13 • Chapter 2 Chapter 2 Ten-Year Capital Plan and Long Range Plan Planning A Ten-Year Capital Plan lays out the path by which a new or existing skill center plans, finances, and con
Trang 1Skill Centers Capital Manual
Guidelines for School Districts
Planning for the 2021-23 State Capital Budget
`
Office of Superintendent of Public Instruction
School Facilities and Organization - Revised October 2019
Trang 2Skill Centers Capital Manual
Guidelines for School Districts Planning for the 2021–23 State Budget
Originally prepared September 2013 by Robert Dengel, Program Development Manager Revised October 2019 by
Tyler Muench, Policy & Outreach Coordinator
Office of Superintendent of Public Instruction School Facilities and Organization
OSPI provides equal access to all programs and services without discrimination based on sex, race, creed, religion, color, national origin, age, honorably discharged veteran or military status, sexual orientation including gender expression or identity, the presence of any sensory, mental, or physical disability, or the use of a trained dog guide or service animal by a person with a disability
The following employee has been designated to handle questions and complaints of alleged discrimination:
Title IX/Section 504 Coordinator:
Equity and Civil Rights Director P.O Box 47200
Olympia, WA 98504-7200 (360) 725-6162
Trang 3Table of Contents
Introduction 4
Chapter 1: New Core, Branch, or Satellite Campuses 12
Chapter 2: Ten-Year Capital Plan and Long Range Plan 13
Chapter 3: Minor Works 17
Chapter 4: Major Works Phases and Deliverables 21
Chapter 5: Major Works Various Project Requirements 26
Chapter 6: Major Works: Preservation Projects 31
Chapter 7: Major Works and New Satellites Prioritization 32
Chapter 8: Major Works Final Budget Project Submittal 48
Chapter 9: Major Works Modified D-Form Process 52
Chapter 10: Major Works Allotment and Reimbursement Documents 54
OSPI School Facilities & Organization Contact Information 56
Appendices Appendix A: New Skill Center Campus Form 57
Appendix B: Ten-Year Capital Plan Example 63
Appendix C: Long Range Plan Example 65
Appendix D: Final Minor Works Rank Summary Form Example 74
Appendix E: Minor Works Reimbursement Request Schedule 76
Appendix F: Major Works Reimbursement Request Schedule 79
Appendix G: Modified D-Form Process 81
Appendix H: Major Project Status Report 85
Appendix I: Special Capital Grant Claim Form 1288SK 88
Appendix J: Expected Use of Bond/COP Proceeds Form 90
Appendix K: Rubric for Priority Criteria 4: Significant Health, Safety, and Energy Issues 93
Appendix L: Rubric for Priority Criteria 10: Flexible Space 94
Appendix M: Capital Budget Request Form Example 96
Appendix N: Administrative Council Resolution 102
Appendix O: C-100 Budget Form 104
Appendix P: DAHP Letter Example 107
Appendix Q: 2017-27 OFM Capital Plan Instructions: Financing Guidelines 109
Trang 4package for skill center capital projects and submits the information to the Governor’s Office of Financial Management (OFM) Authority is provided by WAC 392.600.040
This manual follows a coordinated approach between the skill center directors, host districts, SF&O, and the state’s biennial capital budget Grant funding appropriated by the Legislature to skill center projects is administered by SF&O via reimbursements of host district claims
Alongside the Washington State budget process, OFM provides specific instructions to OSPI for
submitting budget and allotment approval requests Policies and procedures explaining OFM’s processes can be found within Capital Budget Instructions and Allotment Instructions, both of which are updated every 2 years This manual is subsequently updated every 2 years as necessary
Grants may also be provided from other existing funding programs, in which case, the rules of the
program will help direct procedures
Since OSPI’s capital budget process for skill centers continues to evolve, and OFM’s instructions are updated biennially, this manual will be revised as needed to conform to any new requirements The
information will assist skill centers in developing long-range plans that serve as a foundation for capital budget requests
Depending on the type of request, there will be different requirements that need to be met For instance, there is a prioritization process for minor works repair projects performed by a consultant who is hired by the skill center directors By contrast, there is different prioritization process for major works, which is completed by SF&O Satellite facility projects are handled as minor works, however the prioritization process is the same as major works For this reason, it is important to understand the different
categorizations of skill centers contained at the end of this chapter in the Glossary of Skill Center Capital Terms on page 9
This manual is organized into four parts: 1) planning, 2) minor works projects, 3) major works, and 4) major works preservation projects See Figure 0.1
Trang 55 • Introduction Figure 1.0
Trang 66 • Introduction
Minor Works Submittal Timeline
December 15, 2019 Skill center and its host district retain architect and/or
project manager to develop potential project ideas and cost estimates
February 15, 2020 Proposed projects are due to a consultant for evaluation and
prioritization
February 2020 Skill center directors identify primary schedule milestones,
with assistance from a consultant
May 31, 2020 Consultant’s prioritized list is due to directors and SF&O
August 2020 SF&O submits capital budget request to Superintendent
works with the Governor to produce a state capital budget proposal for the Legislature’s consideration
Spring 2021 Legislature passes a capital budget, and the Governor signs it
OFM approves allotment requests and SF&O will send out a grant letter with the approved fund amount OSPI encumbers this amount, ready for reimbursement claims
Trang 77 • Introduction
Major Works Submittal Timeline
Present – December 2019 Skill center and its host district retain architect and/or
project manager to develop potential project ideas and cost estimates
December 15, 2019 Ten-Year Capital Plan and Long Range Plan outlining
potential projects are due to SF&O
August 2020 SF&O submits capital budget request to Superintendent
works with the Governor to produce a state capital budget proposal for the Legislature’s consideration
Spring 2021 Legislature passes a capital budget, and the Governor signs it
PRE-CONSTRUCTION PROJECTS: OFM approves allotment requests and SF&O issues a grant letter with the approved amount OSPI encumbers this amount, ready for reimbursement claims for predesign and/or schematic design Develop project scope for square footage, needed equipment, resources, and budget Begin preparing for Construction Stage request, which will be due next budget submittal cycle
