2 Approved by: HRIT I DEVELOP A COMPLETE LIST OF CRITICAL MEASURES FOR THE UPCOMING: STEPS: i Collect Critical Measure Document from VN LT Deployment Day.. iii Create a document with
Trang 1Title: Integrated Action Planning Process Purpose: To ensure a systematic approach to determine the
integrated actions in delivering the Business Objective
Document No
S-02-05-03-02.3
Process Owner: DMS Owner Prepared by:
DMS Owner
Page 1 of 3 Process Customer:
All Functional Teams
Concurred by :
Plant Leader
Issue Date:
11/30/98
Next Review:
11/30/99
Issue No
2
Approved by:
HRIT I) DEVELOP A COMPLETE LIST OF CRITICAL MEASURES FOR THE UPCOMING:
STEPS:
i) Collect Critical Measure Document from VN LT Deployment Day
ii) Include other focus areas that VN LT will focus on during the year
iii) Create a document with the following column titles:
a) Critical Measures
b) Goal
d) Methodology or Management System iv) Complete the document by filling in all areas
II) DEVELOP MACRO-LEVEL ACTION PLANS AND CONFIRMATION:
STEPS:
For each Critical Measure:
1 System Owner leads the team to create tree chart with the following branch titles:
a What - the Critical Measure
b How - 3 to 5 key drivers to achieve the Critical Measure
c Who - identify a team or individual for each driver
System Owners refer to:
for PRKEA Action Planning Process for IWS KEA Action Planning Process for IH&S Action Planning Process and/ or other practices
2 Include micro-level action plans if any, i.e.work processes
3 Bring the developed macro-level action plan (in tree chart format) to the Action-plan Confirmation meeting
4 Review the plan with the Leadership
5 Leadership checks for sufficiency of the key drives to deliver the deployed goal
6 System Owner adjusts the plan as per review
** The Direction Setting (for Corporate or function) Owner calls the 1st meeting to do the above
III) INTEGRATED ALL MACRO LEVEL ACTIONS:
STEPS:
1 Collect all tree charts after step II)
2 Look for commonality in the macro level actions and ownership
3 Agree on where the macro level action and owner utimately resides
And/ or ensure consistency of ownership for common actions
And/ or determine the schedule of the common actions that reside in other Critical Measures
Consider the following: (Please follow the Organisation Staffing Planning, and Organisation Skill Assessment)
- Priority of work
Trang 2- Competing priorities
- Leverage key drivers for mutiple results
** The Direction Setting Owner calls the 2nd meeting to do the above
IV) COMPLETE CUSTOMER/SUPPLIERS MATRIX:
STEPS:
1 Create document with the following:
a On the left side, add the " Critical Measure Document" - CBA of Step 2
b On the right side, add all appropriate functional teams, charted teams that have had either work deployed to them (System Owner), or will be Suppliers to support the deployed focus areas
2 Complete the document by filling in the intersections of the Critical Measures / Focus Areas and the Functional Teams/Chartered Teams with either a "SO" or "S" (Responsibility Matrix)
SO If the Critical Measure/Focus Areas have been deployed to a Functional team/Chartered Teams
S If the Functional Team/Chartered Team supplies service to Functional Team/Chartered Team to achieve their deployed Critical Measures/Focus Areas
3 System Owner share the outcome with the functional teams/chartered teams that have work deployed to them
Note: Leave the "cell" blank if no foreseeable working relationship is expected
** The Direction Setting Owner calls the 2nd meeting to do the above
V) INFORM THE SUPPLIERS AND/OR IMMEDIATE LEADER :
STEPS:
1 System Owner list all the needs (macro level) of the Supplier in order to deliver their business needs
2 System Owner send the list of needs to the suppliers and their leaders prior to the 3rd meeting
3 The Direction Setting Owner send a memo to invite the suppliers, immediate leaders and the System Owners to attend the 3rd meeting
VI) CAN THE SUPPLIERS MEET THE NEEDS:
STEPS:
1 Immediate Leaders collect all the list of needs from all System Owners
2 Immediate Leaders review the staffing planning as per PMC and/or the Organisation Skill Assessment, PMC to evaluate if resources are adequate and evaluate any gap
3 Individual, Immediate Leader and System Owner decide on what they can deliver to each
Critical Measure
4 System Owner reviews the outcome of the discussion The review focuses on the gap if any
5 If the needs can be delivered by the Suppliers, follow the PMC, W&DP Management
Process
6 If the needs cannot be delivered, go to the next step
Trang 3Note: The 3rd meeting is called to complete the above Step 1 to Step 5
VII) CATCHBALL PROCESS:
STEPS:
1 Both System Owner and Supplier have discussion to begin resolving any outages
2 When the outages cannot be resolved, a meeting with the Leadership to determine capability and
risk
3 In the meeting, the System Owner reviews the outages in plan (actions that cannot be delivered by
the Supplier)
4 Discussion on impact to the result, and what will it take to eliminate the outage/gap will need to
happen The Supplier who has been identified as having an impact on the outage/gap will discuss
what they see as the issues The System Owner will define the risk, and the impact on the result if
the outage/gap is not eliminated
5 The Leadership decides on the appropriate actions to be taken based on the discussion
6 The action plan is adjusted accordingly
7 The System Owner follows the Work and Development Plan Management Work Process,
PMC to ensure the works are linked to individual's Work and Development Plan
** The Direction Setting Owner calls the 4th meeting to do the above
VIII) DEVELOP MICRO- LEVEL ACTION PLANNING:
STEPS:
1 Involve the personnel who are going to work the action plan
2 Obtain agreement from the Leaders/Managers for the team membership
3 The team can apply the below methodology for micro-level action planning:
(i) Quality Improvement Process (QIP)
(ii) Work Process Development, PMC
(iii) Cause and Effect Analysis
(iv) Search and Reapply - PMC
4 Based on the above methodology used, the team develops an Improvement Plan with Ownership
and timing of completion determined
5 The team owner monitors the progress of the Improvement Plan
6 The work is summarized with major action plan and progress identified on a tree chart for monthly/quarterly reviews
by Direction Setting Owner