Journal of Mechanical Science and Technology 30 2 2016 953~962 www.springerlink.com/content/1738-494xPrint/1976-3824Online DOI 10.1007/s12206-016-0149-y Numerical analysis of transient
Trang 1Journal of Mechanical Science and Technology 30 (2) (2016) 953~962 www.springerlink.com/content/1738-494x(Print)/1976-3824(Online)
DOI 10.1007/s12206-016-0149-y
Numerical analysis of transient pressure variation in the condenser of
Xinjun Wang1, *, Zijie Zhou1, Zhao Song1, Qiankui Lu2 and Jiafu Li2
1 Institute of Turbomachinery, Xi’an Jiaotong University, Xi’an, 710049, China
2
Dong Fang Turbine Co., Ltd, Deyang, 618000 , China (Manuscript Received June 2, 2015; Revised September 5, 2015; Accepted September 24, 2015) -
Abstract
To research the characteristics of the transient variation of pressure in a nuclear power station condenser under accident condition, a
mathematical model was established which simulated the cycling cooling water, heat transfer and pressure in the condenser The
calcula-tion program of transient variacalcula-tion characteristics was established in Fortran language The pump’s parameter, cooling line’s organizacalcula-tion,
check valve’s feature and the parameter of siphonic water-collecting well are involved in the cooling water flow’s mathematical model
The initial conditions of control volume are determined by the steady state of the condenser The transient characteristics of a 1000 MW
nuclear power station’s condenser and cooling water system were examined The results show that at the condition of
plant-power-suspension of pump, the cooling water flow rate decreases rapidly and refluxes, then fluctuates to 0 The variation of heat transfer
coeffi-cient in the condenser has three stages: at start it decreases sharply, then increases and decreases, and keeps constant in the end Under
three conditions (design, water and summer), the condenser pressure goes up in fluctuation The time intervals between condenser’s
pres-sure signals under three conditions are about 26.4 s, which can fulfill the requirement for safe operation of nuclear power station
Keywords: Condenser of nuclear power station; Power supply halt of pump; Flow rate of cooling water; Transient heat transfer; Pressure of condenser
-
1 Introduction
As an important equipment in condensing turbine set, the
condenser can keep stated backpressure and coagulate steam
into clean water The condenser is a kind of heat exchanger
which plays the role of cold source in the turbine’s
thermody-namic system
For security thought, three signals are settled in a
con-denser: signal of emergent halt of turbine, signal of emergent
halt of reactor and signal of emergent halt of condenser When
there is a forced outage accident in a nuclear power station,
the recycle water pump shuts down As a result, the flow rate
of cooling water decreases to zero gradually due to siphonage
In consequence, the heat transfer coefficient and capacity of
heat transmission in condenser decline and the condenser
pressure goes up dramatically Ultimately, the rising of
pres-sure in condenser triggers signals of emergent halt of the
tur-bine and emergent halt of the reactor, which causes the
shut-down of both the reactor and main valve of the turbine But
there is still live steam production after the shutdown of the
reactor To avoid overpressure of the second circuit, live
steam should be discharged through the bypass system into the condenser, which means the pressure in the condenser will boost further Consequently, if the signal of emergent halt of the condenser is triggered because of the high pressure, the bypass valve will close so the main steam cannot flow into the condenser, which means the emergency condition in nuclear power station will turn worse Therefore, the condenser in a nuclear power station must fulfill both the requirements under normal condition and emergency condition In emergency condition, a condenser is required to take in and condense the steam of high temperature and high pressure timely
To determine the pressure of emergent halt of condenser signal, the reliability, safety and economy of the system should be taken in consideration If the pressure of emergent halt of reactor or emergent halt of turbine is set at a low level, the frequent fluctuation of condenser’s pressure will cause the continual halt of turbine and reactor, which will shorten the lifetime of the turbine set and the reactor If the pressure is set too high, the condenser pressure will trigger an emergent halt
of the condenser signal in no time when live steam flows into the condenser through the bypass system In this situation, the requirement of a nuclear power station’s secure operation cannot be fulfilled Considering the time needed for the halt and the main steam flow, the interval between emergent halt
* Corresponding author Tel.: +86 29 82660313, Fax.: +86 29 82660313
E-mail address: xjwang@mail.xjtu.edu.cn
† Recommended by Associate Editor Kwang-Hyun Bang
© KSME & Springer 2016
Trang 2of turbine and emergent halt of condenser should be 12 s or
