: COMMISSIONING CHECK SHEET FOR CHILLED WATER PUMP Sheet No... : COMMISSIONING CHECK SHEET FOR COLD WATER TRANSFER PUMP SETS Sheet No.. : COMMISSIONING CHECK SHEET FOR COLD WATER BOOS
Trang 11 Chilled water distribution network pressure tested
and cleared
2 Makeup connection made
3 Dosing pot connected
4 Strainers are cleaned
5 Drain connections to all equipment provided
6 Pressure gauges and flow switches are installed
7 Tightness of electrical connections
8 Supply voltage and motor rating
9 Free rotation of impeller
10 MCC is clean
11 Pump and motor are clean
12 Overload setting and fuse rating
13 Pump and motor alignment
14 Pumps are interfaced with BMS
15 Pumps are in manual made
SUBCONTRACTOR:
EQUIPMENT NO : SEQUENCE NO :
COMMISSIONING CHECK SHEET FOR
CHILLED WATER PUMP
Sheet No
SERIAL NO : DATE :
LOCATION : COMMISSIONED ON :
Trang 21 Areas being fed by AHU are clean.
2 Filters are clean
3 Condense drain tray is clean and connected to
waste line
4 Duct temperatures sensors and differential
pressure switches are installed
5 All VCDs and splitters are open
6 Fan impeller rotates freely
7 Belt tension adjusted
8 Alignment of pulleys and check bearings
9 Overload setting and fuse rating
10 Electrical connections and tight
11 BMS wiring completed
12 Heaters and connected if applicable
13 DRV and GV are adjusted for design flow rate
14 Check flow of condense drain and P trap
EQUIPMENT NO : SEQUENCE NO :
COMMISSIONING CHECK SHEET FOR
AIR HANDLING UNIT
Sheet No
SUBCONTRACTOR:
SERIAL NO : DATE :
LOCATION : COMMISSIONED ON :
Trang 31 Areas being fed by FCU are clean.
2 Filter is clean
3 Condensate drain tray is clean and connected to waste line
4 Three speed switch and DP switch are connected
5 Thermostat is installed
6 Fan impeller rotates freely
7 DRV and GV are adjusted for design flow rate
8 Check fan bearings
9 Check flow of condensate drain and P-trap
EQUIPMENT NO : SEQUENCE NO :
COMMISSIONING CHECK SHEET FOR
FAN COIL UNIT
Sheet No
SUBCONTRACTOR:
SERIAL NO : DATE :
LOCATION : COMMISSIONED ON :
THE ABOVE POINTS HAVE BEEN CHECKED AND FOUND TO COMPLY WITH CONTRACT SPECIFICATIONS
Trang 41 Check cleanliness.
2 Open all VCDs
3 Check free impeller rotation
4 Check pulley alignment/bearing
5 Differential pressure switches are installed
EQUIPMENT NO : SEQUENCE NO :
COMMISSIONING CHECK SHEET FOR
EXTRACT FANS
Sheet No
SUBCONTRACTOR:
SERIAL NO : DATE :
LOCATION : COMMISSIONED ON :
Trang 51 Roof tanks are installed.
2 Float ball valves are installed
3 Pressure switch is fixed
4 Filtered water tank is filled up
5 Electrical connections are tight
6 Supply voltage and motor rating
7 Free rotation of pump impeller
8 Pump and motors are clean
9 Overload setting and fuse rating checked
10 Pump motor alignment
11 Pipe line pressure tested
12 Mounting arrangement for proper floating on
vibration isolating on vibration isolating springs
13 Control wiring is properly done
EQUIPMENT NO : SEQUENCE NO :
COMMISSIONING CHECK SHEET FOR
COLD WATER TRANSFER PUMP SETS
Sheet No
SUBCONTRACTOR:
SERIAL NO : DATE :
LOCATION : COMMISSIONED ON :
Trang 61 Cold water line pressure tested.