MAJOR CONSTRUCTION PROJECTS: OFM approves allotment requests and SF&O issues a grant letter with the approved amount OSPI encumbers this amount, ready for reimbursement claims for final design phases and bid phase Project starts modified D-form process beginning with D-5 and D-7 submittals
Trang 88 • Introduction
PRE-CONSTRUCTION AND MAJOR CONSTRUCTION STAGES: OFM approves allotment requests and SF&O issues a grant letter with the approved amount OSPI encumbers this amount, ready for reimbursement claims for all design, bid, and construction phases Project starts modified D-form process beginning with D-5 and D-7 submittals
PRESERVATION PROJECTS: OFM approves allotment requests and SF&O issues a grant letter with the approved amount OSPI encumbers this amount and host districts can submit reimbursement claims
Following bid opening Submit modified D-9 to SF&O Appropriate documents are
submitted to OFM for allotment approval SF&O issues a grant letter to allow signing of construction contract with the approved amount for construction and related art allocation,
if applicable
Throughout construction phase For projects $5 million or more, submit project status reports
every 6 months until project closeout is complete
Prior to FF&E purchasing Submit documents to SF&O for FF&E allotment approval
OFM approves allotment requests and SF&O issues a grant letter with the approved amount OSPI encumbers this amount, ready for reimbursement claims for FF&E items
At project closeout Submit modified D-11 to SF&O for authority to release
retainage payment to contractor Following final reimbursement claim, submit final project status report
Trang 99 • Introduction
Glossary of Skill Center Capital Terms
Types of Campuses: Core, Branch and Satellites
There are three types of skill center campuses defined in WAC 392.600.010:
Core Campus
“The facility housing a majority of the skill center students enrolled It is operated by the skill center The cooperative shall manage and maintain the core campus.” The school district that hosts the operations (the host district) also receives appropriated capital funding and is responsible for administering the project
Branch Campus
“A common school or higher education facility which provides three or more programs at a
location other than the skill center core campus.” In most cases, the core campus host district administers the project, but an inter-district cooperative agreement can allow the district in which the branch campus resides to administer the project
Satellite Program
“A facility or site which provides less than three programs at a location other than the skill center core campus.” A satellite program may also be approved as a rural satellite; additional information can be found in RCW 28A.245.020
Major vs Minor Capital Projects, including Satellites
OFM defines two primary types of capital projects:
Major Projects have one or more of the following features:
Costs more than $5 million (regardless of fund sources)
Takes 2 or 3 biennia to design, construct, and occupy
Are privately owned buildings under development
Minor Projects
One or more projects valued between $25,000 to one $1.0 million (Total cost cannot exceed $1.0 million.)
Projects that will be completed within the biennium
DOES NOT INCLUDE:
Trang 1010 • Introduction
a Work on a phase of a larger project
b Work that, if combined over a continuous period of time, will exceed $1 million
c Studies (except for technical engineering reviews or designs that lead directly to and
support a project on the same minor works list)
d Supplement funding for projects with funding shortfalls
e Planning activities
f Moving expenses
g Land or facility acquisition
h Design outside the scope of work on a minor works list
i Moveable, temporary, and traditionally funded operating equipment that is not in
compliance with the criteria listed in the Financing Guidelines Allowable and Non-Allowable uses of Long-Term Financing
j Software not dedicated to control of a specialized system
A modernization project includes the “making of major structural changes in such facilities and
may include as incidental thereto the replacement of fixtures, fittings, furnishings, and service systems of a school facility in order to bring it up to a contemporary state consistent with the needs of changing educational programs and applicable codes.” See WAC 392.347.010 Generally, modernization of any individual building should have the estimated cost of major structural change not less than 40% of the estimate cost of replacement
Trang 1111 • Introduction
New-in-Lieu (Replacement)
A new-in-lieu project replaces an existing core or branch building(s) in lieu of modernizing it, because the district’s analysis has determined the cost of modernizing would exceed the cost or effort of new construction A new-in-lieu project is treated as a modernization for prioritization
scoring purposes only
projects are limited to cost between $1.0-$5.0 million
Additional Information
See Appendix Q for OFM’s Capital Plan Instructions, Financing Guidelines This document spells out
what is allowed with state capital funding, and what is not
Trang 12requirements.) The New Skill Center Campus Form will help guide host districts through each phase of obtaining approval for a new skill center core, branch, or satellite
There are two parts to requesting the creation of a new skill center core or branch: 1) request for funding, and 2) review and approval phases including:
Feasibility study and preliminary approval
Inter-district cooperative agreement and final approval
Note: New satellite programs must address the review and approval requirements identified in the form
After completion of each phase of the form, please send it to:
Director of Career and Technical Education
Office of Superintendent of Public Instruction
Trang 1313 • Chapter 2
Chapter 2
Ten-Year Capital Plan and Long Range Plan
Planning
A Ten-Year Capital Plan lays out the path by which a new or existing skill center plans, finances, and
constructs all minor and major capital projects It is required every 10 years, whenever there is an update,
or upon request by OSPI
A Long Range Plan lays out a short and concise road map (10-15 pages) for potential major capital
investments and helps ensure all projects are carried out in a logical and cost-effective manner
Skill center directors must work with their host district’s capital facilities, business, and/or operations staff
as well as their administrative council to complete a Long Range Plan prior to making a capital budget request Developing a Long Range Plan for skill center core, branch, and satellite campuses is an important part of the capital planning process, and will determine how to proceed
Both a Ten-Year Capital Plan and a Long Range Plan must be submitted to OSPI in electronic format (Word, Excel, or PDF) by December of odd-numbered years to meet the capital plan submittal
requirements of WAC 392.600.040 This creates a logical foundation for each project
Below are expanded descriptions of what should be included in a Long Range Plan
