present study and areas for future research
Trang 6Contents
Abstract ii
List of Tables vi
List of Figures viii
1 Introduction 1
2 Literature Review 4
2.1 A Primer in Front End Specifications 4
2.2 Front End Specifications Compared 10
2.3 Identifying the Sources of Claims 29
2.4 Partnering 44
2.5 Literature Summary and Overview of the Present Study 45
3 Research Methodology 48
3.1 Research Design 48
3.2 Participants 49
3.3 Instrumentation 49
3.4 Procedures 52
3.5 Data Analysis 53
4 Results 54
4.1 Survey Assumptions, Limitations and Participant Descriptives 55
4.2 Do Front End Specifications Cause Claims? (Hypothesis 1) 66
4.3 Which Front End Specifications Cause Claims? (Hypothesis 1b) 68
4.4 Front End Specifications Claims: Additional Costs Incurred and Profits Lost (Hypothesis 2) 77
4.5 Complexity and Front End Specifications (Hypothesis 3) 79
4.6 Would the Use of Performance-Based Front End Specifications Increase or Reduce Claims? (Hypothesis 4) 87
4.7 Partnering and Front End Specifications: Claims and Resolution (Hypothesis 5) 91
4.8 Claims Resolution 94
4.9 Research Results – Summary and Preliminary Discussion 95
5 Discussion 100
5.1 Review of Present Findings 100
5.2 Implications .101
Trang 7v
5.3 Improving the Front End Specifications 104
5.4 Towards Uniform Front End Specifications 112
5.5 Suggestions for Future Research 122
5.6 Conclusions 124
Appendix A General Background Review 126
Appendix B ASA Seminar Discussion 129
Appendix C Survey Question Reviewers 131
Appendix D Survey Questions 132
Appendix E Sample Front End Specifications Documents 141
Appendix F UFES Survey Responses 205
Appendix G Glossary and Acronyms 213
References 215
Vita 222
Trang 8List of Tables
Table 2.1: Front End Specifications for a Complex Project 7
Table 2.2: CMAA Form CMAR-3 Topics 8
Table 2.3: Quantitative Specifications Summary 11
Table 2.4: Comparison of Defined Terms 12
Table 2.5: Contract Documents Definitions Compared 13
Table 2.6: Contract for Construction Language Comparison 14
Table 2.7: “The Work” Defined 15
Table 2.8: Comparison: As-Built Drawings Specification 16
Table 2.9: Comparison of Schedule Requirements 19
Table 2.10: Weather Specifications 21
Table 2.11: Comparison of Schedule of Values; Payments 23
Table 2.12: Comparison: Detail Level 27
Table 2.13: CII (1986) “Problem Areas” 34
Table 3.1: Front End Specifications Distribution 51
Table 4.1: Employment Sectors 57
Table 4.2: Business Size 58
Table 4.3: Subsidiary Company 59
Table 4.4: Employment Role/Job Title 59
Table 4.5: Number of Projects 61
Table 4.6: Project Value Summary 60
Table 4.7: Frequency of Claims by Project Value 67
Table 4.8: Frequency of Claims, by Rate of Occurrence, All 69
Table 4.9: Ranking Weights (All Size Categories) 71
Table 4.10: Normalized Claims Rankings, All Companies 72
Table 4.11: Normalized Claims Rankings (Small Companies) 73
Table 4.12: Normalized Claims Rankings (Medium Sized Companies) 74
Table 4.13: Normalized Claims Rankings (Large Companies) 75
Table 4.14: Top Normalized Claims Rankings (All Companies) 75
Table 4.15: Additional Costs and Profit that Would Have Been Retained 78
Table 4.16: Normalized Complexity Response Proportions, All Companies 80
Table 4.17: Normalized Complexity Response Proportions, Small Companies 82
Table 4.18: Normalized Complexity Response Proportions, Medium Companies 83
Table 4.19: Normalized Complexity Response Proportions, Large Companies 84
Table 4.20: Simplicity/Complexity Where SD >=1 86
Table 4.21: Document Authorship and Front End Specifications Claims 90
Table 4.22: Partnering and Negotiation between the Parties without Utilizing Attorneys 92
Table 4.23: Performance-Based Front End Specifications Claims by Partnering and Non-Partnering 93
Table 4.24: Proportion of Claims by Resolution Method 95
Trang 9vii
Table 4.25: Summary of Survey Responses 97
Table 5.1: As-built and Record Drawings 116
Table 5.2: Schedules 117
Table 5.3: Weather 118
Table 5.4: Schedule of Values 119
Table 5.5: Progress Payments 120
Trang 10List of Figures
Figure 3.1: Needs Analysis Methodology 49
Figure 4.1: Business Size (by segment) 58
Figure 4.2: Project Frequency by Contract Value 62
Figure 4.3: Most Often Used Standard Form Contract Types 64
Figure 4.4: Authorship by Project Value 64
Figure 4.5: Top Causes by Percent Claims 70
Figure 4.6: Performance-Based Front End Specifications and Claims 89
Figure 4.7: Partnering and Negotiation without Utilizing Attorneys ……… 92
Trang 111
Chapter 1
Introduction
Front End Specifications are a crucial, integral component of construction
documentation Little is known regarding whether Front End Specifications increase or decrease claims in construction Further, whether construction claims are related to Front End Specification complexity, partnering, business size or document authorship has been unclear
Determining the impact of Front End Specifications on claims is important
Construction is a very complex process requiring the cooperation and coordination of many skilled professionals from multiple organizations For example, a small to
medium-sized ($5-10 million) project may require fifty or more contractors and
organizations (LePatner 2007) With so many participants and activities occurring at any given time, managing the construction process requires more than technical skills Business acumen and organizational expertise can dictate the ultimate success of a project, but only if all parties agree to their roles in advance Therefore, it is important for the parties to agree to specifications before work begins
Modern construction documentation incorporates both procedural (“administrative”) and technical requirements to establish the policies and procedures necessary to govern the project’s lifecycle The administrative and organizational requirements are contained
in the first part or parts of the project specifications and are commonly referred to as the “Front End” specifications.1 Specifically, the Front End Specifications delineate the rights and responsibilities of the parties involved in the contract, as well as their
subcontractors and the way in which the contract will be administered
1 The phrase “General Conditions” is synonymous with Front End Specifications
Trang 12As an experienced construction lawyer, the author has a long-standing professional interest in how construction contracts are administered and managed It has been the author’s experience that the Front End Specifications can often complicate an already complex situation with “fine print” Rather than reduce or eliminate confusion and uncertainty, specifications may have the contrary result However, the anecdotal
experiences of the author are no substitute for the scientific application of objective measures with representative samples of multiple levels of job titles within the
construction industry, including contractors, subcontractors, designers and owners
The purpose of the present study was to objectively determine whether Front End Specifications have a tendency to increase or decrease claims in the construction
industry and further, to determine whether construction claims are related to Front End Specification complexity, partnering, business size and document authorship The present study addressed the following research questions:
• Do the Front End Specifications cause disputes and claims?