longer The sudden absence of the house power is the worst
situation in a nuclear power station The interval between
these two signals directly and dominantly influences the
sta-tion's security and is an important index parameter of
con-denser and cooling water system design
Much research has been conducted on flow rate and the
transient pressure variation at the condition of
plant-power-suspension of pump in a power station [1, 2] But research on
condensers has mainly focused on some aspects like flow and
heat transfer on steady condition, variable working condition
and dynamic performance In the 1970s, Spalding and
Patankar [3] proposed the idea of a porous media model In
that case, the flow in steam side of the condenser is simplified
to the flow of mixture of steam and air in porous media with
distributed resistance and distributed mass Hu and Zhang [4]
investigated the condensate tubes that were submerged by
condensing water, and proposed a new relation to calculate the
heat transfer and flow characteristics in the condenser Hou et
al [5] did numerical research on flow field and heat transfer
characteristics in the vapor side of a condenser using the
po-rous media model Yang et al [6] numerically simulated the
flow in the vapor side in condenser of a 300MW power station
using PHONEICS software Oh and Revankar [7] did some
research on the surface condenser with elevation arranged
tubes by experiment, and observed some characteristics of
heat transfer and variable working conditions Using the
over-all heat transfer coefficient equation of condenser proposed by
the Heat Transfer Institute (HEI), Raj [8] gave some
predic-tion and advice on different condipredic-tions of condenser Zhu et al
[9] did some experimental study and indicated the cooling
water flow's influence on condenser’s heat transfer coefficient,
temperature difference and pressure Electric Power Research
Institute (EPRI) [10] developed a real-time simulation
soft-ware (MMS) which can simulate the dynamic performance of
different facilities in the unit Furthermore, this software can
also evaluate the influence of difference disturbances on the
operation of the unit Carcasci and Facchini [11] at the
Insti-tute of Automation and Computing of Italy developed a highly
flexible computerized method which can do real-time
simula-tion on the power stasimula-tion Using the method of artificial neural
network, Prieto et al [12] made predictions of the heat transfer
coefficient and cleanness factor in the condenser of a power
station cooled by sea water And the result of the prediction
seems to be accurate with error less than 5%
In the condition of plant-power-suspension of pump in
power station, the transient heat transfer process in condenser
is of changeable pressure, changeable steam flow and
change-able cooling water flow Little attention has been devoted to
this situation expect for Jiang and Ding [13], who studied the
transient pressure variation in designed and summer
condi-tions when cooling water lost In Ref [13], the HEI formula
was used in the calculation of the heat transfer rate And the
study in Ref [13] takes no account of the change of the heat
transfer area caused by the reflux of the cooling water
We analyzed the characteristics of cooling water flow and the transient variation of pressure in a 1000 MW nuclear power station condenser when lost house power consumption The flow of cooling water is under the effect of siphonage Different from the literature study [13], the formula by partial
is used in the calculation of the heat transfer rate And the change of the heat transfer area caused by the reflux of the cooling water is taken into consideration The results of this paper may provide a new theoretical foundation for the secure operation of a nuclear power station
2 Transient computation of cooling water flow When cycling water pump lost its power, the cooling water flow in the once-through siphonic cooling system changes The water flow can be affected by the pump, arrangement of cooling line, check valve’s specialty and the parameter of the siphonic water-collecting well
2.1 Model and governing equation of water hammer Fig 1 shows the once-through siphonic cooling system of a
1000 MW nuclear power station The cooling water comes out from the condenser and discharges into the front pool of the siphonic water-collecting well When the water level of the front pool climbs higher than the siphon wall (as shown in the shaded part), the cooling water overflows into the back pool of the siphonic well and comes into the natural water source Water hammer, manifested as the violent changes of fluid flow rate and pressure, is a transient process which occurs when s pump starts, pump suspends or check valve closes In calculation, the siphonic well is assumed to be a pool with constant water level All the cooling lines in the condenser are equivalent to one pipe whose flux is equal to the total flux of the cooling water The sectional area of this equivalent pipe is equal to the total sectional area of all cooling lines The water hammer wave’s propagation speed and friction coefficient in Fig 1 Schematic of the once-through siphonic cooling system