1 Major capital improvement project information:
A Ten-Year Capital Plan for your skill center Refer to any previous submittals made to OSPI
A description of each major capital project that was identified in the Ten-Year Capital Plan Each project must be based on a specific need described in the Long Range Plan Preservation, modernization and new-in-lieu projects should reference the existing building condition section and growth projects should reference enrollment and future program(s) sections as well as the potential project location Describe in 3-4 sentences
a Identify the additional full-time equivalent (FTE) gain to the skill center as a direct
result of the project by program Note: modernizations might not have an FTE gain
Projects seeking state funding in the upcoming biennium must include the additional following information:
a Explanation of the project scope
Trang 14a Modernization and new-in-lieu projects:
A building must be 30 years or older at the time the project would begin to receive construction phase funding
If seeking a new-in-lieu project, include a financial and building condition
justification (cost-benefit analysis) Note: it is recommended that buildings with
a BCA score 62 or higher to be modernized, not replaced Likewise, it is recommended that buildings with a BCA score under 62 to be replaced, not modernized
Specify which building systems require repair/replacement, how long the building system to be replaced has been in use, BCA score, and the expected life of the new building system
Describe whether the preservation project reduces the overall maintenance backlog of the facility
2 Existing building inventory and condition:
Skills Center Building Inventory and Area Analysis Current building inventory data must be entered at the building level into OSPI’s Information and Condition of Schools (ICOS) system Building level square feet must be entered at the area level including the year built
Trang 15 A description of the repairs and replacements needed for the facility as a whole (e.g roof, HVAC, etc.) Please use 1 or 2 sentences for each repair
3 Narrative of skill center programs:
Existing Programs
a Program description, 2-4 sentences each
b Adequacy of program facilities, 1-3 sentences each
c Facility improvements and expansions needed for program, if any
Future Programs
a Program description, 2-4 sentences each
b Facility needs for the program, 1-3 sentences each
c Community and stakeholder support for the program, 1 or 2 sentences each
d Potential location for the program(s)
The amount and sources of local contribution that will be provided for each project explained above Provide 1 or 2 sentences
Trang 1616 • Chapter 2
Host district Superintendent approves skill center project
The skill center’s administrative council resolution approving the Long Range Plan and major capital project requests
Most recent inter-district cooperative agreement, if updated or modified within the last 2 years, consistent with WAC 392.600.020
OSPI Review and Acceptance
SF&O will review each Ten-Year Capital Plan and Long Range Plan for completeness based on the above criteria A written response will be sent identifying any additional information necessary for acceptance Additional Information
See Appendix B for an example of a Ten-Year Capital Plan
See Appendix C for an example of a Long Range Plan
Trang 1717 • Chapter 3
Chapter 3
Minor Works
Minor Works Projects
This chapter only applies to minor works projects To determine whether a project is minor or major works, please see the introduction chapter
OSPI will submit two funding request lists for skill center minor works funding They are:
Repair or program upgrades to existing skill centers
New satellite programs
Requirements that apply to both of these processes are explained below
Prioritization of Repair or Program Upgrades to Existing Skill
Center Facilities
With the assistance of their host district’s facility, business, and/or operations staff, each skill center
director develops a list of minor works projects for their own individual skill center in odd-numbered years
to be considered for funding A consultant hired by the skill center directors group tours each skill center campus making a request, reviews the projects, and prioritizes the list using pre-established criteria The list
is submitted o SF&O using the Final Minor Works Rank Summary Form to be included in the
Superintendent’s budget request to the legislature for funding
The projects are scored by assigning values to priority and deferability choices for the projects The intent
is to mix the importance and urgency of each project and rank them accordingly Priority choices include six categories (listed in descending value order):
Health, safety, environment
Facility use
System use
Increased repair/replacement cost
Increased operating cost
Quality of use
The deferability choices weigh the urgency of completing the project The longer a project can wait, the lower the deferability value The priority choice value is multiplied by the deferability choice value equaling the “severity score.” The highest possible “severity score” is 60 and the lowest possible is 18
Trang 1818 • Chapter 3
Prioritization of New Satellite Programs
New satellite program capital funding requests are considered separately from existing skill center minor works projects for repairs and program upgrades These projects are scored and placed on a ranked
priority funding list along with the major capital projects After being scored and prioritized, the minor works budget request forms described immediately below are submitted
Minor Works Project Allotments and Approval
Following legislative appropriations for minor works and/or satellite projects:
Detailed Scope of Work:
Each minor works project will require a separate detailed scope of work provided by OSPI This form is a condensed version of the cost estimate used for past skill center capital budget requests Depending on the size and complexity of the project, there may not be a need to fill in all the categories of expenses It is important to involve the host district's facility, business, and/or operations staff in this process and to have them review the final version of this form Additional guidance for this form can be found on the instruction tab of the worksheet
Board Resolutions
A board resolution prior to the first reimbursement claim being made certifying:
a Host district personnel that are board-authorized for signature authority
b All state funds appropriated for this project will be utilized by the host district for the purposes specified in the scope of work, project description, and in accordance with public works requirements
c Funds will not be used for non-governmental purposes; which includes the use of bond proceeds to pay the costs of facilities expected to be owned or used by, or to make any loan or grant to:
The federal government (including any federal department or agency)
Any private, non-profit corporation (including any 501(c) (3) organization)
Any other private entity, such as a business corporation, partnership, limited liability company, or association, etc
Reimbursement Request Schedule
The purpose of this form is to report the host district’s anticipated monthly reimbursement
requests The amounts provided to SF&O will be used to communicate bond sale amounts to the
Trang 1919 • Chapter 3
Office of the State Treasurer This will ensure the state has funds available to reimburse projects
without selling too many bonds and accruing penalties on excess bond sale proceeds
Approval Letters
SF&O will issue a project approval letter to the host district after receiving the board resolution, updated project details, detailed scope of work, and reimbursement request schedule from the skill center as well as approval of project allotments from OFM This project approval letter is official authorization that funding is available for reimbursement for the project
Changes to Project Details, Scope of Work, or Budget
Allowed Adjustments to the Scope of Work
As the projects evolve, there may be a need to adjust the scope of work, schedule, or budget due to
unforeseen circumstances Prior approval may be required depending on whether the adjustments of scope are greater than 10% Changes to the scope of work, which expands the capacity of the project beyond what the Legislature intended when they approved the minor works list, will not be approved Any such additional costs incurred outside the scope of work will be the responsibility of the skill center’s host district
Adjustments Less Than 10% of the Total Project Award
Budget adjustments of less than 10% of the total minor works project costs for an individual skill center will not require prior approval The flexibility allowed in this section shall not affect the completion of any
of the approved projects For example, if a skill center has three projects with a total project cost of
$300,000, the skill center may adjust ten percent or $30,000 of the total project cost between projects All three projects must be completed and may not exceed the $300,000 total appropriation
Adjustments 10% or Greater of the Total Project Award
Adjustments to the scope of work or budget, in excess of 10% of the total project award, will require prior approval from before any work can occur Prior approval can be requested by using one of the following processes:
The host district superintendent can submit the request via email or letter to SF&O, or
The administrative council can directly submit the request through the skill center director via email or letter to SF&O
Resubmitting Minor Works Projects
In cases where a skill center has received funding for multiple minor works projects, OSPI will not
resubmit for those funded minor works projects in future budget requests when funding was reallocated to
Trang 2020 • Chapter 3
other projects on the list, and insufficient funds were left to pay for completing the entire list of funded
projects
Reimbursements
All claimed expenditures are reviewed for content and consistency with the approved budget
Reimbursement is made through the state accounting system by warrant or electronic transfer (EFT) and will be processed in an expedient manner Copies of voucher registers (referencing warrant numbers) and invoices must accompany all claims
Additional Information
See Appendix D for an example of the Final Minor Works Rank Summary Form
See Appendix E for the minor works Reimbursement Request Schedule An electronic version is
available
See Appendix I for the Special Capital Grant Claim Form 1288SK to be used when submitting related
invoicing for reimbursement An electronic version is available
Trang 2121 • Chapter 4
Chapter 4
Major Works Phases and Deliverables
Major Construction Phases and Deliverables
SF&O administers funds for major projects based on a modified version of the School Construction Assistance Program’s (SCAP) D-Form process Information regarding the modified D-Form process will
be included with the project’s grant approval letters
Project requests are based on a two-biennia approach: Pre-Construction Stage and Construction Stage,
as a best practice recommendation by skill center directors and SF&O The Legislature has discretion to follow this method or may offer funding in a single biennium for a particular project Lawmakers may also choose to request more information before any funding is appropriated
Historically, the Legislature funded projects over 3 biennia: predesign phase, design phase, and
construction phase Funding may revert to this approach at the Legislature’s option
Pre-Construction Stage
The Pre-Construction stage includes two major parts:
Predesign: includes feasibility studies, program specifications, and any other early planning effort
Schematic Design: includes the early design phases before committing to code compliance, agency approvals, and construction-phase technical details
The goal of the Pre-construction stage is to define the project and provide sufficient information so that a clear concept exists
A Life Cycle Cost Analysis (LCCA) must be included in the predesign submittal at a detail level as
established in consultation with the agency and OFM Typically, the analysis will align with the detail level
of the cost estimate as it is submitted in the predesign
Predesign
The predesign provides a clear definition of the project plan Predesign work may be required for projects that have significant policy implications or may have technical, logistical, or cost concerns to a program or agency Educational specifications also must be developed at this time
Trang 2222 • Chapter 4
Schematic Design
The schematic design phase provides sufficient information for the design concept and alternatives so that clear direction for subsequent design phases can be determined The architect/engineer team, in
consultation with your host district’s planning team and local code agencies completes:
Written description of the project, including how the design responds to educational specifications
Zoning and building codes
Conceptual site and floor plans
Incorporation of high-performance features
Preliminary building sections, systems, and materials
Site plan, building(s) plan, section, and elevations to establish the final project scope
Specifications regarding final material selection and descriptions of the architectural, structural, mechanical, plumbing, technology, and electrical systems
Area analysis
Sketches, study models, product, and material literature, as well as other samples to explain the project
Trang 2323 • Chapter 4
Updated project schedule
Detailed construction cost estimate
A more detailed LCCA must be submitted to OFM prior to receiving the construction allotment
Construction Documents
Construction document phase incorporates further detail from design development documents to
