Implementation of ESI Deregulation • The process started in 1992 and effort over 1992-2000 has concentrated on introduction of competition at the generation level – New Investment : Sma
Trang 1Energy Sector Liberalisation
and Privatisation in Thailand
by Piyasvasti Amranand Inspector General, Office of the Prime Minister
APEC Energy Working Group Implementation Facilitation Team to Thailand (IFAT)
A Follow-up Workshop Karon Villa & Karon Royal Wing
17-18 August 2000
Trang 2Management of the Energy Sector
• Since there is no Energy Ministry in Thailand,
responsibilities related to energy are scattered across 9 Ministries.
• The National Energy Policy Council (NEPC) is responsible
for determining energy policy.
• The National Energy Policy Office (NEPO) acts as the
secretariat to the NEPC NEPO undertakes policy as well
as regulatory work.
• In the near future, an independent regulatory authority
will be established for the electricity and natural gas
sectors.
Trang 3Objectives of Reform
• Increase competition to achieve efficiencies and
ensure supply at reasonable prices
• Promote more efficient energy use
• Reduce the government investment burden
• Ensure best possible service, price and safety
standards
• Encourage public participation
• Develop the capital market
• Optimise the value of the public’s stake in the sector
Trang 4Implementation of ESI
Deregulation
• The process started in 1992 and effort over
1992-2000 has concentrated on introduction of competition at the generation level
– New Investment : Small Power Producer (SPP),
Independent Power Producer (IPP) programs and power purchase from Lao PDR
– Existing Asset : Initial Public Offering (IPO) of
EGCO in the Stock Exchange of Thailand (SET) and sale of 14.9% to China Light and Power
• Development of a long term structure for ESI in
1992 with updates in 1996, 1998 and 2000
Trang 5Implementation of ESI
Deregulation (con’t)
• The latest plan approved by NEPC on 13 July 2000
provides a detailed road map of reform over the next 5 years
• Restructuring under the current plan
– Privatisation of Ratchaburi Power Plant (2000)
– Privatisation of EGAT’s Thermal Power Plants (2003)
– Establishment of a power pool and independent regulatory
body (2002/3)
– Introduction of retail competition (2003)
– Restructuring of MEA and PEA
Trang 6Regulations to Purchase Power
from SPP
• Cogeneration & Renewable
– Cogen: Efficiency >45% and steam >10%
– Renewable: May use up to 25% commercial
energy
• Direct sale to third party outside regulations
• Each sale into transmission system not
greater than 60 MW (90 MW on case by case)
Trang 7Status of the SPP Program
• As of June 2000, 95 proposals had been submitted with total capacity for sale of 4,646 MW
• NEPC has approved the purchase of up to 3,200 MW
from SPP projects by EGAT
• As of June 2000, 52 proposals had been accepted with total capacity for sale of 2,136 MW and 1 proposal is still waiting for approval with capacity for sale of 3 MW
– 50 contracts signed
– 2 contracts under negotiation
– 1 proposal under consideration
Trang 8Status of SPP Projects (con’t)
• 41 projects are already in operation with total generation
capacity of 2,883 MW and total sale to EGAT of 1,580 MW.
• It is estimated that 2 projects (capacity : 510 MW, sale :
130 MW) would not be completed, bringing the amount
of power purchase by EGAT down to 2,006 MW.
