ORIGINAL DATA USED FOR SURVEY- Horizontal control points: Third order horizontal control points in VN2000 coordinate system established by Vietnam National Land Administration Department
Trang 1THAI BINH THERMAL POWER PLANT AND TRANSMISSION LINES
CONSTRUCTION PROJECT
Report on Establishment of the Permanent and Temporary Benchmark
Carried out by: Port Technology Construction Consulting and Commercial JSC(PTECH)
I THE PURPOSE OF SURVEY
In order to obtain the data for the Permanent and Temporary Benchmarks in coordinates and elevations for excecute construction, survey work is required PTECH is assigned to carry out the survey of IV order and Grade 1 traverse control network at the project site from 19th November to 03rd December 2014
II BASIC FOR SURVEY
- Contract dated 7nd March, 2014 between TOA CORPORATION and Port Technology Construction Consulting & Commercial JSC of “Thai Binh Thermal Power Plant and Transmission Lines Construction Project”
- Working statement for Establishment of the Permanent and Temporary Benchmark prepared by PTECH approved
III STANDARD FOR SURVEY.
- QCVN 04:2009/BTNMT - National technical regulation on establishment of Horizontal control network issued by Ministry of Natural Research and Environment in 2009
- QCVN 11: 2008/BTNMT - National technical regulation on eshtablisment of leveling network issued by Ministry of Natural Research and Environment in 2008
- TCVN 9401_2012 - The technical of measuring and processing GPS data in engineering survey
- TCVN 9398: 2012 – Surveying in construction – General Requirements
Trang 2IV ORIGINAL DATA USED FOR SURVEY
- Horizontal control points: Third order horizontal control points in VN2000
coordinate system established by Vietnam National Land Administration Department are used for developing the IV order GPS horizontal control network
- Vertical control points: Third order Benchmark is used for development of IV
order vertical control network
- The table below list the original control points used as based points to develop the IV order Hor/Vertical control network (Detail see in Appendix 1)
Table 1: Table of Original Coordinate, Elevation control points
VN2000 coordinate system, Central Meridian 105 0 00’ , zone 6 0 ,
National Land Survey Datum
No.
coordinate point
Benchmark
Benchmark
V QUANTITY OF SURVEY
4 Establishment of Grade 1 traverse
Trang 3VI SURVEY EQUIPMENTS
The survey work are used Equipment as following:
1 04 Trimble 4600LS receivers made in USA which can receive the signals
from GPS (USA) systems were used to establish the IV order horizontal control network and the Grade 1 traverse points (area outside the fence)
The Accuracy in standard condition is as follows:
± (5mm + 0.5ppm x D) (Static and Fast Static Mode) (D is the distance from reference station to mobile station)
GPS Trimble 4600LS receiver
2 Total station Nikkon DTM551 made in Japan was used for measuring grade
1 traverse control network (area inside the fence) and setting out
The Accuracy in standard condition is as follows:
• Angle measurement accuracy 1”;
• Distance measurement accuracy 2mm + 2pmm;
Trang 4Total station Nikon DTM 551
3 Leveling equipment Topcon AT-B4 and staffs was used for establishing the
IV order vertical control network
Leveling equipment Topcon AT-B4
4 Equipment and softwares for office data processing
• Trimble Business Centre Software was used for baselines processing and adjustment of IV order horizontal control and grade 1 traverse control network (area outside the fence)
• Hhmaps Software was used for network adjustment (area inside the fence)
• AENET Software was used for vertical network adjustment
Trang 5• Microsoft office and assistance drawing software such as AutoCAD, softdesk was used for editing and making the report
VII SURVEY METHODOLOGIES
VII.1 Coordinate and Elevation system
• Coordinate system:
National coordinate system VN2000, with Central Meridian 105030’, zone 30
(Ko=0.9999) was used for whole project The detailed parameters of coordinate system are as follows:
Spheroid
Semi major axis
1/ flattening
Projection
Central Meridian
False Easting
False Northing
Scale factor at C.M
: WGS 84 : 6378137m : 298.257223563 : UTM
: 1050 30' E : 500 km : 0.000 : 0.9999
• Elevation system:
National Land Survey Datum
VII.2 IV order horizontal control network.