• If Front End Specifications do cause claims, which are the most significant and have the most significant impact on projects?
• Do significant costs or lost profits result from claims?
• Are Front End Specifications perceived as being either too simple or too
Trang 133
This doctoral dissertation is arranged in five (5) chapters In Chapter 2, the Literature Review, with a primer in Front End Specifications, is provided in the context of modern construction documentation Next, representative Front End Specifications are
compared, including Front End Specifications in use at Washington University in St Louis Causes of disputes and claims follow This chapter ends with a summary of the literature and an overview of the present study
Chapter 3, the Research Methodology, details the design, participants, instrumentation and determination of which Front End Specifications to include in the present study, and those procedures and data analyses used to address the research questions
Chapter 4 begins with descriptives of participants Then the research results for each of the research questions are detailed, including analyses to objectively address the research questions
Chapter 5 discusses the present findings towards improving Front End Specifications and then provides a critique of a recently-released standardized documents protocol
study are then offered
To guide the reader, Glossary and Acronyms are presented in Appendix G
Trang 14Chapter 2
Literature Review
This Literature Review begins with a primer in Front End Specifications in the context
of modern construction documentation Front End Specifications vary greatly and a side-by-side comparison of Front End Specifications from Washington University and Rochester Institute of Technology highlight the stark differences in Front End
Specifications This chapter ends with a Summary of the Literature Review and an overview of the present study
The purpose of this section is to define and discuss the role of the Front End
Specifications in the context of modern construction documentation and project
administration
The purpose of the Front End Specifications is to provide guidance and direction for the non-technical aspects of the work by addressing numerous administrative issues Examples include specifying the executive and senior-level individuals (such as project manager and senior scheduler) that a contractor (whether designer, construction
manager or prime contractor) must provide for the job, the physical spaces (such as offices and work cubicles) to be provided for the benefit of the owner and the company employees or consultants and often the scheduling software that will be utilized Other project management requirements may direct the type and number of copies of reports
Trang 155
to be produced, to what extent a contractor may change its work sequence without the prior written approval of the owner and in what form and format the contractor will keep its books of account and project records Similar directives regarding the
administration of the project (notice requirements and addresses, form of notice,
approval requirements, etc.) are also commonly included
In an attempt to reduce inconsistencies as well as reduce costs, the Front End
Specifications are frequently recycled from one project to another2 and from one owner
to another; it is thought that such “standardized” language removes or minimizes the effects of uncertainty from one project to the next (Patterson 2001).3 If this were true, the language would be so precise that it would eliminate the possibility of (or need for) claims and litigation over the meaning of the “standardized” specifications.4 As is well documented, claims and litigation have increased over the years5; it is conceivable that the language an owner inserts into the contract documents as protective measures may,
in fact, be responsible for the same disagreements that the owner sought to avoid in the first place.6
These disagreements may result because the “administrative” provisions are in conflict with project execution For example, owners generally state (and the specifications often provide) that the contractor is solely responsible for the “means and methods” of the
6 A brief general background review is contained in Appendix I
Trang 16construction.7 In practice, project requirements may be construed by constructors as dictates by the owner amounting to an assumption of the “means and methods” by the owner and any problems that result are arguably the responsibility and financial
obligation of the owner (Klinger and Susong 2006; Mincks and Johnson 2004)
One must look at the process in its entirety to find the common denominator that may lead to disputes and claims While poorly drafted plans and construction documents contribute to disputes, little investigation into what this means has been conducted (Netherton 1983) It is conceivable that overly restrictive Front End Specifications may
be contributing to these problems
It is appropriate to discuss some of the more common Front End Specifications (see Table 2.1 below) and review their use in actual project examples Since even with the
“standard forms” there are variations in the actual language utilized on any particular contract,8 it is not possible to dissect every variation of such examples.9
As was briefly introduced in the opening paragraphs, the Front End Specifications provide the general organizational and administrative directives for the project
(Bubshait and Almohawis 1994) In reality, there are no minimum requirements for Front End Specifications; indeed, a construction contract need only meet the basic legal requirements (offer, acceptance, consideration, legality, mutuality, capacity to contract)10
in order to be binding As noted in the well-known Schexnayder and Mayo (2004) publication, Construction Management Fundamentals, typical topics (in no particular order) in
a “short form” example may include:
7 See, for example, Sabo, Werner, “Legal Guide to AIA Documents, 4 th Ed., Aspen Publishers Online,
2001 IL: Riverwoods at 264
8 See, for example, Hinze and Tada (1993)
9 A potential for additional research could be analyzing the variations in any one owner’s utilization of its own “standard form” documents
10 See, for example, “Legal Elements of a Contract”, accessed at
Trang 177
• Administration of the contract
• Terms and Definitions
• Changes in the Work
• Time and Schedules
• Payments and Completion
• Safety
• Insurance and Bonding
• Corrections to the Work
• Terminations and Suspension of the Work
Construction Facilities and Temporary
Soil Erosion and Sedimentation
Communications Equipment
Operations
Tools Training
11 Source: City of Detroit River Rouge Reconstruction project
Trang 18At the other end of the spectrum, and most often utilized on complex projects, a detailed topical listing may contain the topics shown in Table 2.1 above The standard form advocated by the Construction Management Association of America (CMAA) has fifteen topical titles as shown in Table 2.2 below:
Table 2.2: CMAA Form CMAR-3 Topics
Work by the Construction Manager or by
Separate Contractors
Dispute Resolution
Payments and Completion
It must first be recognized that more topical content together with additional detail does not guarantee a better document Moreover, topical titles, even if identical, do not automatically result in identical content How and to what extent the various subjects are handled may vary significantly from document to document and project to project, even if utilized by the same owner or builder (Hinze and Tada 1993) Even within a project there can be major differences, both coordinated and conflicting, as prime contractors strive to follow the owner's rules and then pass those same rules, together with their own, on to the subcontractors on the project This remains true regardless of the project’s owner and whether the owner is private or public To the extent that the rules become more complex or cumbersome (admittedly, a subjective term), such as with the Federal Acquisition Regulations (“FARs”), the costs associated with such complexities become part of the contract price, whether itemized or not