• Of the 2,006 MW, 1,828 MW is firm energy
• The surprisingly high success rate is due to capital
injection by a number of foreign strategic partners eg CMS, Sithe Energy, Ogden, National Power, Air Products, Tractebel, Fortum and Heat Oy
Trang 9SPP Proposals Classified by Type of Fuel (as of June 2000)
Number of Projects Capacity (MW) Generating EGAT (MW) Sale to Commercial Energy
Trang 10Power Purchase from SPP
(as of June 2000)
Firm Non Firm Total
Proposals Submitted
Number of projects 67 28 95 Generating Capacity (MW) 7,686.8 665.4 8,352.2 Sale to EGAT (MW) 4,459.9 186.3 4,646.2
Received notification of acceptance
Number of projects 30 22 52 Generating Capacity (MW) 3,496.9 611.3 4,108.2 Sale to EGAT (MW) 1,958.4 177.6 2,136
Contract Signed
Number of projects 30 20 50 Generating Capacity (MW) 3,496.9 556.4 4,053.3 Sale to EGAT (MW) 1,958.4 149.6 2,107.9
Trang 11Power Purchase from IPP’s
• EGAT issued requests for proposals 15 December 1994,
with proposals submitted 30 June 1995
– Western Coast: Prachuap Khiri Khan, Phetchaburi, Ratchaburi,
Samut Sakhon, Samut Songkhram
– Eastern Coast: Chonburi, Rayong, Prachinburi, Sa Kaeo
Trang 12First Round IPP Solicitation
• Seven PPA’s signed
– IPT (THAIOIL, Unocal, Westinghouse)
– TECO (Texaco, Banpu, Edison Mission Energy) – Union Power (Union Energy, Tomen, IVO, CEPA) – Gulf Power (Gulf Electric, Mission Energy)
– BLCP (Banpu, Loxley, Powergen)
– BW2 (Hemaraj, Tractabel)
– Eastern Power - Bangbo (GMS, Marubeni, China Development Bank)
Trang 13Power Purchase from Lao PDR
• MOU of 4 June 1993: Thailand agreed to
purchase 1,500 MW of power from projects
in Lao PDR
• Second MOU of 19 June 1996: Thailand
agreed to increase purchase to 3,000 MW
• Lao PDR also agreed to support passage of
transmission system from the third country, Thailand can purchase power from Yunnan in the future
Trang 14Power Purchase from Lao PDR
Projects with PPA
Nam Theun-Hinboun 187 Lao PDR, Nordic, MDX 3/98 Houay Ho 126 Lao PDR, Daewoo, Loxley 9/99 HOA & PPA under
Hongsa Lignite (Stage 1) 608 Thai-Lao Lignite 3/2008
Xe Kaman 1 407 Hydro-Electric Commission Enterprise
Corporation 3/2008
Xe Pien - Xe Nam Noi 365 Lao PDR, Dong Ah, Thai-Lao Hydropower,
Total 3,596
Trang 15Power Purchase from China
• MOU signed 12 November 1998 for purchase of 3000 MW from China by 2017.
• ADB estimates that Yunnan Province, P.R China, has
hydropower generating capability of 90,000 MW.
• Lancang (Mekong) River has total potential of 22,260
MW Manwan (1,500 MW) is already in operation 2nd
dam under construction.
• Possible project for power sale - Jing Hong Project
– Capacity: 1,500 MW, with 1,500 MW for sale to Thailand
– Investor: GMS/Yunnan Electric
Trang 16Power Supply by Source (PDP 99-02)
Unit:MW
EGAT-HYDRO 2,874 16.9 3,386 13.6 3,886 12.3 EGAT-THERMAL 11,825 69.7 12,287 49.3 11,786 37.4
Trang 17Reform of Electricity Supply Industry
• The Privatization Master Plan
approved by Cabinet on 1 September
1998 provides high level road map.
• In order to draw up a detailed
framework and action plan, a revised reform plan was prepared.
• The new Reform Plan was approved
by the Cabinet on 25 July 2000.
Trang 18G O
EGAT
Direct Customers MEA
PEA
END Users
END Users
Trang 19Reform Plan :
Medium Term ESI Structure (2002)
R E G U L A T O R
IPPs
Direct Customers
Powergens SPPs
END Users
END Users
Power Purchase EGAT System Operation Transmission Hydro Generation
Trang 20Reform Plan :
Long Term ESI Structure (2003/2004)
R E G U L A T O R
Trang 21• All but a few large consumers get their physical
electricity from the DisCo division of a regulated
regional monopoly called “Regulated Electricity
Delivery Company (REDCo)”
• Consumers pay for this electricity either through the
REDCo’s SupplyCo division or through a competitive retailer (RetailCo)
• There is a “Power Pool” consisting of
• Independent System Operator (ISO)
• Market Operator (MO)
• Settlement Administrator (SA)
• The GridCo is independent of the ISO and ultimately
GenCos
Functions and Structure of the
Market
Trang 22• ISO should use an integrated dispatch/spot market
process to determine real-time operation and the
corresponding market prices.