Horizontal control points:
Third order horizontal control two points named III-130420 and III-130419 in VN2000 coordinate system established by Vietnam National Land Administration Department were used for establishment the IV order GPS control network points
Field survey
Trang 6Horizontal control network was connected to at 02 National control points
(III-130420 and III-130419 )
IV order horizontal control network was carried out include 04 sessions Each session, the signal of satellites was recored for at least 120 minutes
All survey information of each measured point such as weather condition, Antenna’s height, number of satellite were recorded into daily report… All data collected at each point were recorded into memory card or internal memory with
10 seconds interval separately by names for post-processing
Network adjustment
Trimble Business Centre software was used for baselines processing and network adjustment
Adjustment module was used for control network adjustment In order to reduce an affect of scale factor and according to technical specification, the network was adjusted in VN-2000 coordinate system central meridian 105030’, zone 30(Ko=0.9999)
Weighting value of all GPS solution is calculated based on “alternative” method After calculating, received result of root means square of weighting unit error is 1.0 and tested result of χ2 with α=95% is PASS All adjustment results are shown in tables of appendix 2
Coordinate in VN2000 grid coordinate system and WGS84 Geographic coordinate system of control points are shown in Appendix 2
VII.3 Grade 1 traverse horizontal control network.
Grade 1 traverse horizontal control network was connected to IV order GPS control points
By position specific of grade 1 traverse control points, with 05 points outside the fence and 11 points inside the fence (see the attached enclosed in Appendix 3) Therefore, the grade 1 traverse control points were establishment according to two methods: The points the inside the fence was established according to the method Total Station (measuring angles and distances), the points outside the fence was established according to the method measurements GPS
Trang 7With 05 points outside the fence:
Field survey:
Based on 02 IV order GPS points (BM-01 and BM-06), Grade 1 traverse control points was established by GPS receivers
Grade 1 traverse horizontal control network was carried out include 03 sessions Each session, the signal of satellites was recorded for at least 90 minutes
All survey information of each measured point such as weather condition, Antenna’s height, number of satellite must be recorded into daily report… All data collected at each point was recorded into internal memory with 10 seconds interval separately by names for post-processing
Network adjustment
Trimble Business Centre software was used for baselines processing and network adjustment
Adjustment module was used for control network adjustment In order to reduce
an affect of scale factor and according to technical specification, the network was adjusted in VN-2000 coordinate system central meridian 105030’, zone 30
(Ko=0.9999)
Weighting value of all GPS solution is calculated based on “alternative” method After calculating, received result of root means square of weighting unit error is 1.0 and tested result of χ2 with α=95% is PASS All adjustment results are shown in tables of appendix 3.1
Coordinate in VN2000 grid coordinate system and WGS84 Geographic coordinate system of control points are shown in Appendix 3.1
Transformation coordinate
Trang 8The network adjustment results of IV order horizontal control and grade 1 traverse control points (for area outside the fence) are using coordinate system VN2000, Center Meridian 105030' , zone = 30 (UTM projection), at location of project deformed distance is 1/20.000 in this projection It's greater than 1/50.000 (according to TCVN 9398: 2012 Surveying construction-General requirements) therefore need to calculate coordinate transformation after network adjustment
Table 2: Coordinate of IV order control and Grade 1 traverse horizontal control points (for area outside the fence) at Coordinate system: VN 2000,
central Meridian 105 0 30’, k=0.9999.