Trang 3this pipe are the same as in one cooling line In this way, the
whole system can be simplified to a system of “pump - inlet
pipe - equivalent cooling line - outlet pipe - water well”
Darcy-Weisbach’s friction expression is introduced in and
the kinematic equation of the water hammer is deduced as
follows:
1
where the inertial force of unit volume is expressed on the left
The three parts on the right mean the pressure of unit volume
of fluid, the friction resistance head of unit length and the
velocity head
The continuity equation of water hammer has the form:
2
= −
∂ ∂ (2)
Coefficient γ is introduced in the linear combination of
Eqs (1) and (2):
2
We assume that Ve x t( ,)and Hp x t( ,) are the solutions of
Eq (3) Comparing the total derivative of Ve x t( ,)and
,
Hp x t( ), we obtain:
2
Ve
Ve
dt
γ
λ
(4)
The solution of Eq (4) is
g
a
γ= ± (5)
Substituting γ into Eqs (3) and (4), then we have:
Along C+:
0 2
Ve Ve
dx
dt
(6)
Along C―:
0 2
Ve Ve
dx
dt
(7)
Eqs (6) and (7) are the characteristic line equation sets and
/
dx dt is the expression of characteristic line Ve x t( ,)and
,
Hp x t( ) satisfy the differential relations on their own charac-teristic lines
Fig 2 shows the computational grid of water hammer basis
on the characteristic line equation set (Eqs (6) and (7)) In this grid, the x axis is along the length of the pipe and y axis de-notes time In view of friction resistance, the whole pipe is sectioned into n parts and the time step is∆ = ∆t x a/ Gener-ally speaking, when ∆x and ∆tminish, the result of compu-tation will approach the real transient flow situation In this figure, AP and BP (marked as C+ and C-) whose slope are 1/a and -1/a, are characteristic lines in x-t plane
Discretize the water hammer’s characteristic line equation
by time, and then we have the general expression of discrete equations:
where the subscripts ( i-1, i+1 and Pi ) stand for the position A,
B and P in Fig 2 Hi+1, Hi−1, Qpi+1 and Qpi−1 respec-tively stands for the mass flow and pressure head of different nods a moment before Their units are m and m3.s-1 Hpi(m) and Qpi( m3.s-1) are the transient pressure and mass flow
x
∆ (m) is the step length of the pipe
a TB Ag
2
f x FP DgA
∆
= are the calculation factors For a certain cooling line system, the values of TB and FP
do not change over t and x Once the flow state before ∆tis known, they can be easily worked out by Eq (8)
2.2 Numerical condition
In the computation process of water hammer using the char-acteristic line equations, the initial conditions and the bound-ary conditions of cooling water are needed Initial conditions are parameters of steady state of the cooling water Boundary conditions consist of (1) the suspension condition of pump, (2) the condition of cascaded pipeline of cooling water, and (3) the constant pressure of the pool For detailed expressions, refer to Ref [2]
2.3 Verification of the program The self-written program is checked by the example "water hammer caused by suspension of pump in a valveless pipe" in
t
P
C-X
x Fig 2 Computational grid of water hammer
Trang 4Ref [1] The calculation condition is briefly listed in Table 1
For more details, see Ref [1] Fig 3 shows the comparison
calculation in Ref [1] and the results of this paper The curves
in Fig 3 express the pressure head, non-dimensional mass
flow and non-dimensional torque From this comparison we
see that the maximal pressure head in this paper is 97 m, while
that in Ref [1] is 96.7 m The max reflux in this paper is 0.98
m3/s, while that in Ref [1] is 1 m3/s After comparing these
two results, a conclusion is drawn that the self-written
calcula-tion program is reliable enough to get a precise result
3 Transient pressure calculation of condenser
In a power station’s surface condenser, the cooling water is
insulated from the steam by the wall of cooling lines The
space in the condenser can be divided into two sides: the
steam side and the water side The space of steam side in
con-denser is invariant and can be divided into three parts: gaseous
phase part, air part and hot well part Though there is no
obvi-ous bound between gaseobvi-ous phase part and air part, the
inter-faces between the hot well part and the gaseous part and the
interface between the hot well part and the air part are vivid
The water side in the condenser is of two parts: cooling lines and cooling water Cooling lines can be divided into two parts: exposed part and nonexposed part (nonexposed part is located
in the condensed water) The exposed part and the nonexposed part convert with the change of quantity of condensed water
