Management issues in mth vietnam – bac giang bac giangdrainage and sanitation project Content 1.. INDIVIDUAL ASSIGNMENTStudent: Nguyen Thi Phuong Thao Class: EMBA7C Bac Giang drainage
Trang 1Management issues in mth vietnam – bac giang bac giang
drainage and sanitation project
Content
1 INTRODUCTION 1
2 DESCIPTION OF THE COMPANY 1
2.1 Background Information 1
2.2 Business Strategy 2
2.3 Environmental Factors Affecting the Company 3
3 INDENTIFICATION AND DISCUSSION OF CURRENT MANAGEMENT PRACTICES AND ISSUES: 5
3.1 Management Practices 5
3.2 Management issues 7
4 ANALYSIS AND ACCESSMENT 8
4.1 Positive sides in MTH management approaches: 8
4.2 Negative sides in MTH management approaches 9
5 RECOMMENDATIONS 10
6 REFENRENCES 11
Trang 2INDIVIDUAL ASSIGNMENT
Student: Nguyen Thi Phuong Thao
Class: EMBA7C
Bac Giang drainage and sanitation project
in - MTHojgaard Vietnam company
1 INTRODUCTION
1
Trang 3- Selected company: MTHoigaard Vietnam – Bac
Giang Drainage and sanitation Project MTH is one of
the biggest construction company in Scandinavian
countries
- Name of the manager interviewed: Søren Rib
VaalakldjfCer Carlsen
- Title: Project Manager; South East Asia Manager
Trang 4- Purpose of the assignment: By analyzing management issues of a real company, this assignment is to help the students and readers:
To get to know about the functional processes of management
To understand the environmental factors that affect the implementation of the project and how to deal with those factors in order to improve the efficiency of studied project
To apply the lesson learnt from the assignment to real cases
Description of the Company
2 DESCIPTION OF THE COMPANY
2.1 Background Information
MT Højgaard (MTH) is an Denmark building and construction company, which was established
in 1918 This company has left its mark on a multitude of building projects in Denmark and abroad
Bac Giang Drainage and sanitation Project has the building period of 2007-2009 with the investment capital of 22 million USD
This project is to carry out a wastewater treatment plant and a drainage system in Bac Giang city The existing drainage system is to be renovated and extended to service seven wards in the city Number of Employees in Bac Giang Project: 42 staffs (excluding the workers of Sub-contractors)
2.2 Business Strategy
MTH aims to be Denmark’s leading building and construction company The company maintains and develops this position by being the best in key areas This applies to its professional competences and its development of existing and new forms of collaboration – both those that are directly targeted to its clients and those regarding optimization of its building processes
Trang 5MTH creates space for people’s activities and achieve building and construction visions by systematizing and combining knowledge and craftsmanship The company acts according to its
six values: Customer-minded; Value-adding; Innovative; Trustworthy; Good employer and Sound financial base.