Before starting this research, it was appropriate to first determine if persons other than the author saw the Front End Specifications as a potential source of disputes and claims During this same time frame, the Construction Management Association of America (“CMAA”) issued a “Request for Grant Proposal” solicitation, which focused
on how a professional construction manager could reduce claims on a project CMAA's interest in the topic remained high and discussions with Bruce D'Agostino, Executive
Trang 199
Director of CMAA, resulted in CMAA assisting in the distribution of research
instruments for this research project.12
To further determine if the proposed research had merit beyond CMAA’s interest, a short survey of twenty-four (24) construction professionals (the details of which are included as Appendix B) was conducted by the author during a claims avoidance
presentation and training session at the American Subcontractors Association's 2005 Business Forum and Convention in Orlando, Florida on March 17, 2005 The ASA is a national organization whose membership is comprised primarily of commercial specialty trade contractors.13
In response to the opening question asking if the contract or specifications’ language itself caused claims or disputes, 92% of the attendees answered in the affirmative With one exception (an attorney), the attendees were all specialty contractors and may have had one or more claims experiences that added some bias to their perspectives
Comments by the participants convinced the author that additional research, which would include owners, prime and specialty contractors and construction managers, was warranted
This research project was undertaken to determine if commonly used Front End
Specifications promote or reduce the number of construction claims Additionally, the findings of this research complement recent efforts to establish wide acceptance for standardized Front End Specifications that address many of the concerns identified by survey participants Two major advantages result by utilizing standardized Front End Specifications First, the cost of creating “new” Front End Specifications is eliminated,
12 Discussion with Bruce D'Agostino, Executive Director of CMAA, February 23, 2005, in San Antonio, Texas, while the author was attending the mid-year meeting of the American Council of Construction Education
13 For clarification, a subcontractor is one who performs work for a prime or general contractor A specialty contractor, also frequently called a “trade contractor”, performs a limited scope of work such as mechanical, steel erection or concrete work A specialty contractor can be either a subcontractor or a prime contractor; the status is defined by the contractual relationship between the parties and this is true regardless if the project is public or private, commercial, industrial or residential
Trang 20thereby reducing initial project document drafting costs Second, the use of consistent language, accepted in advance by the endorsing participants, should reduce the
problems which arise from inconsistent interpretation of “new” language introduced by
an unfamiliar set of Front End Specifications With consistent usage and understanding, fewer disputes and claims should result To demonstrate the extent of the problem, the next section compares Front End Specifications between universities
2.2 Front End Specifications Compared
With the many forms of Front End Specifications available, drawing a comparison between similar project documents places the problem in context To that end, the author acquired copies of “standard” form Front End Specifications from a number of educational institutions, rationalizing that many universities have common goals in their building programs For example, all schools, public or private, are cost-conscious, safety-aware, have the need for accessible facilities and generally want the construction completed by a specific date, often tied to the beginning of the school year or a
semester break The Front End Specifications from four educational institutions14
(including Washington University in Saint Louis, Los Angeles Community Colleges, UC Berkeley and the Rochester Institute of Technology) were selected for comparison purposes; a review of those four documents (See Table 2.3) yields interesting discussion
14 These particular school documents were selected based on the length of the specifications, similarities
to the AIA form document and page counts The two California schools were selected to contrast with the more comprehensive building codes and litigious nature of the state
15 Copies of each of the referenced documents are included in the Appendices
Trang 2111
Table 2.3: Quantitative Specifications Summary
Washington University
Note LACC = Los Angeles Community Colleges, RIT = Rochester Institute of Technology
Comparing the total number of pages (or another arbitrary classification) does not rate content or completeness of the documents "Quality is more important than quantity" applies in the case of both legal and construction documentation Nonetheless, it is of interest that there is such a large difference in the relative sizes of the various
documents, primarily given the arguably consistent goals of each institution
In terms of inclusiveness, the Washington University and Rochester Institute of
Technology Front End Specifications are comparable They are of similar length and their language often closely parallels that of the AIA documents The two larger
documents are from institutions in California and go into much more detail (as well as covering additional topics) than the non-California institutions.16 It is beyond debate that a good lawyer keeps a client out of court by anticipating issues and providing mechanisms for resolution beforehand; hence, the lengthy LACCD document tries to address all potential problems, including those unique to California law
To demonstrate the similarities and differences between the two documents, selected sections are highlighted in the following tables By presenting the comparable
provisions side-by-side, one can see the nuances in document drafting We begin by comparing the topic of “defined terms” which is set forth in Table 2.4 below
Headings alone do not provide a complete description of the contents of each section For example, not only does Washington University define “as-built drawings” in its
16 This is not surprising: California has some of the most comprehensive construction codes, statutes and court decisions in the nation and is a very litigious venue
Trang 22definition section, there is a section (GC-4) devoted exclusively to the subject Similarly, RIT has a section (9.9) on the topic but does not include it in its definitional area and its coverage is somewhat less than that of Washington University
Table 2.4: Comparison of Defined Terms
Owner Architect/Engineer
Contractor Subcontractor
The Project Approved Provide Specifications Requirements Drawings Final Completion Governmental Authority Hazardous Materials Product Project Manual
Note Items in the RIT documentation have been re-ordered for comparison purposes
Trang 2313
Beyond the headings, the content is most important Looking at some of these
provisions in more detail (Table 2.5), we find that the definitions of Contract
Documents are very similar:
Table 2.5: Contract Documents Definitions Compared
The Contract Documents consist of the
Agreement between Owner and Contractor,
these General Conditions, Drawings, Project
Manual and Specifications, addenda issued
before execution of the Agreement, other
documents listed in the Agreement, and
modifications issued after execution of the
Agreement A modification is a written
amendment signed by both parties, a change
order, a construction change directive, or a
written order for a minor change in the Work
issued by the Architect/Engineer
The Contract documents consist of: the Advertisement/Request For Proposal, Form of Proposal, Owner-Contractor Construction Agreement, General Conditions of Contract for Construction, Supplementary General