3.1 Calculation model and governing equation It’s a complex procedure of flow and heat transfer when there is a plant-power-suspension of pump in a power station The steam discharged into the condenser cannot be condensed completely so that the temperature and pressure in the con-denser will rise up The steam then fills in the steam side and a heat transfer and condensation procedure with changeable pressure and mass happens The pressure and mass flow of the cooling water decrease to zero gradually With the rise of cooling water’s level, the cooling water lines become sub-merged To calculate the transient change of pressure in the condenser, we set the gaseous side of condenser and ex-hausted casing of turbine (except for the condensed water) as control volume Assume that:
(1) The gaseous phase of the condenser is in thermody-namic equilibrium;
(2) The steam discharged into condenser from bypass sys-tem is of high pressure, so that the mass flow of discharged steam cannot be influenced by the pressure fluctuation of con-denser;
(3) The mass flow and flow rate of cooling water in con-denser are homogeneous in calculation;
(4) Take no account of chemical filling water and flash of condensation;
(5) In every time node, the heat transfer is steady and the changes between neighboring time nodes are step changes The continuity equation of control volume open system can
be written as:
,
v
v in con
dG
dt
∑ ɺ ɺ , (9)
where ∑Gɺv in, denotes the mass flow of total steam
(includ-ing steam from the bypass system and the turbine’s exhaust steam) into the control volume Gɺcon is the total condensa-tion rate Gvis the steam mass in the control volume And t denotes time
The energy equation of the control volume's vapor filling procedure becomes (ignore the kinetic energy and poten-tial energy of the steam ):
OPS
v in v in con l s
dU
dt
− +ɺ ∑(ɺ )− ɺ = , (10)
where Qɺdenotes the capacity of heat transmission between the control volume and outside When the control volume
Table 1 Condition of the check calculation
Rotating inertia moment of pump 636.5 N·m 2
Rated flow of pump 0.912 m 3 /s
Rated torque of pump 1283.9 N·m
Water hammer wave velocity 860 m/s
0
20
40
60
80
100
120
140
time/s
h(result of literature[1]) h(result of check calculation)
-3 -2 -1 0 1 2 3
4 β(result of literature[1])
β(result of check
calculation)
v(result of literature[1])
v(result of check
calculation)
Fig 3 Comparison of check calculation result and the result of Ref [1]
Trang 5releases heat to the outside, Qɺ is positive Otherwise, Qɺis
negative ∑(Gɺv in v in, h, )denotes the energy which is brought
along with the steam into the control volume hv in, is the
specific enthalpy of the steam in control volume Gɺcon l sh, is
the energy which is brought away by the condensed water
,
l s
h is the specific enthalpy of saturated water under the
pres-sure of condenser UOPS is the total energy of the control
volume
The rate of internal energy’s change in control volume can
be written in the form:
dt = dt ⋅ + dt ⋅ (11)
The capacity of heat transmission Qɺ has two different
sources: One, the capacity of the heat transmission between
steam and water; two, from the heat transmission between
steam , cooling line, condenser casing, and the heat
transmis-sion between casing and outside
We then write the relation between the capacity of heat
transmission and the condensation rate:
,
con v l s
Qɺ=Gɺ h −h (12)
Discretize Eqs (9)-(12) by time, and we have the governing
equations of the transient pressure change of condenser:
,
t t v
,
t t t
v in con
t t t ops ops
v in v in con l s
t t t t t t t t
con v l s
t
t
+∆
+∆
∑
∑
(13) 3.2 Calculation of heat transfer coefficient
When the flow rate of cooling water is higher than 0.9 m/s,
HEI [8] standard can be used to calculate the overall heat
transfer coefficient of condenser:
0 c t m
where K0 is the basic heat transfer coefficient β is the c
correction factor of cooling lines' cleanliness β is the cor-t
rection factor of temperature β is the correction factor of m
cooling lines' material and wall thickness The specific value
of each factor can be found in Ref [15]
When the flow rate of cooling water is less than 0.9 m/s, the
overall heat transfer coefficient can be calculated using
ex-perimental correlations For forced heat convection in tube, we
use the formula recommended by Gnielinski:
w 1/ 2 2/3
w
w
w i
Re
Re d
λ α
λ
−
=
(15)
where awis the forced convection heat transfer coefficient in tube λ is the heat conductivity coefficient of the cooling w water di denotes the inner diameter of the cooling line
w
Re denotes the Reynolds number of the cooling water flow and Prw is the Prandtl number of the cooling water
For the outside surface of the cooling line, we use the cor-rection heat transfer coefficient of film condensation in Ref
[16]:
(16) where α is the condensation heat transfer coefficient in the v steam side Π expresses the influence of air flow’s shear stress on the water film outside the tube α is the film con-n densation heat transfer coefficient of the horizontal tube
Nuis the Nusselt number corresponding to α n Z is the number of passes Sis the correction factor of cooling lines organization ε is the correction factor of air content The 0 specific expression of each coefficient can be found in Refs
[14, 16]
