1 1 Comments: MEKONG WIND POWER JOINT STOCK COMPANY BINH DAI WIND POWER PLANT PROJECT BETWEEN OWNER: MEKONG WIND POWER JOINT STOCK COMPANY CONTRACTOR: POWERCHINA HDEC- INTL CO
Trang 11
1
Comments:
MEKONG WIND POWER JOINT STOCK COMPANY
BINH DAI WIND POWER PLANT PROJECT
BETWEEN
OWNER:
MEKONG WIND POWER JOINT STOCK COMPANY
CONTRACTOR:
POWERCHINA HDEC- INTL CONSORTIUM
Trang 2INSPECTION AND TESTING FOR MASONRY AND PLASTERING
WORK
GMKW-001-QC99-ITP-PC-0009
GMKW-001-QC99-ITP-PC-0009
2
BINH DAI WIND POWER PLANT
PROJECT
INSPECTION AND TESTING PLAN FOR MASONRY AND PLASTERING
WORK GMKW-001-QC99-ITP-PC-0009
MEKONG WIND POWER JOINT STOCK
COMPANY
Project Manager: Mr Thaweesak Boonyong
POWERCHINA HDEC- INTL
CONSORTIUM
Project Manager: Mr Lu Jianhua
Trang 3INSPECTION AND TESTING FOR MASONRY AND PLASTERING
WORK
GMKW-001-QC99-ITP-PC-0009
GMKW-001-QC99-ITP-PC-0009
3
CONTENTS
1 SCOPE OF WORK
2 REFERENCE DOCUMENTS
3 INSPECTION NOTIFICATION
4 INSPECTION SCHEDULE
5 QUANLITY CONTROL FORM
Trang 4INSPECTION AND TESTING FOR MASONRY AND PLASTERING
WORK
GMKW-001-QC99-ITP-PC-0009
GMKW-001-QC99-ITP-PC-0009
4
1 SCOPE OF WORK
This Inspection and Test Plan (ITP) is a typical plan Masonry and Plastering work of Binh Dai Wind Power Plant Project
2 REFERENCE DOCUMENTS:
GMK1-001-PM02-ENR-PC-0005 Technical Design Report - Volume 5-Technical Specifictions Of Substation
Standards:
TCVN 7711-2013: Sulfate resistant blended portland cements
TCVN 6260-2009: Portland blended cement - Specifications
TCVN 9346:2012: Concrete and reinforced concrete structures - Requirementd of protection from corrosion in marine environment
TCVN 7570-2006: Aggregates for concrete and mortar - Specifications
TCVN 4506:2012: Water for concrete and mortar - Technical speccification
TCVN 6477:2016: Concrete bricks
ASTM C290: Standard specification for mortar and unit masonry
3 INSPECTION NOTIFICATION
3.1 The inspection notification shall be made 24 hours in advance in the daily communication between the EPC Contractor and Sub- contractor as per Inspection and Test Plan The Owner shall be given 24 hours notice of all witness point and hold point inspections
3.2 The interface points to be included in this ITP are as follows:
R: Review Point - Denotes the responsibility for review of relevant documents instead of inspection/witness
W: Witness Point - Denotes the responsibility for witnessing and signing for the
work Formal notification must be given to the interested parties in a timely manner This would generally be 24 hour for site activities Attendance by interested parties is mandatory but, on a case-by-case basis, the witness activity may be waived Intention to waive must be by written instruction (email acceptable) The Subcontractor must document the inspection and endorse the record before moving on to the next step
H: Hold Point - Denotes the responsibility for witnessing and signing work to
release Hold Points in the work process Attendance by interested parties is mandatory Work may NOT proceed beyond Hold Points without witness and
Trang 5INSPECTION AND TESTING FOR MASONRY AND PLASTERING
WORK
GMKW-001-QC99-ITP-PC-0009
GMKW-001-QC99-ITP-PC-0009
5
sign off by the identified participants Generally, the formal notification for Hold Point witness will be delivered with at least 24 hour in advance for site activities to ensure availability of interested parties
Trang 6INSPECTION AND TESTING FOR MASONRY AND PLASTERING
WORK
GMKW-001-QC99-ITP-PC-0009
GMKW-001-QC99-ITP-PC-0009
6
4 INSPECTION SCHEDULE
Trang 7EPC Package: Engineering, Procurement and Construction Work For Binh Dai Wind Power Plant Project Owner's Engineer: UL VS (Vietnam) Co.,Ltd.
