Risk Evaluation Using a Fuzzy Logic ModelAmaury Caballero, Syed Ahmed, and Salman Azhar Department of Construction Management Florida International University 10555 W.. This research use
Trang 1Risk Evaluation Using a Fuzzy Logic Model
Amaury Caballero, Syed Ahmed, and Salman Azhar
Department of Construction Management Florida International University
10555 W Flagler Street, Miami, Florida 33174
USA
Abstract:- Construction is a highly risk-prone industry with not a very good track in dealing
with risks The participants of the industry, as a result, have been enduring the agonizing outcomes of failure in the form of unusual delays in project completion, with cost surpassing the budgeted cost and sometimes even failing to meet quality standards and operational requirements Thus, effective analysis and management of construction-associated risks remain a big challenge
to the industry practitioners This research uses as a basis a questionnaire survey and in-depth interviews conducted in the State of Florida, and starting from this, propose a risk management fuzzy logic model for the construction sub-contractors The proposed model is based on a systematic methodology of risk identification, classification, analysis and response The model is expected to help subcontractors to get an initial quantified idea, based on the responses of experts,
of the incurring risks in a project development.
Key Words: - Construction, Risk management, Project management, Fuzzy logic models.
1 Introduction
Different parties in a construction
project face a variety of uncertain
factors These factors can be complied
under the category of risk Making
decisions on the basis of assumptions,
expectations, estimates and forecasts of
future events involves taking risks Risk
and uncertainty characterize situations
where the actual outcome for a particular
event or activity is likely to deviate from
the estimate or forecast value [1]
Construction risk is generally perceived
as events that influence project
objectives of cost, time and quality [2]
The construction industry has long been
recognized as particularly risk laden and
subject to more risk and uncertainty than
many other industries Some of the risks
associated with the construction process
are fairly predictable or readily
identifiable; others may be totally
unseen [3] The process of taking a
project from initial investment appraisal
to completion and into use is complex, generally bespoke, and entails time-consuming design and production processes It requires a multitude of people with different skills and interests and the co-ordination of a wide range of disparate, yet interrelated, activities Such complexity moreover, is compounded by many external, uncontrollable factors [4]
In the context of project management,
risk management is defined as: " A formal orderly process for systematically identifying, analyzing, and responding to risk events throughout the life of a project to obtain the optimum or acceptable degree of risk elimination or control" [5] In practice, a risk management system must be practical, realistic and must be efficient on cost
and schedule control In construction
industry, an effective risk management
Trang 2system depends very much on the
characteristics and conditions of the
project and the attitude of the individuals
of the decision- making group
2 Identification of Critical Risks
Risk identification process is the first
step in risk management modeling It is
the process of systematically and
continuously identifying, classifying,
and assessing the risks associated with a
construction project In this research, the
critical risks were identified in three
stages as follows:
Identification of all possible
risks, which may be encountered
by a subcontractor through
detailed literature and Internet
search
Identification of critical risks in
the Florida construction industry
These risks were identified from
the list generated through a
questionnaire
Verification of critical risks in
the Florida construction industry
via interviews with professionals
Both quantitative and qualitative
analysis was performed depending on
the nature of data collected through
questionnaire and interviews The
analysis includes the identification of
key critical risks as shown in Table 1
3 Development of the Risk
Management Fuzzy Logic Model
The risk management model for the
sub-contractors was developed based on
a systematic methodology of risk
identification, risk classification, risk
allocation and risk response This risk
management information, obtained
from Table 1 can be used by
sub-contractors to accurately classify the
identified risk element; estimate their
probability of occurrence to decide
whether to avoid the risk completely,
retain it and try to reduce its impact by
taking preventive steps; or finally,
transfer it to a party better able to
handle it
The mathematical model gives the sub-contractor a quantified evaluation of the risk that can be used as an element to compare different projects
Lets define the vector P, as the
probability of occurrence of the different possible events For the risk
category i, where i can take values from
1 through 6, this vector can be represented through:
P = [Pi1, Pi2, ………., Pin ], (1) Where Pin is the risk number n in the risk category i The value for any element can vary from 0 to1, and n will
vary in general from one category to another
The vector M will represent the
Maximum Potential Loss, expressed as
a percent of the total cost lost due to each event Where
M = [Mi1, Mi2,……….,Min], (2) Presented in a similar way to the
previously defined P.