o Refurbishing and expanding the sewer system; building a new purification treatment plant in the scheduled time with highest quality at provided capital
o Solving the existing flooding problem and the increasing environmental pollution caused by both domestic and industrial wastewater for better health and better opportunities for economic growth
o Creating jobs for local engineers and construction workers
o Strengthening the diplomatic relationship between Denmark and Vietnam
2.3 Environmental Factors Affecting the Company
In the project, a total of 40 km of pipes with dimensions varying from 300 mm to 2000 mm are to be laid within Bac Giang city Most of the pipes go through areas that people are living, working and doing business Before laying the pipes, workers must dig and excavate the pavement in front of inhabitants’ houses or shops, which cause difficulties for them to travel or
to sell the goods Some people prevent MTH staff from continuing the project and MTH representative have to explain the huge benefit for the city after the project is finished When the citizens understand clearly about the purpose, they are willing to create good conditions for the
Trang 6company to carry out the construction In this case, it is obvious that the management of relationship to the outsider play an important role in the success of the project
MTH is a foreign contractor and Bac Giang is the very first project that this company carries out in Vietnam The company has not understood deeply about Vietnamese construction law and the habit of doing business of Vietnamese subcontractors Moreover, there are also differences between Vietnamese and international law in related issues Therefore, sometimes, MTH face problems in applying the law to manage the project, which lead to difficulties in inspection and arrange payment among main contractor and subcontractor
MTH implement drainage and sanitary project over the period that the international and Vietnamese economy is facing with finance crisis The effect of this chaos is:
- Firstly, materials price increase remarkably in comparison with the time when the contract was signed and cost estimation was generated The company has to re-calculate the expenses and make some corrective items in order to prevent the project from the loss
- Secondly, it is more difficult to mobilize and transfer more capital for the project because parent company in Denmark also has to deal with the shortage of capital to overcome the hard time in crisis
Due to this fact, MTH Vietnam has to tighten the expenditure and re-allocate some costs as well
as to cut down a few unnecessary items
By implementing this project sponsored by loan from Danish government, the relationship between Vietnam and Denmark is strengthened Leaders of Bac Giang People Committee promise to make the most convenient conditions for the company to finish the project on time They help to persuade citizens to follow the contractor’s instructions and plan
Trang 7However, there are quite many parts participate in to the project:
- Vietnamese side includes Project Management Unit (representing Investor), Consultant (responsible for supervising the project) and sub contractors (responsible for carrying out each construction item)
- Danish side: MTH
In some case, this fact may make the procedure slow down Subcontractors are working under a number of supervisors Decision making process going through multi-level system will be less effective
The advantage for MTH Vietnam in the project is that it can acquire the advanced technology
in wastewater treatment and building water drainage system Fifty percent of the pipes are High Density Polyethylene (HDPE) and the other fifty percent is concrete pipes, which are very durable and long-lasting The company also applies really new methods in building the wastewater treatment plant
In short, there are 5 main environmental factors which have both positive and negative effects on the project The company should recognize all of those factors and find out the right approaches
to deal with problems it faces
3 INDENTIFICATION AND DISCUSSION OF CURRENT MANAGEMENT
PRACTICES AND ISSUES:
3.1 Management Practices
In general, the organizational structure of MTH company is not much different from a normal organization Leading the project is the Project manager – Mr Søren Rib VaalakldjfCer Carlsen, who is supported by a Deputy manager – Mr Micheal Kolbe The company is divided into some functional Departments:
+ Sewer Department
Trang 8+ Pipe-line department
+ Wastewater pumping stations & Wastewater treatment Plants
+ Quality Assurance
+ Admin and Coordinators
Each department has a manager who reports to project manager or deputy project manger
The management of the company including the 4 issues: planning, organizing, leading and controlling is as followed:
The contractor makes the plan and submits to Project management Unit of Bac Giang city who are the representatives of the Client or Investor) to get approval The plan is generated based
on analyzing existing resources such as: financial resource, human resource, technical resource… Each item of the project is a part of completed and consistent system In the plan, the building of all the parts such as pipe-line system, wastewater pumping stations, flooding water pumping stations & waste water treatment plant… has the connection to each other and can be executed at the same time if possible in order to save time and work scientifically
Based on the general plan, a detail project schedule is made in which each item is given to each Department The schedule is even detailed to every week/month/quarter The capital is also allocated for each item in this schedule On executing the project, when the company comes up with some problems, occasionally makes the project to be in “freeze mode” for several days (eg Difficulties in land clearance, bad weather…), the manager must be very flexible and quick-minded in taking the corrective actions to rush up with project schedule
Mr Søren sets up a number of measurements to access the performance of his staff, most important of which is fulfilling the task (the construction item) not later than the time in schedule