2 Low level cut out switch installed
3 Pump motor alignment
4 Mounting arrangement for proper operation on
vibration isolating springs
5 Supply voltage and motor rating
6 Electrical connections are tight
7 Overload setting and fuse rating checked
8 Free rotation of pump impeller
9 Pressure vessel is properly charged
10 Control wiring is properly done
EQUIPMENT NO : SEQUENCE NO :
COMMISSIONING CHECK SHEET FOR
COLD WATER BOOSTER PUMP
Sheet No
SUBCONTRACTOR:
SERIAL NO : DATE :
LOCATION : COMMISSIONED ON :
Trang 71 Pipe line pressure tested.
2 AVVs are installed
3 Pressure gauges are installed
4 Pump motor alignment
5 Mounting arrangement for proper floating on
vibration isolating on vibration isolating springs
6 Pump set motors are clean
7 Supply voltage and motor rating
8 Overload setting and fuse rating
9 Tightness of electrical connections
10 Free rotation of pump impeller
11 Calorifer vent line connected
12 Control wiring is properly done
EQUIPMENT NO : SEQUENCE NO :
COMMISSIONING CHECK SHEET FOR
SUMP PUMP
Sheet No
SUBCONTRACTOR:
SERIAL NO : DATE :
LOCATION : COMMISSIONED ON :
Trang 81 Pipe line tested.
2 AVVs are installed
3 Supply voltage matches with motor rating
4 Tightness of electrical connections
5 Control wiring is properly done
6 Mounting arrangement for proper operation on
vibration isolating springs
7 Pump motor alignment
8 Pressure vessel properly charged
9 By pass line to tank provided
10 Raw water tank filled up
11 Non return valve installed
12 Overload setting and fuse rating
EQUIPMENT NO : SEQUENCE NO :
COMMISSIONING CHECK SHEET FOR
SPRINKLER + WET BOOSTER SET
Sheet No.
SUBCONTRACTOR:
SERIAL NO : DATE :
LOCATION : COMMISSIONED ON :
Trang 91 Clean all air intake areas, air conditioned areas.
2 Clean all AHUs, FCUs and fans
3 Open all outlets
4 Seal all unwanted openings in air path
5 Check for free rotation of impeller
6 Set overload protection correctly
7 Check for tightness of electrical connections
8 Ensure installation of filters in all units
9 Clean filters
10 Check belt tension and lubrication
11 Start fans
12 Balance air as per design
EQUIPMENT NO : SEQUENCE NO :
COMMISSIONING CHECK SHEET FOR
AIR DISTRIBUTION SYSTEM
Sheet No.
SUBCONTRACTOR:
SERIAL NO : DATE :
LOCATION : COMMISSIONED ON :
Trang 101 Avoid line air lock.
2 Provide air vents at top points
3 Remove spades from flanges
4 Mark distribution of flow and return on pipes
5 Open all isolating valves after flushing with water
6 Check for free rotation of pump impeller
7 Check starter overload setting and electrical connections
are tight
8 Start pumps
9 Check current, priming of pump motor
10 Check head developed by pump
11 Circulate water through all equipment for four hours and
flush the system
12 Clean strainers
13 Repeat above until clear water is observed
14 Check that water reaches all equipment
15 Balance water flow through equipment and in branches
EQUIPMENT NO : SEQUENCE NO :
COMMISSIONING CHECK SHEET FOR CHILLED WATER DISTRIBUTION SYSTEM
Sheet No.
SUBCONTRACTOR:
SERIAL NO : DATE :
LOCATION : COMMISSIONED ON :
Trang 111 PHYSICAL CHECKS
a Check the earth electrodes in earth pits for proper
installation and connection
b Check the protective conductors from the earth
installation and connection
2 EARTH ELECTRODE RESISTANCE
a Remove the conductor connection from the electrodes
b Measure earth electrode resistance by using an earth
meggar
c Repeat (1) and (2) above for all pits and tabulate readings.
3 CONTINUITY TEST
a Check proper earth bonding by checking continuity of
protective conductor by a D.C ohm meter
b The above to be checked for all protective conductors to
various equipment
c Check continuity resistance between the main earth
terminal of the MDB/DB and the farthest equipment by a
EQUIPMENT NO : SEQUENCE NO :
COMMISSIONING CHECK SHEET FOR EARTHING AND EARTH BONDING
Sheet No.