precisely instruct a general contractor how the project is to be built They include all architectural and engineering drawings as well as specifications necessary to allow contractors to accurately bid the project
for a construction contract These documents include two primary components:
Drawings that show the configuration, location, relationships, and dimensions of work to be done
Note: Construction documents must comply with applicable federal, state, and local codes –
including but not limited to – building, mechanical, plumbing, electrical, and fire codes;
environmental health standards; and accessibility standards
A project manual that includes general conditions, bidding requirements, contract forms, and material and equipment specifications
Bidding
Bidding a project involves sending bid documents out to be reviewed by prospective general contractors They will have the opportunity to assess if the project is feasible for their company to construct, evaluate the design and its systems, determine subcontractors, and calculate a total bid price For any project, but especially modernizations, it is recommended to have a pre-bid site meeting so potential bidders can familiarize themselves with existing conditions Such meetings may be made mandatory or optional
A day and time is set for sealed bids to be delivered to the host district; after which, all bids are then opened and read aloud in a public setting The general contractor who submits the lowest qualified total bid price becomes the “apparent low bidder.” A vetting process is done by the host district and/or its representatives to ensure the contractor has the required experience, ability to be bonded, and will stand by their price
If a project is utilizing the public works process of General Contractor/Construction Manager (GC/CM), instead of traditional design-bid-build, this phase is primarily focused on negotiating a maximum allowable construction cost (MACC) with the general contractor who is already under contract with the host district Bidding for subcontractors occurs throughout the design and construction phases Your host district or project manager can assist in the earliest planning stages to determine if this public works method is
preferred Permission to use GC/CM must be obtained by The Capital Projects Advisory Review Board(CPARB) at some point early in the planning phases
Trang 24Throughout the construction phase, situations may arise that require changes or refinements to the
drawing or specifications, creating Change Orders These are modifications of the signed construction contract amount, usually higher All changes must be recorded and documented in the construction
contract dollar amount and timeframe Since appropriated funds are a fixed amount, the host district is responsible for any financial overage
Primary Players
Architect/Engineer (A/E)
For most construction projects, the A/E assumes overall responsibility (as the owner's agent) for the design, bid, and construction observation functions This includes ensuring that the project is completed within the limits of an established budget The A/E also coordinates the activities of other design
professionals working on the project
Reimbursements and Reporting
Reimbursement Claims
As soon as an approval letter is issued for a particular phase, the host district is eligible to submit
reimbursement claims for related expenses incurred Monthly reporting is encouraged to instill a
predictable spending pattern, which helps OFM predict bond sales It also allows the district to recoup its expenditures faster
Trang 2525 • Chapter 4
All claimed expenditures are reviewed for content and consistency with the approved budget
Reimbursement is made through the state accounting system by warrant or electronic transfer (EFT) and will be processed in an expedient manner Copies of voucher registers (referencing warrant numbers) and invoices must accompany all claims
Financial Reporting for Projects $5 million or more
After granting construction-stage work, a financial and construction update is required every 6 months around January 1 and July 1 using OFM’s Major Project Status Report form
If adjustments of 10% or greater is required in a project’s expected spending, an updates to a project’s Reimbursement Request Schedule should be submitted at the beginning of any quarter (January 1, April 1, July 1, October 1) These updates are reported to OFM to ensure state bonds are continuing to be sold at a proper rate in order to fund the project
Additional Information
See Chapter 9 and Appendix G for more information on the modified D-form process that authorizes
the host district to undertake certain actions
See Appendix F for the Major Works Reimbursement Request Schedule (required at all major project
phases and also quarterly as needed) An electronic version is available
See Appendix H for the Major Project Status Report (required every 6 months) An electronic version is
available
See Appendix I for the Special Capital Grant Claim Form 1288SK to be used when submitting related
invoicing for reimbursement An electronic version is available
Trang 2626 • Chapter 5
Chapter 5
Major Works Various Project Requirements
Prior to submitting information for a project to be prioritized and included in the OSPI Capital Budget Request, it is important to ensure the following considerations have been made Many of these
requirements will apply throughout and following construction
Bond Funding Requirements
Skill Center capital projects are primarily funded by the state with long term financing such as general obligation or reimbursable bonds The state issues tax-exempt bonds with the understanding that the spaces constructed will be used for governmental purposes only during the term of the bonds
Life expectancy
The life expectancy of the project cannot be shorter than the life of the bonds (typically 25 years)
Allowable Uses
OFM lists the acceptable uses of long term financing for capital projects in its capital budget instructions
An OFM Bond/COP form must be completed with capital budget requests, which can be found at: http://www.ofm.wa.gov/budget/capitalforms/expecteduse.doc
Governmental Purpose
Additionally, the facility cannot be sold or leased to a non-governmental agency for the life of the bonds Non-governmental purposes include use of bond proceeds to pay the costs of facilities expected to be owned or used by, or to make any loan or grant to:
The federal government (including any federal department or agency)
Any private nonprofit corporation [including any 501(c) (3) organization]
Any other private entity such as a business corporation, partnership, limited liability company or
association, etc
School Facility Design Safety Guidance
School districts undertaking construction or modernization projects are required to consider school safety
in plans and designs per RCW 28A.335.010(2) to better protects students and staff This is a state