Conditions of the Contract for Construction (and all Enclosures, Appendices and Exhibits thereto), Specifications, Drawings, and any Addenda issued prior to the execution of the Owner-Contractor Agreement and all Modifications thereto A Modification is (1) a written amendment to the Contract signed by both parties, (2) a Change Order, (3) a written interpretation issued by the Architect pursuant to Subparagraph 2.2.5, or (4) a written order for a minor change in the Work issued by the Architect pursuant to Paragraph 12.4
The differences are subtle with the RIT definition being more inclusive In addition to the actual contract for construction, the “Contract Documents” (i.e., all the components
of the agreement) include the general conditions (i.e., the Front End Specifications) as well as the supplemental conditions and addendum, together with any modifications and change orders together with “written order[s] for minor work.” Drawings are also included The RIT document also includes both the solicitation for and the contractor’s response (proposal) but not the project manual Washington University’s definition does not include the solicitation or proposal and does include the Project Manual as well as any “construction change directive” Washington University’s provision is similar
to the language in the AIA document:
The Contract Documents consist of the Agreement between Owner and
Contractor (hereinafter the Agreement), Conditions of the Contract
(General, Supplementary and other Conditions), Drawings,
Specifications, Addenda issued prior to execution of the Contract, other
documents listed in the Agreement and Modifications issued after
execution of the Contract A Modification is (1) a written amendment to
Trang 24the Contract signed by both parties, (2) a Change Order, (3) a
Construction Change Directive or (4) a written order for a minor change
in the Work issued by the Architect Unless specifically enumerated in
the Agreement, the Contract Documents do not include other
documents such as bidding requirements (advertisement or invitation to
bid, Instructions to Bidders, sample forms, the Contractor's bid or
portions of Addenda relating to bidding requirements) (2005, GC-3)
There is no significant difference between the Washington University provision and that
of the AIA form while the RIT specification essentially mimics the AIA language and specifically includes the solicitation and responsive documentation
Compared next is the “Contract for Construction” language (Table 2.6) This provision defines what documents comprise the "contract" as a whole, beyond the single document which carries the title of "Agreement" or "Contract" or even "Contract for Construction"
Table 2.6: Contract for Construction Language Comparison
The Contract Documents form the Contract for
construction and represent the entire integrated
Agreement between the Owner and Contractor,
and shall not be construed to create a contractual
relationship of any kind between any parties other
than the Owner and the Contractor
The Contract Documents form the Contract for Construction This Contract represents the entire and integrated agreement between the parties hereto and supersedes all prior negotiations, representations, or agreements, either written or oral The Contract may be amended or modified only by a Modification as defined in Subparagraph 1.1.1 The Contract Documents shall not be construed to create any contractual relationship of any kind between the Architect and the Contractor, but the Architect shall be entitled to performance
of obligations intended for his benefit, and to enforcement thereof Nothing contained in the Contract Documents shall create any contractual relationship between the Owner or the Architect and any Subcontractor or Sub-subcontractor
In essence, the RIT specification includes all of the language included in the
Washington University provision, supplemented by how the contract can be modified The AIA language is even broader:
The Contract Documents form the Contract for Construction The
Contract represents the entire and integrated agreement between the
parties hereto and supersedes prior negotiations, representations or
Trang 2515
modified only by a Modification The Contract Documents shall not be
construed to create a contractual relationship of any kind (1) between
the Architect and Contractor, (2) between the Owner and a
Subcontractor or Sub-subcontractor, (3) between the Owner and
Architect or (4) between any persons or entities other than the Owner
and Contractor The Architect shall, however, be entitled to
performance and enforcement of obligations under the Contract
intended to facilitate performance of the Architect's duties
Neither the RIT nor Washington University specifications address relationships
with any lower tier contractors (referred to as either subcontractors or
sub-subcontractors), the effect of which should insulate each institution from direct
claims by subcontractors.17 Note that the AIA document also includes language
making the Architect a third-party beneficiary under the contract between the
Owner and the Contractor Finally, as within the definitional areas of these
documents, compare “The Work” (Table 2.7) The Work defines what is to be
done and is also known in the industry by the terms "scope of work" and
"summary of the work", which are used interchangeably in this document If the work is not fully defined, problems arise and claims and disputes follow While
it would be preferable to have all the details of the contractor's obligations in
one place, that is not practicable
Table 2.7: “The Work” Defined
The Work comprises the completed construction
required by the Contract Documents and includes
all labor necessary to produce such construction
and all materials and equipment incorporated in
such construction
The Work comprises the completed construction required by the Contract Documents and includes all labor and supervision necessary to produce such construction, and all materials and equipment incorporated or to be incorporated in such construction or required for the construction
Both documents’ definitions are nearly identical and closely parallel the AIA
language:
17 Some jurisdictions do not require privity of contract for a subcontractor to enforce a claim directly against an owner The discussion of this topic is beyond the scope of this paper See, for example, Cameron, John G., A Practitioner's Guide to Construction Law, New York: ALI-ABA, 2000
Trang 26The "Work" means the construction and services required of the
Contractor by the Contract Documents, whether completed or partially
completed, and includes all other labor, materials, equipment and
services provided or to be provided by the Contractor to fulfill the
Contractor's obligations The Work may constitute the whole or a part
of the Project
The reader may wonder whether the nuances justify the use of custom forms
when a readily available “generic” document such as the AIA or
ConsensusDOCS® forms (discussed in Chapter 5) is readily available
Construction contracts would be improved, and claims avoidance success increased, by better aligning the interests of owners and contractors.18 By better defining and documenting what is expected, the uncertainty is, to a great extent, eliminated and the contractor can focus on getting the project constructed As CII noted:
… negotiating a contract [to establish] the intent and effect of [contract] clauses [will result in] language [that]
can be adopted that both parties agree is clear and appropriate for the work at hand (CII 1986, 6)
Changes occur during the course of the project, for any one of a number of reasons As
a result, it is necessary to revise the drawings to reflect the various changes Looking at the content of the "as-built drawings" requirement more closely, Table 2.8 provides a side-by-side comparison of the relevant language
Table 2.8: Comparison: As-Built Drawings Specification
GC-4 AS-BUILT DRAWINGS
