ACTION PLANon Kotex Softina Public Sampling January 2003 Conducted for Kimberly Clark Shaping OUR FUTURE together... Technique: F2F intercept sampling, giving samples in one way to only
Trang 1ACTION PLAN
on Kotex Softina Public Sampling
January 2003
Conducted for Kimberly Clark
Shaping OUR FUTURE together
Trang 21. Fieldwork Process 11
2. Recording Form 12
Trang 3PROJECT DESCRIPTION
1. Technique: F2F intercept sampling, giving samples in one way to only target respondent going in
or out location
2. Product: Kotex Softina.
3. Target respondents:
Female white collar aged 22-40.
Student girls aged 19-25
Other active women aged 18-40
4. Number of samples given to each respondent:
One sample per target
Trang 4PROJECT DESCRIPTION
5 Kind of public location, Area and Sample Size:
a) Kind of public location:
- Universities/ Colleges/ Night learning
centers
- Women clubs, cultural houses, water parks, women aesthetic and sport centers, beauty salon,
discotheque…
Shopping Centers
- Hypermarkets/ Trade Centers.
- Supermarkets.
(Note: Hypermarkets/ Trade Centers are in top priority of doing sampling).
b) Areas & sample size:
HA NOI 50,000 DANANG 11,000 CANTHO 9,000 HCMC 90,000
TOTAL 160,000
Trang 5PROJECT ORGANIZATION
1. Sample Size for each kind of location:
Note: In each area, the sample size of each kind above may be shared together
2. Quality Control:
No back-check on Public Sampling
The project quality will be controlled at sampling points
3. Timing: 01 March 2003 – 12 March 2003
SAMPLE SIZE 50,000 11,000 9,000 90,000 160,000
Offices 6,000 1000 700 17,000 14,000
Universities/ Colleges/ Night learning
centers 29,000 6,000 5,800 25,000 65,800
Entertainment Locations 5,000 3,000 2,500 3,000 33,500
Shopping Centers 8,000 1,000 - 25,000 34,000
Sampling Location 500 110 90 900 1,600
Trang 6PROJECT ORGANIZATION
4 Location Frequency:
a) Offices: One office / 01 sampling session
morning, and/or in the afternoon, and/or in the evening
Sampling at weekend is preferable
Working time: from 10:00 to 20:00
5 Staff & Uniform
Promoter 36 18 18 40 112
Trang 7I K.C SUPPLY REQUIREMENT:
1 Samples, delivered on 26 Feb 2003 at following addresses:
2 Equipment, delivered on 18 Feb 2003 at 177/35 Nguyen Van Dau, Binh Thanh, HCMC:
3 Others, delivered at the latest of 26 Feb 2003 at 126D Phan Dang Luu, W3 Phu Nhuan, HCMC:
Product information for training
Documents prove the quality and origin of the samples: Certificate of Origin, Certificate of
Quality, legal transport documents for each area (i.e Commercial Invoice or Internal Goods
Issued notes stipulated by The Ministry of Finance, etc.)
PREPARATION
T-shirt 236 Cap 150 Bag 130 Use old bag, in MSV stock
sample
Trang 8II MSV:
1 Recruiting
2 Training
3 Project announcement to Trade Services
4 Facilities necessary for fieldwork organization
5 Uniform transportation to area
6 Mapping system for fieldwork
7 Recording forms
8 Fieldwork organization
Trang 9REPORT
I DAILY REPORT:
1 Time: 4:00 p.m.
2 Content:
List of conducted locations (updated).
Process of each area.
Any problems arisen.
Any information from consumers collected during fieldwork.
II FINAL REPORT:
1 Time: 07 after the last area completion.
2 Content:
Fieldwork Result.
List of conducted locations.
Any information from consumers collected during fieldwork.
Inventory Report.
Trang 10APPENDIXES
Trang 11FIELDWORK PROCESS
Trang 12RECORDING FORM
LOCATION:
KOTEX SOFTINA PANTILINER PUBLIC SAMPLING PROJECT
PROMOTER:
GROUP: GROUP LEADER:
SUPERVISOR:
Trang 13APPROVAL
The Active Plan is approved by K.C.
Phan Ngoc Thuy