Contractor : POWERCHINA HDEC- INTL Consortium
Rev No : A Issued Date : 24-Oct-20
Subcontractor EPC contractor Owner/Owner's
Engineer
Compression strength/ Cường độ nén
- 3 Days/ 3 ngày;
- 28 Days/ 28 ngày
Setting time + Initial set + Final set
Thời gian đông kết + Thời gian bắt đầu đông kết + Thời gian kết thúc đông kết
TCVN 6017 : 2015 Min = 45 Minutes
Fineness + The rest on sieve with 0.09 size + Specific surface - Blaine method
Độ mịn + Phần còn lại trên sàn kích thước lỗ 0.09mm + Bề mặt riêng - phương pháp Blaine
TCVN 4030 : 2003 ≤ 10%
Soundness
SO3 Content
Autoclave Expansion
Sulfate Resistance
Particle size distribution
Thành phần hạt TCVN 7572-2 : 2006 Following table 1 TCVN 7570-2006Theo bảng 1 TCVN 7570-2006 H H R/W Content of dust, mud and clay
Content of Cl
Alkali silica reactivity
Khả năng phản ứng với kiềm Silic TCVN 7572-14 : 2006 Does not cause alkali-silicon reactionKhông gây phản ứng kiềm silic H H R/W
Particle size distribution
Thành phần hạt TCVN 7572-2 : 2006
Following table 4 TCVN 7570-2006
Content of dust, mud and clay
Resistance to degradation of coasre aggregate by abration and impact in the Los Angeles machine
Độ hao mòn khi va đạp của cốt liệu lớn thí nghiệm trong máy Los Angeles
Elongation and flakiness index of coarse aggregate
Alkali silica reactivity
Khả năng phản ứng với kiềm Silic TCVN 7572-14 : 2006 Does not cause alkali-silicon reactionKhông gây phản ứng kiềm silic H H R/W
Determation of oil scum or grease
Xác định váng dầu mỡ và màu nước
TCVN 4506-2012 and Visual check
TCVN 4506-2012 và bằng mắt
Does not contain oil scum or grease
The amount of organic impurities
PH
Total determined soluble salt content
Residue content
Ion Sunfat Content
Ion clorua Content
Minimum thickness of concrete block edge or webs
Chiều dày thành ở vị trí nhỏ nhất
TCVN 6477-2016 and measurement
TCVN 6477-2016 và thước đo ≥ 20mm
Note
Lưu ý
1 Cement (PCB40_MS)Xi măng
TCVN 7711-2013 TCVN 6260:2009 TCVN 9346-2012
1 set/ Lot or 1 set/ every delivery (1 set = 3 specimens)
1 tổ/ Lô hoặc 1 tổ/ lần giao hàng (1 tổ = 3 mẫu)
Laboratory
Phòng thí nghiệm
2 Fine Aggregates
Cốt liệu mịn
TCVN 7570-2006
ITP No : GMKW-001-QC99-ITP-PC-009
INSPECTION AND TESTING PLAN FOR MORTAR WORKS
No. Job DescriptionMô tả công việc Tiêu chí kiểm traTesting Criteria Reference DocumentTài liệu tham khảo Method, InstrumentationBiện pháp, dụng cụ đo đạt Technical RequirementYêu cầu kĩ thuật FrequencyTần suất Testing PositionVị trí kiểm tra
Responsibility
Laboratory
Phòng thí nghiệm
1 set/ 350m3 or 1 set/ 500 Ton (1 set = 3 specimens)
1 tổ/ 350m3 hoặc 1 tổ/ 500 tấn (1 tổ = 3 mẫu)
3 Coarse Aggregates
Cốt liệu thô
TCVN 7570-2006
1 set/ 350m3 or 1 set/ 500 Ton (1 set = 3 specimens)