The presented situation can be solved using Fuzzy logic The use of fuzzy rules provides a systematic way of solving imprecise, ambiguous, and vague input-output relations [6] There exist several advantages when implementing decision-making models based on fuzzy logic:
1) Experts related to the problem area can present their evaluation
of the different parameters with concepts as “worse”, “better”, etc, without having to numerically quantify their opinions from the beginning of the evaluation process
2) The calculus using fuzzy logic is simple and close to the representation of knowledge 3) There is a wide array of software available for solving problems utilizing fuzzy logic
Trang 3The two main factors affecting the risk
are the Probability of Occurrence of any
event and the Maximum Potential Loss
They are presented as fuzzy variables as
well as the Risk, which is the output
The output is represented, as numbers
varying from 0 to 100, where 0 is no
risk at all and 100 is the certainty of
occurrence of a non-desired situation
The selected membership functions for
each input fuzzy variable are: VL
Very Low, L Low, M Medium, and
H High For the output fuzzy variable,
it is added VH Very High
For applying fuzzy logic to each category, the presented rule set on Table
2 was employed The rules structure is
of the type “if X and Y, then Z” This rule set may be changed in dependence
of the real conditions under which the project is developed After the defuzzification a number was obtained for the risk related to each category, and finally added to the other numbers representing each of the six considered categories affecting the final result As the final number will be in general more than 100, it becomes necessary to rationalize All this is represented in the block diagram of Figure 1
Category # 1
- X
Risk (0% to 100%) Figure 1 Block diagram Representing the Necessary Operations for the Risk Calculation
Example:
Table 3 represents a practical situation
in South Florida The numbers for the
probabilities of occurrence of the
different events have been obtained
from experts The universe of discourse
for each fuzzy variable was taken as
follows:
Probability: 0.001 to 0.1
Maximum Potential Loss: 0% to 35%
Risk: 0% to 100%
The numbers for the maximum potential
looses have been obtained from
surveys In this example, only the
factors with high incidence in this particular place have been taken into account The used fuzzy logic software [7] gives the results Figure 2 shows the surface representation for the Risk as per the selected ranges of the input variables and the established fuzzy rules
Under the specified conditions, assuming statistical independence among all the events and giving them the same weight, the obtained risk average is 58.7%
Probability
Loss
Rule Set
Category # 6
Addition
Normalization
Trang 4
Figure 2 Risk Surface Representation X – Probability, Y – Loss, Z - Risk
4 Conclusions
The concept of risk management is
relatively new to the Florida
construction industry The responses to
the questionnaire reveal that formal risk
management is not being carry out by
most subcontractors In fact, some
responses were received stating that
they were not aware of a discipline
called risk management It appears that
Florida subcontractors are still not
aware of the great benefits that risk
management provides to the
construction industry It is found that
the Florida construction industry prefers
to eliminate and transfer risks instead of
finding as systematic procedure to deal
with them through such as risk retention
or risk reduction
The developed fuzzy model can help in:
Identification of all possible
risks, which may be encountered
by a subcontractor
Identification of critical risks in
a construction project
Giving an idea of the risk involved in a project
References:
[1] Raftery, J Risk Analysis in Project
Management, E & FN Spon, London
SE1 8HN, UK 1994
[2] Akintoye, A.S., and Macleod, M.J Risk Analysis and Management in the
Construction, International Journal of
Project Management, Vol 15, No 1, pp.
31-38 1997
[3] Smith, R.J., and Gavin, W Risk Identification and Allocation: Saving Money by Improving Contracts and Contracting Practices A special report
presented to the ASCE Hong Kong
International Group and the Chartered Institute of Arbitrators (HK), March
1998
Trang 5[4] Flanagan, R., and Norman G Risk
Management and Construction
Blackwell Scientific Publications,
Oxford, London 1993
[5] Al-Bahar, J.F Risk Management in
Construction Projects: A Systematic
Analytical Approach for Contractors,
Ph.D Dissertation, Department of Civil Engineering, The University of California at Berkeley, 1988
[6] Kostko B Fuzzy Engineering.
Prentice Hall Publishers 1997
[7] Togai Infralogic, Inc TIL Shell 3.0
BE
Table 1 The Assessed Critical Risks for a Subcontractor
Acts of God (i = 1) Financial (i = 4)
Tax rate changes
Construction Related (i = 2)
Labor productivity
Permits and approvals
Design Related (i = 3) Political pressure/disturbances
Incomplete design
Table 2 Fuzzy Rules
Trang 6
Probability Max Potential Loss Risk
Probability Max Potential Loss Risk
Trang 7Table 3 Risk Evaluation for a Practical Situation
Considered Parameter for Risk
Calculation Probability Max Potential Loss
Acts of God
Construction Related
Design Related
Financial
Physical
Political, Social and
Environmental