Coordinate
Remarks
7 TBM-17 2265996.417 610180.289 Grade 1 traverse horizontalcontrol point
8 TBMO-01 2266112.908 610284.056 Grade 1 traverse horizontalcontrol point
9 TBMO-03 2265803.876 610158.902 Grade 1 traverse horizontalcontrol point
10 TBMO-04 2265989.181 610054.279 Grade 1 traverse horizontalcontrol point
11 TBMO-05 2265740.280 610222.565 Grade 1 traverse horizontal
control point
Trang 9Above coordinate is transformation to the meridian axis in accordance with the geographical location of the project land (central meridian 105 ° 41 '):
Table 3: Coordinate of IV order control and Grade 1 traverse horizontal control points (for area outside the fence) at Coordinate system: VN 2000,
Central Meridian 105 0 41’, k=0.9999.
No Point name
Coordinate
Remarks
7 TBM-17 2265883.736 591054.065 Grade 1 traverse horizontalcontrol point
8 TBMO-01 2266000.105 591157.957 Grade 1 traverse horizontalcontrol point
9 TBMO-03 2265691.228 591032.463 Grade 1 traverse horizontalcontrol point
10 TBMO-04 2265876.642 590928.053 Grade 1 traverse horizontal
control point
11 TBMO-05 2265627.564 591096.052 Grade 1 traverse horizontalcontrol point
Trang 10Transfer of coordinate values from CM=105041’, K=0.9999 to CM=105°30', K=1.000000
To calculate coordinate transformation, was used benchmark named: BM-01 as original point, azimuth side BM-01_BM-02 Result this calculate coordinate transformation is used for construction
Table 4: Coordinate of IV order control and Grade 1 traverse horizontal control points (for area outside the fence) at Coordinate system:
VN 2000, Central Meridian 105 0 30’, k=1.000000.
Coordinate
Remarks
control point
8 TBMO-01 2266112.905 610284.064 Grade 1 traverse horizontalcontrol point
9 TBMO-03 2265803.888 610158.915 Grade 1 traverse horizontalcontrol point
10 TBMO-04 2265989.185 610054.298 Grade 1 traverse horizontalcontrol point
11 TBMO-05 2265740.295 610222.576 Grade 1 traverse horizontalcontrol point
With 11 points inside the fence:
Field survey
Based on 05 IV order GPS points (BM-01, BM-02, BM-03, BM-05 and BM-06), Eleven (11) grade 1 traverse points were established by Total station Nikon DTM551
Trang 11The accuracy of measurement was within following limits:
o The Traverse angles were measured in 3 times with Root Mean Square (RMS) Error of better than 3.1”
o The Traverse lines were measured in 3 times with Relative RMS error of better than 1:28.600
Network adjustment
Hhmaps software was used for processing and network adjustment
This grade 1 traverse control network is used coordinate of 05 IV order GPS
points (BM-01, BM-02, BM-03, BM-05 and BM-06) in Table.4 of Item VII.3
(after transformation) for calculate adjustment
Result of grade 1 traverse horizontal control network (area insde the fence) is shown in appendix 3.2
VII.4 IV order vertical control network.
Vertical control points:
Third order National Benchmarks established by Vietnam National Land Administration Department were used for Establishment of IV order vertical control network
Field survey:
In accordance with standard of V.N.L.A.D the IV order vertical control network was established by using closed geometry levelling method
The benchmarks location were chosen same as location of IV order horizontal control points and Grade 1 traverse control points
National benchmarks were used as basic control points The IV order levelling route run though all IV order control points and Grade 1 traverse control points based on National benchmarks (III(TD-GL)7 and III(TD-GL)6 with miscloser 9.0mm, less than the allowable miscloser of =±85.48mm (where L is the length of levelling route in kilometre = 18.269km)
Network adjustment:
Trang 12The AENET software provided by Geodetic Department of Mining and Geology University was used for adjustment of IV order vertical control network
(Results are shown in appendix 4)
VIII RESULTS:
Table 5: Coordinate and elevation of IV order and Grade 1 traverse control points at
Coordinate system: VN2000, central Meridian 105 0 30’, k=1.000000.