When the flow rate of cooling water is less than 0.9 m/s, the overall heat transfer coefficient of condenser can be expressed as:
o w
1
1 ln 2
K
=
, (17)
where λ ( W/m.K )is the heat conductivity of cooling line m o
d (m) denotes the outside diameter of the cooling line pipe
3.3 Calculation of the temperature of the cooling water and the capacity of heat transmission
Fig 4 shows the calculation grid of cooling water’s flow and heat transfer The cooling line’s wall is shown as the shaded portions The grid is of four sections: inlet Sec (I), heat transfer Sec (W) and outlet Sec (O), and grid M The first three sections of grid trace the position and temperature
of cooling water so that the whole pipe’s capacity of heat transfer can be calculated no matter if backflow happens Grid
M is used for comparison General calculation steps are:
(1) Calculate the cooling water node’s position at t and
t+ ∆t separately according to the known change regularity of cooling water’s flow rate;
(2) Confirm the grid nodes that are in the cooling line at ∆t
Trang 6period by their position coordinates Only these nodes
partici-pate in the heat transfer process
(3) Calculate cooling water’s temperature and heat transfer
capacity by HEI formula or the formula by partial The I, W,
O grid of cooling water should be taken into consideration
(4) Acquire every node’s temperature at the moment of
t+ ∆t Use linear interpolation strategy to calculate M grid’s
temperature at the moment of t+ ∆t Prepare for next
calcu-lation
The logarithmic mean temperature difference is mainly
adopted in the calculation of steady calculation of heat transfer
in condenser In this study, the length of pipe of each grid is
small enough and the temperature variation is not remarkable
In the calculation of cooling water’s temperature, the
tempera-ture difference between cooling water and steam is used for
the heat transfer temperature difference
Adopting implicit format time discretization on grid node
WN we have the equation of heat balance:
n
t t t
t
+∆
−
∆
where cdenotes specific heat at constant pressure; mis the
mass of cooling water; T is the temperature; ∆t denotes
the time step length; A is the area of heat transfer In the
subscript, Wn is the number of segment and v means steam
From Eq (18), we have the temperature calculation
equa-tion of cooling water at the moment of t+ ∆t:
n
t t
T
+∆
+∆
+
=
+ (19)
Calculating all the nodes in grid W according to Eqs (18)
and (19), then we have the cooling water’s temperature of grid
W and the heat transfer rate
n
W
Qɺ of each segment of cooling water We have to use iteration in the calculation of
tempera-ture and heat transfer rate because of using implicit format
After we know the temperature rise and heat transfer rate of
all the nodes, the overall heat transfer rate of cooling water
and condenser can be calculated:
Qɺ =∑Qɺ (20)
Strictly speaking, the heat transfer rate calculated from HEI
equations and the formula by partial is aimed at the whole
condenser Here, the result calculated from the formula by
partial should be corrected When corrected, the heat transfer rate, pressure and temperature of condenser should be the same as the steady state of calculation The correction factor is equal to the heat transfer rate which was calculated from the formula by partial dividing the heat transfer rate calculated from overall:
,1 ,1
HEI HEI SEP SET
fac
=
<
where QɺHEI,1 is section’s heat transfer rate calculated from HEI equations QɺSEP,1 is section’s heat transfer rate calcu-lated from the formula by partial QɺHEI is the overall heat transfer rate calculated from HEI equations QɺSEP is the overall heat transfer rate calculated from the formula by partial
fac denotes the correction factor
The corrected overall heat transfer rate of cooling water and condenser becomes:
1 0/
Qɺ =Qɺ fac (22)
The heat storage rate of the metal wall of cooling water line pipe is:
dT
dt
=
ɺ , (23)
where mmexpresses the mass of the wall of cooling water line pipe cm is the specific heat of metal wall of tube and m
T is the mean temperature of the cooling water line pipe The heat absorptivity of the condenser’s shell can be repre-sented as:
3
shell shell shell
dT
dt
=
ɺ , (24)
where mshell is the mass of condenser’s shell cshell is the specific heat of metal shell Tshell is the temperature of the shell
Assume that the temperature of the condenser shell is al-ways equal to the average temperature of the two sides of wall The shell’s radiation heat transfer rate to outside is:
4 4
273.15
100
shell
shell
T
Qɺ =εσ + ⋅A , (25)
where ε is the blackness or emissivity which is set to 0.8
σ is the radiation coefficient of black body, set to 5.67 shell
A is the radiation area of the condenser
In the control volume, the total heat transfer rate between steam and outside is:
Qɺ=Qɺ +Qɺ +Qɺ +Qɺ (26)
Fig 4 Calculation grid of cooling water's flow and heat transfer
Trang 73.4 Initial conditions
The initial conditions of vapor side in the condenser are the
same as three working conditions: designed, winter and