• ISO/MO also operate a day-ahead forward market for
the convenience of market participants.
• ISO would be an independent government owned
entity governed by its own independent Board and
corporate charter In particular ISO should not be
integrated with GridCo.
• ISO would lease the grid facilities from the GridCo
and decide how they should be used during system operations A Transmission Control Agreement (TCA) would define the respective rights and responsibilities
of the ISO and the GridCo.
Independent System Operator (ISO)
Trang 23• A GridCo unaffiliated with the ISO, could
be allowed to have some interest in
competitive generation or retailers.
• During a transition period EGAT will be
the GridCo and will own generation.
• But eventually all EGAT generation should
be sold or transferred to other entities so that GridCo is independent of any
GenCos, retailers or traders.
GridCo
Trang 24The Problem of Stranded Costs
Stranded Costs
Competition Should Reduce Costs, But
Will Reduce Prices Even More
Trang 25Stranded Costs
• Given the expected high reserve margin of the
system during the next 5 years and unavoidable cos
t of human resource programs, competitive market prices will be low and stranded cost must be recove red by non-competitive processes.
• EGAT will create a special purpose “Debt Co”
function within the state enterprise to hold
stranded debt
• Impose Competition Transition Charge (CTC) paid
by consumers to recover stranded costs CTC shoul
d be used together with vesting contracts (CfDs) in order to stabilize average consumer bills and gener ator revenue during the early years.
Trang 26Stranded Costs (con’t)
• The functions of “Debt Co” are to
– Hold the stranded debt and the vesting CfDs
– Define periodic CTC amounts needed to service
debt
– Service the debt with CTC and CfD payments.
• Stranded costs already exist and is not created by
the introduction of competition Competition simpl
y makes stranded costs transparent.
• Retail tariff to consumers could still be lower even
with the payment of CTC by consumers.
Trang 27Thai Power Capacity
• Current generating capacity is at roughly
20,000 MW.
• Under the Medium Economic Recovery Case
(MER) power supply is expected to grow to 25 ,477 MW in 2001 and 28,312 MW in 2006.
• The share of power supply from EGCO, IPPs,
SPPs and import is expected to grow from 25
% in 1999 to 40% by 2006
• EGAT’s share in power supply, excluding
Ratchaburi, is expected to fall to 48%.
Trang 28Disposition of EGAT’s Generation
Assets
• It is recommended that EGAT’s generation
assets should be separated into 4 groups:
– Ratchaburi power plant (3,645 MW)
– PowerGen 1 (6,581 MW in 2011)
– PowerGen 2 (4,075 MW in 2011)
– Hydro power plants (3,384 MW in 2011)
• The analysis finds that the allocation of power
plants to PowerGen 1 and PowerGen 2 enables maximisation of available operating synergies and results in cost reductions.
Trang 29• PPAs should be managed by
– 2 IPP Traders
– SPP Trader
– Foreign-PPA Trader
• The traders could be EGAT itself or wholly
owned subsidiaries of EGAT
• Vesting contracts might be used to help manage risk and limit market power
Dealing with PPAs
Trang 30• Retail competition as defined can commence for all consumers
in Thailand by the time the power pool commences operation
in 2003 because the method of recovering stranded costs does not require that a pool of customers be held captive for a
number of years to pay off the stranded costs.
• However it will require establishment of pricing and settlement
system; e.g billing system needs to be able to reconcile hourly consumption with hourly price (or average of).
• The required system can be ready by power pool
commencement in 2003 if work starts in 2000.
Retail Competition
Trang 31Year 2003 - Power Pool Commencement
EGAT (State Enterprise)
Governor
Corporate Support
Energy Management Agency Other BUs
• Market education
• DebtCo and PPA
Traders become operational
possible complete divestment in due course
Notes:
DebtCo
PG2 PG1
x%
x% = In process of sell-down
foreign PPA Trader
SPP PPA Trader
100% 100%
Trang 32After 2003 -Corporatisation of
Hydro and GridCo
Governor Corporate Support DebtCo?