requirement even if no state money is involved The guidelines can be found at:
https://www.k12.wa.us/sites/default/files/public/schfacilities/publications/pubdocs/safetyguidance.pdf
Trang 2727 • Chapter 5
High-Performance Schools Requirements and Reporting
High-performance, as it relates to school buildings, refers to features that help provide a healthy,
comfortable, enhanced learning environment while reducing the use of natural resources and reducing operating costs While up-front design and construction costs may be higher, the goal is to improve indoor air quality, reduce energy and water use, and conserve materials Over time, this effort should reduce district operating costs and provide a long-lasting, healthier, more economical school building
All major state-funded capital projects that receive state funding are required to meet a minimum level of high-performance or green building standards (chapter 39.35D RCW) The state threshold is the
Leadership in Energy and Environmental Design (LEED or LEED for Schools) Silver Standard K-12 school districts may choose to use the Washington Sustainable School Design Protocol (WSSP), which is overwhelmingly more popular due to its self-reporting nature, lower administrative cost, and immediate recognition of compliance
Reporting
In addition to documents required within the modified D-form process during the design phases, these standards also require schools to monitor, document, and annually report operating benefits and savings for a minimum of five years, beginning with the first year of occupancy Skill centers are required to use the Energy Star Portfolio Manager to track operating benefits and savings This online program allows the school district, skill center, and OSPI to access and view data Please see High-Performance Schools for
more information, or contact OSPI’s High Performance Schools Coordinator for further guidance
Apprenticeship Utilization
School district public works contracts worth $1 million or more are required to include language stating that a portion of the labor hours must be performed by registered apprentices in state-approved
apprenticeship programs consistent with RCW 39.04.310 and RCW 39.04.320
Art in Public Places
New school facilities that receive state funding must include one-half of one percent (0.5%) of the original (i.e, new or new-in-lieu) construction costs to be expended by the Washington State Arts Commission (ArtsWA) for the acquisition and installation of art See RCW 28A.335.210 for details
Cost for the acquisition of art should be anticipated included with the original budget request SF&O will show a separate line item for art allocation in the construction-phase grant letter Since this amount is a percentage of the total cost of original construction, the actual amount required for public art may differ than the art allocation OSPI has provided in the project approval letter
Note: Please keep in mind the amount determined comes out of the overall project appropriation, and is
not considered additional funds to a capital appropriation
Trang 28For more information regarding public art in schools, contact ArtsWA at this link:
http://www.arts.wa.gov/public-art
Information and Condition of Schools System
The Information and Condition of Schools (ICOS) system is an OSPI-based application where inventory and condition details about facilities and sites operated by school districts are documented and stored ICOS meets the increasing demand for accurate school facility inventory and building condition data that supports statewide programs such as skill centers This information is also used to support the
performance-based Asset Preservation Program ICOS benefits the districts by providing functionality for inventory tracking, condition rating, record keeping, as well as comparative and report analysis
Host districts or their consultants must enter data related to completed capital projects, including but not limited to geographic location, square footage inventory, condition ratings, and room data
Asset Preservation Program
Skill centers receiving state construction funding for new or new-in-lieu projects are required to participate
in the Asset Preservation Program (APP) as outlined in WAC 392.347.023 Certain modernized projects may face this requirement as well
Under this program, completed skill center projects, working through the administrative council and host district, must perform a building condition assessment (BCA) annually for 30 years, following final
construction acceptance by the host district’s school board Results are reported each year to their
administrative council and host district’s board no later than April 1 of each year Every 6 years, this assessment must be performed by a certified evaluator, hopefully as part of a larger district effort to
complete a capital Study and Survey in order to consolidate efforts
Use ICOS to enter or update assessments, and the score will automatically calculate Enter the date that a report was made to the host district’s board in ICOS’ APP Workflow For many districts, this effort can be done in conjunction with a district’s other APP buildings
The Building Condition Standard is an assessment tool for determining compliance with asset preservation
as well as for helping determine future eligibility for state funding assistance This standard is being
developed and supported by best practices in the building design, engineering, construction, and
maintenance industries This lays out an average scoring system based on the yearly depreciation of a building’s systems and infrastructure Contact SF&O for a copy of the standard
Trang 2929 • Chapter 5
For more information, visit the Asset Preservation Program webpage
Life Cycle Cost Analysis
All major capital construction projects must include a Life Cycle Cost Analysis (LCCA) using the new Life Cycle Cost Tool (LCCT) developed by OFM This tool will be used to generate the required analysis for projects expected to cost $5 million or greater, or construction of buildings with an area of 5,000 square feet or greater This became a requirement for projects that began pre-design or design phase in the 2015–
17 biennium and afterwards
The LCCT formally considers the cost to build, own, and operate the building or system The primary features are:
Standard format to simplify review of modeled alternatives
Standard rates and methodologies based on Washington State guidelines and established LCCA processes
Variable levels of detail and study life (detail levels align with Uniformat II cost estimating format)
Cost comparison model that evaluates project or system options based on standard parameters
Automatically produces an executive report for efficient review of project alternatives
LCCA Submittal Requirements:
Predesign submittals will include an analysis using the LCCT at a detail level as established in consultation with the agency and OFM Typically, the analysis will align with the detail level of the cost estimate as it is submitted in the predesign