SUBCONTRACTOR:
SERIAL NO : DATE :
LOCATION : COMMISSIONED ON :
Trang 121 VISUAL CHECKS
a
Check installation of all the components like decks, tuner
amplifier, microphone, speakers, cassettes and power
supply units
b Check cable laying and connection
2 FUNCTIONAL TEST
a Put the system as per manufacturer’s recommendation
b Check performance of the system for its configuration
c Tabulate observation
EQUIPMENT NO : SEQUENCE NO :
COMMISSIONING CHECK SHEET FOR MUSIC AND PUBLIC ADDRESS SYSTEM
Sheet No.
SUBCONTRACTOR:
SERIAL NO : DATE :
LOCATION : COMMISSIONED ON :
Trang 131 VISUAL CHECKS
a Check the components such as antenna mast, amplifier, splitter, power supply etc.
b Check cable installation and connections
2 MEASUREMENT OF SIGNAL LEVELS
a
Put the system into operation as per manufacturer’s
recommendations
b Adjust antennas and amplifier to receive the required signal level at the amplifiers output terminal.
c Measure signal level for the various channels specified
d With the signal monitor see trail pictures of different channels at the amplifier output with amplifier gain
adjusted for clarify
e With a signal monitor check signal levels and picture clarify at the points.
f Tabulate signal levels
EQUIPMENT NO : SEQUENCE NO :
COMMISSIONING CHECK SHEET FOR
MATV SYSTEM
Sheet No.
SUBCONTRACTOR:
SERIAL NO : DATE :
LOCATION : COMMISSIONED ON :
Trang 141 VISUAL CHECKS
a Check installation of all cameras, switches, monitors for
proper support and connection
b Check all cables for proper installation
a Put the system into operation as per manufacturer’s
recommendations
b Check performance of the system for its configuration
c Tabulate observations
EQUIPMENT NO : SEQUENCE NO :
COMMISSIONING CHECK SHEET FOR
CCTV SURVEILLANCE
Sheet No.
SUBCONTRACTOR:
SERIAL NO : DATE :
LOCATION : COMMISSIONED ON :
Trang 151 VISUAL CHECKS
a Check installation of MICC cables for proper laying
termination, clipping, labelling, identification, etc
b Check cable connection to the FACP, battery, repeater
panel
2 INSULATION RESISTANCE TEST
a Check insulation resistance between cores with a 500V
meggar
b Tabulate readings
3(A) Fire Alarm
a Put the system into operation as per manufacturer’s
recommendation
b Simulate fire conditions by generating smoke/heat to
activate the detectors
c Check display of detector number
d Check operation of LED on the detector
e Check display on mimic panel
Check sounder circuits and bells
EQUIPMENT NO : SEQUENCE NO :
COMMISSIONING CHECK SHEET FOR
FIRE ALARM SYSTEM
Sheet No.
SUBCONTRACTOR:
SERIAL NO : DATE :
LOCATION : COMMISSIONED ON :
Trang 161 PHYSICAL CHECKS
The cable installation has to checked for:
a Proper laying and dressing
b Cable tying
c Cable tray supports
d Cable identification and labelling
e Termination
f Damage
2 INSULATION RESISTANCE TEST
a Measure insulation resistance between cores of all cable
with 500V meggar and tabulate readings
b Measure insulation resistance between cores and ECC and
earth terminal with a 500V meggar and tabulate
readingsOnce the valves are found to be satisfactory, the
breakers may be switched on and the following tests may
be carried out
3 PHASE ROTATION TEST
a Check phase rotation at all points
b Phase rotation at all points should be same or rectify
a Switch on all isolators and run all equipment
b Check for any unusual temperature rise in cables,
EQUIPMENT NO : SEQUENCE NO :
COMMISSIONING CHECK SHEET FOR POWER AND CONTROL CABLES
Sheet No.