Hydro
GridCo
EGCO Ratchaburi
• Corporatisation
of Hydro and GridCo and possibly privatisation
Trang 33Restructuring of MEA : After 2003
• Separate accounting of
distribution and supply within MEA REDCo.
• If performance targets are
not achieved, corporatise REDCo and all NSBs.
• Reconsider the structure of
- Information Technology Dept (ITD)
- Power System Maintenance Dept (PMD)
Trang 34Restructuring of PEA : 2003 onwards
PEA (State Enterprise)
Governor
BU1
• REDCos and NSB
corporatised and possibly
privatised
• If efficiency
improvement not sufficient,
consider corporatisation of Network.
Notes:
BU2 BU3 BU4
REDCo1 REDCo2 REDCo12 NSBs
x%
Supporting Service NETWORK
Trang 35Ratchaburi Power Plant
• Ratchaburi will be a 3,645 MW Power Plant
Complex when completed consisting of the
following
– 3 x 725 MW Combined Cycle Gas Turbines
– 2 x 735 MW Thermal units
– Common facilities, including offices,
accommodation, water supply and treatment, storage facilities
– site for additional 2 x 700 MW Thermal units – switchyard
Trang 36Revised Plan for Ratchaburi Privatisation
• The revised plan for Ratchaburi privatisation was
approved by the cabinet on November 30, 1999:
– IPO to the general public and investors of 40% of the shares
on 4 October 2000.
– 15% to be allocated to EGAT employees at par value on
average with reasonable lock up period
– EGAT to retain 45%
• Given that the 15% offer to EGAT employees is
relatively high compared to international
precedent cases, a well-designed locked up
structure which is not negatively perceived by
other IPO investors is critical to a successful IPO.
Trang 37Corporate and Ownership Structure (con’t)
RHCO
Public EGAT
Equity
Bt 18,334 mm
Power plant units
Funds
Debt
Bt 42,779 mm
Trang 38Tentative Time Frame for IPO
• Negotiation & finalization of loan documents at the end of
• 2 nd Week of October Authorized Committee, EGAT and
RHCO member approve IPO price
• Expected proceeds from sale of shares to EGAT employees
and the general public would be 10,000 million baht (at
15 baht/share)
Trang 39Current GSI Structure
Unocal (60%)
PTTEP (25%) (17%) Total
Mitsui (7%) (3%) BG
Others (15%)
PTT (100%) PTT (100%)
EGAT (75%)
LPG+
Petrochemical Feedstock (14%)
Industrial Customers (11%)
Trang 40Competition in Gas Supply Industry
• NEPO’s plan for regulatory & industry structure of
GSI
– division of transmission and trading
– licensing all operators
– independent regulatory authority
– common pipeline tariff
– Third Party Access (TPA) provided
– existing contracts honoured
– open competition in construction & ownership of new
high-pressure pipelines and new low-pressure distributio
n concessions
Trang 41Structure of PTT Gas
PTT/PTT Co., Ltd./(Plc)
PTT Gas
Supporting Units GSP
Trang 42Energy Industry Act
• In order to introduce retail competition and create
a power pool, a new energy law will be needed.
• Energy Industry Act is being drafted and should
become law in 2002.
• The Act will
– create an independent regulatory body, the National
Energy Regulatory Commission (NERC), to regulate
electricity and natural gas supply industries
– create a power pool
Trang 43National Energy Regulatory
Commission (NERC)
• NERC will consist of 5 full time commissioners for a term of 6
years.
• National Energy Regulatory Office (NERO) will serve as the
secretariat of NERC and will be headed by a Secretary
General.
• The Act clearly distinguishes the roles of National Energy
Policy Council (NEPC), which will only be responsible for
policy, and those of NERC.
• Regulatory duties currently the responsibilities of Department
of Energy Development and Promotion, Public Works
Department and NEPO will be transferred to NERC/NERO.