1 tổ/ 350m3 hoặc 1 tổ/ 500 tấn (1 tổ = 3 mẫu)
Laboratory
Phòng thí nghiệm
4 Water
Nước
TCVN 4506-2012
1 set/ Resourse/ 6 months (1 set = specimens)
1 tổ/ Nguồn/ 6 tháng (1 tổ = 2 mẫu)
Laboratory
Phòng thí nghiệm
Trang 8
Subcontractor EPC contractor Owner/Owner's
Engineer Lưu ý
No. Mô tả công việc Tiêu chí kiểm tra Tài liệu tham khảo Biện pháp, dụng cụ đo đạt Yêu cầu kĩ thuật Tần suất Vị trí kiểm tra
minimum compressive strength
Cường độ nén nhỏ nhất TCVN 6477-2016 table 3
Minimum average of 3 units ≥ 7.5Mpa and individual units ≥ 6.7 Mpa
Trung bình cho 3 mẫu thử ≥ 7.5Mpa
và cho một mẫu thử ≥ 6.7Mpa
Water absorption
Weight class
Curvature on the brick surface
The crack are (5-10)mm deep, (10-15)mm length
số vết nứt ở góc cạnh sâu (5-10)mm, dài (10-15)mm
TCVN 6477-2016 table 2 ≤ 2
The crack length ≤ 20 mm
Số vết nứt có chiều dài ≤ 20 mm TCVN 6477-2016 table 2 ≤ 1 Hollowness of block
Minimum compressive strength
Mixing time
Mortar after mixing time
Flow of hydraulic
Maximum air content
LEGEND: R - Review Point
H - Hold Point
W - Witness Point
5 Concrete masonry BlockGạch bê tông TCVN 6477-2016
1 set/Batch (10000 bricks)
1 tổ/ lô (10.000 viên gạch) ( 1 set= 10 bricks) (1 tổ = 10 viên gạch)
6 Mortar (for masonry and plastering)
Vữa ( cho xây và tô) ASTM C270 Prior to start masonry work Phòng thí nghiệmLaboratory
Laboratory
Phòng thí nghiệm
Trang 9INSPECTION AND TESTING FOR MASONRY AND PLASTERING
WORK
GMKW-001-QC99-ITP-PC-0009
GMKW-001-QC99-ITP-PC-0009
7
5 QUALITY CONTROL FORM
Trang 10
BINH DAI WIND POWER PLANT PROJECT EPC PACKAGE FOR ENGINEERING, PROCUREMENT AND CONSTRUCTION WORK
REQUEST FOR INSPECTION
EPC Contractor : POWERCHINA HDEC- INTL CONSORTIUM ITP No: ……….
CONTRACTOR'S REQUEST:
THE FOLLOWING WORKS ARE/WILL BE READY FOR INSPECTION
TCVN 9360:2012 – Quy trình kỹ thuật xác định độ lún công trình dân dụng và công nghiệp bằng phương pháp đo cao hình học
Kế hoạch kiểm tra và nghiệm thu được phê duyệt: Quan trắc lún tại trạm biến áp:GMKW-001-QC03-ITP-PC-0009
COMMENT OF OWNER’S ENGINEER /Ý KI ẾN CỦA ĐƠN VỊ TƯ VẤN
Requested By Contractor/ Yêu cầu bởi Nhà thầu POWERCHINA HDEC- INTL CONSORTIUM
Notified By Owner's Engineer/ Nhận bởi tư vấn Chủ đầu tư
UL VS (Vietnam) Co.,Ltd
Note: This request must be submitted 24 hours before the inspection time for in-site, and 3 days in advance for off-site The Contractor must submit method statement & detailed drawings and relevant documents for inspection.
Ghi chú: Yêu cầu nghiệm thu phải được đệ trình 24 tiếng trước giờ nghiệm thu cho trong công trường, và trước 3 ngày cho ngoài công trường Trước khi nghiệm thu, Nhà thầu phải đệ trình biện pháp thi công và bản vẽ chi tiết có liên quan đến nghiệm thu công việc.