SUBCONTRACTOR:
SERIAL NO : DATE :
LOCATION : COMMISSIONED ON :
Trang 171 PHYSICAL CHECKS
a
Check all MCCs to ensure that all components of correct
ratings have been installed against the approved shop
drawings
b Check that all components are wired correctly and neatly
c Check that all the components are labelled and identified
d Check that all meters and selector switches are correctly
selected
e Check that all nuts and bolts as well as the busbar
connections are tight
f Check that all components and related connections are
earthed
2 INSULATION RESISTANCE TEST
a Disconnect all lamps and meters, which are not supposed
to be subjected to 500V
b Measuring insulation resistance between phases, neutral
and earth with a 500V meggar
c Tabulate readings
3 FUNCTIONAL TEST
a Check the control circuit of each starter/system for its
correct operation in regard to switching on, thermal over
b Check switching on and off all breakers, contractors and
relays for their desired operation
c Check operation all indicating lamps and meters
d Keep all connected equipment running for sufficient time
and check for any abnormal rise in temperature on busbars,
a Set sensitivity currents of RCCBs at
0.5
1
1.5
of the sensitivity currents
b Record trip times and compare with the characteristic
EQUIPMENT NO : SEQUENCE NO :
COMMISSIONING CHECK SHEET FOR MOTOR CONTROL CENTRE
Sheet No.
SUBCONTRACTOR:
SERIAL NO : DATE :
LOCATION : COMMISSIONED ON :
Trang 181 PHYSICAL CHECKS
a Check all MCCs to ensure that all components of correct
ratings have been installed against the approved shop
drawings
b Check that all components are wired correctly and neatly
c Check that all the components are labelled and identified
d Check that all meters and selector switches are correctly
selected
e Check that all nuts and bolts as well as the busbar
connections are tight
f Check that all components and related connections are
earthed
2 INSULATION RESISTANCE TEST
a Disconnect all lamps and meters, which are not supposed
to be subjected to 500V
b Measuring insulation resistance between phases, neutral
and earth with a 500V meggar
c Tabulate readings
3 FUNCTIONAL TEST
a Check ON/OFF/Trip functions of all MCCBs
b Check operation of indication lamps and meters
4 EARTH LEAKAGE PROTECTION
4(A) ELCB Test
a Set sensitivity currents of RCCBs at
0.5
1
1.5
of the sensitivity currents
b Record trip times and compare with RCCB tester and
compare with ELCB the characteristics values
4(B) ELS Test
a Set sensitivity currents of ELCBs at
0.5
1
1.5
of the rated sensitivity current by external means (RCCB
tester may be used)
b Record trip times and compare with EL relay
EQUIPMENT NO : SEQUENCE NO :
COMMISSIONING CHECK SHEET FOR MAIN DISTRIBUTION BOARDS AND SUB MAIN DISTRIBUTION
BOARDS
Sheet No.
SUBCONTRACTOR:
SERIAL NO : DATE :
LOCATION : COMMISSIONED ON :
Trang 191 PHYSICAL CHECKS
a Check all electrical components (equipment such as
conduits, wires, trunking, switches, socket, outlets etc.)
connected to final circuits for the protection and damage
b Check the installation of the DBs
c Check internal wiring for strong connection identification,
labelling etc
d Check that all metallic components are earthed/bonded
a Check that all single pole switches are installed in the live
conductor
3 CONTINUITY OF PROTECTIVE CONDUCTORS
a For all final circuits check continuity of the protective
conductor from the furthest point to the main earth
terminal of the DB by a DC ohm meter
b Repeat (3a.) above for all ring final circuit conductors
c Tabulate the readings
4 INSULATION RESISTANCE TEST
a This test is preferably carried out before the light fittings
or current using equipment are installed
b Measure insulation resistance between phase,
neutral and earth by a 500V meggar
EQUIPMENT NO : SEQUENCE NO :
COMMISSIONING CHECK SHEET FOR FINAL CIRCUITS AND DISTRIBUTION BOARDS
Sheet No.
SUBCONTRACTOR:
SERIAL NO : DATE :
LOCATION : COMMISSIONED ON :