A Contractor shall maintain on-site and submit
for approval of Owner's Representative
upon completion of the work, a
complete set of "As-Built" drawings and
specifications of the Contract
Documents which clearly show with
dimensions any variation from working
drawings in the installation of materials
and equipment
B On-Site Requirements: Contractor shall
maintain a complete bound set of all drawings,
1 AS BUILT DRAWINGS 9.9.1 The Contractor shall red mark blue line prints
of the project indicating all changes to the drawings and submit them to the A/E
prior to submitting final request for payment 9.9.2 Where coordination drawings have been prepared in CAD format, the Contractor shall also submit these CAD files
4.11 DOCUMENTS AND SAMPLES AT THE
Trang 27
17
specifications, addenda, approved shop drawings,
change orders and other modifications of the
Contract Documents for inspection at any time
by Owner's Representative Contractor shall mark
up the on-site set each day to record
measurements, changes and deviations from the
design and additions and deletions thereto, as
approved, as well as existing facilities encountered
in the course of the work, which are not shown
on the drawings It is mandatory that the on-site
set of record drawings be kept up-to-date by
Contractor
C Form of Submittals: "As-Built" drawings
submitted by Contractor to Architect or Engineer
for approval shall be red-lined prints, fully marked
up to show all changes approved by Change
Orders, approved Field Change Requests or
changes approved by Owner's representative
SITE 4.11.1 The Contractor shall maintain and make available at the site for the Owner and Architect one record copy of all Drawings, Specifications, Addenda, Change Orders and other Modifications,
in good order and marked currently to record all changes made during construction, and approved Shop Drawings, Product Data and Samples These shall be delivered to the Owner upon completion
of the Work In addition, Contractor shall be responsible for providing the Architect with record drawings on a CAD disk
The AIA language is similar to that contained in subparagraph 4.11.1 of the Washington University document:
The Contractor shall maintain at the site for the Owner one record copy
of the Drawings, Specifications, Addenda, Change Orders and other
Modifications, in good order and marked currently to record field
changes and selections made during construction, and one record copy
of approved Shop Drawings, Product Data, Samples and similar
required submittals
As noted earlier, the differences are minor and utilization of a generic,
standardized form would satisfy the needs of either institution
These provisions have subtle differences The topic is covered in one singular location
by Washington University's documentation; RIT's document addresses the same topic
in two sections some ten (10) pages apart Separated as such, the opportunity to miss something exists by virtue of being addressed in two separate locations Also, note that
§4.11.1 requires the contractor to mark up the drawings “currently” while §9.9.1 has no requirement of contemporaneous preparation While a minor point, this always has the potential of being an issue of contention should a dispute arise between the parties It would be better to include all the language in one place under the singular topic as in the example below:
Trang 28The Contractor shall maintain and make available at the site for the Owner and Architect one record copy of all Drawings, Specifications, Addenda, Change Orders and other Modifications, in good order and marked currently
in red on the blue line prints of the project to record all changes made during construction, and approved Shop Drawings, Product Data and Samples The Contractor shall submit the marked up drawings to the A/E (on behalf of the Owner) prior to submitting its final request for payment
The language is similar, but with everything regarding the topic in one place, there is less chance of overlooking the additional language.19 The point of this discussion is that consistency defines standardization and standardization will reduce claims by
eliminating the uncertainty inherent in variations on a theme (See the comments
contained in Appendix F)
The project schedule is, without a doubt, one of if not the most important document created after the contract is signed It provides the basis for measuring progress and, when there are delays, a basis for determining the effect of the delay(s) Compare the project schedule and weather specifications are next compared in Tables 2.9 and 2.10
19 While this change might simplify the specification, allowing it to remain split does not relieve the contractor of the need to fully review and understand the contract documents
Trang 2919
Table 2.9: Comparison of Schedule Requirements
GC-27 PROJECT SCHEDULE
A Contractor shall confer with Owner's
Representative to determine a mutually acceptable
schedule
B Contractor shall submit written copies of
schedule for approval Schedule shall be related to
calendar periods and indicate starting and
completion dates of major and critical items of
the work and the various stages of construction
Should changes become necessary, Contractor
shall follow approved Project Schedule unless
Owner subsequently approves rescheduling
individual items of the work Should changes
become necessary, Contractor shall revise the
schedule and re-submit for approval
C Almost all of the Work must be scheduled in
advance to permit Owner to make necessary
adjustments in Owner's operations, which will
allow Contractor to perform his work Contractor
shall follow approved Construction Project
Schedule unless Owner subsequently approves
rescheduling individual items of the Work
D Items scheduled shall be sufficiently small in
scope and detailed to permit ready evaluation of
the progress of completion of the item Division
of the Work into scheduled items may be specific
items, class or type of work or by area as may best
serve for monitoring progress of the item
E The dollar value of each scheduled item from
the Schedule of Values shall be listed on the
Project Schedule
F Items of Subcontractor work shall be
scheduled in similar detail
G The Project Schedule shall be plainly related to
calendar dates to permit identification of
scheduled starting and completion dates for
phases of each item of work and events
H If the value to be claimed on Project Schedules
is not linear and continuous with completion
schedule, percentages shall be indicated at
appropriate points on the item schedule line
I Progress Schedules shall be submitted with
each application for partial payment The
schedule for each scheduled item shall be
distinctively marked to show completion claimed
for payment and the total value claimed shall be
written on the schedule
4.10 PROGRESS SCHEDULE 4.10.1 The Contractor, immediately after being awarded the Contract,
shall prepare and submit for the Owner's and Architect's review and approval an estimated progress schedule for the Work The progress schedule shall be related to the entire Project to the extent required by
the Contract Documents, and shall provide for expeditious and practicable execution of the Work The schedule shall state the proposed starting and completion dates for the various subdivisions of the Work as well as the totality of the Work and identify the Project's critical path
4.10.2 With the Progress Schedule, the Contractor shall provide Owner, and Architect, with copies of
a table showing the projected monthly drawdown for value of work completed throughout the contract period
4.10.3 The Progress Schedule shall be monitored and updated at the job meetings and copies supplied to Owner and Architect as updated Each schedule shall contain a comparison of actual progress with the estimated progress for such point
in time stated in the original schedule
4.10.4 If, in the opinion of Owner, Contractor falls behind the latest