Trang 9at quality requested Moreover, the company offers rather high salary to staff, not only for Danish engineers but also Vietnamese staff In addition, MTH has good policies for Vietnamese staff who works far from their home such as: paying for the apartment rent, buying some housing equipments (air-conditioners, washing machines…) to motivate the employees to concentrate on their work The manager use the code of conduct in the company which include business conduct, societal relations and human rights
MTH is the contractor with main responsibilities of instructing the subcontractors to implement building items and control their quality, therefore the manager required that: site supervisor and inspectors always on site to follow up the work in actual condition and to deal with problems occurred The manager reviews the project schedule every week by having meetings internally or meetings with representatives from related sides such as subcontractors, PMU & consultant… to solve the problems
Problems in the co-operation among the parties: MTH company did not request
consultant to give detailed instructions about the legal steps in related issues such as land clearance, responsibilities dividing… from the beginning Moreover, MTH company – the main contractor does not apply restrict control on subcontractors because it is not familiar with the way of doing business in Vietnam For example, MTH did not provide a clear penalty or bonus if subcontractors complete part of an item behind or exceed the time schedule In Vietnam, this matter is really important because the bonus may motivate subcontractors to work harder while the penalty forces them to meet the requirements of time and quality agreed from the start
Problems in giving responsibilities to departments and building team work: In this
project, the responsibilities each department has to bear is too clear, team working spirit is not good enough so to some tasks that need the co-operation among the departments, the progress
Trang 10seems to be slow down For instant, if site related departments do not work in coherence with Quality assurance department, the effectiveness in work will not be gained In addition, the relationship between Vietnamese staff and Danish managers is not close enough In some cases, they do not understand each other which lead to conflict and inefficient team working
Problems in employee motivation: Although staff are paid high salary and get much social
care, some employees do not feel satisfied with the policies of the company There are very little opportunities for the staff to be promoted because MTH just appoints Danish staff to important positions like department managers and project managers Besides, MTH managers do not organize small parties or picnic to fill in the gap between Vietnamese and Danish, to make them closer and to build up team working spirit Enterprise culture takes a significant task in deciding the productivity of working in group and the effectiveness of the whole company Therefore, if the company is not a united organization, the benefit of the whole company will be badly affected
4 ANALYSIS AND ACCESSMENT
4.1 Positive sides in MTH management approaches:
- Professional management skills: MTH was established 90 years ago Therefore the managers
has a lot of management skills that can be applied in establishing plan and organizing the schedule The plan execution is taken steps by steps at most effective way The more detailed schedule is, the more efficient the project will be When generating the plan in details, the plan makers can think of the problems that may occurs and appropriate solutions for that All parts of the plan has the links with each other, which is very close to the reality This will make the mechanism run more smoothly and save time
In addition, reviewing the performance of the project is a good approach to make sure that it
is executed in the right way, at the right period of time and not behind the schedule This also helps to recognize the problems in the process and take necessary corrective actions
Trang 11- MTH has applied some right policies to the employees which can motivate staff: MTH gives
high salary to employees It is a expression of recognition from the employers to the employees’ experience and skills In fact in Vietnam, salary still plays an important role in employees’ decisions when they choose a job beside the work itself and other working conditions Moreover, when the company provides equipments to the rented apartment for staff living far from home and support the expenses for them, the staff feel that they are cared about High living standard can also contribute to improve employees’ health
Code of conduct that MTH applies has outstanding results It ensures that all staffs comply with the law, directives and its own policies There is a fact that MTH managers and staff are not allowed to receive any kinds of gift which can be perceived as a bribe or they will be heavily punished if the bribery is revealed This fact gains the respect from the society and other partners To the citizens, MTH always requires the staff to carry out activities based on responsibility, dialogue and realistic mutual expectations
4.2 Negative sides in MTH management approaches
- When the contractor do not have the proper understanding about the legal issues in executing the project while consultant does not give full instructions, it can lead to the incorrect progress when MTH implements the project and have to spend more time and money to fix the errors Sometimes, it takes even longer to amend the mistake than to execute
- One of the motivators to the employees is responsibilities It is nature that: employees would feel more self-confident and contributive to the company’s success if they can take some responsibilities at work If not, they may feel useless and aimless Taking responsibilities is somehow like overcoming challenges, which energizes staff to work harder In MTH company, only managers take responsibilities and report to the project manager However, the staff are quite free in their work and not given the strict responsibilities Some employees can become un-selfactive and depend on other colleagues and department when they have to fulfill their tasks