sum-mer working condition The initial condition of water side in
condenser is the steady status of cooling water In steady
working status, the temperature of all nodes of inlet Sec I is
equal to the water source’s temperature The temperature of all
nodes of outlet Sec O is equal to the cooling water’s
ture at the outlet of condenser The cooling water’s
tempera-ture of grid M accords exponential distribution The
calcula-tion expression of initial temperature of grid W is [15]:
x x
w w
K A
q c
v w x v w in
−
∆ = ∆ , (27)
where x is the distance from the inlet opening of the cooling
water ∆Tv w x, , is the temperature difference between steam
and cooling water at x ∆Tv w in, , denotes the temperature
difference between steam and cooling water at the inlet
open-ing Ax is the heat transfer area from inlet opening to x
x
K is the general heat transfer from inlet opening to x
w
q is he mass flow of cooling water and cw is the specific
heat of the cooling water
4 Results and analysis
The study is based on a 1000 MW nuclear power station
set’s cycle cooling water system When 85% of the main
steam is discharged into the condenser through bypass system
and both the cycle cooling water and the attemperation water
are lost, the transient variation of temperature in condenser is
focused on The study was conducted in three working
condi-tions: designed, winter and summer
4.1 The Program and process of calculation
The self-written program based on FORTRAN language is
applied to calculate the transient variation of cooling water
and condenser’s pressure The basic calculation process is
shown in Fig 5
4.2 Characteristics of cooling water flow
In the 1000 MW power station set, there is a check valve at
the outlet of cycle cooling water pump which is controlled by
an electric actuator When there is plant-power-suspension of
pump, the check valve is closed due to elastic force and
grav-ity In that way, the cooling water can flow backwards in a
while When the electric controlled check valve is closed
line-arly, the change of cooling water’s flow rate is shown in Fig 6
The close duration time of the check valve is 45 s The
varia-tion of flow rate is of 3 stages: at 0-18.1 s, the flow rate
de-creases to zero almost linearly; at 18.1-45.0 s, the cooling
water flows backwards; the flow rate decreases to zero again
at 45.0 s and then fluctuates; in the end, the cooling water
stops flowing
4.3 The transient characteristics of pressure variation in condenser
Fig 7 is a schematic of the cycle water system in a nuclear
Fig 5 Calculation process
-1.0 -0.5 0.0 0.5 1.0 1.5 2.0 2.5
Time/s Fig 6 Cooling water’s flow rate variation
Fig 7 Schematic of the cycle water system in a nuclear power station: (a) reactor; (b) steam generator; (c) bypass valve; (d) live steam valve; (e) steam turbine; (f) electric generator; (g) condenser; (h) pump of cycling water; (i) check valve; (j) pump of nuclear loop.
Trang 8power plant Table 2 shows the calculation condition of the
condenser The turbine exhaust steam mass flow is the mass
flow that is designed in normal working condition The
at-tenuation rate of exhaust steam means the decrease rate of
turbine's exhaust steam mass flow when power is lost
sud-denly The steam mass flow of bypass is the steam mass flow
through the bypass system to the condenser when power lost
The bypass valve opens or closes linearly
The variation characteristics of steam mass flow, heat
trans-fer coefficient, heat transtrans-fer capacity, and pressure in
con-denser are shown in Fig 8
Fig 8(a) shows the variation curve of steam mass flow
From this we can see that the change of steam mass flow in
designed, winter and summer conditions are almost the same
When there is plant-power-suspension of the pump, the
tur-bine works as usual and the exhaust steam mass flow is the
same as usual When the condenser pressure reaches 20 kPa and triggers an emergent halt of the turbine signal, the live steam valve closes so that the mass flow of steam that is
dis-Table 2 Condition of the condenser’s calculation
Working condition Designed Summer Winter
Live steam pressure (MPa) 6.5 6.5 6.55
Live steam specific
enthalpy(kJ/kg) 2771.2 2771.2 2770.6
Turbine exhaust steam mass
Exhaust steam specific enthalpy
Condenser pressure (designed)
Attenuation rate of exhaust
steam mass flow (kg/s) 4000 4000 4000
Steam mass flow of bypass
Heat transfer area of condenser
Material of cooling line Ti Ti Ti
External diameter of cooling
Temperature of cooling water
Flow rate of cooling water
Volume of vapor phrase in
condenser (m 3 ) 5800 5800 5800
Volume of exhaust casing (m 3 ) 600×2 600×2 600×2
Live steam valve close duration
Bypass steam valve open
Bypass steam close duration (s) 5 5 5
Emergent halt of turbine (kPa) 20 20 20
Emergent halt of reactor (kPa) 20 20 20
Emergent halt of condenser
0 200 400 600 800 1000
Summer Designed Winter
Time/s (a) Steam mass flow variation
0 5 10 15 20 25 30 35 40 45 50 0
1000 2000 3000
4000
Summer Designed Winter
-2 ·℃
Time/s
(b) Heat transfer coefficient variation
0.0 0.5 1.0 1.5 2.0 2.5
3.0