Trang 11BINH DAI WIND POWER PLANT PROJECT EPC PACKAGE FOR ENGINEERING, PROCUREMENT AND CONSTRUCTION WORK
INPUT MATERIAL INSPECTION REPORT
Report No:………
Item/Location/ H ạng mục/Vị trí:………
Description of inspection/mô t ả công việc nghiệm thu: ………
Time and location of Inspection/th ời gian địa điểm nghiệm thu: Start time/ th ời gian bắt đầu:……… Finish time/thời gian kết thúc:………
Location/địa điểm: ………
Based document for acceptance/ các căn cứ nghiệm thu: + RFI no/ phi ếu yêu cầu nghiệm thu số:
+ ITP no/K ế hoạch nghiệm thu số:
+ Approved construction Drawing/ B ản vẽ thi công được phê duyệt:
+ Manufactory profile/ h ồ sơ nhà sản xuất:
+ Measurement and test result report (if any)/K ết quả đo đạc, thí nghiệm:
No STT Material Description/ Mô t ả vật tư (Follow inspection schedule of ITP) Symbol/Ký hiệu Unit/đơn vị Quantity/Kh lượng ối Delivery no/ Phiếu nhận Certificate’s Material (CO,CQ)/ Chứng chỉ Remark/Ghi chú Remarks and other opinions/ nh ận xét và các ý kiến khác:
Enclosed/Đính kèm:
Conclusion/K ết luận: □ Accept the construction activity, agree to carry out the next construction works/Chấp nhận nghiệm thu, đồng ý triển khai công vi ệc tiếp theo □ Not accept the construction activity/ không chấp nhận nghiệm thu. Owner's Engineer Tư vấn chủ đầu tư UL VS (Vietnam) Co.,Ltd EPC contractor T ổng thầu POWERCHINA HDEC- INTL CONSORTIUM Liên danh Powerchina HDEC - INTL Subcontractor Nhà th ầu phụ Hoa Thanh Trading and Production Co.Ltd Công ty TNHH Thương mại và sản xuất Hòa Thành Position/Ch ức vụ:……… Position/Ch ức vụ:……… Position/Ch ức vụ:………
Trang 12BINH DAI WIND POWER PLANT PROJECT EPC PACKAGE FOR ENGINEERING, PROCUREMENT AND CONSTRUCTION WORK
MASONRY WORK INSPECTION REPORT
Report No:………
Item/Location/ H ạng mục/Vị trí:………
Description of inspection/mô t ả công việc nghiệm thu: ………
Time and location of Inspection/thời gian địa điểm nghiệm thu: Start time/ thời gian bắt đầu:……… Finish time/thời gian kết thúc:………
Location/địa điểm: ………
Based document for acceptance/ các căn cứ nghiệm thu: + RFI no/ phi ếu yêu cầu nghiệm thu số:
+ ITP no/K ế hoạch nghiệm thu số:
+ Approved construction Drawing/ B ản vẽ thi công được phê duyệt:
+ Approved method of statement/Bi ện pháp thi công được phê duyệt:
+ Measurement and test result report (if any)/K ết quả đo đạc, thí nghiệm:
No/ TT Description/ N ội dung kiểm tra (Follow to inspection schedule of ITP) Result/K ết quả Remark/Ghi chú Accept/Đạt Not Accept/ Không đạt 1 Compressive strength of mortar Masonry / Cường độ nén vữa xây 2 Survey of Blockwork, size of openings for doors, windows, cabinets (distance, dimensions)/ Định vị công tác xây, kích thước khe h ở cho cửa đi , cửa sổ, tủ (khoảng cách, kích thước) 3 Mortar Mixing ratio to be followed approval designed proportion/ T ỉ lệ trộn vữa phải tuân theo tỉ lệ thiết kế được duyệt 4 Washed sand to be used/ R ửa sạch cát trước khi sử dụng 5 Filling mortar on horizontal & vertical face shells/ V ữa theo phương ngang và phương dọc phải đầy 6 Reinforcement, ties & expanded metal strip shall be fixed/ C ốt thép, thép buộc phải được cố định 7 Block alignment (vertical and horizontal)/ Căn chỉnh khối xây (theo phương ngang và dọc) 8 Bitumn/ Nhũ tương 9 Scaffolding, safety handrail / giàn giáo, lan can an toàn… 10 Curing: Start date: Finish date: Remarks and other opinions/ nh ận xét và các ý kiến khác:
Enclosed/Đính kèm:
Conclusion/K ết luận: □ Accept the construction activity, agree to carry out the next construction works/Chấp nhận nghiệm thu, đồng ý triển khai công vi ệc tiếp theo □ Not accept the construction activity/ không chấp nhận nghiệm thu. Owner's Engineer Tư vấn chủ đầu tư UL VS (Vietnam) Co.,Ltd EPC contractor T ổng thầu POWERCHINA HDEC- INTL CONSORTIUM Liên danh Powerchina HDEC - INTL Subcontractor Nhà th ầu phụ Hoa Thanh Trading and Production Co.Ltd Công ty TNHH Thương mại và sản xuất Hòa Thành Position/Ch ức vụ:……… Position/Ch ức vụ:……… Position/Ch ức vụ:………
Trang 13BINH DAI WIND POWER PLANT PROJECT EPC PACKAGE FOR ENGINEERING, PROCUREMENT AND CONSTRUCTION WORK
PLASTERING WORK INSPECTION REPORT
Report No:………
Item/Location/ Hạng mục/Vị trí:………
Description of inspection/mô t ả công việc nghiệm thu: ………
Time and location of Inspection/th ời gian địa điểm nghiệm thu: Start time/ th ời gian bắt đầu:……… Finish time/thời gian kết thúc:………
Location/địa điểm: ………
Based document for acceptance/ các căn cứ nghiệm thu: + RFI no/ phi ếu yêu cầu nghiệm thu số:
+ ITP no/K ế hoạch nghiệm thu số:
+ Approved construction Drawing/ B ản vẽ thi công được phê duyệt:
+ Approved method of statement/Bi ện pháp thi công được phê duyệt:
+ Measurement and test result report (if any)/K ết quả đo đạc, thí nghiệm:
No/ TT Description/ N ội dung kiểm tra (Follow to inspection schedule of ITP) Result/K ết quả Remark/Ghi chú Accept/Đạt Not Accept/ Không đạt 1 Survey work: Benchmark making/Công việc định vị: lập điểm chuẩn 2 Surface cleaned off all mould oil, dust and loose particles/ Làm sạch bề măt dầu, bụi, các hạt rời 3 Mortar Mixing ratio to be followed approval designed proportion/ T ỉ lệ trộn vữa phải tuân theo tỉ lệ thiết kế được duyệt 4 Washed sand to be used/ R ửa sạch cát để sử dụng 5 Check all mechanical & electrical services, conduits, pile and fixtures have been installed/ Kiểm tra tất cả các thiết bị cơ và điện, dụng cụ, ống đã được lắp đặt 6 Steel wire mesh/Lưới thép 7 Plaster thickness/Độ dày lớp trát 8 Surface finish coat check( smooth, waviness, irregularities, straight level or plumb angles)/Kiểm tra lớp sơn hoàn thiện bề mặt( độ mịn, độ sần sùi, góc thẳng, góc dọi) 9 Density of mortar layer/ Tỷ trọng của lớp vữa 10 Scaffolding, safety handrail / giàn giáo, lan can an toàn… 11 Curing/ bảo dưỡng: Start date/ ngày bắt đầu: Finish date/ ngày kết thúc: Remarks and other opinions/ nh ận xét và các ý kiến khác:
Enclosed/Đính kèm:
Conclusion/K ết luận: □ Accept the construction activity, agree to carry out the next construction works/Chấp nhận nghiệm thu, đồng ý triển khai công vi ệc tiếp theo □ Not accept the construction activity/ không chấp nhận nghiệm thu. Owner's Engineer Tư vấn chủ đầu tư UL VS (Vietnam) Co.,Ltd EPC contractor T ổng thầu POWERCHINA HDEC- INTL CONSORTIUM Liên danh Powerchina HDEC - INTL Subcontractor Nhà th ầu phụ Hoa Thanh Trading and Production Co.Ltd Công ty TNHH Thương mại và sản xuất Hòa Thành Position/Ch ức vụ:……… Position/Ch ức vụ:……… Position/Ch ức vụ:………