Progress Schedule, the Contractor shall take whatever steps may be necessary to improve its progress and shall, if requested by Owner, submit operational plans demonstrating how the lost time may be regained The Contractor is responsible to maintain its schedule so as not to delay the progress of the Project or the schedules of other contractors If Contractor delays the progress of its work or the work of other Contractors, it shall be the responsibility of Contractor to increase the number of men, the number of shifts, the days of work and/or, to the extent permitted by law, to institute or increase overtime operations, all without additional cost to Owner in order to retain any time lost and maintain the Progress Schedule then in effect as established by Owner
The AIA document references the construction schedule in no less than six places, providing an impediment to simplification and understanding By way of example,
Trang 30§ 3.10.1 The Contractor, promptly after being awarded the Contract, shall prepare and submit for the Owner's and Architect's information a Contractor's construction schedule for the Work The schedule shall not exceed time limits current under the Contract Documents, shall be
revised at appropriate intervals as required by the conditions of the
Work and Project, shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work
§ 6.1.3 The Owner shall provide for coordination of the activities of the Owner's own forces and of each separate contractor with the Work of the Contractor, who shall cooperate with them The Contractor shall participate with other separate contractors and the Owner in reviewing their construction schedules when directed to do so The Contractor shall make any revisions to the construction schedule deemed necessary after a joint review and mutual agreement The construction schedules shall then constitute the schedules to be used by the Contractor,
separate contractors and the Other until subsequently revised
Notably absent from the AIA specification is any mention of the type of
schedule to be provided or the level of detail required While a small, simple project may justify the use of a simple bar chart (timeline), larger complex
projects, especially those with long overall durations, require the use of more complex scheduling techniques such as Critical Path or Linear schedules The RIT specification references the project critical path; the Washington University document is silent on the topic.20
The weather specifications (Table 2.10) are again similar Depending somewhat upon the length and location of the project, as well of the specifics (e.g., interior
or exterior or both), the weather provisions may or may not be actually
necessary, though a good draftsperson would include the language in any event
20 Issues surrounding scheduling methodologies and techniques are outside the scope of this study
Trang 3121
Table 2.10: Weather Specifications
(Weather)
J Contractor shall revise the Project schedule
whenever Owner requests Contractor may revise
the Project Schedule at any time Revised Project
Schedules are subject to Owner's approval The
Project Schedule shall be revised and resubmitted
when the project is 15 percent, 40 percent, 75
percent and 90 percent complete
K The project schedule shall include an allowance
of 63 bad weather days per year This allowance is
divided into the following monthly breakdown:
In the event that weather-related conditions
preclude performance of 60% of critical path
activities scheduled for a particular day, the day
may be claimed by the contractor as a weather day
and charged against the allowance included for that
project If good weather conditions prevail
throughout the contract period and the allowed
number of weather days are not encountered, the
Contractor will not be required to complete the
contract correspondingly ahead of the contract
completion date If poor weather conditions prevail
such that all of the allowed bad weather days are
exceeded, a no cost change order extending the
date of scheduled completion will be executed
preclude performance of 60% of critical path
activities scheduled for a particular day, the day
may be claimed by the contractor as a weather day
and charged against the allowance included for that
project If good weather conditions prevail
throughout the contract period and the allowed
number of weather days are not encountered, the
Contractor will not be required to complete the
contract correspondingly ahead of the contract
completion date If poor weather conditions prevail
such that all of the allowed bad weather days are
exceeded, a no cost change order extending the
date of scheduled completion will be executed
(Weather) 12.3.4 Owner shall not be liable to any Contractor or Subcontractor for damages caused
by any breach of contract, delay in performance
or other act of neglect by any other Contractors
or Subcontractors having Contracts for performance of any portion of the Work or by bad weather, or any causes designated Acts of God or force majeure by any court of law or any cause outside Owner's reasonable control
Trang 32A much more pronounced difference in content and potential for disagreement is evident in these specifications It is a given that both Rochester, New York, and St Louis, Missouri get “winter” weather (snow, ice, etc.) on a regular basis.21 Rochester does not define what constitutes “bad weather”; in contrast, Washington University allows for 19” of rain between March and May even though 33” is the “norm” (NOAA
2007).22 Granted, contractors can often work in adverse weather conditions; however, leaving “normal” undefined invites dispute
The AIA specification takes yet a third approach, requiring the contractor to meet three requirements:
If adverse weather conditions are the basis for a Claim for additional
time, such Claim shall be documented by data substantiating that
weather conditions were abnormal for the period of time, could not
have been reasonably anticipated and had an adverse effect on the
an unexpected time? The ability to "carry back" or "carry forward" un-utilized weather days could address the issue and avoid potential disputes
In the next example, Table 2.11, the Schedule of Values specifications are compared RIT’s language is straightforward while Washington University’s borders on
micromanagement In the end, both institutions will acquire the same product,
21 According to records maintained by the National Oceanic and Atmospheric Administration (NOAA), Rochester averages about 85-93” of snowfall and 160” of rain while St Louis can reasonably expect 19”
of snow and 108” of rain per year
22 Information obtained from NOAA’s National Weather Service Weather Forecast Office, last accessed
on 1/20/2007 at www.crh.noaa.gov/lsx/climate/STL/annual_snowfall.php and
Trang 3323
regardless of the language, provided that the individuals reviewing the reports
understand the underlying process and procedures
Table 2.11: Comparison of Schedule of Values; Payments
GC-26 SCHEDULE OF VALUES
A Contractor shall submit to Owner for approval a
breakdown showing portions of the Contract Sum
as the value of each item of the work
B Contractor's schedule of values shall be
subdivided for each item of work identified in the
Contract Documents and additional value
subdivisions for each subcontractor
GC-9 PROGRESS PAYMENTS
A Owner shall pay Contractor value of work in
place and materials stored on site upon approval of
Application for Progress Payments submitted by
Contractor not more than once per month The
Owner will attempt to make payment within ten
days of receipt of invoice to Contractors that have
sub-contracted with MBE and WBE firms Direct
payment will be made to the MBE and WBE firms
The application for payment shall be submitted on
AIA Document G702 or it’s equivalent with
continuation sheets The continuation sheets shall
be complete showing individual lines for each
specification section and contractor
B Owner shall retain ten (10%) percent of each
scheduled value of each payment to contractor to
ensure the proper performance of the contract
C With application for Progress Payment
Contractor(s) shall furnish notarized waivers of lien
for the value of the progress payment, and