Summer Designed Winter
(c) Heat transfer capacity variation
0 5 10 15 20 25 30 35 40 45 50 0.00
0.01 0.02 0.03 0.04 0.05 0.06 0.07 0.08
Time/s
Summer Designed Winter
(d) Variation of condenser's pressure Fig 8 Variation of condenser's parameter
Trang 9charged into the condenser decreases sharply When the
by-pass valve opens, the steam entering into the condenser
through bypass system increases The emergent halt of
con-denser signal and emergent halt of reactor signal are triggered
when the condenser’s pressure reaches 50 kPa Then the steam
mass sharply decreases to zero again
Fig 8(b) shows the variation heat transfer coefficient The
changes of heat transfer coefficient in three working
condi-tions are same too The variation is of three stages: first, the
pipe’s convection heat transfer coefficient and the overall heat
transfer coefficient decrease sharply and touch bottom when
the cooling water’s flow rate is zero and the steam mass flow
is minimum Second, the cooling water flows back The pipe’s
convection heat transfer coefficient and the overall heat
trans-fer coefficient increase first and then decrease Third, the heat
transfer coefficient touches bottom and keeps constant while
the cooling water fluctuates at 0 and the steam mass flow is 0
The capacity of heat transfer of the condenser is related to
the heat transfer coefficient, steam mass flow and the
tempera-ture difference (the heat transfer area is fixed) Based on the
change characteristics of these three parameters, the change of
heat transfer capacity can be calculated and Fig 8(c) shows
this change
The pressure variation of the condenser, which is affected
by cooling water flow rate, heat transfer coefficient, heat
transfer capacity, steam mass flow and temperature difference,
is shown in Fig 8(d) In three working conditions, the
con-denser pressure increases in fluctuation At the start of
plant-power-suspension of the pump, the steam mass flow keeps
invariant while the condenser pressure increases gradually and
reaches the peak value in about 17 s Soon afterwards, the
main steam valve closes and the bypass valve opens The
steam flow rate increases and decreases sharply At the same
time, the cooling water is refluxing As a result, the condenser
pressure decreases a little and then increases quickly At 20 s,
it peaks for the second time From 20 s to 45 s, the bypass
steam mass flow is constant and the cooling water refluxes
while the heat transfer coefficient and capacity increase and
then decrease As a consequence, the condenser pressure
de-creases and then inde-creases At about 45 s, the condenser
pres-sure reaches the third peak value At the end, the steam mass
flow that enters into condenser decreases to zero rapidly and
the condenser pressure starts to decrease because of the
emer-gent halt of the condenser signal The time when condenser
pressure reaches the third peak value is later than the emergent
halt of the condenser signal-50 kPa because the reactor still
generates live steam while stopping
From Fig 8(d), we can conclude that when there is
plant-power-suspension of pump, the condenser pressure increases
to 20 kPa and triggers an emergent halt of the turbine signal in
some time In summer, designed and winter condition, it needs
15.7 s, 16.7 s and 17.0 s severally The pressure of the
con-denser increases to 50 kPa and triggers an emergent halt of the
condenser signal in some time In summer, designed and
win-ter condition, it needs 42.1 s, 43.1 s and 43.4 s severally In
these three conditions, the time interval between these two signals is 26.4 s, 26.4 s and 26.3 s In conclusion, the time intervals can fulfill the operation requirements of the nuclear power station
5 Conclusions The calculation model of cooling water flow and transient pressure variation of condenser has been established using the self–written calculation program of water hammer in once-through siphonage cooling water system We focused on the change of cooling water flow, heat transfer and pressure in a 1000MW nuclear power station in designed, winter and sum-mer working conditions Based on the analytical and mathe-matical investigation, the following conclusions may be drawn: (1) When there is plant-power-suspension of pump, the cooling water flow rate decreases sharply and refluxes, and then it fluctuates to zero
(2) Corresponding to the change of cooling water flow rate and steam mass flow, the variation of the condenser’s heat transfer factor can be divided into three stages: decreases sharply, increases and then decreases, keeps constant
(3) In a 1000 MW power station, if the electric controlled valve closes linearly in 45 s, the time interval between con-denser-pressure-signal of emergent halt of turbines and that of condensers is more than 12 s, which can fulfill the operation requirements of the nuclear power station no matter if the work condition is designed, winter or summer