Design phase will include a more detailed analysis submitted to OFM prior to receiving the
Other Requirements per State Statute
Major capital projects are also subject to standard state laws that pertain to all public works jobs Contact your host district for assistance in preparing your project specifications during the design phase This includes, but is not limited to:
Chapter18.27 RCW
Registration of Contractors
Trang 3030 • Chapter 5
RCW 39.04.320
Apprenticeship Training Programs — Public Works Contracts — Adjustment of Specific Projects
— Report and Collection of Agency Data — Apprenticeship Utilization Advisory Committee Created
Provisions in Buildings for Aged and Handicapped Persons
Other Agency Approvals
Skill centers will need to work with their local county/city planning offices to ensure all public works, permitting, land use, zoning, environmental reviews, and other requirements are met
Additional Information
See Appendix J for OFM’s Expected Use of Bond/COP Proceeds form An electronic version is
available
Trang 3131 • Chapter 6
Chapter 6
Major Works: Preservation Projects
This chapter only applies to preservation projects To determine whether a project is classified as a
preservation project, please see the introduction chapter
Preservation Project Eligibility
Preservation project funding is only available to skill centers that meet the following criteria:
Skills centers must have complete information in the Information and Condition of Schools
(ICOS) data system
Completed building condition assessment (BCA)
Building system ICOS BCA score less than or equal to 30
Skill center capital maintenance account
Compliance with RCW 28A.245.100
Preservation Project Priority Scoring Criteria
The Skill Center Directors Committee must evaluate final applications from eligible districts The
committee must submit a prioritized list of grants to OSPI If applications for planning grants exceed funds available, OSPI may prioritize the recipients of planning grants in order to help districts with the most serious apparent building deficiencies
Priority Scoring
Skill Center Preservation Project Scoring Criteria
Trang 3232 • Chapter 7
Chapter 7
Major Works and New Satellites Prioritization
Skill centers must submit their capital projects for prioritization by May 1 of even-numbered years
Prioritization of projects is needed prior to submitting the final budget project See Chapter 8, Major Works Final Budget Submittal
SF&O and CTE, in cooperation with the Washington State Skill Center Directors Association, created this skill center capital facility prioritization process to rank capital budget requests to the Governor and
Legislature With input and buy-in from the Washington State Skill Center Directors Association, this objective process has been updated and modified to simplify the process, increase objectivity, and better meet objectives of identifying those projects most in need of capital funding
The goal of the prioritization process is to develop lists of skill center projects that can be provided to the Superintendent of Public Instruction, the Governor and the Legislature so they can make informed
decisions about which projects are most in need and positioned for capital funding
Scope of Process
All prioritized major works construction projects include modernization, growth, and new core and branch campuses Satellite projects, which are minor works, are also prioritized through this process Repairs of existing skill centers, which are all minor works, are addressed through the minor works process identified
in Chapter 3
Submitting a Project
Skill centers requesting a major works or new satellite campus project will need to submit written
documentation for the evaluators to score the projects by May 1 of even-numbered years, if not already included in the Long Range Plan It is important to provide organized and complete information for the evaluators
The project forms described below should be submitted electronically, using Word, Excel, or PDF format,
so information can be copied and pasted as needed
Minimum Project Requirements
All projects must meet the minimum requirements below to be scored
Projects for existing skill center campuses must have been identified in a previous Ten-Year
Trang 3333 • Chapter 7
Capital Plan, as well as the latest Long Range Plan
If funded, projects for buildings seeking modernization or new-in-lieu replacement must be at 30
years old at the time the project begins to receive construction phase funding
New skill center campuses must have a completed and approved New Skill Center Campus Form
Priority Scoring Criteria
Provide any necessary back-up documentation to support the information in the applicable scoring criteria
Different criteria will apply, depending on the project type The documentation should address questions
for each applicable criterion
Definitions for each phase and type of project can be found in the Introduction chapter The following is a
list of the criteria that applies to each type of phase and project See also figure 6.1
Figure 7.1
Trang 34
34 • Chapter 7
Priority Scoring Criteria Descriptions
Criteria 1: Minor Repair and Maintenance Capital Accounts
RCW 28A.245.100 requires each host district of a cooperative skills center to maintain a separate minor repair and maintenance capital account for facilities constructed or renovated with state funding Participating school districts must make annual deposits into the account to pay for future minor repair and maintenance costs of those facilities Score is based on
the 2017-18 school year per student FTE expenditure from the required minor repair and maintenance capital account compared to the statewide school district per FTE expenditure for the same time period 2017-18 School Year Statewide Average Expenditure Data
Per FTE Spending % = _ Points (15 Point Maximum)
Note: See OSPI Accounting Manual for School Districts Chapter 6 for Activity Code Descriptions
Criteria 2: Building Age
Skill center host district completes building information in ICOS
Score is based on the current age of the building or time since the last major modernization, whichever is less If more than one building is involved, this score will be weighted
(Current number of years since built or last modernized - 28) x 2 = _ Points
(25 Point Maximum)
Activity
Statewide Expenditure
62 Grounds Maintenance $ 79,823,417.23
67 Building and Property Security $ 26,075,036.30
2017-18 School Year Total Expenditures $ 376,703,217.51
2017-18 Statewide Student FTE 1,112,719.23
Expenditure Per Student FTE $ 338.54
Trang 3535 • Chapter 7
Note: An affected building must be a minimum of 30 years since built, or last modernized, at the time
pre-construction stage funding will be received
Criteria 3: Building Condition
Skill center host district completes building information in ICOS