subcontractors and material suppliers shall furnish
notarized waivers of lien for the prior progress
payment, conforming to the requirements of
Chapter 429 RSMo
D With Application for Progress Payment,
Contractor shall submit a copy of the Construction
Progress Schedule, which shall show the portions of
the work claimed as completed for payment as
related to the Schedule of Values Application for
payment shall show retainage as a line item for each
scheduled value
E Storage of Materials Off site and Payment (1)
The Contractor and his Subcontractors shall obtain
prior written approval from the Owner through the
Architect for permission to store only materials to
be incorporated in and made a permanent part of
the Work, for which Progress Payments will be
requested, at off site locations Any and all charges
for storage, including insurance, and any and all
9.2 SCHEDULE OF VALUES 9.2.1 At least 30 days before the first Application for Payment, the
Contractor shall submit to the Owner and the Architect for approval a schedule of values which
in the aggregate equals the total Contract Sum, divided so as to facilitate payments to
Subcontractors, supported by such data or evidence of correctness as the Architect may direct or as required by the Owner This schedule, when approved by the Architect and Owner, shall
be used to monitor the progress of the Work and
to compute the amounts of the various payments requisitioned on the Certificates For Payment All items with entered values will be transferred by the Contractor to the "Application and Certificate For Payment," and shall include the latest approved Change Orders Change Order values shall be broken down to show the various subcontracts The Application For Payment shall
be on a form as provided by the Architect and approved by Owner Each item shall show its total scheduled value, value of previous applications, value of the application, percentage completed, value completed and value yet to be completed All blanks and columns must be filled in, including every percentage complete figure No Application for Payment shall be required to be approved until after the Schedule of Values has been approved by the Owner and Architect
9.2.2 The Schedule of Values and Applications for Payment shall be prepared by the Contractor using
a modified version of A.I.A Forms 702 and
G-703, "Application & Certification for Payment" The Schedule of Values shall be submitted to the Owner and the Architect for approval a minimum
of thirty (30) days before the first Application for Payment A milestone payment schedule may be required by the Owner, and shall be made a part
of the Schedule of Values when agreed upon by the parties Profit and general office overhead shall be included in each item All Applications for Payment, Change Orders, and other documents involving monetary statements shall have totals rounded off to the whole dollar amount for 0 cents through 50 cents All items above 50 cents through 99 cents to the next dollar
Trang 34charges for transportation to the site shall be borne solely by the Contractor Before approval, Owner requires that off-site materials be stored in an approved warehouse, with proper proof of
insurance and a letter stating the following
information (a) The name of the Contractor and/or Subcontractor leasing the storage space (b) The location of such leased space (c) The leased area: the entire premises or certain areas of a warehouse giving the number of floors or portions thereof (d) The date on which the material was first stored (e) The value of the material stored (2) The
Contractor and his Subcontractors shall notify the Architect and the Owner, at least once each month,
to visit the warehouse where the materials are being stored (3) The Contractor and his Subcontractors shall mark each sealed carton with the name of the project and the Architect (4) A perpetual inventory shall be maintained for all materials held in storage for which payment has been requested (5)
Payments for materials stored off site in an
approved warehouse and insured shall be at the sole discretion of the Owner Any additional costs to the Owner resulting from storage of material off site for which payment is requested, such as, but not limited
to, travel expenses and time for inspectors, shall be back charged to, and paid by the Contractor Title
to materials stored off site shall be transferred to the Owner when the Owner pays for such stored materials F All applications for payment shall be submitted on AIA document G702, Application and Certificate for Payment Applications for payment shall reflect all items detailed in the approved schedule of values with corrections made for new items or Contractors as Work progresses
G On projects greater than $300,000 in value, Contractor shall furnish a bound monthly project report with the Application for Progress Payment The report shall contain the following information: (1) A cover letter describing the general status of construction activities as they relate to the project schedule and description of activities anticipated during the next month (2) An activity report describing items completed during the month for each individual construction task Include a log of daily weather conditions and temperatures (3) A manpower summary for the month indicating daily manpower levels for each contractor and trade (4)
A minority report summarizing the daily workforce composition by ethnic group and gender for the month (5) A log of change requests (6) A log of submittals (7) A log of requests for information (8) All project meeting and conference call notes for the month (9) Engineers’ certifications for the month (10) Four 8-inch by 10-inch color
Trang 3525
photographs of work progress recorded during the
month (11) List of unresolved issues that may
impede meeting project milestones or schedule
H In the event Contractor or any subcontractor
tenders substitute security, the following shall apply:
(1) All such substitute security shall be solely in the
name of “Washington University” (2) Contractor at
its sole cost shall cause all substitute security to at all
times be held by a financial institution, title
company or other third party custodian in the St
Louis, Missouri metropolitan area acceptable to
Owner under terms which permit Owner to take
immediate possession of any or all substitute
security on demand at any time during normal
business hours with or without cause (3)
Contractor at its sole cost and as agent for Owner
shall administer any and all substitute security as
required by applicable law including without
limitation making release thereof and payment of
interest and income thereon to itself and/or to
subcontractors as and when required by the
Contract Documents and applicable law (4) Not
less often than monthly, Contractor at its sole cost
shall provide Owner a written certification and
report of all substitute security itemized by
subcontractor and in detail reasonably satisfactory
to Owner (5) Contractor hereby agrees to
indemnify, defend and hold harmless Owner and its
trustees, officers and employees against any and all
claims, demands or liabilities arising out of the
negligent or otherwise improper administration by
Contractor of substitute security and/or any
negligence of the custodian.I Applications for
Progress Payment shall not include costs for items
that are not a direct expense of the work Costs that
are not authorized include, but are not limited to the
following: (1) Professional dues for contractors and
their employees (2) Cumulative rental costs for
equipment that exceeds their purchase price (3)
Workers’ Compensation Insurance credits – Credits
given by the insurance company shall be reflected as
a credit to the Owner
The Washington University provision is seemingly simple and to the point In actuality, when read in conjunction with the Progress Payment specification (GC-9), it is much lengthier than the corresponding RIT provision It is very detailed as to how payments are to be made, varies the requirements somewhat based on contract size, requires lien releases with each payment, and, in the final section, specifically excludes certain items