(4) The calculation model of cooling water flow and tran-sient pressure variation of condenser in once-through sipho-nage cooling water system can be used in the accident sce-nario in a nuclear power plant The self-written program may provide an analysis method and tool for the design of a nu-clear power plant's condensation system
Nomenclature -
a : Spread rate of water hammer, m/s
A : Heat transfer area, m2
c : Constant pressure specific heat, kJ/(kg.K)
i
d : Inner diameter of cooling line, m
o
d : External diameter of cooling pipe, m
D : Diameter of pipe, m
f : Resistance coefficient of pipe fac : Correct factor of heat transfer rate
g : Gravitational acceleration, m/s2
Gɺ : Steam mass flow, kg/s
h : Specific enthalpy, kJ/kg
H : Pressure head of cooling water, m
p
K :Overall heat transfer coefficient of condenser, W/(m2.K)
0
K : Basic heat transfer coefficient of HEI, W/(m2.K)
m : Mass of cooling water, kg
Nu : Nusselt number corresponding to
w
Pr : Prandtl number of cooling water
Trang 10Qp : Volume flow rate of cooling water, m3/s
Qɺ : Heat transfer capacity between control volume and
outside, kW
w
Re : Reynolds number of cooling water
S : Correct number factor of cooling line’s organization
t
∆ : Time step length , s
T : Temperature , K
u : Internal energy, kJ/kg
U : Total energy of control volume, kJ
Ve : Flow rate of cooling water, m/s
x : Flow direction of cooling water
x
∆ : Step length of calculation pipe
n
α : Film condensation heat transfer coefficient on horizontal
circular tube, W/(m2.K)
v
α : Condensation heat transfer coefficient of vapor phase,
W/(m2.K)
w
α : Forced convection heat transfer coefficient inside tube,
W/(m2.K)
c
β : : Correction factor of cleanness of tube
m
β : Correction factor of wall thick and material of tube
t
β : Correction factor of cleanness of tube
0
ε : Correction factor of air content
Π : Influence factor of air flow’s sheer stress on the water
film outside the cooling piping
λ : Heat conductivity coefficient, W/(m2.K)
Subscripts
0 : Heat transfer coefficient between condenser and cooling
water (calculated)
1 : Heat transfer coefficient between condenser and cooling
water (corrected)
2 : Heat transfer rate between condenser and cooling
pip-ing’s wall
3 : Heat absorptivity of condenser’s shell
4 : Radiation heat transfer rate between condenser’s shell
and outside
con : Steam condensation in control volume
ops : Control volume
shell : Condenser shell
References
[1] N C Jiang and X H Wang, Water hammer and protection,
China Building Industry Press, Beijing, China (1993)
[2] Z X Liu and G L Liu, Water hammer protection of pump stations, China Water & Power Press, Beijing, China (1992) [3] S V Patankar and D B Spalding, A calculation procedure for the transient and steady-state behavior of shell-and-tube heat exchangers, McGraw-Hill, New York, USA (1974) [4] H G Hu and C Zhang, A new inundation correlation for the prediction of heat transfer in steam condensers, Numerical Heat Transfer, Part A: Applications, 54 (1) (2008) 34-46 [5] P L Hou, M Z Yu, L P Dai and X G Wang, Numerical prediction and improvement of the three-dimensional steam flow field and heat transfer behavior of a power plant con-denser, J of Engineering Thermophysics, 25 (4) (2004)
649-651
[6] W J Yang, F Z Sun, X Y Huang, Y T Shi, N H Wang and H Cui, Three-dimensional numerical simulation and analysis of the steam flow field and heat exchange perform-ance of a 300MW steam turbine's condenser, Chinese J of Power Engineering, 25 (2) (2005) 174-178
[7] S Oh and S T Revankar, Experimental and theoretical investigation of film condensation with noncondensable gas, International J of Heat and Mass Transfer, 49 (2006) 2523-2534
[8] K S S Raj, Deviations in predicted condenser performance for power plants using HEI correction factors: A case study, J of Engineering for Gas Turbines and Power, 130 (2) (2008) 023003-023010
[9] R Zhu, D T Chong and J P Liu, Test study on the influ-ence of cooling water flow rate upon condenser's perform-ance, Thermal Power Generation, 35 (4) (2006) 10-13 [10] J Makansi and J Reason, Monitoring power plant per-formance, Power, Oak Ridge, USA, 128 (9) (1984) 11 [11] C Carcasci and B Facchini, A numerical method for power plant simulations, Journal of Energy Resources Tech-nology, 118 (1) (1996) 36-43
[12] M M Prieto, E Montanes and O Menendez, Power plant condenser performance forecasting using a non-fully con-nected artificial neural network, Energy, 26 (1) (2001) 65-79 [13] C R Jiang and J P Ding, Nuclear power station condenser unavailable calculation and analysis, Nuclear Power Engi-neering, 30 (2) (2009) 39-44
[14] S M Yang and W Q Tao, Heat transfer, Higher Educa-tion Press, Beijing, China (2005)
[15] Heat exchange institute, HEI standards for steam surface condensers, 9th Ed., Heat Exchange Institute Inc., Cleveland,
OH (1995)
[16] Z C Zhang, Condenser in large scale power plant, China Machine Press, Beijing, China (1993)
Xinjun Wang, Ph.D., is an Assistant professor, Institute of Turbomachinery, School of Energy and Power Engineer-ing, Xi’an Jiaotong University He has been mainly engaged in the research of aerodynamics and two-phases flow in turbomachinery