Score is based on an up-to-date certified building condition assessment (BCA) This evaluation should be performed by an independent contractor who has taken a certified training course by OSPI for this task Ideally, the host district will have had this already completed in a recent Study & Survey
The basic scoring formula for this criterion is located in WAC 392.343.515, but without considering a cost benefit analysis for new-in-lieu construction, which should have been addressed through long range
planning requirements
91–100 0 points
31–90 Points are awarded proportionally using the following equation:
(90–BCA score)*.50=proportional score
30 or less 30 points
BCA Score _ Final Score based on above equation _ Points (30 Point Maximum)
Trang 3636 • Chapter 7
Criteria 4: Significant Health, Safety, and Energy Issues
Skill center host district completes health and safety worksheet
Score is based on existing significant health, safety, and energy issues that would need to be resolved in order to bring a building up to date A health and safety checklist must be completed with appropriate documentation to verify that each issue exists
Score based on total of the OSPI’s health and safety checklist Points (30 Point Maximum)
Total score based on Health and Safety Worksheet
30-41: Thirty points
20-29: Twenty points
10-19: Ten points
0-10: Five points
Criteria 5: Cohort Projections for Enrollment
OSPI provides from district-reported data
Score is based on the estimated amount of skill center growth or decline Using WAC 392.343.045 to determine how to project enrollment 3 to 5 years into the future, OSPI will determine the enrollment of grades 11 and 12 from all member districts in the skill center cooperative Using a 3-year average of skill center enrollment information (October headcounts), OSPI will determine the percentage of students attending the skill center from each member school district This percentage is individually applied to each school district of the cooperative to determine future enrollment
For New Core or Branch campuses that have no enrollment history, OSPI will follow the same process as existing skill center campuses as described above, but OSPI will either use information from the feasibility study or equivalent information to project enrollment
The percentage of change in enrollment from the current school year to the projection will derive the scoring for this section based on a range
If Negative Projected Cohort Decline:
-6 to -10 3 Points
0 to -5 6 Points
Cohort Projection = Percent Decline Points
If Positive Projected Cohort Growth:
(Cohort Projection = Percent Growth x 3) + 4 = Points (30 Point Maximum)
Trang 3737 • Chapter 7
Criteria 6: Temporary Locations
Skill center host district provides information
Score is based on the number of temporary locations used by current programs, and would be addressed
by the project 6 points are awarded for each A temporary location can include an off-campus site (e.g leased), a portable building, and an on-campus area that was not constructed or acquired for instructional purposes (e.g storage area, garage)
If a program is currently being held in a portable building and counted as a temporary location; the same portable, housing a temporary program, cannot be counted in the future for a point in this category The intent is to create permanent space to replace temporary accommodations
Programs offered at temporary locations x 6 Points = _ Points (30 Point Maximum)
Trang 3838 • Chapter 7
Criteria 7: Facility Utilization by Program
Skill center or host district provides this calculation
Facility utilization is calculated using morning and afternoon FTE count for the facility based on October enrollments The scoring is calculated by dividing the average student enrollment by the area capacity of the instructional space
Facility Utilization Scoring
(Morning Enrollment + Afternoon Enrollment) / 2 = Projected Average Enrollment
(Projected Average Enrollment / Instructional Space Capacity = Facility Utilization
Trang 3939 • Chapter 7
Criteria 8: High-Demand Programs
Skill center or host district provides in space below or on a separate sheet
Score is based on each program (associated with the project) receiving a maximum of 2 points by being identified as either a local area demand program or a statewide demand program—but not both The programs must have a logical nexus with the demand occupation it is being identified with
Local Area Demand Program
Local area demand programs are identified by the skills center’s advisory council or the Washington State Employment Security Department as those providing for local area demand occupations in a skill center service area or the skill center is the only “training” facility in an area which is filling a local need
https://esd.wa.gov/labormarketinfo/learn-about-an-occupation#/search
List each local area demand program followed by the relevant local area demand occupation(s)
Statewide Demand Program
Statewide demand programs prepare students for high demand occupations per RCW 28A.700.020
Trang 4040 • Chapter 7
Criteria 9: Identified Partnerships
Skill center or host district provides documentation
Score is based on partnerships from: a) the community (e.g local governments, clubs, non-profits, and community leaders, etc.); b) post-secondary organizations (e.g colleges and trade schools); and c) labor and business partnerships (e.g specific businesses, unions, service clubs and trade associations, which can provide a contribution such as in-kind services, equipment donations or other investments) Each
partnership is awarded 1 point with a maximum point value for this criterion of 15 points Attach a letter
of support for each identified partnership or a signed resolution by the skill center administrative council acknowledging particular partnerships
Please see the descriptions above for Community, Post-secondary, and Labor and Business
Type of Partnership Number of Partnerships
Community (Maximum of 5 points)
Post-secondary (Maximum of 3 points)
Labor and Business (Maximum of 7 points)
TOTAL Partnerships = Points (15 Point Maximum, Satellites 6 Point Maximum)
Criteria 10: Flexible Space
Skill center or host district provides in a rubric
Score is based on the designed flexibility of the space to accommodate evolving and future high demand use Design consideration should be made to ensure the space can be easily transformed at low-cost such
as non-load bearing walls, stub-outs for future plumbing and lab needs, additional capacity for potential future electrical needs, adaptable FF&E, etc A self-scoring rubric with details is shown in the Appendix L and must be completed with appropriate documentation to verify that each issue exists.Provide a
description for each item identified in the rubric that you are looking to score points for in this category.Score based on rubric _ _ Points (15 Point Maximum, Satellites 15 Point Maximum)