It requires the contractor to provide progress photographs with each payment
Trang 36application (neither the RIT nor AIA documents have comparable requirements) and discusses “substitute security”23 for the contractual obligations Again, both the AIA and RIT have no similar language.24 From Washington University's perspective this appears
to be beneficial, yet there is a potential claim, if not a lawsuit, in the language Looking
at section GC-9.H(2), Washington University (Department of Facilities Planning and Management 2005, p GC-8) has claimed the right to
“ take immediate possession of any or all substitute security on demand at any time during normal business hours with or without cause.” (Emphasis added)
On its face, the language allows Washington University to arbitrarily claim the security for any reason whatsoever, appearing to be penal in nature It is unlikely that the
University would exercise that power in the absence of compelling facts (at least from its perspective) While the University is a non-public institution and not subject to the same due process claims as a public body, a court could easily find that the language is against public policy, at least to the extent that cause is not required for the University
to act, and a contractor subjected to its application might well raise the issue even though it voluntarily signed the contract document A minor change in the language might possibly avoid having the language stricken:
take immediate possession of any or all substitute security on demand at any time during normal business hours when the Owner has a good faith belief that performance of the contract is jeopardized and possession of the security is necessary
to protect its interests
While there is no guarantee that the suggested change will avoid any potential dispute, it does serve to eliminate the argument that the University has acted capriciously
23 Substitute security is a mechanism for protecting the owner’s interest The most common security is a performance bond; substitutes (alternatives) could be cash, assignments of interest or receivables or similarly acceptable assets
Trang 3727
There is always the issue of too little versus too much detail There is no one right answer; the decision is often driven by business and legal considerations Table 2.12 compares the level of overall detail in the RIT and Washington University
specifications:
Table 2.12: Comparison: Detail Level
GC-10 Extras/ Changes to Work
GC-11 Substantial Completion and Acceptance
GC-12 Final Inspection, Acceptance, Payment
E PURCHASED MATERIALS
GC-13 Equipment and Materials
GC-14 Purchase of Material and Equipment
GC-15 Shop Drawings and Samples
GC-16 Samples and Testing
F WORK ON CAMPUS
GC-17 Contractor’s Working Conditions on
Campus
GC-18 Responsibilities of Contractor
GC-19 Equal Employment Opportunity
GC-20 Job Site Safety and Security
14 3.3 Right To Stop Work
15 3.4 Right to Carry out Work
16 3.5 Right to Audit Contractor's Records
17
18 4 CONTRACTOR
19 4.1 Definition
20 4.2 Review of Contract Documents
21 4.3 Supervision & construction Procedures
22 4.4 Labor & Materials
29 4.11 Documents & Samples at the Site
30 4.12 Shop Drawings, Product Data & Samples
Trang 387 MISCELLANEOUS PROVISIONS 7.1 Governing Law
7.2 Successors and Assigns 7.3 Written Notice 7.4 Claims for Damages 7.5 Performance Bond & Labor & Material Payment Bond
7.6 Rights & Remedies 7.7 Tests
7.8 Interest 7.9 Dispute Resolution 7.10 Waiver of Remedies
8 TIME 8.1 Definition 8.2 Progress & Completion 8.3 Delays & Extensions of Time
9 PAYMENTS & COMPLETION 9.1 Contract Sum
9.2 Schedule of Values 9.3 Application for Payment 9.4 Certificates for Payment 9.5 Progress Payments 9.6 Payments Withheld 9.7 Substantial Completion 9.8 Final Completion & Final Payment 9.9 As Built Drawings
10 PROTECTION OF PERSONS &
PROPERTY 10.1 Safety Precautions & Programs 10.2 Safety of Persons & Property 10.3 Emergencies
10.4 Hazardous Materials
11 INSURANCE 11.1 Contractor's Liability Insurance 11.2 Commercial General Liability Policy 11.3 Certificates of Insurance
11.4 Subcontractor Insurance 11.5 Builders Risk Insurance 11.6 Miscellaneous Provisions
12 CHANGES IN THE WORK/SUBSTITUTIONS
Trang 3929
12.1 Change Orders 12.2 Concealed Conditions 12.3 Claims for Additional Cost 12.4 Minor Changes in the Work 12.5 Substitutions
13 UNCOVERING & CORRECTION OF WORK
13.1 Uncovering of Work 13.2 Correction of Work 13.3 Acceptance of Defective or Non-Conforming Work
14 TERMINATION OF THE CONTRACT 14.1 Termination by the Contractor
14.2 Termination by the Owner 14.3 Termination by the Owner for Convenience
It is possible that each of these sets of specifications has been developed and evolved as
a result of the experiences of the institution and the people who represent it Certainly, also at play is the influence of the institutions’ respective legal counsels whose role and goal is to protect the institutions’ interests This is no different, of course, from the role legal counsel plays in any other enterprise, regardless of the nature of the business However, adding complexity does not automatically result in improved results Tailoring specifications to a particular project was recommended by the 1986 CII study Long,
“boilerplate” documents such as the Washington University (and, to a greater extent, the even longer AIA document) add additional bulk and complexity to a project’s documentation
A “claim” need not be reduced to a matter in arbitration or litigation A “claim” starts with notice to the superior participant (e.g., from subcontractor to prime, from prime contractor to owner, etc.) of a potential demand for additional time, money or both Many times the notices are provided on an “abundance of caution” basis; most
construction contracts require that notice be provided within a given number of days of knowledge or occurrence of an event, incident or awareness For example, a Front End specification may provide the following:
Trang 40Notwithstanding any other provision of the Contract, if the Contractor intends to claim any additional payment pursuant to any Clause of these Conditions or otherwise,
he shall give notice of his intention to the Engineer, with a copy to the Employer, within 28 days after the event giving rise to the claim has first arisen (Federation Internationale Des Ingenieurs-Conseils 1987, 1988, 1992, §20.)
In this section, previous research efforts focusing on the Front End Specifications are reviewed and, where appropriate, the effect on this research is noted While much time and effort has gone into research about construction claims, little has been documented about the role of Front End Specifications in that arena
Project specifications are divided into two general categories The largest category is comprised of the design or building specifications (requirements) such as soil
compaction requirements, interior finishes and plumbing and mechanical requirements These technical specifications have traditionally been set forth as Divisions Two
through Sixteen of the construction specifications, following the guidelines of the Construction Specifications Institute (CSI 2003) The other category is comprised of the administrative requirements, which are most often contained in Division One of the contract specifications (Jellinger 1981; Rosen 1974) These Division One specifications are known as the Front End Specifications and are also referred to as the General Conditions.25
2.3.1 Background
Reams of paper have been devoted to the related topics of construction disputes and claims Washington University’s library system contains no less than eighty volumes Few of the publications (less than 10%) specifically discuss Front End Specifications to any significant extent, though there are often generalized references to the contract specifications While these non-judicial published materials tend to focus on the
25 “Division One” refers to the location of the provisions in the format developed by the Construction