No Point name
Remarks
7 TBM-01 2265876.768 610335.730 4.280 Grade 1 traverse horizontal , IV order vertical point
8 TBM-03 2265865.385 610470.094 4.464 Grade 1 traverse horizontal , IV order vertical point
, IV order vertical point
10 TBM-05 2265953.053 610482.692 4.131 Grade 1 traverse horizontal , IV order vertical point
, IV order vertical point
12 TBM-08 2265790.863 610532.676 4.800 Grade 1 traverse horizontal , IV order vertical point
13 TBM-09 2265708.584 610523.148 4.869 Grade 1 traverse horizontal , IV order vertical point
, IV order vertical point
15 TBM-12A 2265697.446 610661.641 5.171 Grade 1 traverse horizontal , IV order vertical point
, IV order vertical point
17 TBM-15 2265609.501 610431.234 4.646 Grade 1 traverse horizontal , IV order vertical point
18 TBM-17 2265996.420 610180.302 4.916 Grade 1 traverse horizontal , IV order vertical point
Trang 1319 TBMO-01 2266112.905 610284.064 4.669 Grade 1 traverse horizontal , IV order vertical point
, IV order vertical point
21 TBMO-04 2265989.185 610054.298 4.667 Grade 1 traverse horizontal , IV order vertical point
22 TBMO-05 2265740.295 610222.576 4.676 Grade 1 traverse horizontal , IV order vertical point
This is point the same Plant Coordinate
X(East)=0.000,
Y (North)=0.000,
Table 6: Coordinate and elevation of IV order and Grade 1 traverse control
points at Coordinate system: Plant.
No Point name
Remarks
7 TBM-01 521.570 851.453 4.280 Grade 1 traverse horizontal, IV order vertical point
8 TBM-03 608.530 748.395 4.464 Grade 1 traverse horizontal, IV order vertical point
9 TBM-04 521.529 751.396 4.040 Grade 1 traverse horizontal, IV order vertical point
10 TBM-05 679.429 801.477 4.131 Grade 1 traverse horizontal, IV order vertical point
IV order vertical point
12 TBM-08 600.088 651.448 4.800 Grade 1 traverse horizontal, IV order vertical point
13 TBM-09 535.170 600.005 4.869 Grade 1 traverse horizontal, IV order vertical point
14 TBM-10 668.876 599.980 4.930 Grade 1 traverse horizontal, IV order vertical point
Trang 1415 TBM-12A 625.224 494.200 5.171 Grade 1 traverse horizontal, IV order vertical point
IV order vertical point
17 TBM-15 400.115 594.936 4.646 Grade 1 traverse horizontal, IV order vertical point
18 TBM-17 496.272 1045.964 4.916 Grade 1 traverse horizontal, IV order vertical point
IV order vertical point
20 TBMO-03 345.009 924.947 4.725 Grade 1 traverse horizontal, IV order vertical point
IV order vertical point
22 TBMO-05 345.057 834.964 4.676 Grade 1 traverse horizontal, IV order vertical point
This is point the same Plant Coordinate
X(East)=0.000,
Y (North)=0.000,
Remark: Relative between plant coordinate and VN2000 system:
- Vertical axis symbol N(Y), parallel to the west fence of the TB1 thermal power plant
- South-West corner point of Project is assigned the value: X=0.000 (m); Y=0.000 (m) the same with VN2000 coordinate system Easting = 610568.993 (m); Northing
= 2264905.894 (m)
IX CONCLUSION
Report on Establishment of the Permanent and Temporary Benchmark for Thai Binh Thermal Power Plant and Transmission Lines Construction Project prepared
by PTECH follow Technical Specification and Technical standard Results of Elevation and Coordinate ensure for construction
XI REPORT
The final report are submitted to the client including 08 sets English
The Establishment of the Permanent and Temporary Benchmark report consists of the following:
•Technical report